Line loss exception processing method and device

After judging the abnormality of the wire loss of the power grid, a corresponding work order is generated for rapid processing, which solves the problem of low efficiency in the processing of abnormal wire loss in the power grid, realizes rapid positioning and processing, and reduces economic losses.

CN119315521APending Publication Date: 2025-01-14HAINAN POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411288575.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2025-01-14

AI Technical Summary

Technical Problem

The prior art is difficult to quickly deal with abnormal line losses in the power grid, resulting in serious economic losses.

Method used

After determining the abnormality of the power grid line loss, determine whether the file and collection are abnormal, generate corresponding work orders based on the abnormal situation, and use grassroots staff to quickly locate and process them.

Benefits of technology

By quickly dealing with line loss abnormalities, economic losses are reduced and the efficiency and reliability of power grid operation are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119315521A_ABST
    Figure CN119315521A_ABST
Patent Text Reader

Abstract

The embodiment of the invention discloses a line loss abnormity processing method and device, and the method comprises the steps: positioning the line loss abnormity after the line loss abnormity of a power grid is determined, and judging whether a file is abnormal or not, and judging whether the collection is abnormal or not. And if the file is abnormal, generating a first abnormal work order according to the file abnormity details. And if the acquisition is abnormal, generating a second abnormal work order. And if the acquisition is not abnormal, checking voltage abnormity, low voltage, current loss and reversed polarity, determining an on-site checking level, and generating a third abnormal work order according to the checking level, so that the line loss abnormity can be quickly processed by basic-level workers after being positioned.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of line loss, and in particular to a method and device for handling abnormal line loss. Background Art

[0002] Line loss is the power loss of the power grid. If there is a large amount of abnormal line loss in the power grid, it will cause great economic losses. Therefore, it is very necessary to deal with abnormal line loss in a timely and rapid manner. Therefore, how to quickly deal with abnormal line loss has become a technical problem that needs to be solved urgently by those skilled in the art. Summary of the invention

[0003] The present application provides a method and device for handling abnormal line loss. In this method, after determining that the line loss of the power grid is abnormal, it continues to determine whether the file is abnormal and whether the collection is abnormal. If the file is abnormal, a first abnormal work order is generated according to the abnormal details of the file. If the collection is abnormal, a second abnormal work order is generated. If the collection is not abnormal, the voltage abnormality, low voltage, loss of current and reverse polarity are checked, and the on-site verification level is determined. A third abnormal work order is generated according to the verification level, so that grassroots staff can quickly handle the abnormal line loss after locating it.

[0004] In a first aspect, a method for handling abnormal line loss is provided, comprising:

[0005] Determine whether the power grid line loss is abnormal;

[0006] If the line loss is abnormal, determining whether the file is abnormal;

[0007] If the file is abnormal, determine the abnormal details of the file;

[0008] Generate a first abnormal work order according to the abnormal file details;

[0009] Determine whether the collection is abnormal;

[0010] If the collection is abnormal, a second abnormal work order is generated;

[0011] If the acquisition is not abnormal, the voltage abnormality, low voltage, current loss and reverse polarity are checked to divide the on-site inspection level;

[0012] A third abnormal work order is generated according to the on-site verification level.

[0013] In some embodiments, the method further comprises:

[0014] When receiving a message generated after the problem is solved based on the first abnormal work order, the second abnormal work order and the third abnormal work order, re-execute the step of determining whether the power grid line loss is abnormal;

[0015] If the line loss is not abnormal, re-save the file.

[0016] In some embodiments, the step of determining whether the file is abnormal includes:

[0017] Determine whether the electricity customer information, metering point information, substation information, line section information, 10kV line files and substation basic files are abnormal;

[0018] If the electricity customer information, metering point information, substation information, line section information, 10kV line file and / or substation basic file are abnormal, then determine that the file is abnormal;

[0019] If the electricity customer information, metering point information, substation information, line section information, 10kV line file and substation basic file are all normal, it is determined that the file is normal.

[0020] In some embodiments, the step of determining whether collection is abnormal includes:

[0021] Collect abnormal messages;

[0022] Analyze the abnormal message to obtain an analysis result;

[0023] If the analysis result includes message truncation, communication timeout and / or continuous offline, determining that the collection is abnormal;

[0024] If the analysis result does not include message truncation, communication timeout and continuous offline, it is determined that the acquisition is not abnormal.

[0025] In some embodiments, the step of checking the voltage anomaly includes:

[0026] If the voltage of any phase A, B, C of the three-phase four-wire high-supply high-meter or high-supply low-meter electric energy metering device is lower than 85% of the rated value or higher than 250V for 10 times or more in a day, it is determined that there is a voltage abnormality;

[0027] If the voltage of any phase of a three-phase three-wire high-supply and high-meter electric energy metering device is lower than 90% of the rated value for 10 times or more in a day, it is determined that there is a voltage abnormality.

