Multi-cabin combined assembly type prefabricated cable working well mold and prefabricating method
Through the multi -cabin combination prefabricated cable workmanum mold, the problem of long -term industry in the existing technologies and great influence due to geographical environment, and the guarantee of improving construction efficiency and the safety of operational safety.
Patent Information
- Application Number
- CN202411630201.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-01-21
AI Technical Summary
The on-site casting period of existing cable inspection wells is long and greatly affected by the geographical environment, resulting in low construction efficiency.
Adopt a multi -cabin combined prefabricated cable workmanum mold, and use the combination of components and other components of the steel bottom plate, outer mold bottom plate, bottom steel shelter, inner template, and embedded parts to create a suitable specifications in advance to reduce the site Manufacturing waiting time.
Improved construction efficiency, shortened the construction period, and ensured the safety of workers during the repairs.
Smart Images

Figure CN119328881A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of cable inspection wells, and in particular to a multi-compartment combined assembled prefabricated cable inspection well mould and a prefabrication method. Background Art
[0002] The cable inspection well is an important facility used for cable joints, branches, maintenance and repair in power engineering. It is usually a structure with a certain depth and width, which can facilitate the entry and operation of workers.
[0003] The existing cable inspection wells are cast-in-place, which takes a long time to construct. In addition, cast-in-place inspection wells have limitations and are greatly affected by geographical conditions. The construction is troublesome, resulting in low construction efficiency. Summary of the invention
[0004] The purpose of the present invention is to provide a multi-compartment combined assembled prefabricated cable manhole mold and a prefabrication method, which solves the problem of long construction period and great influence of geographical environment in on-site casting of cable inspection wells, thereby improving construction efficiency.
[0005] The present invention solves the technical problem by adopting the following technical solutions:
[0006] A multi-cabin combined assembled prefabricated cable manhole mold, comprising an I-beam bottom plate, an outer mold bottom plate is provided on the upper surface of the I-beam bottom plate, a bottom steel bar frame is provided on the upper surface of the outer mold bottom plate, an inner mold plate is provided on the upper surface of the bottom steel bar frame, through circular holes are provided on both side surfaces of the inner mold plate, a fixing mechanism is provided on the inner side surface of the inner mold plate, an embedded part is provided on the outer side surface of the inner mold plate, a threaded hole is provided at the center of the embedded part, the threaded hole of the embedded part is communicated with the through hole on the side surface of the inner mold plate, the front and rear side surfaces of the outer mold bottom plate are fixedly connected to side sealing plates, the front side surface of the side sealing plates is provided with through circular holes, a through pipe is provided in the through circular hole of the side sealing plates, and both ends of the through pipe are on the outside of the inner mold plate. The purpose of setting an I-beam bottom plate is to facilitate the support of the outer mold bottom plate and to facilitate the movement of the outer mold bottom plate by a forklift. The purpose of setting a bottom steel bar frame is to facilitate the enhancement of the strength of the prefabricated cable well after forming. The purpose of setting a fixing mechanism is to facilitate the fixing of embedded parts on the inner template. The purpose of setting embedded parts is to facilitate the grounding of the cables inside the prefabricated cable well, thereby ensuring the safety of workers when going down the well for maintenance. The purpose of setting a through pipe is to facilitate the appearance of connecting holes in the prefabricated cable well after forming. The purpose of setting side sealing plates is to facilitate the blocking of both ends of the mold.
[0007] Moreover, the bottom reinforcement frame is fixedly connected to the side reinforcement frame near the top of both sides, and the side reinforcement frame is outside the inner template. The side reinforcement frame is arranged to facilitate the strength of the prefabricated cable well after the formation.
[0008] Moreover, the outer mold bottom plate is fixedly connected to the outer mold near the two side edges, the outer mold top is fixedly connected to the outer mold top plate, and the upper surface of the outer mold top plate is provided with a filling port. The filling port is provided to facilitate the injection of concrete into the assembled mold.
