Lifting type beam plate formwork supporting structure and operation method thereof
Through the lifting beam and plate formwork support structure, the cable is driven by the power support segment and multi-stage gear lifting device to realize the automatic lifting of beam formwork and plate formwork, solving the risk of supporting frames being installed at high places in the prior art. The problem of large space and time-consuming installation has improved construction efficiency and application height.
Patent Information
- Application Number
- CN202411858348.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-17
- Publication Date
- 2025-02-07
AI Technical Summary
The existing steel pipe support frame is highly dangerous when erected at high places, takes up a large space, and is time-consuming and labor-intensive to erect and dismantle, and cannot meet the higher support height.
The lifting beam and plate formwork support structure is adopted, including support lifting device, beam formwork support device, plate formwork support device and cable. The cable is rolled up through the power support segment and multi-stage gear lifting device to drive the support lifting frame to lift , realize automatic improvement of beam formwork and plate formwork.
It reduces the risk of supporting frame erection and demolition, utilizes the lower space, improves construction efficiency, and is suitable for casting of beams and slabs at higher heights.
Smart Images

Figure CN119392916A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building formwork construction, and in particular to a lifting type beam and slab formwork supporting structure and an operating method thereof. Background Art
[0002] When pouring concrete beams and slabs of building structures, it is necessary to set up a support frame and set up a formwork on it to complete the pouring operation. In order to ensure the quality of beam and slab pouring and the safety of the construction process, the formwork support should have a certain strength, rigidity and stability to withstand the load during the construction process. The existing formwork support frame is usually made of steel pipes, which are composed of horizontal, vertical and oblique steel pipes to form a formwork bracket, and the main beam, secondary beam and panel are set up on it to support the pouring and forming of concrete.
[0003] The steel pipe support frame is generally a full-frame support, which occupies all the space under the cast beams and slabs. During the erection of the support, personnel cannot pass through the erection area, which also restricts the transportation and movement of materials and other supplies; the steel pipe support frame is erected and dismantled manually, which consumes a lot of manpower and time, and the high-altitude support is more dangerous. When the casting height of the building structure beams and slabs is high, the full-frame support is erected from the bottom to the designed height, the self-weight of the steel pipe support increases, the load increases, and its overall stability and bearing capacity decrease accordingly. Therefore, the steel pipe support frame cannot meet the higher support height. Summary of the invention
[0004] The present invention aims to solve the deficiencies of the prior art and provides a lifting type beam and slab formwork supporting structure and an operating method thereof.
[0005] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a lifting type beam-slab formwork support structure, comprising a support lifting device, a beam formwork support device, a plate formwork support device, and a cable, wherein the four lifting devices are distributed in a rectangular shape, the beam formwork support device can be detachably mounted on two support lifting devices corresponding to the beam, and the plate formwork support device can be detachably mounted between the two beam formwork support devices, and the support lifting device lifts the beam formwork support device and the plate formwork support device to a designed height through a cable to provide support for pouring a concrete beam-slab structure;
[0006] The support and lifting device comprises a power support segment, a standard support segment, a fixed support segment, a cable steering segment, and a support and lifting sleeve; the power support segment is arranged at the bottom of the support and lifting device, a plurality of standard support segments are stacked up and down and connected to the top of the power support segment, the fixed support segment and the cable steering segment are stacked up and down from bottom to top in sequence and connected to the top of the topmost standard support segment, the cable lifting sleeve slides up and down along the power support segment, the standard support segment, and the fixed support segment, a plurality of cables are guided by the cable steering segment, one end of which is fixedly connected to the cable lifting sleeve, and the other end is connected to the power support segment, and the cable lifting sleeve is driven to rise and fall by the power support segment to drive the cable lifting sleeve to rise and fall;
[0007] The beam formwork support device is composed of a number of standard beam formwork support segments connected at the end, and the two standard beam formwork support segments located at the head and the tail are detachably connected to the corresponding cable lifting sleeves; the plate formwork support device includes a number of groups of standard plate formwork support segments, each group of standard plate formwork support segments is connected at the end, and the standard plate formwork support segment located at the end is adjacent to the beam formwork standard support segment and a sliding connecting frame is detachably installed at one end, and the sliding connecting frame is slidably connected to the two formwork standard support segments.
[0008] In particular, the power support segment includes four multi-stage gear lifting devices, four first support structures and several pairs of first connecting structures. The four first support structures are distributed in a rectangular shape. The first connecting structure includes a pair of L-shaped first connecting blocks, and the several pairs of first connecting blocks are fixed on the opposite surfaces of two adjacent first support structures from top to bottom and connected and fixed to each other by bolts and nuts. First sliding grooves are correspondingly provided on the opposite surfaces of two adjacent first support structures. The multi-stage gear lifting devices are respectively installed at the bottom of the opposite surfaces of two adjacent first support structures and drive the cable to wind and unwind. The cable drives the support lifting sleeve to rise and fall along the first sliding groove.
[0009] In particular, each standard support segment includes four second support structures and several pairs of second connecting structures. The four second support structures are distributed in a rectangular shape. The second connecting structure includes a pair of L-shaped second connecting blocks. The several pairs of second connecting blocks are fixed on the opposite surfaces of two adjacent second support structures from top to bottom and connected and fixed with each other through bolts and nuts. The second support structures of several standard support segments are stacked and connected and fixed in sequence up and down, and the second support structure of the lowest standard support segment is fixedly installed on the top of the corresponding first support structure. A second sliding groove connected to the first sliding groove is provided on the opposite surfaces of the two connected second support structures, and the support lifting sleeve is lifted and lowered along the second sliding groove.
[0010] In particular, the fixed support segment includes four third support structures, four embedded support blocks and several pairs of third connecting structures. The four third support structures are distributed in a rectangular shape. The third connecting structure includes a pair of L-shaped third connecting blocks, and the several pairs of third connecting blocks are fixed on the opposite surfaces of two adjacent third support structures from top to bottom and connected and fixed with each other by bolts and nuts. Slots are correspondingly provided at the lower parts of the two adjacent third support structures, and bolt holes are correspondingly provided at the bottom of the embedded support block and the bottom of the third support structure. The embedded support block is inserted into the slot and penetrates the bolt hole with a bolt and then the nut is tightened to fix it. The third support structure is fixedly installed on the top of the second support structure of the uppermost standard support segment. A third sliding groove connected to the second sliding groove is provided on the opposite surfaces of the two adjacent third support structures. The support lifting sleeve is lifted and lowered along the third sliding groove and supported by the embedded support block.