[0028] In some embodiments, the step of checking the flow loss comprises:

[0029] If the current of any phase of A, B, and C on that day is 0, and the primary side current value of the phase line with the largest power consumption exceeds a predetermined threshold within a certain period of time, it is determined that there is a current loss.

[0030] In some embodiments, the step of checking the reverse polarity includes:

[0031] If at the same time point in a three-phase four-wire high-supply low-meter electric energy metering device, the sum of the absolute values ​​of the active power of phases A, B, and C and 50% of the difference between the total active power is equal to the active power of one of the three phases A, B, and C, then reverse polarity is determined to exist.

[0032] In a second aspect, a line loss abnormality processing device is provided, comprising:

[0033] A first judgment unit, used to judge whether the power grid line loss is abnormal;

[0034] A second judgment unit, configured to judge whether the file is abnormal if the line loss is abnormal;

[0035] A determination unit, configured to determine the abnormality details of the file if the file is abnormal;

[0036] A first generating unit, configured to generate a first abnormal work order according to the abnormal file details;

[0037] A third judgment unit is used to judge whether the collection is abnormal;

[0038] A second generating unit, configured to generate a second abnormal work order if the collection is abnormal;

[0039] The verification unit is used to verify the voltage abnormality, low voltage, current loss and reverse polarity if the acquisition is not abnormal, so as to divide the on-site verification level;

[0040] The third generating unit is used to generate a third abnormal work order according to the on-site verification level.

[0041] In a third aspect, an electronic device is provided, comprising: at least one processor; and a memory communicatively connected to the at least one processor;

[0042] The memory stores instructions that can be executed by the at least one processor, and the instructions are configured to execute the above method.

[0043] According to a fourth aspect, a computer-readable storage medium is provided, storing computer-executable instructions for executing the method.

[0044] In the above embodiment, a method and device for handling abnormal line loss is provided. In this method, after determining that the power grid line loss is abnormal, the line loss abnormality is located, and the steps of determining whether the file is abnormal and determining whether the collection is abnormal are performed. If the file is abnormal, a first abnormal work order is generated according to the abnormal file details. If the collection is abnormal, a second abnormal work order is generated. If the collection is not abnormal, the voltage abnormality, low voltage, loss of current and reverse polarity are checked, and the on-site verification level is determined. A third abnormal work order is generated according to the verification level, so that the grassroots staff can quickly handle the line loss abnormality after locating it. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] Figure 1 A flowchart of a method for handling abnormal line loss is exemplarily shown according to some embodiments;

[0046] Figure 2 A schematic structural diagram of a line loss abnormality processing device provided according to some embodiments is exemplarily shown. DETAILED DESCRIPTION

[0047] In order to make the purpose and implementation method of the present application clearer, the exemplary implementation method of the present application will be clearly and completely described below in conjunction with the drawings in the exemplary embodiments of the present application. Obviously, the described exemplary embodiments are only part of the embodiments of the present application, rather than all the embodiments.

[0048] It should be noted that the brief description of terms in this application is only for the convenience of understanding the embodiments described below, and is not intended to limit the embodiments of this application. Unless otherwise specified, these terms should be understood according to their common and usual meanings.

[0049] The terms "first", "second", "third", etc. in the specification and claims of this application and the above drawings are used to distinguish similar or similar objects or entities, and do not necessarily mean to limit a specific order or sequence, unless otherwise noted. It should be understood that the terms used in this way can be interchangeable under appropriate circumstances.

[0050] The terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover but not exclude inclusion, for example, a product or device comprising a list of components is not necessarily limited to all the components expressly listed but may include other components not expressly listed or inherent to such product or device.

[0051] Line loss is the power loss of the power grid. If there is a large amount of abnormal line loss in the power grid, it will cause great economic losses. Therefore, it is very necessary to deal with abnormal line loss in a timely and rapid manner. Therefore, how to avoid and quickly deal with abnormal line loss has become a technical problem that needs to be solved urgently by those skilled in the art.

[0052] In order to solve the above technical problems, an embodiment of the present application provides a method for handling abnormal line loss. In this method, after determining that the power grid line loss is abnormal, the line loss abnormality is located, and the steps of determining whether the file is abnormal and determining whether the collection is abnormal are performed. If the file is abnormal, a first abnormal work order is generated according to the abnormal file details. If the collection is abnormal, a second abnormal work order is generated. If the collection is not abnormal, the voltage abnormality, low voltage, loss of current and reverse polarity are checked, and the on-site verification level is determined, and a third abnormal work order is generated according to the verification level, so that the grassroots staff can quickly handle the line loss abnormality after locating it.