[0009] Moreover, the top end of the side reinforcement frame is fixedly connected to the top reinforcement frame, and the top reinforcement frame is between the upper surface of the inner formwork and the lower surface of the outer formwork top plate.
[0010] Moreover, the fixing mechanism includes a baffle, a nut and a bolt, the screw of the bolt passes through the through circular hole of the inner template, and the top of the screw of the bolt is threadedly engaged in the threaded hole of the embedded part. The bolt is provided to facilitate the engagement with the threaded hole of the embedded part, thereby fixing the position of the embedded hole.
[0011] Moreover, the head of the bolt is inside the inner template, the nut is threadedly fitted on the rod of the bolt, and the nut is inside the inner template.
[0012] Moreover, a through circular hole is arranged at the center of the baffle, and the rod of the bolt passes through the through circular hole at the center of the baffle, and the baffle is between the nut and the inner template.
[0013] Moreover, a support frame is fixedly connected to the inner surface of the inner template, and the number of the support frames is multiple, and the number of the I-beam bottom plates is multiple. The support frame is provided to facilitate the support of the inner template.
[0014] Moreover, the side sealing plate is in contact with the inner template, and the side sealing plate and the inner template are fixedly connected.
[0015] A prefabrication method of a multi-cabin combined assembled prefabricated cable well mold includes the following specific prefabrication steps:
[0016] S1. The outer mold base is placed on a plane composed of multiple I-beam base plates, and then the outer mold base plate is tied with a bottom steel frame on the surface;
[0017] S2. Place the inner template on the bottom steel bar frame, then pass the rod of the bolt through the through-hole of the inner template, and place the embedded part close to the outer surface of the inner template. Turn the bolt so that the top thread of the bolt fits in the threaded hole of the embedded part, and then tighten the nut to move the baffle until the baffle is pressed against the inner surface of the inner template.
[0018] S3. The side reinforcement frames are made on both sides of the bottom reinforcement frame, and then the top reinforcement frame is made at the top of the side reinforcement frame;
[0019] S4. The outer template is fixedly connected to the outer mold bottom plate, and then the outer mold top plate is fixedly connected to the top of the outer template, and then the side sealing plate is fixed to the outer mold bottom plate and the front and rear surfaces of the inner template;
[0020] S5. Insert the through-tube into the through-hole of the side sealing plate, and then pour concrete from the filling port;
[0021] S6. After the concrete is completely solidified, remove the through pipe, side sealing plate, outer formwork top plate, outer formwork, fixing mechanism, and inner formwork in sequence;
[0022] S7. Use equipment to remove the formed prefabricated cable well from the upper surface of the outer mold bottom plate, and then clean the surface of the outer mold bottom plate, side sealing plate, outer mold top plate, outer mold plate, and inner mold plate.
[0023] Working principle: Traditional on-site pouring requires on-site splicing of molds and waiting for the poured concrete to completely solidify, which takes a long time. However, manufacturing cable wells of suitable specifications in advance reduces the waiting time required for on-site manufacturing, which greatly improves construction efficiency. Embedded parts are embedded in the prefabricated cable wells and grounded to the outside through the embedded parts, thereby ensuring that the inside of the prefabricated cable well is in a safe working environment.
[0024] The advantages and positive effects of the present invention are:
[0025] The present invention provides a multi-chamber combined assembly type prefabricated cable well mold and a prefabrication method. It has the following beneficial effects:
[0026] 1. The cable well is cast in advance. During the construction process, you only need to install the prefabricated cable well at the designated location, which improves the construction efficiency.
