Pile bearing platform foundation and construction method thereof

By setting up an anchor base, pre-installed block and fastening rod in the bridge support structure, combining the design of the connecting components and curved sleeves, the anchor piles are used to anchor on the foundation, and the problem of poor firmness of the bridge support structure is solved, achieving a higher level of strength stability and service life.

CN119392701APending Publication Date: 2025-02-07CHINA RAILWAY NO 2 ENG GROUP CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411771272.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-04
Publication Date
2025-02-07

AI Technical Summary

Technical Problem

In the prior art, the bridge support structure has poor firmness, and when the bridge sways, concrete cracking, steel bar bending and other problems are prone to occur.

Method used

A pile bearing foundation and its construction method are adopted. By setting up an anchor base to anchor in the foundation, the pre-assembled block at the bottom of the bearing is embedded in the pre-assembled groove on the pre-assembled sleeve, so that the two sets of mounting sleeves are installed on the pile respectively. On the outside of the foundation, four sets of fastening rods are used to penetrate the fastening sleeve, pre-assembled sleeve and pre-assembled block from the outside to the inside, and the connecting components are connected to the arc-shaped sleeve plate and the mounting sleeve bolt, and are anchored to the foundation by anchor piles.

Benefits of technology

The firmness and stability of the bridge support structure are achieved, and problems such as concrete cracking and reinforcement bending are avoided. The overall structure is stronger and more convenient to use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119392701A_ABST
    Figure CN119392701A_ABST
Patent Text Reader

Abstract

The invention discloses a pile cap foundation and a construction method thereof, and belongs to the technical field of bridge supporting.The pile cap foundation comprises a bridge, a convex frame is fixedly connected to the bottom of the bridge, a concave frame is arranged at the bottom of the convex frame, and a cap is connected to the bottom of the concave frame in an embedded mode; a pile foundation is arranged below the bearing platform, the bottom of the pile foundation is fixedly connected with an anchoring base, two sets of installation sleeves are installed on the outer side of the pile foundation from top to bottom, one side of each installation sleeve is in bolted connection with a connecting assembly, and one side of each connecting assembly is in bolted connection with an arc-shaped sleeve plate. One side of the arc-shaped sleeve plate is fixedly connected with an arc-shaped plate; the anchoring base is arranged to be anchored in a foundation, the pre-assembling block at the bottom of the bearing platform is embedded into the pre-assembling groove in the pre-assembling sleeve, so that the two sets of mounting sleeves are installed on the outer side of the pile foundation correspondingly, then the four sets of fastening rods penetrate through the fastening sleeve, the pre-assembling sleeve and the pre-assembling block from outside to inside correspondingly, the overall firmness is high, and use is convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge support, and more specifically, to a pile cap foundation and a construction method thereof. Background Art

[0002] The cap is an important part connecting the pile foundation and the bridge. It is necessary to transfer the load on the bridge to the pile foundation. The cap plays a decisive role in whether the bridge is stable. The cap is usually embedded in the top of the pile foundation, and the bridge is embedded in the top of the cap. The cap, pile foundation and bridge are all rigidly connected.

[0003] The existing patent number 202122562774.1 is a pile cap foundation and its construction method. When in use, the cap and the pile foundation can produce relative displacement in the horizontal direction through the setting of the fixed component. The gravel layer and the rubber layer can make the cap and the pile foundation produce relative displacement in the vertical direction, which plays a buffering role and extends the service life of the bridge.

[0004] Based on the above, the inventors found that: the above patent adopts a buffer component and a gravel layer and a rubber layer to achieve a buffer effect. Although it can extend the service life of the bridge, the firmness of the bridge support structure is relatively poor. When the bridge shakes, problems such as concrete cracking and steel bar bending will still occur. Therefore, in view of this, the existing structure is studied and improved, and a pile cap foundation and a construction method thereof are provided, in order to achieve a more practical purpose. Summary of the invention

[0005] 1. Technical problems to be solved

[0006] In view of the problems existing in the prior art, the purpose of the present invention is to provide a pile cap foundation and a construction method thereof, which can prevent the relatively poor firmness of the bridge support structure, and prevent problems such as concrete cracking and steel bar bending from occurring when the bridge shakes.