[0053] Figure 1 The flowchart of a method for handling abnormal line loss according to some embodiments is exemplarily shown. The method includes S100-S900.

[0054] S100: Determine whether the power grid line loss is abnormal.

[0055] In the embodiment of the present application, abnormal line loss refers to a situation in which the line loss exceeds the normal range or expected value during the power transmission and distribution process.

[0056] In some embodiments, the step of determining whether the grid line loss is abnormal includes: light load determination.

[0057] Light load determination can be made according to the monthly light load determination rules or according to the daily light load determination rules.

[0058] The rules for identifying monthly light loads include line light loads and substation light loads; line light loads include line loss rates greater than or equal to 7% or less than -2%, the absolute value of daily line loss electricity is greater than the value of the feeder gateway meter multiplier multiplied by 0.01 kWh, and the monthly electricity is less than 5,000 kWh, which is considered light load. Substation light loads include daily electricity corresponding to the transformer's daily electricity consumption being less than 30% of its rated capacity (power factor is calculated as 0.8, and daily is calculated as 24 hours), and the monthly electricity consumption is less than 3,000 kWh, which is considered light load for the transformer.

[0059] The daily light load identification rules include: taking the total active power and total reactive power of the line gateway table to calculate the load rate at each 15-minute point, and taking the maximum load rate of the day as the daily load for judgment. If the daily load rate is less than 10%, it can be judged as a light-load line, and the line loss is determined to be abnormal. The 10% threshold is adjustable.

[0060] S200: If the line loss is normal, archive the data.

[0061] In the embodiment of the present application, if the line loss is not abnormal, the judgment result is archived for subsequent use.

[0062] S300: If the line loss is abnormal, determine whether the file is abnormal.

[0063] In the embodiment of the present application, since abnormal line loss will cause many losses, after determining the abnormal line loss, the abnormal position is located, so that the location where the problem occurs can be processed later. First, it can be determined whether the file is abnormal. In some cases, the abnormal line loss may be caused by problems with the file, so in the embodiment of the present application, it is determined whether the file is abnormal.

[0064] In addition, in some embodiments, if the line loss is abnormal, an abnormal work order can be directly generated, and grassroots staff can handle the line loss abnormality according to the abnormal work order.

[0065] In some embodiments, the step of determining whether the file is abnormal includes:

[0066] Determine whether the electricity customer information, metering point information, substation information, line section information, 10kV line file and substation basic file are abnormal respectively; if the electricity customer information, metering point information, substation information, line section information, 10kV line file and / or substation basic file are abnormal, determine that the file is abnormal; if the electricity customer information, metering point information, substation information, line section information, 10kV line file and substation basic file are not abnormal, determine that the file is not abnormal.

[0067] In the embodiment of the present application, the abnormality of the file is judged by using a variety of information, so that the judgment result can be more accurate.

[0068] The step of determining whether the electricity customer information is abnormal includes:

[0069] Get user profile;

[0070] Determine whether there are differences and omissions in the user category, operating status, voltage level, electricity consumption category, industry classification, contract capacity, operating capacity, fee control mode and power source type in the user profile.

[0071] If there are differences and / or omissions, it is determined that the user customer information is abnormal;

[0072] If there are no differences or omissions, it is determined that the user customer information is not abnormal.

[0073] In the embodiment of the present application, the user number is used as the unique identification code, and the customer files are checked for differences and omissions according to user category, operating status, voltage level, electricity category, industry classification, contract capacity, operating capacity, fee control mode, and power type. Statistics are collected and details are drilled down according to the province, bureau, and institute.

[0074] User categories can specifically determine whether the user categories in the customer profile are accurate, such as industrial users, commercial users, residential users, etc. Check whether there is any category confusion or misclassification.

[0075] The operation status can specifically determine whether the operation status information in the customer file is updated in a timely manner, such as normal, suspended, deregistered, etc. Check whether there are any records that do not match the actual operation status.

[0076] The voltage level can be used to determine whether the voltage level information in the customer file is accurate, such as high voltage, low voltage, etc. Check whether there are any errors or omissions.

[0077] The electricity usage category can be used to determine whether the electricity usage category in the customer file is consistent with the actual electricity usage, such as single-phase, three-phase, large industrial electricity, etc. Check whether there is an error in the electricity usage category or it has not been updated in time.

[0078] Industry classification can specifically determine whether the industry classification in the customer file is accurate, such as manufacturing, service, agriculture, etc. Check whether there is an error in industry classification or no subdivision.

