Ultra-low energy consumption building structure based on light materials and intelligent construction method

By adopting lightweight materials and intelligent construction methods in ultra-low energy consumption building structures, the problems of high construction costs and low efficiency are solved, and an efficient and energy-saving and environmentally friendly architectural design is achieved.

CN119507593AInactive Publication Date: 2025-02-25BEIJING DAHAN CONSTRUCTION ENGINEERING CO LTD

Patent Information

Application Number
CN202411599222.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-11
Publication Date
2025-02-25
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing ultra-low energy consumption building structures are costly and inefficient during construction, and the technological maturity and reliability limit their large-scale application.

Method used

It adopts ultra-low energy consumption building structure design based on lightweight materials, including exterior walls, windows, fresh air heat recovery systems and other components, and is factory-made prefabricated and unit-assembled exterior wall structures through intelligent construction methods.

Benefits of technology

It reduces energy consumption and carbon emissions, improves thermal insulation performance, reduces energy loss inside the building, shortens construction cycles and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119507593A_ABST
    Figure CN119507593A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of intelligent construction, in particular to an ultra-low energy consumption building structure based on light materials and an intelligent construction method.The ultra-low energy consumption building structure based on the light materials comprises an outer wall and a window, the outer wall is composed of a structural layer, a heat insulation layer, a waterproof layer, a heat preservation layer, a decoration layer and a plate buckle structure and used for heat preservation, heat insulation and control of indoor and outdoor heat exchange, and the window is composed of a window frame, glass and sealing strips. The fresh air heat recovery system is used for optimizing a heat transfer path, reducing heating, refrigeration and ventilation energy consumption of a building, preventing moisture from invading a room and avoiding wall mildew and structural damage, and the fresh air heat recovery system is composed of a heat exchange system, a power system, a filtering system, a box body and a control system and is used for ventilation, air exchange, air purification and indoor environment adjustment, so that the energy consumption of an air conditioning system is reduced, and the energy consumption of the air conditioning system is reduced. The energy-saving technology of light materials is adopted, energy consumption and carbon emission are reduced, the intelligent construction scheme is adopted, the construction period is shortened, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of intelligent construction, and in particular to an ultra-low energy consumption building structure based on lightweight materials and an intelligent construction method. Background Art

[0002] With the global emphasis on energy conservation and emission reduction and the growing demand for sustainable development in the construction industry, energy-saving technology for building exterior walls has become particularly critical. Traditional buildings often ignore energy efficiency during design and construction, resulting in a lot of energy waste and environmental pollution. For example,

[0003] Traditional building exterior walls are mostly made of a single material, such as ordinary bricks or concrete. Although these materials have certain structural strength, they perform poorly in terms of thermal insulation and heat preservation. In addition, the existing technology also has certain limitations in construction methods. For example, there is a lack of an effective multi-layer material collaborative working mechanism, and the existing technology does not accurately adjust the selected exterior wall panel buckle structure, which has a significant impact on construction.

[0004] Chinese Patent Publication No.: CN109138146A discloses a low-energy assembled building, in which the exterior wall of the building is an assembled energy-saving double-layer curtain wall, the interior partition wall of the building is installed with phase change wall heating, the interior ceiling is an energy storage ceiling, the interior floor is an energy storage floor, photovoltaic thermal solar panels are installed on the roof and the exterior of the building, the building doors and windows use reverse phase change glass windows, the building's household water pipes are connected to the ground source heating water system, the hollow wall of the double-layer curtain wall is connected to the indoor air inlet, and the other end of the hollow wall is connected to the ground source heating fresh air system. The building with multiple energy storage systems of the present invention has the functions of autonomously providing indoor energy, hot water and fresh air, automatically regulating indoor temperature, saving energy and reducing consumption; and it is convenient to build, directly assembled and constructed, integrating ecological environment, ecological energy utilization and building structure, integrating the two systems of traditional architectural aesthetics and green building technology, and truly achieving a high degree of unity between ecological energy conservation and architectural innovation; the building structure also has multiple functions such as light weight, earthquake resistance, fire prevention, and sound insulation. It can be seen that the low-energy assembly building has the following problems: the building adopts a variety of advanced technologies and materials, such as assembled energy-saving double-layer curtain walls, phase change wall heating, energy storage ceilings and floors, photovoltaic thermal solar panels, etc. The maturity, reliability and high cost of these technologies may limit their promotion in large-scale applications. Summary of the invention

[0005] To this end, the present invention provides an ultra-low energy consumption building structure based on lightweight materials and an intelligent construction method, so as to overcome the problems of high construction cost and low construction efficiency of ultra-low energy consumption building structures in the prior art.