[0007] 2. Technical solution

[0008] To solve the above problems, the present invention adopts the following technical solutions.

[0009] A pile cap foundation comprises a bridge, wherein a convex frame is fixedly connected to the bottom of the bridge, a recessed frame is arranged at the bottom of the convex frame, a cap is connected to the bottom of the recessed frame in an inlaid manner, a pile foundation is arranged below the cap, the bottom of the pile foundation is fixedly connected to an anchoring base, and two groups of mounting sleeves are respectively installed on the outer side of the pile foundation from top to bottom, one side of the mounting sleeve is bolted to a connecting assembly, one side of the connecting assembly is bolted to an arc-shaped sleeve plate, one side of the arc-shaped sleeve plate is fixedly connected to an arc-shaped plate, an anchor pile is arranged below the arc-shaped plate, the top of the pile foundation is fixedly connected to a pre-installed sleeve, the outer side of the pre-installed sleeve is sleeved with a fastening sleeve, and the outer side of the fastening sleeve is threadedly connected to a fastening rod.

[0010] Furthermore, the installation sleeve is composed of a semi-arc sleeve, a connecting plate and a fixing plate. The fixing plate is fixedly connected to one side of the semi-arc sleeve, and the connecting plates are symmetrically arranged on both sides of the semi-arc sleeve.

[0011] Furthermore, the semi-arc sleeves, connecting plates and fixing plates are arranged in four groups, and the structural composition of each group of semi-arc sleeves, connecting plates and fixing plates is consistent.

[0012] Furthermore, the outer wall of the anchoring base is fixedly connected with protrusions distributed in a surrounding shape.

[0013] Furthermore, the arc-shaped sleeve plates are provided in four groups, and the inner side walls of each group of arc-shaped sleeve plates are fixedly connected with two groups of symmetrical strip plates.

[0014] Furthermore, the connection assembly is composed of an adapter frame, a connection frame 1 and a connection frame 2, wherein the connection frame 1 and the connection frame 2 are respectively bolted to two sides of the adapter frame, the connection frame 1 is bolted to the fixing plate, and the connection frame 2 is bolted to the strip plate.

[0015] Furthermore, a thread groove 1 is provided on the inner side of the fastening sleeve.

[0016] Furthermore, a pre-installed block is fixedly connected to the bottom of the support platform, and a second threaded groove is provided on the inner side of the pre-installed block.

[0017] Furthermore, a pre-installation groove is provided on the inner side of the pre-installation sleeve, and three threaded grooves are provided on the outer wall of the pre-installation sleeve. Four groups of fastening rods are provided, and each group of fastening rods is threadedly connected to the fastening sleeve, the pre-installation sleeve and the pre-installation block from the outside to the inside.

[0018] A construction method for setting a pile cap foundation comprises the following steps:

[0019] Step 1: Anchor the anchor base in the foundation, and use the pre-installed block at the bottom of the cap to embed it into the pre-installed groove on the pre-installed sleeve, so that the two sets of installation sleeves are respectively installed on the outside of the pile foundation;

[0020] Step 2: Use four sets of fastening rods to penetrate the fastening sleeve, pre-installed sleeve and pre-installed block from outside to inside respectively, and the connecting components are bolted to the arc sleeve plate and the installation sleeve respectively, and the connecting plates on the four sets of semi-arc sleeves are bolted to each other;

[0021] Step 3: Use anchor piles to anchor the foundation. The overall stability is high, which can effectively avoid problems such as concrete cracking and steel bar bending. The overall firmness is strong and easy to use.

[0022] 3. Beneficial effects

[0023] Compared with the prior art, the advantages of the present invention are:

[0024] (1) This solution is to anchor the anchor base in the foundation, and use the pre-installed block at the bottom of the pedestal to embed it into the pre-installed groove on the pre-installed sleeve, so that the two sets of installation sleeves are respectively installed on the outside of the pile foundation, and then use four sets of fastening rods to penetrate the fastening sleeve, pre-installed sleeve and pre-installed block from the outside to the inside, respectively. The overall firmness is strong and it is convenient to use.

