Drying and waterproofing method and system for intelligent air pipeline of new energy bus and application

By setting humidity sensors and electrical controllers at the intake end and air end of the new energy buses, in real -time detection and controlling air humidity, the lack of dehumidification and waterproof measures in the existing technology has been solved. The dry control of the passenger air compressor ensures the safety and stable output air pressure of the vehicle.

CN119373688APending Publication Date: 2025-01-28ANHUI ANKAI AUTOMOBILE
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411530113.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-30
Publication Date
2025-01-28

AI Technical Summary

Technical Problem

In the prior art, the air compressor of new energy buses lacks dehumidification and waterproofing measures, which leads to prone to accumulation of water or freezing in humid environments, resulting in braking failure and affecting the safety of the vehicle.

Method used

Adopting the dry water and waterproofing method of intelligent air pipe roads, setting humidity sensors and electronic control preheat heater at the air pressure end of the air pressure machine, and controlling the air humidity in real time to form an isolation and dehumidification area for preheating and dehumidification to ensure dry air to ensure dry air Enter the gas tank or discharge.

Benefits of technology

The precise and dry control of the air pressure and air end of the new energy passenger car and the air end of the air, avoiding the problem of braking failure caused by water accumulation or freezing, ensuring the safety of the vehicle and the formation of stable output air pressure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119373688A_ABST
    Figure CN119373688A_ABST
Patent Text Reader

Abstract

The invention discloses a drying and waterproofing method for an intelligent air pipeline of a new energy bus. The drying and waterproofing method comprises the following steps that the current air inlet humidity value of the inlet end of a vehicle-mounted air compressor is obtained; if the current air inlet humidity value is larger than the preset air inlet humidity threshold value, an isolation dehumidification area is formed in an air inlet pipe of the air compressor, and preheating dehumidification is conducted on the isolation dehumidification area through an electric control preheater; and dry air which is preheated and dehumidified in the isolation dehumidification area is input into an air storage tank of the air compressor. By the adoption of the technical scheme, vehicle-mounted intelligent control is convenient, detection data are fed back to the ECU control end module, and therefore automatic analysis and judgment can be carried out, the electric control preheating module and the air compressor execution end module can be controlled to carry out corresponding actions, it can be ensured that the humidity of sucked air and the humidity of output air are accurately controlled respectively, and the control efficiency is improved. Therefore, the air compressor can compress the dry air to store or discharge the dry air.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of transmission and distribution pipelines of new energy buses, and in particular to a drying and waterproofing method, system and application of intelligent gas pipelines of new energy buses. Background Art

[0002] The air compressor of new energy buses is a device used to compress air and store it in the on-board high-pressure gas cylinder to provide a high-pressure gas source for the vehicle's braking system and other units. New energy buses generally adopt the air brake principle. The pneumatic brake system is widely used in the braking process of buses, using high-pressure air compressed by the air compressor for braking. During the operation of the air compressor, the compressed high-temperature and high-pressure air must ensure that the water content is lower than the design standard to avoid the impact of compressed air with a high water content on the air pipeline and pneumatic components during the transportation process, thereby ensuring the safety of pneumatic brakes of new energy buses.

[0003] When driving new energy buses in coastal areas, the proportion of moisture in the air is relatively high. The air compressor is prone to continuously accumulate moisture in the air storage tank during operation. The continuous accumulation of high-pressure air with high moisture content and supply to the brake system is prone to water accumulation, which is easy to freeze in low temperatures in winter, causing blockage of the brake valve and air path, resulting in bus brake failure and seriously affecting vehicle driving safety. In the prior art, the air compressor lacks corresponding dehumidification and waterproofing measures at both the air inlet and outlet ends to reduce the moisture content in the compressed air, and cannot ensure that the air compressor can form a stable output air pressure to achieve the expected effect. Summary of the invention

[0004] The purpose of the present invention is to provide a drying and waterproofing method, system and application of an intelligent air pipeline of a new energy bus, so as to solve the problem that the prior art lacks corresponding dehumidification and waterproofing measures to reduce the water content in compressed air.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] The drying and waterproofing method of the intelligent air pipeline of the new energy bus includes the following steps:

[0007] S10, obtaining the current intake air humidity value at the inlet end of the vehicle-mounted air compressor;

[0008] S11. If the current intake air humidity value is greater than a preset intake air humidity threshold, an isolation dehumidification zone is formed in the air compressor intake pipe, and the isolation dehumidification zone is preheated and dehumidified by an electronically controlled preheater;

[0009] S12, inputting the dry air after preheating and dehumidification in the isolation dehumidification area into the air storage tank of the air compressor.