[0079] Contract capacity and operating capacity: Specifically, it can determine whether the contract capacity in the customer file is consistent with the actual operating capacity. Check whether there is a large capacity difference or failure to update in time. For customers who change capacity, verify whether the change procedures are complete and compliant.

[0080] The fee control mode can specifically determine whether the fee control mode information in the customer file is accurate, such as prepaid, postpaid, etc. Check whether the fee control mode is consistent with the actual charging method, and whether there is any improper fee control strategy setting.

[0081] The power type can be used to determine whether the power type information in the customer file is accurate, such as mains power, self-provided power, etc. Check whether the power type is consistent with the actual power supply.

[0082] Discrepancies usually refer to inconsistencies between the information in the archives and the actual situation or other related records. Missing refers to the situation where some necessary information in the archives is not recorded or omitted.

[0083] In some embodiments, the step of determining whether the metering point information is abnormal includes:

[0084] Obtain metering point archives;

[0085] Determine whether there are any differences or omissions in the metering point name, metering point status, metering point voltage level, electricity consumption category, metering point category code, PT, CT, metering point usage code, station area identification and line section identification in the metering point file;

[0086] If there is a difference and / or a missing, determining that the metering point information is abnormal;

[0087] If there is no difference or missing, it is determined that the metering point information is not abnormal.

[0088] In the embodiment of the present application, the metering point number is used as the unique identification code, and the metering point files are checked for differences and omissions according to the metering point name, metering point status, metering point voltage level, electricity category, metering point category code, PT, CT, metering point use code, station area identification, and line segment identification. Statistics are collected and details are drilled in the form of province, bureau, and institute.

[0089] Measuring point name: Determine whether the name is accurate and whether there are any duplicate or wrong names.

[0090] Metering point status: Determine whether the status is consistent with the actual situation, such as normal, disabled, faulty, etc.

[0091] Voltage level at the metering point: Determine whether the voltage level is accurate and consistent with the actual voltage used.

[0092] Electricity usage category: Determine whether the electricity usage category matches the customer's actual electricity usage.

[0093] Metering point category code: Determine whether the code is accurate and whether there are any wrong codes or missing codes.

[0094] PT (voltage transformer) and CT (current transformer): Determine whether the specifications, models, accuracy levels and other information of PT and CT are complete and correct.

[0095] Metering point usage code: Determine whether the code accurately reflects the actual usage of the metering point.

[0096] Area identification: For low-voltage users in an area, determine whether the area identification is accurate to ensure that each user belongs to the correct area. In some embodiments, the area identification is for low-voltage users in an area.

[0097] Line segment identification: Check whether the line segment identification is complete to ensure that the line location of the metering point can be accurately tracked.

[0098] In some embodiments, the step of determining whether the station area is abnormal includes:

[0099] Get the area archives;

[0100] Determine whether there are any differences or omissions in the substation name, substation operation status, power supply unit code and substation type in the substation file;

[0101] If there is a difference and / or a lack, determining that the station area is abnormal;

[0102] If there is no difference and no missing, it is determined that the station is not abnormal.

[0103] In the embodiment of the present application, the substation number is used as the unique identification code, and the substation files are checked for differences and omissions according to the substation name, substation operation status, power supply unit code, and substation type. Statistics are collected and details are drilled in the form of province, bureau, and institute. Abnormal analysis and statistics are conducted on the substations that affect the accurate calculation rate of line loss in the same period.

[0104] The specific name of the station area can be compared with the name in the station area file with the actual site or related records to check whether there are any inconsistencies or errors.

[0105] Status verification can specifically check whether the operating status of the substation is consistent with the actual situation, for example, whether there is a substation that is incorrectly marked as "normal" but is actually in a "faulty" state.

[0106] The specific code of the power supply unit can determine whether each substation is correctly assigned to the corresponding power supply unit and the code is accurate.

[0107] The substation type can be used to check whether the substation type is consistent with its actual use. For example, an industrial substation should not be mistakenly classified as a residential substation.

[0108] Discrepancies may include data mismatches, inconsistencies or redundancies, while missing data may mean that certain key fields or information were not recorded or updated.

[0109] In some embodiments, the step of determining whether the line segment is abnormal includes:

[0110] Get the route segment file;

[0111] Determine whether there are any differences or omissions in the line name, line operation status, line voltage level, line category, line type, segmentation mark, superior mark, subordinate mark and ownership in the line file;

[0112] If there is a difference and / or a missing, determining that the route segment is abnormal;

[0113] If there is no difference and no missing, it is determined that the line segment is not abnormal.