[0025] (2) This solution provides a connection assembly that is bolted to the arc sleeve and the mounting sleeve, and uses the connection plates on the four groups of semi-arc sleeves to be bolted to each other, and then uses anchor piles to anchor to the foundation. The overall stability is high and can effectively avoid problems such as concrete cracking and steel bar bending. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a three-dimensional schematic diagram of the present invention;

[0027] Figure 2 is a schematic diagram of a support assembly of the present invention;

[0028] Figure 3 is a schematic diagram of the support structure of the present invention;

[0029] Figure 4 is a schematic diagram of a reinforcement assembly of the present invention;

[0030] Figure 5 It is a schematic diagram of turning over the reinforcing assembly of the present invention;

[0031] Figure 6 is a schematic diagram of a pile foundation of the present invention;

[0032] Figure 7 It is a schematic diagram of the disassembly of the foundation of the platform of the present invention.

[0033] Description of the numbers in the figure:

[0034] 1. Bridge; 2. Protruding frame; 3. Concave frame; 4. Pile foundation; 5. Mounting sleeve; 51. Semi-arc sleeve; 52. Connecting plate; 53. Fixing plate; 6. Anchor base; 7. Connecting assembly; 71. Adapter frame; 72. Connecting frame one; 73. Connecting frame two; 8. Arc sleeve plate; 81. Strip plate; 9. Arc plate; 10. Anchor pile; 11. Fastening sleeve; 1101. Thread groove one; 12. Cap; 1201. Pre-installed block; 1202. Thread groove two; 13. Fastening rod; 14. Pre-installed sleeve; 1401. Thread groove three; 1402. Pre-installed groove. DETAILED DESCRIPTION

[0035] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention; it is obvious that the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments, and all other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making creative work are within the scope of protection of the present invention.

[0036] Example:

[0037] See also Figure 1-7 A pile cap foundation is provided, comprising a bridge 1, a convex frame 2 is fixedly connected to the bottom of the bridge 1, a concave frame 3 is provided at the bottom of the convex frame 2, the concave frame 3 is used to install a cap 12, the bottom of the concave frame 3 is engaged with the cap 12, a pile foundation 4 is provided below the cap 12, the cap 12 and the pile foundation 4 are used to support the bridge 1, an anchoring base 6 is fixedly connected to the bottom of the pile foundation 4, the anchoring base 6 is used to anchor the pile foundation 4, thereby increasing stability, and two sets of mounting sleeves 5 are respectively installed on the outer side of the pile foundation 4 from top to bottom, the mounting sleeves 5 are used to Install the reinforcement component, one side of the installation sleeve 5 is bolted to the connecting component 7, one side of the connecting component 7 is bolted to the arc sleeve plate 8, one side of the arc sleeve plate 8 is fixedly connected to the arc plate 9, and anchor piles 10 are arranged under the arc plate 9. The arc plate 9 and the anchor piles 10 are used to increase the stability of the pile foundation 4. The top of the pile foundation 4 is fixedly connected to the pre-installed sleeve 14, the outer side of the pre-installed sleeve 14 is sleeved with a fastening sleeve 11, and the outer side of the fastening sleeve 11 is threadedly connected to a fastening rod 13. The fastening sleeve 11 and the fastening rod 13 are used to limit the base 12.

[0038] See also Figure 4 and Figure 5 The mounting sleeve 5 is composed of a semi-arc sleeve 51, a connecting plate 52 and a fixing plate 53. The fixing plate 53 is fixedly connected to one side of the semi-arc sleeve 51, and the connecting plates 52 are symmetrically arranged on both sides of the semi-arc sleeve 51. The mounting sleeve 5 is used to install the reinforcement component.

