Slope protection structure and construction method thereof

By using skeleton structure and assembled joints in slope protection, combined with prestressed anchor cables and rapid construction methods, the defects of the existing technology in applicability, beautification environment and construction efficiency are solved, and the stability of the slope is improved. Shorten construction time and cost savings.

CN119466001APending Publication Date: 2025-02-18MCC TIANGONG GROUP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411758631.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-03
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

The existing slope protection technology has defects in applicability, beautification environment and construction efficiency, especially on steep and unstable soil slopes, and the construction time is long and the cost is high.

Method used

A slope protection structure is adopted, including a skeleton structure and assembled joints, and the beam main body and assembled joints are connected through prestressed anchor cables to form a stable skeleton structure, and the construction time is shortened through prefabricated and rapid installation construction methods.

Benefits of technology

This technology can improve the stability of slopes, is suitable for slopes with different soil quality and slope ratios, shorten construction time, save costs, avoid natural disasters such as mudslides and landslides, and beautify the environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119466001A_ABST
    Figure CN119466001A_ABST
Patent Text Reader

Abstract

The invention provides a slope protection structure and a construction method thereof, and relates to the technical field of building construction.The slope protection structure comprises a framework structure, a slope protection structure and a protection structure, each splicing connector comprises a body, a plurality of flanges extending towards the outer side of the body are arranged on the periphery of the body, and the flanges can be connected with the splicing grooves; a pre-stressed anchor cable preformed hole is formed in the body. The construction method comprises the steps that the plane position of the slope protection structure is determined; prefabricating components of the slope protection structure; mounting components of the prefabricated slope protection structure; prestress tensioning and locking are conducted on the anchor cables on the slope protection structure; according to the construction method, gaps among components in the slope protection structure are poured, secondary grouting is carried out on gaps between the components and the slope surface, and the construction method has the beneficial effects that the stability of the slope can be improved, the adaptability is high, the environment is beautified, the construction time can be shortened, and the cost is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a slope protection structure and a construction method thereof. Background Art

[0002] In the process of road and bridge construction, the strength and stability of the roadbed construction have a direct impact on the overall quality of the project. The focus of roadbed protection construction is roadbed slope protection, which is mainly aimed at the roadbed formed during the filling and excavation of the rock and soil. When the roadbed is deformed and moved due to factors such as slope stability, natural factors, and changes in the physical and mechanical properties of the rock and soil, it is necessary to adopt slope protection construction technology.

[0003] At present, the types of engineering protection for slopes include stone slope protection, concrete block slope protection, shotcrete anchor slope protection, etc.

[0004] The applicant has found that the existing engineering protection applicability and environmental beautification have certain defects, mainly as follows:

[0005] The stone slope protection is only suitable for relatively stable soil layers and stone slopes, and is not suitable for relatively steep slopes with unstable soil, and has certain limitations, such as red clay and high liquid limit soil.

[0006] Concrete block slope protection, concrete block bricks have high unit prices, and due to the limitations of block size, the construction time of block paving is long and other defects.

[0007] Sprayed anchor slope protection is to hang a mesh and spray grout on the slope, but it has certain defects in beautifying the environment along the project and improving the ornamental value of the project. Summary of the invention

[0008] The purpose of the present invention is to provide a slope protection structure and a construction method thereof, which can not only improve the stability of the slope, have strong adaptability and beautify the environment, but also shorten the construction time and save costs, and ensure that the ecological environment and environmental geology problems such as mudslides, landslides and vegetation destruction will not be caused by the destruction of slope stability.

[0009] The various technical effects that can be produced by the preferred technical solutions among the various technical solutions provided by the present invention are described in detail below.

[0010] To achieve the above object, the present invention provides the following technical solutions:

[0011] The present invention provides a slope protection structure, comprising:

[0012] The skeleton structure comprises a plurality of beam bodies, each of which has a splicing groove at both ends and a prestressed anchor cable reserved hole on the beam body;

[0013] A plurality of assembling joints are arranged in the skeleton structure, and the assembling joints include a main body, and a plurality of flanges extending toward the outside of the main body are arranged on the periphery of the main body, and the flanges can be connected to the splicing grooves; and the prestressed anchor cable reserved holes are arranged on the main body.