[0011] In particular, the cable steering segment includes a rectangular cable frame, the tops of the four sides of the cable frame are provided with grooves, a plurality of fixed pulleys are installed in the grooves, the cable frame is fixed to the tops of the four third support structures, and the cables are guided by the fixed pulleys.
[0012] In particular, the support lifting sleeve includes four support plates, four lifting connecting blocks, four inverted U-shaped support frames, and four pairs of beam formwork support device connecting frames. The four support plates are distributed in a rectangular shape and fixed together. The lifting connecting block is fixed to the bottom of the support plate, and a number of stiffening plates are provided at the angle between the lifting connecting block and the outer wall of the support plate. A sliding bar is provided on the side wall of the lifting connecting block, and the sliding bar slides along the first sliding groove, the second sliding groove, and the third sliding groove. One end of the cable is fixed to the top of the lifting connecting block, and the support frame is fixed to the top of the support plate. The tops of the four support plates are provided with connected lower transverse sliding grooves, and the tops of the four support frames are provided with connected upper transverse sliding grooves. The beam formwork support device connecting frame includes a column, one end of the top of the column is provided with an upper notch, and the other end is provided with a first connecting head connected to the beam formwork support device. A lower notch is provided at the bottom of the column, and the column is hung on the top of the support frame through the upper notch and slides along the upper transverse sliding groove, and is inserted into the support plate through the lower notch and slides along the lower transverse sliding groove.
[0013] In particular, each standard support segment of the beam formwork includes a pair of first Bailey support plates, and a first opening and closing plate is detachably installed between the opposite surfaces of the pair of first Bailey support plates. A first connecting tenon is provided at one end on the same side of the upper and lower beams of the first Bailey support plate, and a first connecting tenon is provided at the other end. When two adjacent standard support segments of the beam formwork are connected end to end, the adjacent first connecting tenons are inserted into the first connecting tenon and fixed by bolts and nuts. Fourth sliding grooves are correspondingly provided on the inner and outer sides of the upper and lower beams of the first Bailey support plate, and through installation notches are provided on the front and rear sides of the vertical beams on both sides of the first Bailey support plate, and a plurality of support limit sockets are provided on the left and right sides from top to bottom. A support limit block is inserted; the first opening and closing piece includes a first supporting beam, a first opening and closing support, a first connecting shaft, a first sliding installation shaft, and a beam plug-in block; a fifth sliding groove is provided on the top of the first supporting beam; the two first opening and closing supports are arranged in a scissors-shaped manner and are rotatably connected through the first connecting shaft; the first sliding installation shaft is installed at the end of the first opening and closing support and is slidably connected in the fifth sliding groove; the beam plug-in block is fixed at both ends of the first supporting beam adjacent to the first Bailey support piece on one side; the beam plug-in block is inserted in the installation groove and supported by the support limit block; a limit socket is provided on the top of the support limit block; a limit rod is provided at the bottom of the beam plug-in block, and the limit rod is inserted into the limit socket.
[0014] Particularly, the first connecting head matches with the adjacent first connecting groove or the first connecting tenon, and the first connecting head is connected and fixed with the corresponding first connecting groove or the first connecting tenon by bolts and nuts after being plugged in.
[0015] In particular, the standard support segment of the plate formwork includes a pair of second Bailey support plates, a second opening and closing plate and a width adjustment rod are provided between the pair of second Bailey support plates, a second connecting tenon is provided at one end on the same side of the upper and lower beams of the second Bailey support plate, and a second connecting tenon is provided at the other end, and when two adjacent standard support segments of the plate formwork are connected end to end, the adjacent second connecting tenons are inserted into the second connecting tenon and fixed by bolts and nuts; the second opening and closing plate includes a second supporting beam, a second opening and closing strut, a second connecting shaft, and a second sliding installation shaft, the second supporting beam is fixed to the top of the upper beam of the second Bailey support plate, a sixth sliding groove is provided on the top of the second supporting beam, and the two second opening and closing struts are arranged in a scissors-type manner and are rotatably connected through the second connecting shaft. The second sliding mounting shaft is installed at the end portion of the second opening and closing support and is slidably connected in the sixth sliding groove; the width adjusting rod includes a screw and a sleeve, and the opposite ends of the two screws are respectively threadedly connected to the two ends of the sleeve, and the opposite ends are respectively fixed to the centers of the opposite surfaces of a pair of second Bailey support plates; the sliding connecting frame includes a C-shaped connecting rod, and the upper and lower plates of the connecting rod are provided with sliding teeth on the opposite surfaces of the connecting rod, and the connecting rod is clamped in the fourth sliding groove through the sliding teeth and slides along the fourth sliding groove. A second connecting head is provided on the side of the connecting rod adjacent to the standard support segment of the plate formwork, and the second connecting head matches the adjacent second connecting tenon or connecting tenon groove, and the second connecting head is connected and fixed by bolts and nuts after being plugged into the corresponding second connecting tenon or connecting tenon groove.