[0039] See also Figure 4 and Figure 5The semi-arc sleeve 51, the connecting plate 52 and the fixing plate 53 are arranged in four groups, and the structural composition of each group of semi-arc sleeve 51, the connecting plate 52 and the fixing plate 53 is consistent. By arranging the semi-arc sleeve 51, the connecting plate 52 and the fixing plate 53, the installation sleeve 5 can be quickly disassembled and assembled.

[0040] See also Figure 2 and Figure 3 The outer wall of the anchor base 6 is fixedly connected with convex heads distributed in a surrounding shape, and the anchoring effect can be increased by providing the convex heads.

[0041] See also Figure 3 and Figure 5 There are four groups of arc-shaped sleeve plates 8, and the inner side walls of each group of arc-shaped sleeve plates 8 are fixedly connected with two groups of symmetrical strip plates 81, and the strip plates 81 can be connected to the connecting frame 72 by setting them.

[0042] See also Figure 2 and Figure 5 The connecting assembly 7 is composed of an adaptor frame 71, a connecting frame 1 72 and a connecting frame 2 73. The connecting frame 1 72 and the connecting frame 2 73 are respectively bolted to the two sides of the adaptor frame 71. The connecting frame 1 72 is bolted to the fixing plate 53, and the connecting frame 2 73 is bolted to the strip plate 81. By setting the connecting assembly 7, the mounting sleeve 5 can be connected to the arc sleeve plate 8.

[0043] See also Figure 6 and Figure 7 A thread groove 1101 is provided on the inner side of the fastening sleeve 11, and the thread groove 1101 can facilitate the insertion of the fastening rod 13.

[0044] See also Figure 6 and Figure 7 The bottom of the support platform 12 is fixedly connected with a pre-installed block 1201, and a thread groove 1201 is provided on the inner side of the pre-installed block 1201. By setting the pre-installed block 1201, the support platform 12 can be embedded in the pre-installed sleeve 14.

[0045] See also Figure 3 , Figure 6 and Figure 7 A pre-installation groove 1402 is provided on the inner side of the pre-installation sleeve 14, and a threaded groove 1401 is provided on the outer wall of the pre-installation sleeve 14. Four groups of fastening rods 13 are provided, and each group of fastening rods 13 is threadedly connected with the fastening sleeve 11, the pre-installation sleeve 14 and the pre-installation block 1202 from the outside to the inside respectively. By setting the fastening sleeve 11 and the fastening rods 13, the support platform 12 can be limited.

[0046] When in use: first, anchor the anchor base 6 in the foundation, and use the pre-installed block 1201 at the bottom of the pedestal 12 to embed it into the pre-installed groove 1402 on the pre-installed sleeve 14, so that the two groups of installation sleeves 5 are respectively installed on the outside of the pile foundation 4, and then use four groups of fastening rods 13 to penetrate the fastening sleeve 11, the pre-installed sleeve 14 and the pre-installed block 1201 from the outside to the inside, respectively, and the connecting component 7 is bolted to the arc sleeve plate 8 and the installation sleeve 5 respectively, and the connecting plates 52 on the four groups of semi-arc sleeves 51 are bolted to each other, and then the anchor piles 10 are used to anchor it to the foundation. The overall stability is high, and the problems of concrete cracking and steel bar bending can be effectively avoided; the overall firmness is strong and it is convenient to use.

[0047] Finally, it should be noted that in the description of the present invention, it should be noted that the terms "vertical", "up", "down", "horizontal", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, they cannot be understood as limitations on the present invention.