[0027] 2. Pre-embedded grounding parts are provided to ensure the safety of workers when they go down the well for maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is a schematic diagram of the overall structure of a multi-cabin combined assembly type prefabricated cable well mold proposed by the present invention;
[0029] Figure 2 This is a schematic diagram of the mold structure after the side sealing plate of a multi-chamber combined assembly type prefabricated cable well mold proposed by the present invention is removed;
[0030] Figure 3 This is a schematic diagram of the inner template surface structure of a multi-cabin combined assembly type prefabricated cable well mold proposed by the present invention;
[0031] Figure 4 This is a schematic diagram of the installation position structure of the embedded parts of a multi-cabin combined assembly type prefabricated cable well mold proposed by the present invention;
[0032] Figure 5 This is an enlarged view of the partial structure of the multi-cabin combined assembly type prefabricated cable well mold proposed by the present invention;
[0033] Figure 6 The present invention provides a schematic cross-sectional structure diagram of the fixing mechanism and the matching parts of the embedded parts of a multi-compartment combined assembly type prefabricated cable well mold proposed by the present invention.
[0034] Among them, 1. I-beam bottom plate; 2. Side sealing plate; 3. Through pipe; 4. Outer mold bottom plate; 5. Outer mold top plate; 6. Filling port; 7. Fixing mechanism; 7-1. Baffle; 7-2. Nut; 7-3. Bolt; 8. Side steel frame; 9. Top steel frame; 10. Support frame; 11. Bottom steel frame; 12. Inner formwork; 13. Embedded parts; 14. Outer formwork. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] like Figure 1-6 As shown, an embodiment of the present invention provides a multi-cabin combined assembled prefabricated cable well mold, including an I-beam bottom plate 1, an outer mold bottom plate 4 is arranged on the upper surface of the I-beam bottom plate 1, a bottom steel bar frame 11 is arranged on the upper surface of the outer mold bottom plate 4, an inner mold plate 12 is arranged on the upper surface of the bottom steel bar frame 11, through holes are arranged on both sides of the inner mold plate 12, a fixing mechanism 7 is arranged on the inner side surface of the inner mold plate 12, an embedded part 13 is arranged on the outer side surface of the inner mold plate 12, a threaded hole is arranged in the center of the embedded part 13, and the embedded part The threaded hole 13 is communicated with the through hole on the side surface of the inner template 12, the front and rear side surfaces of the outer template bottom plate 4 are fixedly connected to the side sealing plate 2, the front side surface of the side sealing plate 2 is provided with a through circular hole, and the through circular hole of the side sealing plate 2 is provided with a through pipe 3, both ends of the through pipe 3 are on the outside of the inner template 12, the side sealing plate 2 is in contact with the inner template 12, the side sealing plate 2 and the inner template 12 are fixedly connected, and the inner surface of the inner template 12 is fixedly connected with a support frame 10, the number of support frames 10 is multiple, and the number of I-beam bottom plates 1 is multiple. The side sealing plate 2 and the outer mold bottom plate 4 and the inner mold plate 12 are fixedly connected by screws. The fixing mechanism 7 needs to be removed after the prefabricated cable shaft is formed, and the embedded parts 13 are cast in the prefabricated cable shaft. The embedded parts 13 connect the iron sheet and the external ground for contact, thereby achieving the effect of grounding, thereby ensuring that the inside of the prefabricated cable shaft is in a safe working environment. There is a groove on the closed surface of the side sealing plate 2, and the grooves of the two side sealing plates 2 have different shapes. After casting, the two ends of the adjacent prefabricated cable shafts can be spliced together through a socket structure.
[0037] The fixing mechanism 7 includes a baffle 7-1, a nut 7-2 and a bolt 7-3. The screw of the bolt 7-3 passes through the through circular hole of the inner template 12, and the top thread of the screw of the bolt 7-3 is threadedly engaged in the threaded hole of the embedded part 13. After the prefabricated cable well is completely solidified, the bolt 7-2 is screwed to disengage the bolt 7-2 from the threaded hole of the embedded part 13.
[0038] The head of the bolt 7-3 is inside the inner template 12, the nut 7-2 is threadedly engaged with the rod of the bolt 7-3, the nut 7-2 is inside the inner template 12, a through circular hole is provided in the center of the baffle 7-1, the rod of the bolt 7-3 passes through the through circular hole in the center of the baffle 7-1, and the baffle 7-1 is between the nut 7-2 and the inner template 12.