[0016] An operating method of a lifting type beam and slab formwork supporting structure comprises the following steps:
[0017] S1, ground assembly board formwork support device;
[0018] S11, adjust the second opening and closing piece and the width adjustment rod of the standard support section of the plate formwork to adjust the two second Bailey support pieces to a suitable width;
[0019] S12, adjacent standard sections of the slab formwork are connected end to end through the second connecting tenon and the second connecting tenon groove and spliced to the required length to form a slab formwork support beam;
[0020] S13, repeat the above operation to place multiple board formwork support beams in parallel and close to each other;
[0021] S2, ground assembly beam formwork support device;
[0022] S21, adjust the first opening and closing piece of the standard support segment of the beam template to a suitable width, insert the crossbeam plug-in block into the installation notch, lift it to a suitable height and fix it with the support limit block;
[0023] S22, connecting the standard support segments of the beam formwork end to end through the first connecting tenon and the second connecting tenon groove and splicing them to a required length to form a beam formwork support device;
[0024] S23, installing a sliding connection frame matching the plate formwork support device in the fourth sliding groove of the beam formwork support device;
[0025] S3, connecting the beam formwork support device and the plate formwork support device;
[0026] Connect the second connecting head with the corresponding second connecting tenon or second connecting tenon groove to achieve the connection between the beam formwork support device and the plate formwork support device;
[0027] S4. Install the support and lifting device;
[0028] S41, install the power support segment;
[0029] S42, installing the support and lifting sleeve, and inserting the sliding bar into the first sliding groove;
[0030] S43. Continue to install the standard support segment on the power support segment to a suitable height;
[0031] S44, install the fixed support segment, and finally install the cable steering segment;
[0032] S45, connecting the supporting lifting sleeve frame and the multi-stage gear lifting device with a cable;
[0033] S5, connecting the beam formwork support device, the plate formwork support device and the support lifting device; the first connecting head on the support lifting sleeve is connected and fixed with the adjacent first connecting tenon or second connecting tenon groove;
[0034] S6, lifting of beam formwork support device and slab formwork support device;
[0035] S61. Set up secondary ribs and panels on the beam formwork support device and the plate formwork support device;
[0036] S62, provide power through the multi-stage gear lifting device, drive the cable to wind up and drive the beam formwork support device and the plate formwork support device to lift to the designed height, and install the embedded support block for support;
[0037] S7, pouring beam and slab concrete, and lowering the beam formwork support device and the slab formwork support device when the concrete reaches the design strength requirement;
[0038] S8. Dismantle the beam formwork support device and the slab formwork support device in the opposite order of the erection sequence.
[0039] The beneficial effects of the present invention are:
[0040] (1) The erection and removal of beam and slab supports are all at the bottom, which reduces the danger of erecting the support frame;
[0041] (2) The space under the support frame can be utilized to provide convenience for material storage and personnel passage;
[0042] (3) The beam formwork support device can provide support for the pouring of concrete beams of different widths and heights by adjusting the opening range of the first opening and closing piece and setting the first opening and closing piece at the position of the first Bailey support piece;
[0043] (4) The slab formwork support device can adapt to the pouring of concrete slabs of different widths by adjusting the opening angle of the second opening and closing piece;
[0044] (5) When the supporting lifting device is installed on the column, it has good stability and can be used for casting conditions of beam and slab formwork with large height. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 It is a schematic diagram of an angle structure of the present invention;
[0046] Figure 2 It is another perspective structural schematic diagram of the present invention;
[0047] Figure 3 It is a structural schematic diagram of the supporting and lifting device of the present invention;
[0048] Figure 4 It is a schematic diagram of the structure of the power support segment of the present invention;
[0049] Figure 5 It is a schematic diagram of the standard support segment structure of the present invention;
[0050] Figure 6 It is a schematic diagram of the fixed support segment structure of the present invention;
[0051] Figure 7 It is a schematic diagram of the cable steering segment structure of the present invention;
[0052] Figure 8 It is a schematic diagram of the supporting and lifting sleeve structure of the present invention;
[0053] Fig. 9 This is a schematic diagram of a single-side structure of the support and lifting sleeve of the present invention;
[0054] Fig.10 It is a schematic diagram of the structure of the connecting frame of the beam formwork support device of the present invention;
[0055] Fig.11 This is a schematic diagram of the standard support segment structure of the beam formwork of the present invention;
[0056] Fig.12 It is an exploded schematic diagram of the standard support segment structure of the beam formwork of the present invention;
[0057] Fig.13It is a schematic diagram of the standard support segment structure of the plate formwork of the present invention;
[0058] Fig.14 This is a schematic diagram of the end-to-end connection of the standard support segments of the slab formwork of the present invention;
[0059] Fig.15 It is a schematic diagram of the structure of the sliding connection frame of the present invention;
[0060] In the figure:
[0061] 1-support lifting device; 11-power support segment; 111-multi-stage gear lifting device; 112-first support structure; 1121-first sliding groove; 113-first connecting structure; 12-standard support segment; 121-second support structure; 1211-second sliding groove; 122-second connecting structure; 13-fixed support segment; 131-third support structure; 1311-slot; 1312-third sliding groove; 132-embedded support block; 133-third connecting structure Structure; 14-cable steering segment; 141-cable frame; 142-groove; 143-fixed pulley; 15-support lifting sleeve; 151-support plate; 1511-lower transverse sliding groove; 152-lifting connecting block; 1521-sliding bar; 153-support frame; 1531-upper transverse sliding groove; 154-beam template support device connecting frame; 1541-column; 1542-upper notch; 1543-first connector; 1544-lower notch; 155-stiffening plate;
[0062] 2-beam formwork support device; 21-beam formwork standard support segment; 211-first Bailey support plate; 2111-first connecting mortise; 2112-first connecting tenon; 2113-fourth sliding groove; 2114-installation notch; 2115-support limit plug hole; 2116-support limit block; 212-first opening and closing plate; 2121-first supporting beam; 2122-first opening and closing support; 2123-first connecting shaft; 2124-first sliding installation shaft; 2125-beam plug-in block; 2126-fifth sliding groove;
[0063] 3-board formwork support device; 31-board formwork standard support segment; 311-second Bailey support plate; 3111-second connecting mortise; 3112-second connecting tenon; 312-second opening and closing plate; 3121-second supporting crossbeam; 3122-second opening and closing support; 3123-second connecting shaft; 3124-second sliding installation shaft; 3125-sixth sliding groove; 313-width adjustment rod; 3131-screw rod; 3132-sleeve; 32-sliding connecting frame; 321-connecting rod; 322-sliding tooth mouth; 323-second connecting head;
[0064] 4- Cable;
[0065] The following is a detailed description of the embodiments of the present invention with reference to the accompanying drawings. DETAILED DESCRIPTION
[0066] The present invention will be further described below in conjunction with embodiments:
[0067] like Figure 1-Figure 15 As shown, a lifting type beam and slab formwork support structure includes a support lifting device 1, a beam formwork support device 2, a slab formwork support device 3, and a cable 4. The four lifting devices 1 are distributed in a rectangular shape. The beam formwork support device 2 can be detachably mounted on two support lifting devices 1 corresponding to the beam, and the slab formwork support device 3 can be detachably mounted between the two beam formwork support devices 2. The support lifting device 1 lifts the beam formwork support device 2 and the slab formwork support device 3 to the designed height through the cable 4 to provide support for the pouring of the concrete beam and slab structure.