[0010] As a further solution of the present invention: the method for obtaining the current intake air humidity value in step S10 includes:

[0011] An intake gate valve 1 and an intake gate valve 2 are sequentially arranged in the air delivery direction of the intake pipe of the vehicle-mounted air compressor, wherein the intake gate valve 1 is in a normally open state, and the intake gate valve 2 is in a normally closed state, and the intake gate valve 1 and the intake gate valve 2 are electrically connected to the ECU respectively;

[0012] An intake air humidity sensor is arranged on the pipe section between the first intake gate valve and the second intake gate valve, and the intake air humidity sensor is used to obtain the current intake air humidity value and feed it back to the ECU.

[0013] As a further solution of the present invention: the method for preheating and dehumidifying the isolated dehumidification zone in step S11 includes:

[0014] The current intake humidity value obtained by the intake humidity sensor is greater than the preset intake humidity threshold, and the ECU electronically closes the intake gate valve 1. At this time, the pipe section between the intake gate valve 1 and the intake gate valve 2 is a closed cavity, so that an isolated dehumidification area is formed in the air compressor intake pipe;

[0015] The electronically controlled preheater is turned on by the ECU, and the isolated dehumidification area is preheated and dehumidified by the electronically controlled preheater.

[0016] As a further solution of the present invention: the method of inputting dry air into the air storage tank in step S12 includes:

[0017] If the current intake humidity value obtained by the intake humidity sensor is less than the preset intake humidity threshold, the ECU electronically opens the intake gate valve 2. At this time, the intake gate valve 1 is in a normally open state, and dry air below the preset intake humidity threshold is input into the air storage tank;

[0018] The humid air in the isolation and dehumidification area is preheated and dehumidified until the intake humidity sensor obtains a current intake humidity value greater than a preset intake humidity threshold value, and the ECU electronically opens the intake gate valve 2. At this time, the intake gate valve 1 is in an electronically controlled closed state, and dry air below the preset intake humidity threshold value is input into the air storage tank.

[0019] As a further solution of the present invention: when the humid air in the isolation and dehumidification zone is preheated and dehumidified, a temperature sensor is provided on the pipe section between the intake gate valve 1 and the intake gate valve 2, and the temperature sensor is used to obtain the intake temperature value of the isolation and dehumidification zone and feed it back to the ECU.

[0020] The waterproof system of the intelligent air pipeline of new energy buses includes:

[0021] The intake humidity detection module is used to measure the current intake humidity value at the inlet of the air compressor execution end module and feed it back to the ECU control end module;

[0022] The outlet humidity detection module is used to measure the current outlet humidity value at the outlet of the air compressor execution end module and feed it back to the ECU control end module;

[0023] An electrically controlled preheating module is used to preheat and dehumidify the isolated dehumidification area;

[0024] The air compressor execution end module is used for the air compressor to perform air suction, air compression, air storage and air discharge actions;

[0025] The ECU control end module is used to run the instruction generation program of the intake humidity detection module, the outlet humidity detection module, the electronic control preheating module and the air compressor execution end module. When the instruction generation program is executed by the ECU control end module, the steps of the drying and waterproofing method for the intelligent air pipeline of the new energy bus are implemented as described above.