[0039] The outer mold bottom plate 4 is fixedly connected to the outer mold plate 14 near the two side edges, and the top of the outer mold plate 14 is fixedly connected to the outer mold top plate 5 . The upper surface of the outer mold top plate 5 is provided with a filling port 6 .
[0040] The top ends of the bottom reinforcement frames 11 near both sides are fixedly connected to the side reinforcement frames 8 , which are on the outside of the inner formwork 12 , and the top ends of the side reinforcement frames 8 are fixedly connected to the top reinforcement frames 9 , which are between the upper surface of the inner formwork 12 and the lower surface of the outer formwork top plate 5 .
[0041] A prefabrication method of a multi-cabin combined assembled prefabricated cable well mold includes the following specific prefabrication steps:
[0042] S1. The outer mold base plate 4 is placed on a plane formed by a plurality of I-beam base plates 1, and then the outer mold base plate 4 is tied with a bottom steel frame 11 on the upper surface;
[0043] S2. Place the inner template 12 on the bottom steel bar frame 11, then pass the rod of the bolt 7-3 through the through hole of the inner template 12, and place the embedded part 13 close to the outer surface of the inner template 12, turn the bolt 7-3, so that the top thread of the bolt 7-3 fits in the threaded hole of the embedded part 13, and then tighten the nut 7-2 to move the baffle 7-1 until the baffle 7-1 is pressed against the inner surface of the inner template 12;
[0044] S3. The side reinforcement frame 8 is made on both sides of the bottom reinforcement frame 11, and then the top reinforcement frame 9 is made at the top of the side reinforcement frame 8;
[0045] S4. The outer template 14 is fixedly connected to the outer mold bottom plate 4, and then the outer mold top plate 5 is fixedly connected to the top of the outer mold 14, and then the side sealing plate 2 is fixed to the outer mold bottom plate 4, the front and rear surfaces of the inner template 12;
[0046] S5. The through-tube 3 is inserted into the through-hole of the side sealing plate 2, and then concrete is poured from the filling port 6;
[0047] S6. After the concrete is completely solidified, the through pipe 3, the side sealing plate 2, the outer mold top plate 5, the outer mold 14, the fixing mechanism 7, the inner mold 12 are removed in sequence;
[0048] S7. Use equipment to remove the formed prefabricated cable well from the upper surface of the outer mold bottom plate 4, and then clean the surfaces of the outer mold bottom plate 4, the side sealing plate 2, the outer mold top plate 5, the outer mold plate 14, and the inner mold plate 12.
[0049] Before assembling the mold, it is necessary to spray the release agent on the surface of all parts that come into contact with the concrete to avoid difficulties in demolding.
[0050] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A multi-chamber assembled prefabricated cable well mold, comprising an I-beam bottom plate (1), characterized in that: The upper surface of the I-beam bottom plate (1) is provided with an outer mold bottom plate (4), the upper surface of the outer mold bottom plate (4) is provided with a bottom steel bar frame (11), the upper surface of the bottom steel bar frame (11) is provided with an inner mold plate (12), the two side surfaces of the inner mold plate (12) are provided with through circular holes, the inner side surface of the inner mold plate (12) is provided with a fixing mechanism (7), the outer side surface of the inner mold plate (12) is provided with an embedded part (13), the center of the embedded part (13) is provided with a threaded hole, the threaded hole of the embedded part (13) is communicated with the through hole on the side surface of the inner mold plate (12), the front and rear side surfaces of the outer mold bottom plate (4) are fixedly connected to the side sealing plate (2), the front side surface of the side sealing plate (2) is provided with a through circular hole, a through pipe (3) is provided in the through circular hole of the side sealing plate (2), and both ends of the through pipe (3) are on the outside of the inner mold plate (12).
2. A multi-chamber combined assembly type prefabricated cable well mold according to claim 1, characterized in that: The bottom reinforcement frame (11) is fixedly connected to the side reinforcement frames (8) near the top ends of both sides, and the side reinforcement frames (8) are located outside the inner template (12).
