Ecological slope protection structure for river regulation and ecological slope protection construction method

By adopting an ecological slope protection structure in river management, including a composite waterproofing board slope protection frame and planting foundation, the problems of water pollution and high construction difficulty caused by traditional slope protection methods are solved, and rapid construction and ecological governance of river slope protection are achieved.

CN119392652APending Publication Date: 2025-02-07ECOLOGICAL ENG CO LTD OF CCCC FIRST HARBOR ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411711335.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-27
Publication Date
2025-02-07

AI Technical Summary

Technical Problem

Traditional river slope protection methods use a large amount of solid-state protective materials, which leads to water environmental pollution, cumbersome construction processes, high costs, and long construction cycles, which are prone to flooding.

Method used

An ecological slope protection structure is adopted, including a slope protection frame and a planting foundation. The slope protection frame is composed of a composite waterproof board. The planting foundation forms a planting groove through the substrate and the groove board to plant vegetation. This structure simplifies the construction process, reduces the construction difficulty and cost, and achieves rapid molding.

Benefits of technology

The rapid construction of river slope protection has been achieved, the negative impact of slope protection on the river ecological environment has been reduced, the use of solid-state protective materials has been significantly reduced, and the construction efficiency and overall safety have been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119392652A_ABST
    Figure CN119392652A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of ecological slope protection, and relates to an ecological slope protection structure for river regulation and an ecological slope protection construction method. The ecological slope protection structure comprises a slope protection frame and a vegetation protection slope. The slope protection frame comprises two side panels which are oppositely arranged, a top panel, a bottom panel and a back frame plate, a first baffle which is turned downwards is arranged at the front end of the top panel, a second baffle which is turned upwards is arranged at the front end of the bottom panel, and the top surface of the second baffle is higher than a preset waterline of a river channel; the bottom panel is connected with the bottom wall of the foundation trench, the back frame plate is of a square frame structure, and a preset gap is reserved between the slope protection frame and the side wall of the foundation trench; the vegetation slope protection comprises a vegetation foundation, the vegetation foundation comprises a base plate connected with the first baffle and the second baffle and a plurality of groove plates arranged on the front side of the base plate, and a plurality of planting grooves are formed between the vegetation foundation and the slope protection frame; the interior of the slope protection frame and the preset gap in the rear side are filled with earthwork during excavation of the foundation trench; the slope protection frame and the vegetation foundation are both made of composite waterproof plates. Rapid construction of the riverway slope protection can be achieved, and the negative influence of the slope protection on the ecological environment of the riverway is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of ecological slope protection, and in particular relates to an ecological slope protection structure for river channel management and an ecological slope protection construction method. Background Art

[0002] In the process of river management, slope protection projects are a widely used infrastructure construction; the overall safety of river protection plays a key role in its performance in subsequent flood prevention, flood control and other related aspects.

[0003] The traditional slope protection method is to add a series of protective walls and slopes on the banks on both sides of the river. The slopes are mostly made of layered concrete. This protective measure plays a solid protective role. However, although this slope protection method can achieve the basic function of flood prevention and control, the large-scale use of solid protective materials will bring obvious polluting elements to the water environment, which is extremely unfavorable to the ecological development of the river, thus bringing a series of negative impacts to the water environment and other ecosystems; in addition, the construction process of this slope protection method is relatively cumbersome, the construction is difficult, the construction cost is high, and the concrete pouring and solidification speed is slow, resulting in a long construction period for the slope protection project, which is prone to flooding problems. Summary of the invention

[0004] In view of the shortcomings existing in the related technologies, the present invention provides an ecological slope protection structure and an ecological slope protection construction method for river management, aiming to achieve rapid construction of river slope protection and reduce the negative impact of slope protection on the river ecological environment.