[0026] The waterproof application of the intelligent air pipeline of the new energy bus includes an ECU, wherein the ECU is used to run the application scenario program of the intake humidity sensor, the outlet humidity sensor, the temperature sensor, the electronically controlled preheater and the air compressor, and the application scenario program is executed by the ECU to implement the drying and waterproofing method steps of the intelligent air pipeline of the new energy bus as described above;

[0027] Among them, the steps of waterproofing the outlet of the vehicle-mounted air compressor are as follows:

[0028] S20, obtaining the current outlet humidity value of the air storage tank outlet of the air compressor;

[0029] S21, if the current outlet humidity value is greater than the preset outlet humidity threshold, a reflux temporary storage area is formed in the air compressor outlet pipe, and the output air in the reflux temporary storage area is discharged to the air compressor inlet through the return air pipe, and preheated and dehumidified;

[0030] S22, inputting the output air in the reflux temporary storage area into a pneumatic brake system or an air conditioning refrigeration system.

[0031] As a further solution of the present invention: the method for obtaining the current intake air humidity value in step S20 includes:

[0032] An outlet gate valve 1 and an outlet gate valve 2 are sequentially arranged in the gas delivery direction of the outlet pipe of the vehicle-mounted air compressor, wherein the outlet gate valve 1 is in a normally closed state, the outlet gate valve 2 is in a normally closed state, and the outlet gate valve 1 and the outlet gate valve 2 are electrically connected to the ECU respectively;

[0033] An outlet air humidity sensor is provided on the pipe section between the outlet air gate valve 1 and the outlet air gate valve 2. The ECU electrically controls the outlet air gate valve 1 to open. The outlet air humidity sensor is used to obtain the current outlet air humidity value and feed it back to the ECU.

[0034] As a further solution of the present invention: the method for discharging the output air in the reflux temporary storage area into the air inlet of the air compressor in step S21 includes:

[0035] The outlet humidity sensor obtains that the current outlet humidity value is greater than the preset outlet humidity threshold, and the ECU opens the outlet gate valve 1 electronically and closes the outlet gate valve 1 electronically, so that a reflux temporary storage area is formed in the air compressor outlet pipe;

[0036] The reflux gate valve is opened by the ECU, and the output air in the reflux temporary storage area is discharged into the air intake port of the air compressor through the return air pipe, and preheated and dehumidified.

[0037] As a further solution of the present invention: the method for applying the output air in the reflux temporary storage area in step S22 includes:

[0038] If the outlet humidity sensor obtains a current outlet humidity value that is less than a preset outlet humidity threshold, the ECU electronically opens the outlet valve 2. At this time, the outlet valve 1 is in a normally open state, and dry air below the preset outlet humidity threshold is output for application;

[0039] The humid output air below the preset outlet air humidity threshold in the reflux temporary storage area is refluxed, and the electric control preheater is turned on in the air intake pipe for preheating and dehumidification until the condition that the outlet air humidity sensor obtains a current outlet air humidity value less than the preset outlet air humidity threshold is met, and the dry air below the preset outlet air humidity threshold is output for application.

[0040] The beneficial effects of the present invention are as follows: the on-board intelligent control is convenient, and the detection data is fed back to the ECU control end module, so that automatic analysis and judgment can be performed to control the electronic control preheating module and the air compressor execution end module to perform corresponding actions, and the humidity of the inhaled air and the humidity of the output air can be ensured to be accurately controlled respectively, so that the air compressor can compress dry air for storage or discharge, meeting the needs of new energy buses traveling in coastal areas, and the air dryness can be ensured from the air inlet and outlet ends of the air compressor, so as to ensure that the air compressor can form a stable output air pressure to achieve the expected effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The present invention will be further described below in conjunction with the accompanying drawings.

[0042] Figure 1 It is a schematic flow chart of the drying and waterproofing method of the intelligent air pipeline of the new energy bus in Example 1;

[0043] Figure 2 is a schematic diagram of the air compressor structure in Example 1;

[0044] Figure 3 It is a framework diagram of the waterproof system of the intelligent air pipeline of the new energy bus in Example 2;

[0045] Figure 4 This is a waterproof application scenario diagram of the intelligent air pipeline of a new energy bus in Example 3;

[0046] Figure 5 It is a schematic diagram of the application process at the outlet end of the air compressor in Example 3.