3. The multi-chamber assembled prefabricated cable well mold according to claim 1, characterized in that: The outer mold bottom plate (4) is fixedly connected to the outer mold plate (14) near the two side edges, and the top of the outer mold plate (14) is fixedly connected to the outer mold top plate (5), and a filling port (6) is provided on the upper surface of the outer mold top plate (5).
4. The multi-chamber assembled prefabricated cable well mold according to claim 1, characterized in that: The top end of the side steel bar frame (8) is fixedly connected to the top steel bar frame (9), and the top steel bar frame (9) is between the upper surface of the inner formwork (12) and the lower surface of the outer formwork top plate (5).
5. The multi-chamber assembled prefabricated cable well mold according to claim 1, characterized in that: The fixing mechanism (7) comprises a baffle (7-1), a nut (7-2) and a bolt (7-3); the screw rod of the bolt (7-3) passes through the through circular hole of the inner template (12); and the top end of the screw rod of the bolt (7-3) is threadedly engaged in the threaded hole of the embedded part (13).
6. The multi-chamber combined assembly type prefabricated cable well mold according to claim 5, characterized in that: The head of the bolt (7-3) is inside the inner template (12), the nut (7-2) is threadedly fitted on the rod of the bolt (7-3), and the nut (7-2) is inside the inner template (12).
7. The multi-chamber assembled prefabricated cable well mold according to claim 5, characterized in that: A through circular hole is arranged at the center of the baffle (7-1), and the rod of the bolt (7-3) passes through the through circular hole at the center of the baffle (7-1). The baffle (7-1) is between the nut (7-2) and the inner template (12).
8. The multi-chamber combined assembly type prefabricated cable well mold according to claim 1, characterized in that: A support frame (10) is fixedly connected to the inner surface of the inner template (12), the support frames (10) are in plurality, and the I-beam bottom plates (1) are in plurality.
9. The multi-chamber assembled prefabricated cable well mold according to claim 1, characterized in that: The side sealing plate (2) is in contact with the inner template (12), and the side sealing plate (2) and the inner template (12) are fixedly connected.
10. A prefabrication method according to any one of claims 1 to 9, characterized in that: The following specific prefabrication steps are included: S1. The outer mold base plate (4) is placed on a plane formed by a plurality of I-beam base plates (1), and then a bottom steel bar frame (11) is tied on the upper surface of the outer mold base plate (4); S2. Place the inner template (12) on the bottom steel bar frame (11), then pass the rod of the bolt (7-3) through the through-hole of the inner template (12), and place the embedded part (13) close to the outer surface of the inner template (12), turn the bolt (7-3) so that the top thread of the bolt (7-3) fits in the threaded hole of the embedded part (13), and then turn the nut (7-2) to drive the baffle (7-1) to move until the baffle (7-1) is pressed against the inner surface of the inner template (12); S3. A side steel frame (8) is formed on both sides of the bottom steel frame (11), and then a top steel frame (9) is formed at the top of the side steel frame (8); S4. The outer mold plate (14) is fixedly connected to the outer mold bottom plate (4), and then the outer mold top plate (5) is fixedly connected to the top of the outer mold plate (14), and then the side sealing plate (2) is fixed to the outer mold bottom plate (4) and the front and rear surfaces of the inner mold plate (12); S5. The through-tube (3) is inserted into the through-hole of the side sealing plate (2), and then concrete is poured from the filling port (6); S6. After the concrete is completely solidified, the through pipe (3), the side sealing plate (2), the outer formwork top plate (5), the outer formwork (14), the fixing mechanism (7), and the inner formwork (12) are removed in sequence; S7. Use equipment to remove the formed prefabricated cable well from the upper surface of the outer mold bottom plate (4), and then clean the surfaces of the outer mold bottom plate (4), the side sealing plate (2), the outer mold top plate (5), the outer mold plate (14), and the inner mold plate (12).