[0005] The present invention provides an ecological slope protection structure for river channel management, which is arranged in a foundation trench excavated at a river channel bank slope. The ecological slope protection structure comprises:

[0006] The slope protection frame comprises two oppositely arranged side panels, a top panel connected between the upper parts of the two side panels, a bottom panel connected between the lower parts of the two side panels, and a back frame panel connected between the two side panels on the sides away from the river channel; the end surfaces of the side panels, the top panel and the bottom panel facing the river channel are coplanar slope surfaces; a first baffle plate folded downward is provided at one end of the top panel facing the river channel, and a second baffle plate folded upward is provided at one end of the bottom panel facing the river channel, and the top surface height of the second baffle plate is higher than a preset water level line of the river channel; the bottom panel is used to be connected to the bottom wall of the base trench, and the back frame panel is a square frame structure; a preset gap is left between the slope protection frame and the side walls of the base trench;

[0007] The vegetation slope protection comprises a vegetation foundation; the vegetation foundation comprises a base plate and a plurality of groove plates, the upper and lower parts of the base plate are respectively connected to the inner wall of the first baffle plate and the second baffle plate on the side away from the river channel, and the plurality of groove plates are connected to the end surface of the base plate facing the river channel at intervals in the upper and lower parts, so that a plurality of planting grooves are formed between the vegetation foundation and the slope protection frame; and vegetation is planted in each planting groove;

[0008] The inner cavity of the slope protection frame and the preset gap between the slope protection frame and the side wall of the foundation trench are filled with earth excavated during the foundation trench excavation; the side panels, top panels, bottom panels, back frame panels, base panels and trench panels are all composite waterproof panels.

[0009] In some of the embodiments, the top panel and the two side panels, the bottom panel and the two side panels, and the back frame panel and the two side panels are all connected by mortise and tenon structures, and the top panel and the bottom panel are horizontally inserted between the two side panels in a direction away from the river channel, and the back frame panel is vertically inserted between the two side panels.

[0010] In some of the embodiments, a plurality of first bolt through holes are arranged on the bottom panel; and first bolts corresponding to the first bolt through holes are pre-embedded on the bottom wall of the base groove.

[0011] In some of the embodiments, a plurality of second bolt through holes are arranged on the side panel.

[0012] In some of the embodiments, a drainage groove is recessed on the side of the side panel facing away from the inner cavity of the slope protection frame, and the drainage groove extends downwardly in a direction toward the river channel.

[0013] In some of the embodiments, a plurality of diagonal bracing members are arranged between the end surface of the base plate facing away from the river channel and the bottom plate.

[0014] In some of the embodiments, a plurality of weight-reducing grooves are concavely formed on the end surface of the substrate facing away from the river channel, and a plurality of reinforcing ribs are disposed in each of the weight-reducing grooves.

[0015] In some of the embodiments, the back frame plate includes two side frames arranged opposite to each other, a top frame connected between the upper portions of the two side frames, and a bottom frame connected between the lower portions of the two side frames, and the two side frames are respectively connected to the two side panel plates; the back frame plate also includes multiple reinforcement frames, and the reinforcement frames are connected between the top frame and the bottom frame or between the two side frames.

[0016] The present invention also provides an ecological slope protection construction method for river management, which is applicable to the above-mentioned ecological slope protection structure, including a foundation trench construction step and an ecological slope protection structure construction step; wherein:

[0017] The steps of foundation trench construction include:

[0018] Measure and lay out the edges of the foundation pit according to the design drawings;

[0019] Excavation of foundation trench: excavation of foundation trench is carried out according to the laid out foundation trench edge line until the preset foundation trench depth is reached; the earthwork during foundation trench excavation is piled nearby;

[0020] Pre-embedding of first bolts and pouring of bottom concrete: burying a plurality of first bolts on the bottom surface of the foundation trench according to the design drawings; pouring of bottom concrete on the bottom surface of the foundation trench;

[0021] The construction steps of ecological slope protection structure include:

[0022] The slope protection frame and the vegetation foundation are installed by inserting the bottom panel into the two side panels, and then placing it on the bottom concrete, and the first bolt through holes on the bottom panel are set outside the first bolts one by one, and the bottom panel is pressed onto the bottom concrete by tightening the nuts; then the top panel is inserted into the two side panels; then the vegetation foundation is lowered from the preset gap, and then pushed between the two side panels, and the base plate is connected to the first baffle and the second baffle; then the back frame is inserted into the two side panels; thus, the slope protection frame and the vegetation foundation of an ecological slope protection structure are installed in the base groove; in this way, the slope protection frames and the vegetation foundation of multiple ecological slope protection structures are installed in the base groove, and two adjacent slope protection frames are connected to each other;

[0023] Backfilling: the soil excavated during foundation trench excavation is first backfilled into the inner cavity of the slope protection frame through the preset gap, and then the preset gap is backfilled with soil;

[0024] Planting vegetation: Fill each planting trough with planting soil and then plant vegetation.