[0114] In the embodiment of the present application, the line number is used as the unique identification code, and the line file is checked for differences and omissions in line segment files according to line name, line operation status, line voltage level (only 10kV is compared with marketing), line category, line type, segment mark, superior mark, subordinate mark, and property ownership. Statistics are collected and details are drilled in accordance with the province, bureau, and institute.

[0115] The line name can specifically determine whether the line name is accurate, consistent, and corresponds to the actual line.

[0116] The line operation status can specifically determine whether the line operation status is consistent with the actual situation, such as in operation, under maintenance, or out of service.

[0117] The line voltage level can be specifically judged by focusing on comparing the 10kV voltage level lines to ensure that its information is accurate and consistent with the marketing data.

[0118] The line category can be specifically judged based on the purpose and nature of the line, and the classification can be checked to see if it is accurate.

[0119] The line type can specifically determine whether the line type (such as overhead lines, cables, etc.) is consistent with the actual situation.

[0120] The segmentation mark can specifically determine whether the segmentation mark of the line is set correctly and whether it is consistent with the actual segmentation situation.

[0121] Superior and subordinate identification: It can be used to determine whether the superior and subordinate relationship identification of the line is accurate, ensuring that the hierarchical relationship between the lines is clear.

[0122] Ownership: It can determine the ownership of the line in detail and check whether there are any unclear or incorrect ownership issues.

[0123] During the investigation, we focus on whether there are discrepancies and omissions in the line files. Differences may be manifested as inconsistent data, contradictory information, etc.; omissions may be manifested as blank key fields, information not entered, etc.

[0124] In some embodiments, the step of determining whether the 10 kV line file is abnormal includes: using the model generation rules of 10 kV and below feeders to check the 10 kV line file.

[0125] In the embodiment of the present application, the 10kV feeder model plays a vital role in the power system and is the basis for power system analysis, design, operation and control. This model is mainly used to describe the electrical characteristics, operating status and interaction with other system components of the 10kV feeder. Data is required when generating the model of 10kV and below feeders. The source of this data is the 10kV line archive, so the model generation rules can be used to check the 10kV line archive.

[0126] In some embodiments, the step of determining whether the basic file of the station area is abnormal includes: using the station area model to generate rules and verify the basic file of the station area.

[0127] In the embodiment of the present application, the substation model is a tool used in the power system to describe and manage the operation of the substation (i.e., the power supply range of the distribution transformer). Mainly through the real-time collection, processing and analysis of the power consumption data of the substation, the accurate measurement of the power consumption of the substation is achieved, providing strong support for the operation and management of the power system. When generating the substation model, data is required, and the source of these data is the basic files of the substation, so the basic files of the substation can be checked using the substation model generation rules.

[0128] S400, if the file is abnormal, determine the abnormal details of the file;

[0129] S500, generating a first abnormal work order according to the abnormal file details;

[0130] In the embodiment of the present application, when it is determined that the file is abnormal, the abnormal file details are obtained. According to the first abnormal work order generated by the abnormal file details, the abnormality can be directly located to determine the content in the file that may cause abnormal line loss.

[0131] S600: Determine whether collection is abnormal.

[0132] In the embodiment of the present application, the abnormal line loss may be caused by file abnormality or a problem in the collected data, so the collection abnormality is also judged.

[0133] In some embodiments, the step of determining whether collection is abnormal includes:

[0134] Collect abnormal messages.

[0135] Analyze the abnormal message to obtain an analysis result;

[0136] If the analysis result includes message truncation, communication timeout and / or continuous offline, determining that the collection is abnormal;

[0137] If the analysis result does not include message truncation, communication timeout and continuous offline, it is determined that the acquisition is not abnormal.

[0138] S700: If the collection is abnormal, generate a second abnormal work order.

[0139] In the embodiment of the present application, if the collection is abnormal, the corresponding equipment, time and abnormal description list are provided, and a second abnormal work order is generated based on the equipment, time and abnormal description list. In this way, the grassroots operator can check the collection process according to the second abnormal work order to eliminate the error of abnormal collection.

[0140] S800. If the data collected is normal, check for voltage abnormality, low voltage, current loss and reverse polarity to divide the on-site inspection level.

[0141] In the embodiment of the present application, if the acquisition is not abnormal, the situation causing abnormal line loss may be an on-site problem. Therefore, in the embodiment of the present application, voltage abnormality, low voltage, current loss and reverse polarity are checked, and the on-site inspection level is divided.

[0142] In some embodiments, the step of checking the voltage anomaly includes:

[0143] If the voltage of any phase A, B, C of the three-phase four-wire high-supply high-meter or high-supply low-meter electric energy metering device is lower than 85% of the rated value or higher than 250V for 10 times or more in a day, it is determined that there is a voltage abnormality;

[0144] If the voltage of any phase of a three-phase three-wire high-supply and high-meter electric energy metering device is lower than 90% of the rated value for 10 times or more in a day, it is determined that there is a voltage abnormality.