[0068] The support and lifting device 1 includes a power support segment 11, a standard support segment 12, a fixed support segment 13, a cable steering segment 14, and a support and lifting sleeve 15; the power support segment 11 is arranged at the bottom of the support and lifting device 1, and a plurality of standard support segments 12 are stacked up and down and connected to the top of the power support segment 11, and the fixed support segment 13 and the cable steering segment 14 are stacked from bottom to top in sequence and connected to the top of the topmost standard support segment 12, and the cable lifting sleeve 15 slides up and down along the power support segment 11, the standard support segment 12, and the fixed support segment 13, and a plurality of cables 4 are guided by the cable steering segment 14, and one end is fixedly connected to the cable lifting sleeve 15, and the other end is connected to the power support segment 11, and is driven to be wound and unwound by the power support segment 11, thereby driving the cable lifting sleeve 15 to rise and fall.
[0069] The power support segment 11 includes four multi-stage gear lifting devices 111, four first support structures 112 and a plurality of pairs of first connection structures 113. The four first support structures 112 are distributed in a rectangular shape. The first connection structure 113 includes a pair of L-shaped first connection blocks. The plurality of pairs of first connection blocks are fixed on opposite surfaces of two adjacent first support structures 112 from top to bottom and connected and fixed to each other by bolts and nuts.
[0070] First sliding grooves 1121 are correspondingly arranged on the opposite surfaces of two adjacent first supporting structures 112. The multi-stage gear lifting devices 111 are respectively installed at the bottom of the opposite surfaces of the two adjacent first supporting structures 112 and drive the cable 4 to wind up and unwind. The cable 4 drives the supporting lifting sleeve 15 to rise and fall along the first sliding grooves 1121.
[0071] Specifically, the multi-stage gear lifting device 111 provides power for lifting, and lifts the support lifting sleeve 15 through the cable 4, driving the beam formwork support device 2 and the plate formwork support device 3 to the designed height. The first support structure 112 is a vertical support structure. The first connecting structure 113 connects the four first support structures 112. The first sliding groove 1121 provides an out-of-plane constraint for the vertical lifting process of the support lifting sleeve 15.
[0072] Each standard support segment 12 includes four second support structures 121 and a plurality of pairs of second connection structures 122. The four second support structures 121 are distributed in a rectangular shape. The second connection structure 122 includes a pair of L-shaped second connection blocks. The plurality of pairs of second connection blocks are fixed on opposite surfaces of two adjacent second support structures 121 from top to bottom and connected and fixed to each other by bolts and nuts. The second support structures 121 of a plurality of standard support segments 12 are stacked and connected and fixed in sequence up and down. The second support structure 121 of the lowest standard support segment 12 is fixedly installed on the top of the corresponding first support structure 112. A second sliding groove 1211 communicating with the first sliding groove 1121 is provided on the opposite surfaces of the two connected second support structures 121. The support lifting sleeve 15 is lifted and lowered along the second sliding groove 1211.
[0073] Specifically, the second support structure 121 is a vertical support structure, the second connection structure 122 connects four second support structures 121 , and the second sliding groove 1211 provides an out-of-plane constraint for the vertical lifting process of the support lifting sleeve 15 .
[0074] The fixed support segment 13 includes four third support structures 131, four embedded support blocks 132 and a plurality of pairs of third connection structures 133. The four third support structures 131 are distributed in a rectangular shape. The third connection structure 133 includes a pair of L-shaped third connection blocks. The plurality of pairs of third connection blocks are fixed on opposite surfaces of two adjacent third support structures 131 from top to bottom and connected and fixed by bolts and nuts after being butted against each other. Slots 1311 are provided at the lower parts of the two adjacent third support structures 131. Bolt holes are provided at the bottoms of the embedded support blocks 132 and the third support structures 131. The embedded support blocks 132 are inserted into the slots 1311 and are fixed by tightening nuts after bolts penetrate through the bolt holes. The third support structure 131 is fixedly mounted on the top of the second support structure 121 of the uppermost standard support segment 12. A third sliding groove 1312 communicating with the second sliding groove 1211 is provided on opposite surfaces of the two adjacent third support structures 131. The support lifting sleeve 15 is lifted and lowered along the third sliding groove 1312 and supported by the embedded support blocks 132.
[0075] Specifically, the third support structure 131 is a vertical support structure, the third connecting structure 133 connects the four third support structures 131, the third sliding groove 1312 provides an out-of-plane constraint for the vertical lifting process of the support lifting sleeve 15, and the embedded support block 132 provides vertical support for the support lifting sleeve 15 after lifting.
[0076] The cable steering segment 14 includes a rectangular cable frame 141. The tops of the four sides of the cable frame 141 are provided with grooves 142. A plurality of fixed pulleys 143 are installed in the grooves 142. The cable frame 141 is fixed to the tops of the four third support structures 131. The cable 14 is guided by the fixed pulleys 143 to change the force direction of the cable 4 during the lifting process.
[0077] The support and lifting sleeve 15 includes four support plates 151, four lifting connection blocks 152, four inverted U-shaped support frames 153, and four pairs of beam formwork support device connection frames 154. The four support plates 151 are distributed in a rectangular shape and fixed together. The lifting connection block 152 is fixed to the bottom of the support plate 151. A plurality of stiffening plates 155 are provided at the angle between the lifting connection block 152 and the outer wall of the support plate 151. A sliding bar 1521 is provided on the side wall of the lifting connection block 152. The sliding bar 1521 slides along the first sliding groove 1121, the second sliding groove 1211, and the third sliding groove 1312.
[0078] One end of the cable 4 is fixedly connected to the top of the lifting connection block 152, the support frame 153 is fixed to the top of the support plate 151, the tops of the four support plates 151 are provided with connected lower transverse sliding grooves 1511, the tops of the four support frames 153 are provided with connected upper transverse sliding grooves 1531, the beam formwork support device connecting frame 154 includes a column 1541, one end of the top of the column 1541 is provided with an upper notch 1542, and the other end is provided with a first connector 1543 connected to the beam formwork support device 2, and the bottom of the column 1541 is provided with a lower notch 1544, the column 1541 is hung on the top of the support frame 153 through the upper notch 1542 and slides along the upper transverse sliding groove 1531, and is inserted into the support plate 151 through the lower notch 1544 and slides along the lower transverse sliding groove 1511;
[0079] Specifically, the support plate 151 provides vertical support for the beam formwork support device connecting frame 154, the upper transverse sliding groove 1531 and the lower transverse sliding groove 1511 allow the beam formwork support device connecting frame 154 to slide to adjust the width of the beam formwork support device 2, the stiffening plate 155 is arranged at the lower part of the support plate 151 to improve the bearing capacity of the support plate 151, and sliding bars 1521 are arranged at both ends of the lifting connection block 152 to maintain the stability of the formwork during the lifting process.