[0025] In some of the embodiments, the construction steps of the ecological slope protection structure also include, after the backfilling step is completed, piling soil and rocks on the slope surface of each slope protection frame below the preset water level line of the river channel to perform a foot pressing operation on it.

[0026] Based on the above technical scheme, the ecological slope protection structure and ecological slope protection construction method for river management in the embodiments of the present invention simplify the river slope protection construction process, realize rapid construction, and reduce the negative impact of slope protection on the river ecological environment, thereby achieving the technical effect of rapid prototyping and ecological management. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0028] Figure 1 This is a structural schematic diagram of an ecological slope protection structure for river management of the present invention;

[0029] Figure 2This is a second structural diagram of the ecological slope protection structure for river management of the present invention;

[0030] Figure 3 It is a structural cross-sectional view of the ecological slope protection structure for river management of the present invention;

[0031] Figure 4 It is a structural schematic diagram of the slope protection frame in the present invention;

[0032] Figure 5 It is a structural explosion diagram of the slope protection frame in the present invention;

[0033] Figure 6 The first structural diagram of the planting base in the present invention;

[0034] Figure 7 The second structural diagram of the planting base in the present invention;

[0035] Figure 8 The present invention is a flow chart of the ecological slope protection construction method for river management.

[0036] In the figure:

[0037] 10. Base trench; 11. Trench bottom wall; 12. Trench side wall; 20. Slope protection frame; 21. Side panel; 211. Second bolt hole; 212. Drainage trough; 22. Top panel; 221. First baffle plate; 23. Bottom panel; 231. Second baffle plate; 232. First bolt hole; 24. Back frame; 241. Side frame; 242. Top frame; 243. Bottom frame; 244. Reinforcement frame; 25. Diagonal brace; 26. Mortise; 27. Tenon; 28. First bolt; 29. ​​Fastening nut; 30. Vegetation slope protection; 31. Vegetation foundation; 311. Base plate; 3111. Weight reduction trough; 3112. Reinforcement rib; 312. Trench plate; 313. Planting trough; 32. Vegetation. DETAILED DESCRIPTION

[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0039] In the description of the present invention, it should be understood that the terms "center", "lateral", "longitudinal", "up", "down", "top", "bottom", "inside", "outside", "left", "right", "front", "back", "vertical", "horizontal", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0040] The terms "first", "second", etc. are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first", "second", etc. may explicitly or implicitly include one or more of the features.

[0041] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0042] refer to Figure 1-Figure 8 As shown, the present invention provides an ecological slope protection structure for river channel management, which is arranged in a foundation trench 10 excavated at a river channel bank slope. The ecological slope protection structure includes a slope protection frame 20 and a vegetation foundation 31.

[0043] The slope protection frame 20 includes a top panel 22, a bottom panel 23, a back frame 24 and two side panels 21; wherein the two side panels 21 are arranged opposite to each other, the top panel 22 is connected between the upper parts of the two side panels 21, the bottom panel 23 is connected between the lower parts of the two side panels 21, and the back frame 24 is connected between the two sides of the two side panels 21 away from the river channel; the front end surfaces of the side panels 21, the top panel 22 and the bottom panel 23, i.e., the end surfaces facing the river channel, are slope surfaces in a coplanar state. A first baffle 221 folded downward is provided at one end of the top panel 22 facing the river channel, and a second baffle 231 folded upward is provided at one end of the bottom panel 23 facing the river channel, and the top surface height of the second baffle 231 is higher than the preset water level line of the river channel. The bottom plate 23 of the slope protection frame 20 is used to connect with the bottom wall 11 of the base trench 10 to achieve the connection between the slope protection frame 20 and the base trench 10; the back frame plate 24 is a square frame structure, that is, there is a hollow opening structure on the back frame plate 24. A preset gap D is left between the slope protection frame 20 and the side wall 12 of the base trench 10, that is, the back frame plate 24 does not fit the side wall 12 of the base trench 10.