[0047] In the figure: 1. Air compressor; 2. Electronically controlled preheater; 3. ECU; 4. Inlet humidity sensor; 5. Outlet humidity sensor; 6. Temperature sensor;

[0048] 10. Inlet pipe; 11. Inlet gate valve 1; 12. Inlet gate valve 2; 13. Drain pipe; 14. Drain gate valve; 15. Outlet pipe; 16. Outlet gate valve 1; 17. Outlet gate valve 2; 18. Return pipe; 19. Return gate valve;

[0049] 100, air compressor execution end module; 200, electronic control preheating module; 300, ECU control end module; 400, intake air humidity detection module; 500, outlet air humidity detection module. DETAILED DESCRIPTION

[0050] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] In the description of the present invention, it should be understood that the terms indicating orientation or positional relationship are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention; in the description of the present invention, the meaning of "multiple" and "several" is at least two, for example two, three, etc., unless otherwise clearly and specifically defined.

[0052] Example 1

[0053] See also Figure 1 and 2 As shown, the present invention is a drying and waterproofing method for an intelligent air pipeline of a new energy bus, comprising the following steps:

[0054] S10, obtaining the current intake air humidity value at the inlet end of the vehicle-mounted air compressor 1.

[0055] The method for obtaining the current intake air humidity value in this step includes: an intake gate valve 11 and an intake gate valve 2 12 are sequentially arranged on the air delivery direction of the intake pipe 10 of the vehicle-mounted air compressor 1, wherein the intake gate valve 11 is in a normally open state, and the intake gate valve 2 12 is in a normally closed state, and the intake gate valve 11 and the intake gate valve 2 12 are electrically connected to the ECU 3 respectively; an intake air humidity sensor 4 is arranged on the pipe section between the intake gate valve 11 and the intake gate valve 2 12, and the intake air humidity sensor 4 is used to obtain the current intake air humidity value and feed it back to the ECU 3.

[0056] S11. If the current intake air humidity value is greater than a preset intake air humidity threshold, an isolation dehumidification zone is formed in the intake pipe 10 of the air compressor 1, and the isolation dehumidification zone is preheated and dehumidified by the electronically controlled preheater 2.

[0057] In this step, the method for preheating and dehumidifying the isolated dehumidification zone includes: the intake humidity sensor 4 obtains that the current intake humidity value is greater than the preset intake humidity threshold, and the ECU3 electrically controls the intake gate valve 11 to close. At this time, the pipe section between the intake gate valve 11 and the intake gate valve 2 12 is a closed cavity, so that an isolated dehumidification zone is formed in the intake pipe 10 of the air compressor 1; the electronically controlled preheater 2 is turned on by the ECU3, and the isolated dehumidification zone is preheated and dehumidified by the electronically controlled preheater 2.

[0058] S12, inputting the dry air after preheating and dehumidification in the isolated dehumidification area into the air storage tank of the air compressor 1.

[0059] In this step, the method of inputting dry air into the air storage tank includes: first, if the intake humidity sensor 4 obtains a current intake humidity value that is less than the preset intake humidity threshold, the ECU3 electronically opens the intake gate valve 2 12. At this time, the intake gate valve 11 is in a normally open state, and dry air below the preset intake humidity threshold is input into the air storage tank; second, the humid air in the isolation dehumidification area is preheated and dehumidified until the intake humidity sensor 4 obtains a current intake humidity value that is greater than the preset intake humidity threshold, and the ECU3 electronically opens the intake gate valve 2 12. At this time, the intake gate valve 11 is in an electronically closed state, and dry air below the preset intake humidity threshold is input into the air storage tank.