[0080] The beam formwork support device 2 is composed of a plurality of beam formwork standard support segments 21 connected at the end, and the two beam formwork standard support segments 21 located at the head and the tail are detachably connected to the corresponding cable lifting sleeve 15;
[0081] Each beam formwork standard support segment 21 includes a pair of first Bailey support plates 211, and a first opening and closing plate 212 is detachably installed between the opposite surfaces of the pair of first Bailey support plates 211. A first connecting groove 2111 is provided at one end on the same side of the upper and lower cross beams of the first Bailey support plate 211, and a first connecting tenon 2112 is provided at the other end. When two adjacent beam formwork standard support segments 21 are connected end to end, the adjacent first connecting tenons 2112 are inserted into the first connecting groove 2111 and fixed by bolts and nuts.
[0082] Fourth sliding grooves 2113 are correspondingly arranged on the inner and outer sides of the upper and lower cross beams of the first Bailey support piece 211, and through installation slots 2114 are arranged on the front and rear sides of the vertical beams on both sides of the first Bailey support piece 211, and a plurality of support limit plug holes 2115 are arranged on the left and right sides from top to bottom, and support limit blocks 2116 are inserted into the support limit plug holes 2115;
[0083] The first opening and closing piece 212 includes a first supporting beam 2121, a first opening and closing support 2122, a first connecting shaft 2123, a first sliding installation shaft 2124, and a beam plug-in block 2125. A fifth sliding groove 2126 is provided on the top of the first supporting beam 2121. The two first opening and closing supports 2122 are arranged in a scissor-shaped manner and are rotatably connected through the first connecting shaft 2123. The first sliding installation shaft 2124 is installed at the end of the first opening and closing support 2122 and is slidably connected in the fifth sliding groove 2126. The beam plug-in block 2125 is fixed at both ends of the first supporting beam 2121 adjacent to one side of the first Bailey support piece 211. The beam plug-in block 2125 is plugged into the installation slot 2114 and supported by the support limit block 2116. A limit plug hole is provided on the top of the support limit block 2116. A limit plug rod is provided at the bottom of the beam plug-in block 2125, and the limit plug rod is inserted into the limit plug hole.
[0084] The first connection head 1543 matches with the adjacent first connection groove 2111 or the first connection tenon 2112, and the first connection head 1543 is connected and fixed with the corresponding first connection groove 2111 or the first connection tenon 2112 by bolts and nuts after being inserted;
[0085] Specifically, the first opening and closing piece 212 adjusts the width between the two first Bailey support pieces 211, the first support beam 2121 is a force-bearing support structure, the first connecting tenon groove 2111 and the first connecting tenon 2112 are used to connect the adjacent beam template standard support segment 21 or the support lifting sleeve 15, the fourth sliding groove 2113 is used to install the plate template support device 3, the installation notch 2114 provides an insertion position for the first opening and closing piece 212, and the support limit socket 2115 is used to adjust the first opening and closing piece The installation height of 212 is adjusted, and the top of the support limit block 2116 has a small hole, which is installed in the support limit socket 2115 to support the first opening and closing piece 212 and limit its escape; the two first opening and closing supports 2122 are connected and opened and closed by the first connecting shaft 2123, and the first opening and closing supports 2122 are installed on the first supporting beam 2121 through the first sliding installation shaft 2124. The fifth sliding groove 2126 allows the first opening and closing supports 2122 to slide on the first supporting beam 2121 after opening and closing.
[0086] The plate formwork support device 3 includes a plurality of groups of plate formwork standard support segments 31, each group of plate formwork standard support segments 31 is connected at the end, and a sliding connection frame 32 is detachably installed at one end of the plate formwork standard support segment 31 adjacent to the beam formwork standard support segment 21, and the sliding connection frame 32 is slidably connected to the two formwork standard support segments 21;
[0087] The standard support segment 31 of the board formwork includes a pair of second Bailey support pieces 311, a second opening and closing piece 312 and a width adjustment rod 313 are provided between the pair of second Bailey support pieces 311, a second connection groove 3111 is provided at one end on the same side of the upper and lower cross beams of the second Bailey support piece 311, and a second connection tenon 3112 is provided at the other end, and when two adjacent standard support segments 31 of the board formwork are connected end to end, the adjacent second connection tenons 3112 are inserted into the second connection groove 3111 and fixed by bolts and nuts;
[0088] The second opening and closing piece 312 includes a second supporting beam 3121, a second opening and closing strut 3122, a second connecting shaft 3123, and a second sliding mounting shaft 3124. The second supporting beam 3121 is fixed to the top of the upper beam of the second Bailey supporting piece 311. A sixth sliding groove 3125 is provided on the top of the second supporting beam 3121. The two second opening and closing struts 3122 are arranged in a scissor-like manner and are rotatably connected through the second connecting shaft 3123. The second sliding mounting shaft 3124 is installed at the end of the second opening and closing strut 3122 and is slidably connected in the sixth sliding groove 3125.
[0089] The width adjustment rod 313 includes a screw rod 3131 and a sleeve 3132. The opposite ends of the two screw rods 3131 are respectively threadedly connected to the two ends of the sleeve 3132, and the opposite ends are respectively fixed to the centers of the opposite surfaces of a pair of second Bailey support plates 311.
[0090] The sliding connection frame 32 includes a C-shaped connection rod 321, and the upper and lower plates of the connection rod 321 are provided with sliding teeth 322 on the opposite surfaces, and the connection rod 321 is clamped in the fourth sliding groove 2113 through the sliding teeth 322 and slides along the fourth sliding groove 2113. The connection rod 321 is provided with a second connection head 323 on the side adjacent to the standard support segment 31 of the plate formwork, and the second connection head 323 matches the adjacent second connection tenon 3112 or the connection tenon groove 3111. The second connection head 323 is connected and fixed with the corresponding second connection tenon 3112 or the connection tenon groove 3111 through bolts and nuts after being plugged in.