[0044] The vegetation slope protection 30 includes a vegetation foundation 31; the vegetation foundation 31 includes a base plate 311 and a plurality of groove plates 312. The base plate 311 is located inside the slope protection frame 20 and connected between the top panel 22 and the bottom panel 23. Specifically, the upper part of the base plate 311 is attached to the inner wall of the first baffle 221 on the side away from the river channel, and the lower part of the base plate 311 is attached to the inner wall of the second baffle 231 on the side away from the river channel. The front end surface of the base plate 311, i.e., the end surface facing the river channel, is parallel to the slope surface of the slope protection frame 20. Through the arrangement of the first baffle 221 and the second baffle 231, the convenience and stability of the connection between the base plate 311 and the top panel 22 and the bottom panel 23 are achieved, and the base plate 311 is reliably limited. The connection method between the base plate 311 and the first baffle 221 and the second baffle 231 includes but is not limited to bolt connection. A plurality of slot plates 312 are connected to the end surface of the base plate 311 facing the river channel at intervals, thereby forming a plurality of planting slots 313 between the vegetation base 31 and the slope protection frame 20; each planting slot 313 is planted with vegetation 32. It can be understood by those skilled in the art that the planting slots 313 can be first filled with planting soil, and then grass seeds can be sown, shrubs can be planted, or turf can be spread at a suitable planting time; or vegetation bags filled with planting soil and vegetation seeds can be directly laid.

[0045] The inner cavity of the slope protection frame 20 is filled with earth when the foundation trench 10 is excavated; further, the vegetation foundation 31 is connected to the slope protection frame 20, so that the slope protection frame 20 forms an inner cavity with only a hollow opening on the back frame plate 24; after the slope protection frame 20 and the vegetation foundation 31 are installed, earth is filled into the inner cavity of the slope protection frame 20 from the hollow opening on the back frame plate 24. The preset gap D between the slope protection frame 20 and the side wall 12 of the foundation trench 10 is also filled with earth when the foundation trench 10 is excavated. Thus, an ecological slope protection structure is set in the excavated foundation trench 10 at the river bank slope.

[0046] Furthermore, the side panel 21, the top panel 22, the bottom panel 23, the back frame panel 24, the base plate 311 and the trough plate 312 are all composite waterproof panels; the composite waterproof panels have good anti-seepage properties, deformation resistance, corrosion resistance and water erosion resistance, which can prevent the mud on the river bank from being washed into the river without affecting the ecological environment of the river; the processing and manufacturing of the composite waterproof panels are simple and fast, which reduces the construction difficulty and construction cost of river management.

[0047] It should be noted that river management is usually carried out in sections. First, a foundation trench 10 is excavated in a construction section of a preset length, and then multiple slope protection frames 20 and the vegetation foundations 31 thereon are installed one by one in the foundation trench 10 along the length direction of the river and connected to each other. Then, backfilling and planting of vegetation 32 are carried out to form an ecological slope protection and improve the natural landscape of the river.

[0048] The above-mentioned schematic embodiment simplifies the river slope protection structure through the specific arrangement of the slope protection frame 20 and the vegetated slope protection 30, thereby simplifying the river slope protection construction process, reducing the construction difficulty and cost, and improving the construction efficiency; compared with the traditional concrete slope protection structure, this embodiment can reduce the polluting elements brought to the water environment by solid protective materials such as concrete, significantly reduce the negative impact of the slope protection on the river ecological environment, and realize the rapid forming of the river slope protection.