[0060] During the use of the waterproof method of the present application, the inhaled air of the air intake pipe 10 of the air compressor 1 is detected in real time to determine whether the humidity of the inhaled air is within the preset air intake humidity threshold. If it is greater than the preset air intake humidity threshold, an isolation dehumidification zone is formed in the air intake pipe 10 of the air compressor 1, and the isolation dehumidification zone is preheated and dehumidified by the electronically controlled preheater 2. The isolation dehumidification zone is easy to operate to control the dry inhaled air, and can ensure that the humidity of the inhaled air is accurately controlled, so that the air compressor 1 can compress the dry air for gas storage, meet the needs of new energy buses running in coastal areas, ensure that the inhaled air is dry from the air intake end of the air compressor 1, and ensure that the air compressor 1 can form a stable output air pressure to achieve the expected effect.

[0061] During the use of the waterproof method of the present application, when the humid air in the isolation dehumidification zone is preheated and dehumidified, a temperature sensor 6 is provided on the pipe section between the air intake gate valve 11 and the air intake gate valve 2 12. The temperature sensor 6 is used to obtain the intake temperature value of the isolation dehumidification zone and feed it back to the ECU 3. When the air compressor 1 is in normal air intake, the intake temperature value of the isolation dehumidification zone obtained by the temperature sensor 6 will not exceed the preset intake temperature threshold. When the preheating and dehumidification operation is performed in the isolation dehumidification zone, the intake temperature value of the isolation dehumidification zone obtained by the temperature sensor 6 may exceed the preset intake temperature threshold. Generally, the preset intake temperature threshold is 40°C. In this way, the internal structural components of the air compressor 1 will not be damaged due to excessive temperature. Therefore, it is necessary to detect the intake temperature through the temperature sensor 6 and control the intake compression and storage below the preset intake temperature threshold.

[0062] During the use of the waterproof method of the present application, water will be generated during the preheating and dehumidification process of the isolation dehumidification zone. By connecting the drain pipe 13 to the air intake pipe 10, the drain gate valve 14 can be electronically opened through the ECU3 to facilitate the discharge of the water in the isolation dehumidification zone from the drain pipe 13, thereby preventing the accumulated water from affecting the preheating and dehumidification effect of the isolation dehumidification zone.

[0063] Example 2

[0064] Combination Figure 3As shown, the present invention also provides a waterproof system for an intelligent air pipeline of a new energy bus, including an intake humidity detection module 400, an outlet humidity detection module 500, an electric control preheating module 200, an air compressor execution end module 100 and an ECU control end module 300. The intake humidity detection module 400 is used for the current intake humidity value at the inlet end of the air compressor execution end module 100, and is fed back to the ECU control end module 300. The outlet humidity detection module 500 is used for the current outlet humidity value at the outlet end of the air compressor execution end module 100, and is fed back to the ECU control end module 300. The U control end module 300 and the electric control preheating module 200 are used to preheat and dehumidify the isolated dehumidification area. The air compressor execution end module 100 is used for the air compressor 1 to perform air intake, air compression, air storage and air discharge actions. The ECU control end module 300 is used to run the instruction generation program of the air intake humidity detection module 400, the air outlet humidity detection module 500, the electric control preheating module 200 and the air compressor execution end module 100. When the instruction generation program is executed by the ECU control end module 300, the drying and waterproofing method steps of the intelligent air pipeline of the new energy bus as mentioned above are implemented.

[0065] The waterproof system of the present application is convenient for intelligent control, and the detection data is fed back to the ECU control end module 300, so that analysis and judgment can be performed to control the electronically controlled preheating module 200 and the air compressor execution end module 100 to perform corresponding actions, which can ensure that the humidity of the inhaled air and the humidity of the output air are respectively precisely controlled, so that the air compressor 1 can compress dry air for storage or discharge, meeting the needs of new energy buses running in coastal areas. The air can be kept dry from the air inlet and outlet ends of the air compressor 1, thereby ensuring that the air compressor 1 can form a stable output air pressure to achieve the expected effect.

[0066] Example 3

[0067] Combination Figure 4 and Figure 5 As shown, the present invention also provides a waterproof application of an intelligent air pipeline for new energy buses, including an ECU3, wherein the ECU3 is used to run an application scenario program of an intake humidity sensor 4, an outlet humidity sensor 5, a temperature sensor 6, an electronically controlled preheater 2 and an air compressor 1. When the application scenario program is executed by the ECU3, the steps of the drying and waterproofing method for the intelligent air pipeline of the new energy bus are implemented as described above.