[0091] Specifically, a number of standard support segments 31 of plate formwork are connected end to end to form a plate formwork support beam. Multiple plate formwork support beams are placed in parallel and fit together longitudinally, and the ends are connected to the sliding connecting frame 32. The sliding connecting frame 32 is connected to the beam formwork support device 2; the second supporting beam 3121 is provided with a sixth sliding groove 3125 to support the sliding of the second opening and closing piece 312 when opening and closing. The second connecting tenon 3112 and the connecting tenon groove 3111 are used to connect adjacent standard support segments 31 of plate formwork or sliding connecting frames 32. The two ends of the width adjustment rod 313 are respectively installed in the mounting holes in the centers of the two second Bailey support pieces 311 to fix the width between the two second Bailey support pieces 311; the sliding tooth mouth 322 is connected to the upper and lower beams of the first Bailey support piece 211, and the position of the sliding tooth mouth 322 can be adjusted through the fourth sliding groove 2113.
[0092] An operating method of a lifting type beam and slab formwork supporting structure comprises the following steps:
[0093] S1, ground assembly board formwork support device 3;
[0094] S11, adjusting the second opening and closing piece 312 and the width adjustment rod 313 of the standard support segment 31 of the plate formwork to adjust the two second Bailey support pieces 311 to a suitable width;
[0095] S12, adjacent standard sections of slab formwork 31 are connected end to end through the second connecting tenon 3112 and the second connecting tenon groove 3111 and spliced to a required length to form a slab formwork support beam;
[0096] S13, repeat the above operation to place multiple board formwork support beams in parallel and close to each other;
[0097] S2, ground assembly beam formwork support device 2;
[0098] S21, adjust the first opening and closing piece 212 of the standard support segment 21 of the beam template to a suitable width, insert the crossbeam plug-in block 2125 into the installation slot 2114, lift it to a suitable height and fix it with the support limit block 216;
[0099] S22, connecting the beam formwork standard support segments 21 end to end through the first connecting tenon 2112 and the second connecting tenon groove 2111 and splicing them to the required length to form the beam formwork support device 2;
[0100] S23, installing a sliding connection frame 32 matching the plate formwork support device 3 in the fourth sliding groove 2113 of the beam formwork support device 2;
[0101] S3, connecting the beam formwork support device 2 and the plate formwork support device 3;
[0102] Connect the second connecting head 323 with the corresponding second connecting tenon 3112 or second connecting tenon groove 3111 to achieve the connection between the beam formwork supporting device 2 and the plate formwork supporting device 3;
[0103] S4, installing the support and lifting device 1;
[0104] S41, installing the power support segment 11;
[0105] S42, installing the support and lifting sleeve 15, and inserting the sliding bar 1521 into the first sliding groove 1121;
[0106] S43, continue to install the standard support segment 12 on the power support segment 11 to a suitable height;
[0107] S44, installing the fixed support segment 13, and finally installing the cable steering segment 14;
[0108] S45, the support and lifting device 1 can be installed with or without a column according to the situation; the support and lifting frame 15 is connected to the multi-stage gear lifting device 111 by a cable 4;
[0109] S5, connecting the beam formwork support device 2, the plate formwork support device 3 and the support and lifting device 1; the first connecting head 1543 on the support and lifting sleeve 15 is connected and fixed with the adjacent first connecting tenon 2112 or the second connecting tenon groove 2111;
[0110] S6, the beam formwork support device 2 and the plate formwork support device 3 are lifted;
[0111] S61, setting up secondary ribs and panels on the beam formwork support device 2 and the plate formwork support device 3;
[0112] S62, providing power through the multi-stage gear lifting device 111, driving the cable 4 to reel up and drive the beam formwork support device 2 and the plate formwork support device 3 to be lifted to the designed height, and installing the embedded support block 132 for support;
[0113] S7, pouring beam and slab concrete, when the concrete reaches the design strength requirement, lowering the beam formwork support device 2 and the slab formwork support device 3;
[0114] S8. Dismantle the beam formwork support device 2 and the slab formwork support device 3 in a dismantling manner opposite to the erection sequence.
[0115] The beam and slab supports of the present invention are both erected and dismantled at the bottom, which reduces the danger of erecting the support frame; the space below the support frame can be utilized to provide convenience for material storage and personnel passage; the beam formwork support device 2 can provide support for the casting of concrete beams of different widths and heights by adjusting the opening amplitude of the first opening and closing piece 212 and the first opening and closing piece 212 being erected at the position of the first Bailey support piece 211; the slab formwork support device 3 can adapt to the casting of concrete slabs of different widths by adjusting the opening angle of the second opening and closing piece 312; when the support lifting device is installed by holding the column, it has good stability and can be applied to the casting conditions of beams and slab formworks with larger heights.
[0116] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0117] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0118] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0119] The above is an exemplary description of the present invention. Obviously, the specific implementation of the present invention is not limited to the above-mentioned method. As long as various improvements are made using the method concept and technical solution of the present invention, or they are directly applied to other occasions without improvement, they are all within the protection scope of the present invention.
Claims
1. A lifting beam and slab formwork support structure, characterized in that: It comprises a support and lifting device (1), a beam formwork support device (2), a plate formwork support device (3), and a cable (4); the four lifting devices (1) are distributed in a rectangular shape; the beam formwork support device (2) can be detachably mounted on two support and lifting devices (1) corresponding to the beam; the plate formwork support device (3) can be detachably mounted between the two beam formwork support devices (2); the support and lifting device (1) lifts the beam formwork support device (2) and the plate formwork support device (3) to a designed height through the cable (4) to provide support for pouring a concrete beam and plate structure; The support and lifting device (1) comprises a power support segment (11), a standard support segment (12), a fixed support segment (13), a cable steering segment (14), and a support and lifting frame (15); the power support segment (11) is arranged at the bottom of the support and lifting device (1); a plurality of standard support segments (12) are stacked up and down and connected to the top of the power support segment (11); the fixed support segment (13) and the cable steering segment (14) are stacked up and down and connected to the top of the uppermost standard support segment (12); the cable lifting frame (15) slides up and down along the power support segment (11), the standard support segment (12), and the fixed support segment (13); a plurality of cables (4) are guided by the cable steering segment (14), one end of which is fixedly connected to the cable lifting frame (15), and the other end is connected to the power support segment (11); and the cable lifting frame (15) is driven to rise and fall by the power support segment (11) to drive the cable lifting frame (15) to rise and fall; The beam formwork support device (2) is composed of a plurality of beam formwork standard support segments (21) connected at the end, and the two beam formwork standard support segments (21) located at the head and the tail are detachably connected to the corresponding cable lifting sleeve (15); the plate formwork support device (3) includes a plurality of groups of plate formwork standard support segments (31), each group of plate formwork standard support segments (31) is connected at the end, and the plate formwork standard support segment (31) located at the end is adjacent to the beam formwork standard support segment (21) and is detachably installed with a sliding connection frame (32), and the sliding connection frame (32) is slidably connected to the two template standard support segments (21).