[0049] refer to Figure 4 , Figure 5 As shown, in some embodiments, the top panel 22 and the two side panels 21, the bottom panel 23 and the two side panels 21, and the back frame panel 24 and the two side panels 21 are all connected by a mortise and tenon structure; the mortise and tenon structure includes a mortise portion 26 (also called a mortise groove) and a tenon portion 27 (also called a tenon head); Figure 5 The middle side panel 21 is provided with a mortise 26, the top panel 22, the bottom panel 23, and the back frame panel 24 is provided with a tenon 27 adapted thereto, but this is not limited thereto, and the positions of the mortise 26 and the tenon 27 are interchangeable. The top panel 22 and the bottom panel 23 are horizontally inserted between the two side panels 21 in a direction away from the river channel, and the back frame panel 24 is vertically inserted between the two side panels 21, thereby realizing convenient assembly and connection between the various components of the slope protection frame 20. Moreover, through the assembly setting of the slope protection frame 20, the slope protection frame 20 can be installed in parts in the base trench 10; specifically, the bottom panel 23 is first inserted into the two side panels 21 and placed in the base trench 10 together, and then the top panel 22 is inserted into the two side panels 21, and then the vegetation foundation 31 is installed into the slope protection frame 20 from the side of the slope protection frame 20 away from the river channel and connected to the slope protection frame 20, and then the back frame plate 24 is inserted into the two side panels 21; thereby, the transportation convenience is improved, and the construction difficulty of the overall transportation and hoisting of the slope protection frame 20 and the vegetation foundation 31 is reduced, thereby greatly reducing the construction cost and improving the construction efficiency.

[0050] refer to Figure 2 , Figure 3As shown, in some embodiments, a plurality of first bolt through holes 232 are arranged on the bottom plate 23 of the slope protection frame 20. The first bolts 28 corresponding to the first bolt through holes 232 are pre-buried on the bottom wall 11 of the trench 10 of the excavated river channel. When the slope protection frame 20 is installed in the trench 10, the first bolt through holes 232 on the bottom plate 23 are sleeved outside the first bolts 28, and the fastening nuts 29 are screwed into the upper part of the first bolts 28, and the fastening nuts 29 are screwed to press the bottom plate 23, thereby firmly connecting the bottom plate 23 to the trench bottom wall 11 of the trench 10; it can be understood that the first bolt through holes 232 can be step holes so that the fastening nuts 29 are located below the top surface of the bottom plate 23, so as to facilitate the subsequent installation of the planting foundation 31 in the slope protection frame 20. This exemplary embodiment realizes the connection and installation of the slope protection frame 20 in the trench 10.

[0051] refer to Figure 1 , Figure 2 As shown, in some embodiments, a plurality of second bolt holes 211 are arranged on the side panels 21 of the slope protection frames 20. By passing a bolt assembly through the second bolt holes 211 on the adjacent side panels 21 of two slope protection frames 20, convenient connection between two adjacent slope protection frames 20 within a construction section of a preset length can be achieved.

[0052] refer to Figure 1 As shown, in some embodiments, a drainage groove 212 is recessed on the side of the side panel 21 away from the inner cavity of the slope protection frame 20. The drainage groove 212 extends downward in a direction toward the river channel and passes through the front and rear ends of the side panel 21. The inclination angle of the drainage groove 212 can be set to about 3°, which is convenient for guiding the seepage water in the earthwork on the rear side of the slope protection frame 20 into the river channel.

[0053] refer to Figure 3 As shown, in some embodiments, a plurality of diagonal bracing members 25 are arranged between the end surface of the base plate 311 facing away from the river channel and the bottom panel 23, that is, one end of the diagonal bracing member 25 is crimped onto the top surface of the bottom panel 23, and the other end is against the rear end surface of the base plate 311; the plurality of diagonal bracing members 25 can be arranged in multiple rows and columns; through the provision of the diagonal bracing members 25, a more stable support is provided for the vegetation base 31 and the vegetation 32 thereon, that is, the vegetation slope protection 30.

[0054] refer to Figure 7 As shown, in some embodiments, a plurality of weight-reducing grooves 3111 are recessed on the end surface of the base plate 311 facing away from the river channel, and a plurality of reinforcing ribs 3112 are provided in each weight-reducing groove 3111; by providing the weight-reducing grooves 3111, the overall weight of the planting base 31 is reduced, thereby facilitating the transportation and installation of the planting base 31; and by providing the reinforcing ribs 3112, the structural strength of the base plate 311 itself is enhanced.