[0068] During the waterproof application process of the present application, the humidity of the inhaled air can be precisely controlled so that the air compressor 1 can compress the dry air for air storage, meeting the needs of new energy buses traveling in coastal areas. The inhaled air is ensured to be dry from the air inlet end of the air compressor 1, ensuring that the air compressor 1 can form a stable output air pressure to achieve the expected effect.

[0069] The steps of the waterproof method for the outlet of the vehicle-mounted air compressor 1 are as follows:

[0070] S20, obtaining the current outlet air humidity value of the air storage tank outlet of the air compressor 1.

[0071] The method for obtaining the current intake air humidity value in this step includes: an outlet gate valve 16 and an outlet gate valve 2 17 are sequentially arranged on the air delivery direction of the outlet pipe 15 of the vehicle-mounted air compressor 1, wherein the outlet gate valve 16 is in a normally closed state, and the outlet gate valve 2 17 is in a normally closed state, and the outlet gate valve 16 and the outlet gate valve 2 17 are electrically connected to the ECU3 respectively; an outlet air humidity sensor 5 is arranged on the pipe section between the outlet gate valve 16 and the outlet gate valve 2 17, and the ECU3 electronically controls the outlet gate valve 16 to open, and the outlet air humidity sensor 5 is used to obtain the current outlet air humidity value and feed it back to the ECU3.

[0072] S21. If the current outlet humidity value is greater than the preset outlet humidity threshold, a reflux temporary storage area is formed in the outlet pipe 15 of the air compressor 1, and the output air in the reflux temporary storage area is discharged to the inlet pipe 10 of the air compressor 1 through the return pipe 18, and preheated and dehumidified.

[0073] In this step, the method for discharging the output air in the reflux temporary storage area into the air inlet pipe 10 of the air compressor 1 includes: the outlet humidity sensor 5 obtains that the current outlet humidity value is greater than the preset outlet humidity threshold, and the ECU3 electrically controls the outlet gate valve 16 to open and the outlet gate valve 16 to close, so that a reflux temporary storage area is formed in the outlet pipe 15 of the air compressor 1; the reflux gate valve 19 is opened by the ECU3, and the output air in the reflux temporary storage area is discharged into the air inlet pipe 10 of the air compressor 1 through the return pipe 18, and preheating and dehumidification are performed.

[0074] S22, inputting the output air in the reflux temporary storage area into the pneumatic brake system or the air conditioning refrigeration system.

[0075] In this step, the method for applying the output air in the reflux temporary storage area includes: first, if the outlet air humidity sensor 5 obtains a current outlet air humidity value that is less than the preset outlet air humidity threshold, the ECU 3 electronically controls the outlet air gate valve 2 17 to open. At this time, the outlet air gate valve 16 is in a normally open state, and the dry air below the preset outlet air humidity threshold is output for application; second, the humid output air below the preset outlet air humidity threshold in the reflux temporary storage area is refluxed, and the electronically controlled preheater 2 is opened in the intake pipe 10 for preheating and dehumidification, until the condition that the outlet air humidity sensor 5 obtains a current outlet air humidity value that is less than the preset outlet air humidity threshold is met, and the dry air below the preset outlet air humidity threshold is output for application.

[0076] During the waterproof application process of the present application, the exhaust air of the air outlet pipe 15 of the air compressor 1 can be detected in real time to determine whether the exhaust air humidity is within the preset exhaust air humidity threshold. If it is greater than the preset exhaust air humidity threshold, a reflux temporary storage area is formed in the air outlet pipe 15 of the air compressor 1 to return the exhaust air to the air inlet pipe 10, and the reflux circulating air is preheated and dehumidified by the electronically controlled preheater 2, which can ensure that the humidity of the exhaust air is precisely controlled, so that the air compressor 1 can discharge dry compressed air to meet the needs of new energy buses running in coastal areas, and the exhaust air can be ensured to be dry from the air outlet end of the air compressor 1, ensuring that the air compressor 1 can form a stable output air pressure to achieve the expected effect.