[0145] In the embodiment of the present application, when the line loss is abnormal, the voltage of the electric energy metering device under the line or substation is checked to see if there is a loss of voltage, undervoltage or overvoltage. In some embodiments, before executing the step of checking the voltage anomaly, factors such as low voltage caused by data quality, fault repair, power shortage or long power supply radius are eliminated, so that the verification result can be more accurate.

[0146] In some embodiments, the step of checking the low voltage includes: according to the system substation low-voltage electricity consumption monitoring function, setting the substation low-voltage users as low-voltage monitoring points, analyzing the voltage characteristics of the line / substation user group, and observing the voltage data changes, so as to accurately detect single metering failures, or voltage drops caused by heating of the grid line.

[0147] In some embodiments, the step of checking the flow loss comprises:

[0148] If the current of any phase of A, B, and C on that day is 0, and the primary side current value of the phase line with the largest power consumption exceeds a predetermined threshold within a certain period of time, it is determined that there is a current loss.

[0149] In the embodiment of the present application, when the line loss is abnormal, the line is checked and the electric energy metering device is checked in the substation to see if there is a current loss. Before executing the step of checking the current loss, it also includes: eliminating data quality and customer phase loss operation factors.

[0150] In some embodiments, the step of checking the reverse polarity includes:

[0151] If at the same time point in a three-phase four-wire high-supply low-meter electric energy metering device, the sum of the absolute values ​​of the active power of phases A, B, and C and 50% of the difference between the total active power is equal to the active power of one of the three phases A, B, and C, then reverse polarity is determined to exist.

[0152] In the embodiment of the present application, the on-site inspection levels are divided according to the inspection results of voltage anomalies, low voltage, current loss and reverse polarity.

[0153] In the embodiment of the present application, the weights of the verification results corresponding to different items can be set, and the on-site verification level can be calculated in combination with the above verification results. The on-site verification level can be used to evaluate the risk level. The higher the risk level, the greater the probability of problems and failures, and the more attention it needs to be paid.

[0154] S900. Generate a third abnormal work order according to the on-site inspection level.

[0155] In an embodiment of the present application, a third abnormal work order is generated according to the on-site verification level, and the risk level can be clearly stated on the third abnormal work order. The higher the risk level of the third abnormal work order, the more it needs to be processed quickly by grassroots operators.

[0156] In some embodiments, the method further comprises:

[0157] When receiving a message generated after the problem is solved based on the first abnormal work order, the second abnormal work order and the third abnormal work order, re-execute the step of determining whether the power grid line loss is abnormal;

[0158] If the line loss is not abnormal, re-save the file.

[0159] In the embodiment of the present application, after the problem causing the abnormal line loss is processed, the step of determining whether the grid line loss is abnormal is re-executed, and after determining that the line loss is not abnormal, the data is archived.

[0160] In the above embodiment, a method for handling abnormal line loss is provided. In this method, after determining that the power grid line loss is abnormal, the line loss abnormality is located, and the steps of determining whether the file is abnormal and determining whether the collection is abnormal are performed. If the file is abnormal, a first abnormal work order is generated according to the abnormal file details. If the collection is abnormal, a second abnormal work order is generated. If the collection is not abnormal, the voltage abnormality, low voltage, loss of current and reverse polarity are checked, and the on-site verification level is determined. A third abnormal work order is generated according to the verification level, so that grassroots staff can quickly handle the line loss abnormality after locating it.

[0161] Further, as Figure 1 The specific implementation of the method, the embodiment of the present application provides a structural schematic diagram of a line loss abnormality processing device, such as Figure 2 As shown, the device comprises:

[0162] The first judging unit 201 is used to judge whether the line loss of the power grid is abnormal;

[0163] The second judgment unit 202 is used to judge whether the file is abnormal if the line loss is abnormal;

[0164] A determination unit 203, configured to determine the abnormality details of the file if the file is abnormal;

[0165] A first generating unit 204, configured to generate a first abnormal work order according to the abnormal file details;

[0166] The third judgment unit 205 is used to judge whether the collection is abnormal;

[0167] The second generating unit 206 is used to generate a second abnormal work order if the collection is abnormal;

[0168] The verification unit 207 is used to verify the voltage abnormality, low voltage, current loss and reverse polarity if the acquisition is not abnormal, so as to classify the on-site verification level;

[0169] The third generating unit 208 is used to generate a third abnormal work order according to the on-site verification level.