[0055] refer to Figure 2 , Figure 5As shown, in some embodiments, the back frame plate 24 includes two side frames 241 arranged opposite to each other, a top frame 242 connected between the upper parts of the two side frames 241, and a bottom frame 243 connected between the lower parts of the two side frames 241. The two side frames 241 are respectively connected to the two side panels 21; thus, the back frame plate 24 is an overall square frame structure. The back frame plate 24 also includes a plurality of reinforcing frames 244, which are connected between the top frame 242 and the bottom frame 243 or between the two side frames 241. The reinforcing frames 244 can be arranged vertically, horizontally or obliquely, so that the back frame plate 24 has a plurality of hollow opening structures and ensures the structural strength of the back frame plate 24.

[0056] refer to Figure 1-Figure 8 As shown, the present invention also provides an ecological slope protection construction method for river management, which is applicable to the above-mentioned ecological slope protection structure, including the construction steps of the foundation trench 10 and the construction steps of the ecological slope protection structure.

[0057] The construction steps of the foundation trench 10 further include:

[0058] Construction preparation: divide the bank slopes on both sides of the river to be managed into multiple construction sections according to preset lengths, and set up a temporary cofferdam structure in the river area where the construction section with preset length is located on one side of the bank slope;

[0059] Survey and lay out, and lay out the edge of the foundation trench 10 of the preset length construction section according to the design drawings; it is understood that before construction, the construction unit should measure according to the coordinates of the design drawings based on the construction control network; the plane and elevation control points arranged by the survey should be buried in an area outside the construction site that is not affected by the construction, and the frame should be buried, marked with the number, and properly protected; during the construction process, the survey control points should be re-measured regularly, and if the allowable error is exceeded, it should be corrected in time; if there is any damage, it should be re-measured;

[0060] For foundation treatment, determine whether foundation treatment is needed based on the geological conditions around the river channel and the results of simulation analysis; if the burial depth can meet the anti-scouring requirements, no special treatment is required; if the river section contains soft foundation, fine-grained soil and sand layers and other unfavorable geological conditions greater than the burial depth, all of them should be dug out and replaced with stone blocks; for the foundation of the backfill behind the embankment, it is necessary to remove the debris and backfill soil on the surface of the natural foundation, clear the waste thickness of 0.2m, and press the surface of the foundation. At the same time, according to the requirements of the "Design Code for Embankment Engineering", reserve the settlement of the earth embankment in advance before construction;

[0061] The foundation trench 10 is excavated according to the laid out foundation trench 10 edge line, using a 1m 3The excavator excavates the foundation trench 10 until the preset depth of the foundation trench 10 is reached; the earthwork during the excavation of the foundation trench 10 is piled nearby for subsequent backfilling; it is understood that before excavation, temporary drainage measures inside and outside the excavation area should be planned as much as possible in combination with the layout of permanent drainage facilities, and attention should be paid to protecting the excavated bank slope and nearby buildings and their foundations from scouring and erosion damage; when excavating the foundation trench 10, special attention should be paid to the drainage of the foundation trench 10, and necessary drainage facilities should be equipped to ensure that the foundation trench 10 is basically in a water-free environment during the construction process;

[0062] The first bolts 28 are pre-buried and the bottom concrete is poured. According to the design drawings, multiple first bolts 28 are buried in the bottom surface of the foundation trench 10; the bottom concrete is poured on the bottom surface of the foundation trench 10; it can be understood that when pouring the bottom concrete, it is also necessary to ensure that the foundation trench 10 is basically in a water-free environment.