[0006] To achieve the above objectives, on the one hand, the present invention provides an ultra-low energy consumption building structure based on lightweight materials, comprising:

[0007] External wall, which is installed on the outer surface of the ultra-low energy consumption building structure, directly contacts with the external environment, and is used for heat preservation and insulation, and controls the exchange of indoor and outdoor heat;

[0008] The window is composed of a window frame, glass and a sealing strip. The window frame is installed at the periphery of the window and connected to the outer wall to fix the window and support the overall weight of the window. The glass is installed in the middle of the window and connected to the window frame to be used for heat insulation. The sealing strip is installed between the window frame and the glass and between the window frame and the outer wall to fill the gap and provide sealing;

[0009] The fresh air heat recovery system is composed of a heat exchange system, a power system, a filtering system, a box, and a control system. The heat exchange system is installed at the intersection of the air ducts of the air intake and exhaust, and is used to recover the cold and heat in the exhaust air and preheat and precool the intake air. The power system includes an air intake fan and an exhaust fan, which are connected to the heat exchange system and are used to drive the air intake and exhaust generated by the fan. The filtering system is installed at the air inlet of the air intake fan and is used to remove harmful substances in the intake air. The box is the outer shell of the fresh air heat recovery system and is used to protect the fresh air heat recovery system. The control system is installed in the equipment room and is used to monitor and adjust the temperature, humidity and air volume in the system in real time.

[0010] Furthermore, the outer wall comprises:

[0011] A heat-insulating layer installed on the second layer of the exterior wall to isolate the temperature difference between the indoor and outdoor environments of the ultra-low energy consumption building structure;

[0012] A waterproof layer, which is installed on the third layer of the exterior wall and is used to isolate rainwater erosion and penetration;

[0013] An insulation layer, which is installed on the fourth layer of the exterior wall and is used to control the transfer of heat inside and outside the ultra-low energy consumption building structure;

[0014] A decorative layer, which is installed on the outermost layer of the exterior wall and is used to provide an appearance design of the ultra-low energy consumption building structure and withstand external physical impact;

[0015] The plate buckle structure is installed at the edge of the external wall and is formed by the first flange, the second flange and the first groove, the second groove of two plates engaging with each other to provide stability and durability.

[0016] In another aspect, the present invention provides an intelligent construction method for an ultra-low energy consumption building structure based on lightweight materials, the method comprising:

[0017] Step S1, acquiring building size data, and locating the building base point according to the building size data to obtain the building base point coordinates;

[0018] Step S2, calculating the thickness of the outer wall corresponding to the building base point according to the building base point coordinates to obtain the outer wall thickness size;

[0019] Step S3, performing a stress analysis on the plate buckle structure of the exterior wall structural unit according to the building base point coordinates, the exterior wall thickness and the exterior wall structural unit information to obtain an unstable exterior wall structural unit;

[0020] Step S4, performing environmental index analysis according to the building environmental information, and adjusting the process of performing stress analysis on the plate buckle structure of the exterior wall structural unit according to the analysis results;

[0021] Step S5, performing environmental service analysis according to the user's required service life, and adjusting the environmental indicator analysis process according to the analysis results;

[0022] Step S6, reinforcing the unstable exterior wall structural unit with plate buckles;

[0023] Step S7, performing stress simulation on the plate buckle reinforcement, and providing feedback on the plate buckle reinforcement status according to the simulation results;

[0024] Step S8, optimizing the plate buckle reinforcement process according to the feedback result;

[0025] Step S9, performing a thermal analysis on the exterior wall structural unit according to the user's building thermal habits, and setting the fresh air heat recovery system and the exterior wall structural unit attribute distribution according to the thermal analysis results.

