The invention discloses a flexible attachment arranging and selecting method of an ultra-large type
cooling tower construction
tower crane based on
tower barrel safety. The flexible attachment arranging and selecting method of the ultra-large type
cooling tower construction
tower crane based on the tower
barrel safety is characterized by comprising the following steps. The first step is that a
cooling tower finite
element model is selected to be analyzed in three-dimensional mode, and the three-
dimensional analysis of the cooling tower finite
element model comprises selecting a concrete material parameter in a construction period, setting a calculating border and confirming a wind load in the construction period and a construction load; the second step is that an initial steel
wire rope tensile force and an attachment overall arranging scheme are drawn up, wherein the attachment overall arranging scheme comprises a vertical arranging scheme and a transverse arranging scheme, then the initial steel
wire rope tensile force and the attachment overall arranging scheme are applied to the cooling tower finite
element model in the construction period to be calculated, the overall arranging scheme is adjusted according to calculation results, and therefore the number of
layers and transverse intervals of flexible attachment are confirmed; and the third step is that a local analysis model is built, concrete age when concrete is tensioned by a prestressing force, local intervals and specific reinforcing method are confirmed, and by calculating and analyzing process, the overall arranging scheme and local arranging schemes of a cooling tower are confirmed. By means of the flexible attachment arranging and selecting method of the ultra-large type cooling tower construction
tower crane based on the tower
barrel safety, the influence of the wind load in the construction period and construction load to a tower barrel is overcome, improvement of the safety and the stability of the tower barrel is facilitated, construction safety of a
tower crane is guaranteed, the construction period can be guaranteed, and manufacturing cost of a cooling tower body is controlled.