[0077] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A drying and waterproofing method for intelligent air pipelines of new energy buses, characterized in that: The following steps are involved: S10, obtaining the current intake air humidity value at the inlet end of the vehicle-mounted air compressor (1); S11, if the current intake air humidity value is greater than a preset intake air humidity threshold value, an isolation dehumidification zone is formed in the intake pipe (10) of the air compressor (1), and the isolation dehumidification zone is preheated and dehumidified by an electrically controlled preheater (2); S12, inputting the dry air after preheating and dehumidification in the isolation dehumidification zone into the air storage tank of the air compressor (1).

2. The drying and waterproofing method for intelligent air pipeline of new energy buses according to claim 1 is characterized in that: The method for obtaining the current intake air humidity value in step S10 includes: An air intake gate valve 1 (11) and an air intake gate valve 2 (12) are sequentially arranged in the air delivery direction of the air intake pipe (10) of the vehicle-mounted air compressor (1), wherein the air intake gate valve 1 (11) is in a normally open state, and the air intake gate valve 2 (12) is in a normally closed state, and the air intake gate valve 1 (11) and the air intake gate valve 2 (12) are electrically connected to the ECU (3) respectively; An intake air humidity sensor (4) is provided on the pipe section between the intake gate valve 1 (11) and the intake gate valve 2 (12), and the intake air humidity sensor (4) is used to obtain a current intake air humidity value and feed it back to the ECU (3).

3. The drying and waterproofing method of the intelligent air pipeline of the new energy bus according to claim 2 is characterized in that: The method for preheating and dehumidifying the isolated dehumidification area in step S11 includes: When the current intake humidity value obtained by the intake humidity sensor (4) is greater than a preset intake humidity threshold, the ECU (3) electrically controls the intake gate valve 1 (11) to close. At this time, the pipe section between the intake gate valve 1 (11) and the intake gate valve 2 (12) is a closed cavity, so that an isolated dehumidification zone is formed in the intake pipe (10) of the air compressor (1); The electronically controlled preheater (2) is turned on by the ECU (3), and the electronically controlled preheater (2) is used to preheat and dehumidify the isolated dehumidification area.

4. The drying and waterproofing method for intelligent air pipeline of new energy buses according to claim 3 is characterized in that: The method of inputting dry air into the air storage tank in step S12 includes: If the current intake humidity value obtained by the intake humidity sensor (4) is less than a preset intake humidity threshold, the ECU (3) electrically controls the intake gate valve 2 (12) to open. At this time, the intake gate valve 1 (11) is in a normally open state, and dry air below the preset intake humidity threshold is input into the air storage tank; The humid air in the isolated dehumidification area is preheated and dehumidified until the intake humidity sensor (4) obtains a current intake humidity value greater than a preset intake humidity threshold value, and the ECU (3) electrically controls the intake gate valve 2 (12) to open. At this time, the intake gate valve 1 (11) is in an electrically controlled closed state, and dry air below the preset intake humidity threshold value is input into the air storage tank.

5. The drying and waterproofing method for intelligent air pipeline of new energy buses according to claim 4 is characterized in that: When the humid air in the isolation and dehumidification zone is preheated and dehumidified, a temperature sensor (6) is provided on the pipe section between the first intake gate valve (11) and the second intake gate valve (12), and the temperature sensor (6) is used to obtain the intake temperature value of the isolation and dehumidification zone and feed it back to the ECU (3).

6. The waterproof system of the intelligent air pipeline of new energy buses is characterized by: include: An intake air humidity detection module (400) is used to detect the current intake air humidity value at the inlet end of the air compressor execution end module (100) and feed it back to the ECU control end module (300); An outlet air humidity detection module (500) is used to detect the current outlet air humidity value at the outlet of the air compressor execution end module (100) and feed it back to the ECU control end module (300); An electrically controlled preheating module (200) is used to preheat and dehumidify the isolated dehumidification area; An air compressor execution end module (100) is used for the air compressor (1) to execute air intake, air compression, air storage and air discharge actions; The ECU control end module (300) is used to run the instruction generation program of the intake humidity detection module (400), the outlet humidity detection module (500), the electronically controlled preheating module (200) and the air compressor execution end module (100); when the instruction generation program is executed by the ECU control end module (300), the drying and waterproofing method steps of the intelligent air pipeline of the new energy bus are implemented as described in any one of claims 1 to 5.