[0014] Preferably, the splicing groove is configured as a "U"-shaped groove opened along the end surface of the beam body toward the inner side of the beam body.

[0015] Preferably, the width of the "U"-shaped groove is 1 / 2 of the width of the beam body.

[0016] Preferably, the main body adopts a square structure, the flange is arranged on four surfaces of the main body that are distributed in a "cross" shape, and the flange is located in the middle of the surface on which it is located.

[0017] Preferably, the prestressed anchor cable reserved hole is arranged at the center of the body.

[0018] Preferably, the diameter of the reserved hole for the prestressed anchor cable is 5 cm.

[0019] Preferably, a mounting hole is provided on the beam body.

[0020] A construction method of the above-mentioned slope protection structure comprises the following steps:

[0021] S1: Determine the plane position of the slope protection structure;

[0022] S2: Prefabricating components of the slope protection structure, including prefabricating a plurality of beam bodies and a plurality of assembly joints according to the plane position of the required slope protection structure;

[0023] S3: installing components of the prefabricated slope protection structure, including installing components of the prefabricated slope protection structure on the slope to be protected to form a slope protection structure;

[0024] S4: prestressing and locking the anchor cables on the slope protection structure;

[0025] S5: Grout the gaps between the components in the slope protection structure, and perform secondary grouting on the gaps between the components and the slope surface.

[0026] The slope protection structure provided by the present invention connects multiple beam bodies through assembly joints, and the multiple beam bodies form a skeleton structure. Stress anchor cable reserved holes are set on the assembly joints and the beam bodies. The structure has strong stability and can effectively prevent natural disasters such as debris flow and landslide from damaging and collapsing roads or other buildings. It can be applied to slope protection of different soils and different slope ratios, has the functions of protecting slopes and beautifying the environment, and can replace traditional protection measures such as spray anchor slope protection and stone slope protection under the same conditions. The use of this slope protection structure for slope protection can not only improve the stability of the slope, but also shorten the construction time and save costs.

[0027] The construction method of the slope protection structure provided by the present invention includes determining the plane position of the slope protection structure; prefabricating components of the slope protection structure, including prefabricating multiple beam bodies and multiple assembly joints according to the plane position of the required slope protection structure; installing the components of the prefabricated slope protection structure on the slope to be protected to form the slope protection structure; prestressing and locking the anchor cables on the slope protection structure; grouting the gaps between the components in the slope protection structure, and performing secondary grouting on the gaps between the components and the slope surface. The construction method can be quickly completed, which can not only improve the stability of the slope, but also shorten the construction time and save costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0029] Figure 1 It is a structural schematic diagram of an embodiment of a slope protection structure of the present invention;

[0030] Figure 2 It is a structural schematic diagram of the skeleton structure in the slope protection structure of the present invention;

[0031] Figure 3 It is a structural schematic diagram of an assembly joint in a slope protection structure of the present invention;

[0032] Figure 4 It is a structural schematic diagram of the connection between the assembly joint and the beam body in the slope protection structure of the present invention;

[0033] Figure 5 It is a flow chart of the construction method of the slope protection structure of the present invention.

[0034] In the figure: 1, skeleton structure; 10, beam body; 100, splicing groove;

[0035] 2. Assembling joint; 20. Body; 200. Flange;

[0036] 30. Reserved holes for prestressed anchor cables. DETAILED DESCRIPTION

[0037] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.

[0038] Figure 1 Schematic diagram of the structure of this embodiment. Figure 1 As shown, this embodiment provides a slope protection structure, including a skeleton structure 1 and a plurality of assembly joints 2.