[0063] The construction steps of the ecological slope protection structure further include:

[0064] The slope protection frame 20 and the vegetation foundation 31 are installed. The bottom panel 23 is inserted into the two side panels 21, and then placed on the bottom concrete, and the first bolt through holes 232 on the bottom panel 23 are set outside the first bolt 28 one by one, and the bottom panel 23 is pressed onto the bottom concrete by tightening the nut 29; then the top panel 22 is inserted into the two side panels 21; then the vegetation foundation 31 is lowered from the preset gap D, and then pushed between the two side panels 21, and the base plate 311 is connected to the first baffle 221 and the second baffle 231; then the back frame plate 24 is inserted into the two side panels 21; thus, the slope protection frame 20 and the vegetation foundation 31 of an ecological slope protection structure are installed in the base trench 10; according to this, the slope protection frames 20 and the vegetation foundation 31 of multiple ecological slope protection structures are installed in the base trench 10 of the preset length construction section, and the two adjacent slope protection frames 20 are connected to each other;

[0065] Backfilling: The soil excavated during the foundation trench 10 is first backfilled into the inner cavity of each slope protection frame 20 through the preset gap D and the hollow opening on the back frame plate 24. When the inner cavity of the slope protection frame 20 is filled with soil, the preset gap D between the slope protection frame 20 and the side wall 12 of the foundation trench 10 is backfilled with soil until the preset gap D in the preset length construction section is filled;

[0066] Planting of vegetation 32, filling planting soil in each planting groove 313, and then carrying out vegetation planting operations such as sowing grass seeds, planting shrubs or spreading turf on the planting soil, after the planting is completed, the soil can be covered with 2cm, the surface is cleaned and compacted, and watered and cleaned.

[0067] The above-mentioned schematic embodiment, by applying the slope protection frame 20 assembled by the composite waterproof board and the specific construction steps of the ecological slope protection, greatly simplifies the river slope protection construction process, reduces the construction difficulty and construction cost, improves the construction efficiency, and realizes the rapid forming of the ecological slope protection, thereby solving the problems of the traditional concrete slope protection method with complicated construction process, low construction efficiency, and failure to form quickly, which easily causes flooding; and compared with the traditional concrete slope protection method, this embodiment significantly reduces the polluting elements brought to the water environment by the solidified protective material, reduces the negative impact of the slope protection on the river ecological environment, and realizes ecological governance.

[0068] refer to Figure 1-Figure 8 As shown, in some embodiments, the construction steps of the ecological slope protection structure also include, after the backfilling step is completed, piling soil and rocks on the slope surface of each slope protection frame 20 below the preset water level line of the river to perform a foot pressing operation on it; thereby further improving the stability of the ecological slope protection structure, increasing its ability to resist water flow impact, and enhancing the overall safety of river protection, which is particularly suitable for rivers with large flow and fast flow rate.

[0069] To sum up, the ecological slope protection structure and ecological slope protection construction method for river channel management of the present invention realize the rapid construction of river channel slope protection, and reduce the negative impact of slope protection on the river channel ecological environment, achieve the technical effects of rapid prototyping and ecological management, and provide an efficient and practical means of slope protection and consolidation for river channel management.

[0070] Finally, it should be noted that: the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0071] The above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the present invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.

Claims

1. An ecological slope protection structure for river management, arranged in a foundation trench excavated at the river bank slope, characterized in that: The ecological slope protection structure comprises: The slope protection frame comprises two oppositely arranged side panels, a top panel connected between the upper parts of the two side panels, a bottom panel connected between the lower parts of the two side panels, and a back frame panel connected between the two side panels on the side away from the river channel; the end surfaces of the side panels, the top panel and the bottom panel facing the river channel are coplanar slope surfaces; the end of the top panel facing the river channel is provided with a first baffle plate folded downward, and the end of the bottom panel facing the river channel is provided with a second baffle plate folded upward, and the top surface height of the second baffle plate is higher than the preset water level line of the river channel; the bottom panel is used to be connected to the bottom wall of the base trench, and the back frame plate is a square frame structure; a preset gap is left between the slope protection frame and the side walls of the base trench; A vegetation slope protection, comprising a vegetation foundation; the vegetation foundation comprises a base plate and a plurality of groove plates, the upper and lower parts of the base plate are respectively connected to the inner wall of the first baffle plate and the second baffle plate on the side away from the river channel, and the plurality of groove plates are connected to the end surface of the base plate facing the river channel at intervals in the upper and lower parts, so that a plurality of planting grooves are formed between the vegetation foundation and the slope protection frame; and vegetation is planted in each of the planting grooves; The inner cavity of the slope protection frame and the preset gap between the slope protection frame and the side wall of the foundation trench are filled with earth when the foundation trench is excavated; the side panels, top panels, bottom panels, back frame panels, base panels and trench panels are all composite waterproof panels.