[0048] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0049] The above is only a preferred specific implementation of the present invention; however, the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical solution and its improved conception within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A pile cap foundation, comprising a bridge (1), wherein a convex frame (2) is fixedly connected to the bottom of the bridge (1), a concave frame (3) is provided at the bottom of the convex frame (2), and a cap (12) is embedded and connected to the bottom of the concave frame (3), characterized in that: A pile foundation (4) is arranged below the cap (12), the bottom of the pile foundation (4) is fixedly connected to an anchor base (6), and two groups of mounting sleeves (5) are respectively installed on the outside of the pile foundation (4) from top to bottom, one side of the mounting sleeve (5) is bolted to a connecting assembly (7), one side of the connecting assembly (7) is bolted to an arc-shaped sleeve plate (8), one side of the arc-shaped sleeve plate (8) is fixedly connected to an arc-shaped plate (9), an anchor pile (10) is arranged below the arc-shaped plate (9), the top of the pile foundation (4) is fixedly connected to a pre-installed sleeve (14), the outer side of the pre-installed sleeve (14) is sleeved with a fastening sleeve (11), and the outer side of the fastening sleeve (11) is threadedly connected to a fastening rod (13).

2. A pile cap foundation according to claim 1, characterized in that: The mounting sleeve (5) is composed of a semi-arc sleeve (51), a connecting plate (52) and a fixing plate (53); the fixing plate (53) is fixedly connected to one side of the semi-arc sleeve (51); and the connecting plate (52) is symmetrically arranged on both sides of the semi-arc sleeve (51).

3. A pile cap foundation according to claim 2, characterized in that: The semi-arc sleeve (51), the connecting plate (52) and the fixing plate (53) are arranged in four groups, and the structural composition of each group of semi-arc sleeve (51), the connecting plate (52) and the fixing plate (53) is consistent.

4. The pile cap foundation according to claim 1, characterized in that: The outer wall of the anchoring base (6) is fixedly connected with protrusions distributed in a surrounding shape.

5. The pile cap foundation according to claim 1, characterized in that: The arc-shaped sleeve plates (8) are provided in four groups, and the inner side walls of each group of arc-shaped sleeve plates (8) are fixedly connected to two groups of symmetrical strip plates (81).

6. The pile cap foundation according to claim 1, characterized in that: The connection assembly (7) is composed of an adapter frame (71), a first connection frame (72) and a second connection frame (73), wherein the first connection frame (72) and the second connection frame (73) are respectively bolted to two sides of the adapter frame (71), the first connection frame (72) is bolted to a fixing plate (53), and the second connection frame (73) is bolted to a strip plate (81).

7. The pile cap foundation according to claim 1, characterized in that: A thread groove 1 (1101) is provided on the inner side of the fastening sleeve (11).

8. The pile cap foundation according to claim 1, characterized in that: A pre-installed block (1201) is fixedly connected to the bottom of the support platform (12), and a second thread groove (1202) is provided on the inner side of the pre-installed block (1201).

9. The pile cap foundation according to claim 1, characterized in that: The inner side of the pre-installation sleeve (14) is provided with a pre-installation groove (1402), and the outer wall of the pre-installation sleeve (14) is provided with a third thread groove (1401). The fastening rods (13) are provided with four groups, and each group of fastening rods (13) is respectively threadedly connected to the fastening sleeve (11), the pre-installation sleeve (14) and the pre-installation block (1201) from the outside to the inside.

10. A construction method for setting a pile cap foundation, characterized in that: It includes the following steps: Step 1: Anchor the anchor base in the foundation, and use the pre-installed block at the bottom of the cap to embed it into the pre-installed groove on the pre-installed sleeve, so that the two sets of installation sleeves are respectively installed on the outside of the pile foundation; Step 2: Use four sets of fastening rods to penetrate the fastening sleeve, pre-installed sleeve and pre-installed block from outside to inside respectively, and the connecting components are bolted to the arc sleeve plate and the installation sleeve respectively, and the connecting plates on the four sets of semi-arc sleeves are bolted to each other; Step three: Use anchor piles to anchor to the foundation. The overall stability is high and can effectively avoid problems such as concrete cracking and steel bar bending. The overall firmness is strong and easy to use.

Citation Information

Patent Citations

  • Group inclined pile model and use method thereof

    CN116104122A

  • Pile foundation reinforcing structure for road and bridge engineering

    CN216041393U

  • Reinforcing device for highway bridge pile foundation

    CN216075085U

  • Foundation provided with pile cap

    CN216194871U

  • Bridges and bridge scour scour prevention methods to prevent the ball

    KR101662063B1