[0039] in, Figure 2 Schematic diagram of the skeleton structure in this embodiment. Figure 1 As shown, the skeleton structure 1 in this embodiment includes a plurality of beam bodies 10, and a splicing groove 100 is respectively arranged at both ends of each beam body 10. Optionally, a prestressed anchor cable reserved hole 30 is arranged on the beam body.

[0040] Figure 3 : is a schematic diagram of the structure of the assembled joint in this embodiment, Figure 4 Schematic diagram of the structure of the connection between the assembly joint and the beam body in this embodiment. Figure 3 and Figure 4 As shown, the slope protection structure is provided with a plurality of assembling joints 2 , and the plurality of assembling joints 2 are all arranged in the skeleton structure 1 .

[0041] The assembly joint 2 in this embodiment includes a body 20, and a plurality of flanges 200 extending toward the outside of the body 20 are arranged on the periphery of the body 20, and the flanges 200 can be connected to the splicing groove 100. In addition, a prestressed anchor cable reserved hole 30 is arranged on the body 20.

[0042] This slope protection structure connects multiple beam bodies 10 through an assembly joint 2, and the multiple beam bodies 10 form a skeleton structure. Prestressed anchor cable reserved holes 30 are set on the assembly joints 2 and the beam bodies 10. When used, it can not only improve the stability of the slope, have strong adaptability and beautify the environment, but also shorten the construction time and save costs, ensuring that the ecological environment and environmental geology problems such as mudslides, landslides and vegetation destruction will not be caused by the destruction of slope stability.

[0043] Preferably, the prestressed anchor cable reserved hole 30 in this embodiment is arranged at the center of the main body 20, and the diameter of the prestressed anchor cable reserved hole 30 is 5 cm, so as to ensure the smooth progress of the construction.

[0044] As an optional embodiment, the splicing groove 100 is configured as a "U"-shaped groove opened along the end surface of the beam body 10 toward the inner side of the beam body 10, so that the beam body 10 can be quickly installed and used with the splicing joint 2.

[0045] The width of the "U"-shaped groove in this embodiment is 1 / 2 of the width of the beam body 10. This arrangement can ensure both the efficiency of installation and the connection strength, thereby improving the stability of the slope protection structure.

[0046] As an optional embodiment, the main body 20 adopts a square structure, and the flange 200 is arranged on four surfaces of the main body 20 that are distributed in a "cross" shape, and the flange 200 is located in the middle of the surface on which it is located.

[0047] Such arrangement, on the one hand, can ensure that the beam body 10 is installed in the middle of the main body 20, thereby improving the stability of the overall structure; on the other hand, since the flanges 200 are arranged on the four surfaces of the main body 20 in a "cross" distribution, the overall structure can be arranged regularly, which has the function of protecting the slope while being more aesthetically pleasing and playing a role in beautifying the environment.

[0048] During the highway roadbed protection construction process, it is necessary to select and apply different roadbed protection construction measures according to different geological conditions and environmental characteristics to ensure the applicability and effectiveness of the adopted construction measures.

[0049] To this end, this embodiment provides a construction method for the above-mentioned slope protection structure. This method adopts the construction technology of prefabricated prestressed anchor cable assembly skeleton. The start and end time of skeleton prefabrication can be combined with the construction schedule so that prefabricated components can be installed in time after the roadbed slope is formed.

[0050] Figure 5 It is a construction flow chart of an embodiment, such as Figure 5 As shown in FIG. 1 , the construction method of the slope protection structure specifically includes the following steps:

[0051] S1: Determine the plane position of the slope protection structure;

[0052] In this embodiment, the plan positions of the prefabricated frame and the cast-in-place frame are first determined according to the design drawings, and the prefabrication and installation plan of the prefabricated frame is drawn, and it is ensured that the construction of the roadbed slope, frame prefabrication, frame installation, etc. meets the design and specification requirements. The start and end time of the frame prefabrication can be combined with the construction schedule so that the prefabricated components can be installed in time after the roadbed slope is formed.