2. The lifting type beam and slab formwork support structure according to claim 1 is characterized in that: The power support segment (11) comprises four multi-stage gear lifting devices (111), four first support structures (112) and a plurality of pairs of first connection structures (113). The four first support structures (112) are distributed in a rectangular shape. The first connection structures (113) comprise a pair of L-shaped first connection blocks. The plurality of pairs of first connection blocks are fixed on opposite surfaces of two adjacent first support structures (112) from top to bottom and connected and fixed to each other by bolts and nuts. First sliding grooves (1121) are correspondingly arranged on opposite surfaces of two adjacent first support structures (112). The multi-stage gear lifting devices (111) are respectively installed at the bottom of opposite surfaces of two adjacent first support structures (112) and drive the cable (4) to wind up and unwind. The cable (4) drives the support lifting sleeve (15) to rise and fall along the first sliding groove (1121).
3. The lifting type beam and slab formwork support structure according to claim 2 is characterized in that: Each standard support segment (12) comprises four second support structures (121) and a plurality of pairs of second connection structures (122), the four second support structures (121) are distributed in a rectangular shape, the second connection structures (122) comprise a pair of L-shaped second connection blocks, and the plurality of pairs of second connection blocks are fixed on opposite surfaces of two adjacent second support structures (121) from top to bottom and connected and fixed to each other by bolts and nuts, the second support structures (121) of the plurality of standard support segments (12) are stacked and connected and fixed in sequence up and down, and the second support structure (121) of the lowest standard support segment (12) is fixedly mounted on the top of the corresponding first support structure (112), and a second sliding groove (1211) connected to the first sliding groove (1121) is provided on the opposite surfaces of the two connected second support structures (121), and the support lifting sleeve (15) is lifted and lowered along the second sliding groove (1211).
4. The lifting type beam and slab formwork support structure according to claim 3 is characterized in that: The fixed support segment (13) comprises four third support structures (131), four embedded support blocks (132) and a plurality of pairs of third connection structures (133). The four third support structures (131) are distributed in a rectangular shape. The third connection structures (133) comprise a pair of L-shaped third connection blocks. The plurality of pairs of third connection blocks are fixed from top to bottom on opposite surfaces of two adjacent third support structures (131) and connected and fixed to each other by bolts and nuts. The lower parts of the two adjacent third support structures (131) are correspondingly provided with slots (1311) which are embedded in the bottom of the support blocks (132). A bolt hole is provided corresponding to the bottom of the third support structure (131), the embedded support block (132) is inserted into the slot (1311) and is fixed by tightening the nut after the bolt passes through the bolt hole. The third support structure (131) is fixedly installed on the top of the second support structure (121) of the uppermost standard support segment (12), and a third sliding groove (1312) connected to the second sliding groove (1211) is provided on the opposite surfaces of two adjacent third support structures (131). The support lifting sleeve (15) is lifted and lowered along the third sliding groove (1312) and is supported by the embedded support block (132).
5. The lifting type beam and slab formwork support structure according to claim 4, characterized in that: The cable steering segment (14) comprises a rectangular cable frame (141), the tops of the four sides of the cable frame (141) are all provided with grooves (142), a plurality of fixed pulleys (143) are installed in the grooves (142), the cable frame (141) is fixed on the tops of the four third support structures (131), and the cable (14) is guided by the fixed pulleys (143).
6. The lifting type beam and slab formwork support structure according to claim 5, characterized in that: The support and lifting sleeve frame (15) comprises four support plates (151), four lifting connection blocks (152), four inverted U-shaped support frames (153), and four pairs of beam formwork support device connection frames (154). The four support plates (151) are distributed in a rectangular shape and fixed together. The lifting connection block (152) is fixed to the bottom of the support plate (151). A plurality of stiffening plates (155) are provided at the angle between the lifting connection block (152) and the outer wall of the support plate (151). A sliding bar (1521) is provided on the side wall of the lifting connection block (152). The sliding bar (1521) slides along the first sliding groove (1121), the second sliding groove (1211), and the third sliding groove (1312). One end of the cable (4) is fixedly connected to the top of the lifting connection block (152). The support frame (153) is fixed to the support The top of the support plate (151) is provided with a connected lower transverse sliding groove (1511) on the top of the four support plates (151), and the top of the four support frames (153) is provided with a connected upper transverse sliding groove (1531). The beam formwork support device connecting frame (154) includes a column (1541), and an upper notch (1542) is provided at one end of the top of the column (1541), and a first connecting head (1543) connected to the beam formwork support device (2) is provided at the other end. A lower notch (1544) is provided at the bottom of the column (1541). The column (1541) is hung on the top of the support frame (153) through the upper notch (1542) and slides along the upper transverse sliding groove (1531), and is inserted into the support plate (151) through the lower notch (1544) and slides along the lower transverse sliding groove (1511).
7. The lifting type beam and slab formwork support structure according to claim 6, characterized in that: Each beam formwork standard support segment (21) comprises a pair of first Bailey support plates (211), a first opening and closing plate (212) is detachably mounted between the opposite surfaces of the pair of first Bailey support plates (211), a first connecting tenon groove (2111) is provided at one end on the same side of the upper and lower cross beams of the first Bailey support plate (211), and a first connecting tenon (2112) is provided at the other end, and the first connecting tenons (2112) that are adjacent to each other when two adjacent beam formwork standard support segments (21) are connected end to end Inserted into the first connection tenon groove (2111) and connected and fixed by bolts and nuts, the inner and outer sides of the upper and lower cross beams of the first Bailey support plate (211) are correspondingly provided with fourth sliding grooves (2113), the front and rear sides of the vertical beams on both sides of the first Bailey support plate (211) are provided with through installation notches (2114), and the left and right sides are provided with a plurality of support limit plug holes (2115) from top to bottom, and the support limit plug holes (2115) are plugged with support limit blocks (2116); the first opening and closing plate (212 ) comprises a first supporting crossbeam (2121), a first opening and closing support (2122), a first connecting shaft (2123), a first sliding installation shaft (2124), and a crossbeam plug-in block (2125), wherein a fifth sliding groove (2126) is provided on the top of the first supporting crossbeam (2121), two first opening and closing supports (2122) are arranged in a scissor-like manner and are rotatably connected through the first connecting shaft (2123), and the first sliding installation shaft (2124) is installed at the end of the first opening and closing support (2122). The crossbeam plug-in block (2125) is fixed at both ends of the first supporting crossbeam (2121) adjacent to the first Bailey support plate (211), the crossbeam plug-in block (2125) is plugged into the installation slot (2114) and supported by the support limit block (2116), a limit plug hole is provided at the top of the support limit block (2116), a limit plug rod is provided at the bottom of the crossbeam plug-in block (2125), and the limit plug rod is inserted into the limit plug hole.