7. Waterproof application of intelligent air pipeline of new energy buses, characterized by: The invention comprises an ECU (3), wherein the ECU (3) is used to run an application scenario program of an intake humidity sensor (4), an outlet humidity sensor (5), a temperature sensor (6), an electronically controlled preheater (2) and an air compressor (1), wherein when the application scenario program is executed by the ECU (3), the steps of the drying and waterproofing method for an intelligent air pipeline of a new energy bus are implemented; The steps of the waterproofing method for the outlet of the vehicle-mounted air compressor (1) are as follows: S20, obtaining the current outlet humidity value of the air at the outlet of the air storage tank of the air compressor (1); S21, if the current outlet humidity value is greater than a preset outlet humidity threshold, a reflux temporary storage area is formed in the outlet pipe (15) of the air compressor (1), and the output air in the reflux temporary storage area is discharged to the inlet pipe (10) of the air compressor (1) through the return pipe (18), and preheating and dehumidification are performed; S22, inputting the output air in the reflux temporary storage area into a pneumatic brake system or an air conditioning refrigeration system.

8. The waterproof application of the intelligent air pipeline of the new energy bus according to claim 7 is characterized in that: The method for obtaining the current intake air humidity value in step S20 includes: An outlet gate valve 1 (16) and an outlet gate valve 2 (17) are sequentially arranged in the air delivery direction of an outlet pipe (15) of a vehicle-mounted air compressor (1), wherein the outlet gate valve 1 (16) is in a normally closed state, and the outlet gate valve 2 (17) is in a normally closed state, and the outlet gate valve 1 (16) and the outlet gate valve 2 (17) are electrically connected to an ECU (3) respectively; An outlet air humidity sensor (5) is provided on the pipe section between the outlet air gate valve 1 (16) and the outlet air gate valve 2 (17), and the ECU (3) electrically controls the outlet air gate valve 1 (16) to open. The outlet air humidity sensor (5) is used to obtain a current outlet air humidity value and feed it back to the ECU (3).

9. The waterproof application of the intelligent air pipeline of the new energy bus according to claim 7 is characterized in that: The method for discharging the output air in the reflux temporary storage area into the air intake pipe (10) of the air compressor (1) in step S21 comprises: When the outlet humidity sensor (5) obtains a current outlet humidity value greater than a preset outlet humidity threshold, the ECU (3) electrically controls an outlet gate valve (16) to open and electrically controls an outlet gate valve (16) to close, thereby forming a reflux temporary storage area in the outlet pipe (15) of the air compressor (1); The ECU (3) opens the return gate valve (19), and the output air in the return temporary storage area is discharged to the air intake pipe (10) of the air compressor (1) through the return air pipe (18), and preheated and dehumidified.

10. The waterproof application of the intelligent air pipeline of the new energy bus according to claim 7 is characterized in that: The method for applying the output air in the reflux temporary storage area in step S22 includes: If the outlet humidity sensor (5) obtains a current outlet humidity value that is less than a preset outlet humidity threshold, the ECU (3) electrically controls the outlet valve 2 (17) to open. At this time, the outlet valve 1 (16) is in a normally open state, and dry air below the preset outlet humidity threshold is output for use; The humid output air below the preset outlet humidity threshold in the reflux temporary storage area is refluxed, and the electrically controlled preheater (2) is turned on in the air inlet pipe (10) for preheating and dehumidification until the outlet humidity sensor (5) obtains a current outlet humidity value less than the preset outlet humidity threshold, and the dry air below the preset outlet humidity threshold is output for application.

Citation Information

Cited By

  • Improved bubble type water level measuring instrument

    CN120213159A