[0053] S2: Prefabricate components of the slope protection structure, including prefabricating a plurality of beam bodies 10 and a plurality of assembly joints 2 according to the plane position of the required slope protection structure;

[0054] In this embodiment, before construction, the beam body 10 and the assembly joint 2 of the slope protection structure are prepared according to the design drawings and the drawn plan.

[0055] The skeleton prefabrication can be constructed according to the construction process of site construction - cleaning the formwork, applying the release agent - mixing concrete - vibrating on a flat vibration table - surface calendering - automatic spray curing - demoulding - finished product curing, and the prefabricated geometric dimensions, anchor cable reserved holes and reserved positions and other parameters must meet the design and specification requirements. The prefabricated components should also be numbered according to the skeleton installation diagram. After demoulding, all components should be placed in the seats and stacked in sections to guide the transportation and installation of the components.

[0056] S3: installing components of the prefabricated slope protection structure, including installing components of the prefabricated slope protection structure on the slope to be protected to form a slope protection structure;

[0057] In this embodiment, after the slope is formed, the slope surface is trimmed according to the design requirements, and the anchor hole location, drilling, anchor cable installation, grouting, slope surface grooving, base concrete pouring and other preparatory work are carried out in combination with the design drawings and plan. After everything is ready, the prefabricated components are installed according to the design drawings and plan.

[0058] S4: After the installation is completed, the anchor cables are prestressed and locked on the slope protection structure as required;

[0059] S5: Grout the gaps between the components in the slope protection structure, and perform secondary grouting on the gaps between the components and the slope surface.

[0060] Specifically, in this embodiment, after the anchor cable is locked, the gaps between the components are first grouted, and then the gaps between the components and the slope are grouted for the second time to ensure that the prefabricated components are tightly attached to the slope without any voids. After the skeleton installation work is completed, the slope soil should be shaped immediately, and the leveled slope should be compacted manually to ensure that the soil does not slide automatically and the particles do not roll off.

[0061] As an optional implementation, after the construction is completed, grass planting protection construction is carried out on the skeleton structure 1.

[0062] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A slope protection structure, characterized in that: include: The skeleton structure comprises a plurality of beam bodies, each of which has a splicing groove at both ends and a prestressed anchor cable reserved hole on the beam body; A plurality of assembling joints are arranged in the skeleton structure, and the assembling joints include a main body, and a plurality of flanges extending toward the outside of the main body are arranged on the periphery of the main body, and the flanges can be connected to the splicing grooves; and the prestressed anchor cable reserved holes are arranged on the main body.

2. A slope protection structure according to claim 1, characterized in that: The splicing groove is configured as a "U"-shaped groove opened along the end surface of the beam body toward the inner side of the beam body.

3. A slope protection structure according to claim 2, characterized in that: The width of the "U"-shaped groove is 1 / 2 of the width of the beam body.

4. A slope protection structure according to any one of claims 1 to 3, characterized in that: The main body adopts a square structure, the flange is arranged on four faces of the main body that are distributed in a "cross" shape, and the flange is located in the middle of the face on which it is located.

5. A slope protection structure according to any one of claims 1 to 3, characterized in that: The prestressed anchor cable reserved hole is arranged at the center of the body.

6. A slope protection structure according to claim 5, characterized in that: The diameter of the reserved hole for the prestressed anchor cable is 5 cm.

7. A slope protection structure according to any one of claims 1 to 3, characterized in that: The beam body is provided with a mounting hole.

8. A construction method for a slope protection structure according to any one of claims 1 to 7, characterized in that: The steps include: S1: Determine the plane position of the slope protection structure; S2: Prefabricating components of the slope protection structure, including prefabricating a plurality of beam bodies and a plurality of assembly joints according to the plane position of the required slope protection structure; S3: installing components of the prefabricated slope protection structure, including installing components of the prefabricated slope protection structure on the slope to be protected to form a slope protection structure; S4: prestressing and locking the anchor cables on the slope protection structure; S5: Grout the gaps between the components in the slope protection structure, and perform secondary grouting on the gaps between the components and the slope surface.