2. The ecological slope protection structure according to claim 1 is characterized in that: The top panel and the two side panels, the bottom panel and the two side panels, and the back frame panel and the two side panels are all connected by mortise and tenon structures, and the top panel and the bottom panel are horizontally inserted between the two side panels in a direction away from the river channel, and the back frame panel is vertically inserted between the two side panels.

3. The ecological slope protection structure according to claim 2 is characterized in that: A plurality of first bolt through holes are arranged on the bottom panel; and first bolts corresponding to the first bolt through holes are pre-buried on the bottom wall of the base groove.

4. The ecological slope protection structure according to claim 3 is characterized in that: The side panel is provided with a plurality of second bolt through holes.

5. The ecological slope protection structure according to claim 3 is characterized in that: A drainage groove is recessed on the side of the side panel away from the inner cavity of the slope protection frame, and the drainage groove extends downwardly in an inclined direction toward the river channel.

6. The ecological slope protection structure according to claim 3 is characterized in that: A plurality of diagonal bracing members are arranged between the end surface of the base plate facing away from the river channel and the bottom plate.

7. The ecological slope protection structure according to claim 3 is characterized in that: A plurality of weight-reducing grooves are concavely arranged on the end surface of the base plate facing away from the river channel, and a plurality of reinforcing ribs are arranged in each of the weight-reducing grooves.

8. The ecological slope protection structure according to claim 3 is characterized in that: The back frame plate includes two side frames arranged opposite to each other, a top frame connected between the upper parts of the two side frames, and a bottom frame connected between the lower parts of the two side frames, and the two side frames are respectively connected to the two side panel plates; the back frame plate also includes multiple reinforcement frames, and the reinforcement frames are connected between the top frame and the bottom frame or between the two side frames.

9. An ecological slope protection construction method for river management, applicable to the ecological slope protection structure as described in any one of claims 3 to 8, characterized in that: It includes the steps of foundation trench construction and ecological slope protection structure construction; among which, The foundation trench construction steps include: Measure and lay out the edges of the foundation pit according to the design drawings; Excavation of foundation trench: excavation of foundation trench is carried out according to the laid out foundation trench edge line until the preset foundation trench depth is reached; the earthwork during foundation trench excavation is piled nearby; Pre-embedding of first bolts and pouring of bottom concrete: burying a plurality of first bolts on the bottom surface of the foundation trench according to the design drawings; pouring of bottom concrete on the bottom surface of the foundation trench; The construction steps of the ecological slope protection structure include: The slope protection frame and the vegetation foundation are installed by inserting the bottom panel into the two side panels, and then placing it on the bottom concrete, and the first bolt through holes on the bottom panel are set outside the first bolts one by one, and the bottom panel is pressed onto the bottom concrete by tightening the nuts; then the top panel is inserted into the two side panels; then the vegetation foundation is lowered from the preset gap, and then pushed between the two side panels, and the base plate is connected to the first baffle and the second baffle; then the back frame is inserted into the two side panels; thus, the slope protection frame and the vegetation foundation of the ecological slope protection structure are installed in the base groove; according to this, multiple slope protection frames and the vegetation foundation of the ecological slope protection structure are installed in the base groove, and two adjacent slope protection frames are connected to each other; Backfilling: the soil excavated during foundation trench excavation is first backfilled into the inner cavity of the slope protection frame through the preset gap, and then the preset gap is backfilled with soil; Planting vegetation: Fill each planting trough with planting soil and then plant vegetation.

10. The ecological slope protection construction method according to claim 9, characterized in that: The ecological slope protection structure construction step also includes, after the soil backfilling step is completed, piling soil and rocks on the slope surface of each slope protection frame below the preset water level line of the river channel to perform a foot pressing operation on it.