[0170] In a specific application scenario, the device further includes:

[0171] a re-execution unit, configured to re-execute the step of determining whether the power grid line loss is abnormal when receiving a message generated after the problem is processed based on the first abnormal work order, the second abnormal work order, and the third abnormal work order;

[0172] The archiving unit is used for re-archiving if the line loss is not abnormal.

[0173] In a specific application scenario, the second judgment unit includes:

[0174] The fourth judgment unit is used to judge whether the electricity customer information, metering point information, substation information, line section information, 10kV line files and substation basic files are abnormal;

[0175] A file abnormality determination unit, used to determine that the file is abnormal if the electricity customer information, metering point information, substation information, line section information, 10kV line file and / or substation basic file are abnormal;

[0176] The file non-abnormal determination unit is used to determine that the file is non-abnormal if the electricity customer information, metering point information, substation information, line section information, 10kV line file and substation basic file are all normal.

[0177] In a specific application scenario, the third judgment unit includes:

[0178] A collection unit, used for collecting abnormal messages;

[0179] An analysis unit, used for analyzing the abnormal message to obtain an analysis result;

[0180] a collection abnormality determination unit, configured to determine that if the analysis result includes message truncation, communication timeout and / or continuous offline, then the collection is abnormal;

[0181] The acquisition non-abnormal determination unit is used to determine that the acquisition is non-abnormal if the analysis result does not include message truncation, communication timeout and continuous offline.

[0182] In specific application scenarios, the verification units include:

[0183] A voltage anomaly determination unit is used to determine that a voltage anomaly exists if the voltage of any one of the three phases A, B, and C of the three-phase four-wire high-supply high-meter or high-supply low-meter electric energy metering device is lower than 85% of the rated value or higher than 250V for 10 times or more on the same day;

[0184] If the voltage of any phase of a three-phase three-wire high-supply and high-meter electric energy metering device is lower than 90% of the rated value for 10 times or more in a day, it is determined that there is a voltage abnormality.

[0185] In specific application scenarios, the verification unit also includes:

[0186] The current loss determination unit is used to determine that there is a current loss if the current of any phase of the three-phase currents A, B, and C is 0 on that day, and the primary side current value of the phase line with the largest power consumption exceeds a predetermined threshold within a certain period of time.

[0187] In specific application scenarios, the verification unit also includes:

[0188] The reverse polarity determination unit is used to determine the presence of reverse polarity if, at the same time point in the three-phase four-wire high-supply and low-metering electric energy metering device, the sum of the absolute values ​​of the active power of the three phases A, B, and C and 50% of the difference between the total active power is equal to the active power of one of the three phases A, B, and C.

[0189] It should be noted that for other corresponding descriptions of the functional units involved in the line loss abnormality processing device provided in this embodiment, reference can be made to Figure 1 The corresponding description in will not be repeated here.

[0190] Based on the above Figure 1 The method shown in the embodiment of the present application accordingly provides a storage medium on which a computer program is stored, and when the program is executed by a processor, the above-mentioned Figure 1 The line loss abnormality handling method is shown.

[0191] Based on this understanding, the technical solution of the present application can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (which can be a CD-ROM, a USB flash drive, a mobile hard disk, etc.), and includes a number of instructions for enabling an electronic device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each implementation scenario of the present application.

[0192] Based on the above Figure 1 The method shown, and Figure 2 In order to achieve the above-mentioned purpose, the embodiment of the present application also provides a physical device for line loss abnormality processing, which can be a computer, a smart phone, a tablet computer, a smart watch, a server, or a network device, etc. The physical device includes a storage medium and a processor; the storage medium is used to store a computer program; the processor is used to execute the computer program to achieve the above-mentioned Figure 1 The line loss abnormality handling method is shown.

[0193] Optionally, the physical device may also include a user interface, a network interface, a camera, a radio frequency (RF) circuit, a sensor, an audio circuit, a WI-FI module, etc. The user interface may include a display, an input unit such as a keyboard, etc., and the optional user interface may also include a USB interface, a card reader interface, etc. The network interface may optionally include a standard wired interface, a wireless interface (such as a WI-FI interface), etc.

[0194] Those skilled in the art will appreciate that the electronic device structure provided in this embodiment does not limit the electronic device, and may include more or fewer components, or a combination of certain components, or different component arrangements.

[0195] The storage medium may also include an operating device and a network communication module. The operating device is a program that manages and saves the hardware and software resources of the electronic device, and supports the operation of the information processing program and other software and / or programs. The network communication module is used to realize the communication between the various controls inside the storage medium, and the communication with other hardware and software in the physical device.