8. The lifting type beam and slab formwork support structure according to claim 7, characterized in that: The first connecting head (1543) matches the adjacent first connecting groove (2111) or the first connecting tenon (2112), and the first connecting head (1543) is connected and fixed with the corresponding first connecting groove (2111) or the first connecting tenon (2112) by bolts and nuts after being plugged in.
9. The lifting type beam and slab formwork support structure according to claim 7, characterized in that: The standard support segment (31) of the board formwork comprises a pair of second Bailey support plates (311), a second opening and closing plate (312) and a width adjustment rod (313) are arranged between the pair of second Bailey support plates (311), a second connecting tenon groove (3111) is arranged at one end on the same side of the upper and lower cross beams of the second Bailey support plate (311), and a second connecting tenon (3112) is arranged at the other end, and when two adjacent standard support segments (31) of the board formwork are connected end to end, the adjacent second connecting tenons (3112) are inserted into the second connecting tenon groove (3111) and connected by bolts. The second opening and closing piece (312) comprises a second supporting beam (3121), a second opening and closing support (3122), a second connecting shaft (3123), and a second sliding installation shaft (3124). The second supporting beam (3121) is fixed to the top of the upper beam of the second Bailey supporting piece (311). The top of the second supporting beam (3121) is provided with a sixth sliding groove (3125). The two second opening and closing supports (3122) are arranged in a scissor-like shape and are rotatably connected through the second connecting shaft (3123). The second sliding installation shaft (3124) is provided with a sixth sliding groove (3125). 4) is installed at the end of the second opening and closing support (3122) and is slidably connected in the sixth sliding groove (3125); the width adjustment rod (313) includes a screw rod (3131) and a sleeve (3132), the opposite ends of the two screw rods (3131) are respectively threadedly connected to the two ends of the sleeve (3132), and the opposite ends are respectively fixed to the center of the opposite surfaces of a pair of second Bailey support plates (311); the sliding connection frame (32) includes a C-shaped connecting rod (321), and the upper and lower plates of the connecting rod (321) are correspondingly provided with sliding teeth (322) on the opposite surfaces. , and the connecting rod (321) is clamped in the fourth sliding groove (2113) through the sliding tooth mouth (322) and slides along the fourth sliding groove (2113), and a second connecting head (323) is provided on the side of the connecting rod (321) adjacent to the standard support segment (31) of the plate formwork, and the second connecting head (323) matches the adjacent second connecting tenon (3112) or connecting tenon groove (3111), and the second connecting head (323) is connected and fixed with the corresponding second connecting tenon (3112) or connecting tenon groove (3111) through bolts and nuts after being plugged in.
10. An operating method of the lifting type beam and slab formwork support structure according to claim 9, characterized in that: The following steps are involved: S1, ground assembly board formwork support device (3); S11, adjusting the second opening and closing piece (312) and the width adjustment rod (313) of the standard support segment (31) of the plate formwork to adjust the two second Bailey support pieces (311) to a suitable width; S12, adjacent standard sections of slab formwork (31) are connected end to end through the second connecting tenon (3112) and the second connecting tenon groove (3111) and spliced to a required length to form a slab formwork support beam; S13, repeat the above operation to place multiple board formwork support beams in parallel and close to each other; S2, ground assembly beam formwork support device (2); S21, adjusting the first opening and closing piece (212) of the standard support segment (21) of the beam template to a suitable width, inserting the crossbeam plug-in block (2125) into the installation slot (2114), lifting it to a suitable height and fixing it with the support limit block (216); S22, connecting the beam formwork standard support segments (21) end to end through the first connecting tenon (2112) and the second connecting tenon groove (2111) and splicing them to a required length to form a beam formwork support device (2); S23, installing a sliding connection frame (32) matching the plate formwork support device (3) in the fourth sliding groove (2113) of the beam formwork support device (2); S3, connecting the beam formwork support device (2) and the plate formwork support device (3); The second connecting head (323) is connected to the corresponding second connecting tenon (3112) or second connecting tenon groove (3111) to achieve the connection between the beam formwork supporting device (2) and the plate formwork supporting device (3); S4, installing the support and lifting device (1); S41, installing the power support segment (11); S42, installing the support and lifting sleeve (15), and inserting the sliding bar (1521) into the first sliding groove (1121); S43, continue to install the standard support segment (12) on the power support segment (11) to a suitable height; S44, installing the fixed support segment (13), and finally installing the cable steering segment (14); S45, connecting the supporting lifting sleeve (15) and the multi-stage gear lifting device (111) with a cable (4); S5, connecting the beam formwork support device (2), the plate formwork support device (3) and the support and lifting device (1); the first connecting head (1543) on the support and lifting sleeve (15) is connected and fixed to the adjacent first connecting tenon (2112) or the second connecting tenon groove (2111); S6, the beam formwork support device (2) and the slab formwork support device (3) are lifted; S61, setting up secondary ribs and panels on the beam formwork support device (2) and the plate formwork support device (3); S62, providing power through the multi-stage gear lifting device (111), driving the cable (4) to reel in and drive the beam formwork support device (2) and the plate formwork support device (3) to be lifted to the designed height, and installing the embedded support block (132) for support; S7, pouring beam and slab concrete, and lowering the beam formwork support device (2) and the slab formwork support device (3) when the concrete reaches the design strength requirement; S8. Dismantle the beam formwork support device (2) and the plate formwork support device (3), and the dismantling method is opposite to the erection order.