[0196] Through the description of the above implementation methods, those skilled in the art can clearly understand that the present application can be implemented by means of software plus a necessary general hardware platform, or by hardware.

[0197] Those skilled in the art will appreciate that the accompanying drawings are only schematic diagrams of a preferred implementation scenario, and the units or processes in the accompanying drawings are not necessarily necessary for implementing the present application. Those skilled in the art will appreciate that the units in the devices in the implementation scenario can be distributed in the devices of the implementation scenario according to the description of the implementation scenario, or can be changed accordingly and located in one or more devices different from the present implementation scenario. The units of the above-mentioned implementation scenarios can be combined into one unit, or can be further split into multiple sub-units.

[0198] The above serial numbers of this application are only for description and do not represent the advantages and disadvantages of the implementation scenarios. The above disclosure is only a few specific implementation scenarios of this application, but this application is not limited to them, and any changes that can be thought of by technicians in this field should fall within the scope of protection of this application.

Claims

1. A method for handling abnormal line loss, characterized in that: include: Determine whether the power grid line loss is abnormal; If the line loss is abnormal, determining whether the file is abnormal; If the file is abnormal, determine the abnormal details of the file; Generate a first abnormal work order according to the abnormal file details; Determine whether the collection is abnormal; If the collection is abnormal, a second abnormal work order is generated; If the acquisition is not abnormal, the voltage abnormality, low voltage, current loss and reverse polarity are checked to divide the on-site inspection level; A third abnormal work order is generated according to the on-site verification level.

2. The method according to claim 1, characterized in that Also includes: When receiving a message generated after the problem is solved based on the first abnormal work order, the second abnormal work order and the third abnormal work order, re-execute the step of determining whether the power grid line loss is abnormal; If the line loss is not abnormal, re-save the file.

3. The method according to claim 1, characterized in that The step of determining whether the file is abnormal includes: Determine whether the electricity customer information, metering point information, substation information, line section information, 10kV line files and substation basic files are abnormal; If the electricity customer information, metering point information, substation information, line section information, 10kV line file and / or substation basic file are abnormal, then determine that the file is abnormal; If the electricity customer information, metering point information, substation information, line section information, 10kV line file and substation basic file are all normal, it is determined that the file is normal.

4. The method according to claim 1, characterized in that: The step of determining whether collection is abnormal includes: Collect abnormal messages; Analyze the abnormal message to obtain an analysis result; If the analysis result includes message truncation, communication timeout and / or continuous offline, determining that the collection is abnormal; If the analysis result does not include message truncation, communication timeout and continuous offline, it is determined that the acquisition is not abnormal.

5. The method according to claim 1, characterized in that The steps of checking the voltage anomaly include: If the voltage of any phase A, B, C of the three-phase four-wire high-supply high-meter or high-supply low-meter electric energy metering device is lower than 85% of the rated value or higher than 250V for 10 times or more in a day, it is determined that there is a voltage abnormality; If the voltage of any phase of a three-phase three-wire high-supply and high-meter electric energy metering device is lower than 90% of the rated value for 10 times or more in a day, it is determined that there is a voltage abnormality.

6. The method according to claim 1, characterized in that The steps of verifying the flow loss include: If the current of any phase of A, B, and C on that day is 0, and the primary side current value of the phase line with the largest power consumption exceeds a predetermined threshold within a certain period of time, it is determined that there is a current loss.

7. The method according to claim 1, characterized in that The steps of checking the reverse polarity include: If at the same time point in a three-phase four-wire high-supply low-meter electric energy metering device, the sum of the absolute values ​​of the active power of phases A, B, and C and 50% of the difference between the total active power is equal to the active power of one of the three phases A, B, and C, then reverse polarity is determined to exist.

8. A line loss abnormality processing device, characterized in that: include: A first judgment unit, used to judge whether the power grid line loss is abnormal; A second judgment unit, configured to judge whether the file is abnormal if the line loss is abnormal; A determination unit, configured to determine the abnormality details of the file if the file is abnormal; A first generating unit, configured to generate a first abnormal work order according to the abnormal file details; A third judgment unit is used to judge whether the collection is abnormal; A second generating unit, configured to generate a second abnormal work order if the collection is abnormal; The verification unit is used to verify the voltage abnormality, low voltage, current loss and reverse polarity if the acquisition is not abnormal, so as to divide the on-site verification level; The third generating unit is used to generate a third abnormal work order according to the on-site verification level.

9. An electronic device, characterized in that: include: at least one processor; and, a memory communicatively coupled to the at least one processor; The memory stores instructions executable by the at least one processor, wherein the instructions are configured to execute the method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: Computer executable instructions are stored, and the computer executable instructions are used to execute the method according to any one of claims 1 to 7.