[0026] Furthermore, in step S2, the thickness of the outer wall corresponding to the building base point coordinates (x, y, z) is calculated:

[0027]

[0028] Among them, H is the thickness of the outer wall, T is the temperature value obtained through real-time monitoring, T0 is the preset temperature, z is the height of the outer wall, z0 is the preset height of the outer wall, B is the noise value obtained through real-time monitoring, and B0 is the preset noise value that affects the thickness of the outer wall.

[0029] Furthermore, in step S3, when the plate buckle structure of the external wall structural unit is subjected to stress analysis, a stress strength analysis is performed according to the building base point coordinates, the external wall thickness and the external wall structural unit information, and the stress strength N of the plate buckle structure is compared with the preset stress strength NO, and the stability of the external wall structural unit is judged according to the comparison result, wherein:

[0030] When N>NO, the exterior wall structural unit is determined to be stable;

[0031] When N≤NO, the exterior wall structural unit is determined to be unstable and marked as an unstable unit.

[0032] Furthermore, in step S4, when analyzing the environmental index according to the building environmental information, the environmental index A is compared with the preset environmental index A0, and the process of performing the stress analysis on the plate buckle structure of the exterior wall structural unit is adjusted according to the comparison result, wherein:

[0033] When A>AO, the environmental index is determined to be abnormal, a correction coefficient is set, and the preset force intensity NO is adjusted according to the correction coefficient. The adjusted preset force intensity is Na, and Na=N0×a is set;

[0034] When A≤AO, the environmental index is judged to be normal, and there is no need to adjust the stress analysis process of the plate buckle structure of the exterior wall structural unit.

[0035] Furthermore, in step S5, when the environmental service analysis is performed according to the user's required service life, the required service life S is compared with the preset required service life S0, and the environmental service analysis is performed according to the comparison result, wherein:

[0036] When S>S0, it is difficult to judge the service environment, and the correction coefficient is set The preset environmental index A0 is adjusted according to the correction coefficient, and the adjusted environmental index is Aa, Aa = A0 × b;

[0037] When S≤S0, it is easy to determine the environmental service and there is no need to adjust the environmental indicator analysis process.

[0038] Furthermore, in step S6, when the unstable exterior wall structural unit is reinforced with plate buckles, the plate buckle model is optimized, and the force strength level of the plate buckle model is divided into three levels: A, B, and C, wherein:

[0039] If the stress strength of the unstable exterior wall structure unit plate buckle model is A, the stress strength grade of the optimized plate buckle model is A;

[0040] If the stress strength of the unstable exterior wall structure unit plate buckle model is B, the stress strength level of the optimized plate buckle model is A;

[0041] If the stress strength of the unstable exterior wall structure unit plate buckle model is C, the stress strength grade of the optimized plate buckle model is B.

[0042] Furthermore, in step S7, when feedback is given on the reinforcement of the plate buckle, a simulation model of the plate buckle structure is established using simulation software, and the stress strength is simulated and analyzed, the stress strength simulation result N1 is compared with the preset stress strength NO, and feedback is given on the reinforcement of the plate buckle according to the comparison result, wherein:

[0043] When N1>N0, the plate buckle reinforcement is determined to be effective;

[0044] When N1≤N0, the plate buckle reinforcement is determined to be invalid;

[0045] In step S8, when optimizing the plate buckle reinforcement process according to the feedback results, when N1≤N0 and the plate buckle reinforcement is invalid, it is necessary to adjust the plate buckle reinforcement quantity S and set the correction coefficient c=1+0.1(N1-N0)+0.01(N1-N0) 2 , and adjust the number of plate buckle reinforcements S according to the correction coefficient. The adjusted number of plate buckle reinforcements is Sa, and Sa is set to S×c.

[0046] Furthermore, in step S9, when setting the attribute distribution of the fresh air heat recovery system and the exterior wall structure unit, the heat usage mode, heat usage days and average temperature parameters are input into the heat usage habit analysis model to obtain the output results of the heat usage habit analysis model, including the heat dissipation area, the heat usage area and the thermoelectric conversion area, which are used as the user's building heat usage habits, and an insulation layer is set on the heat dissipation area pipe, a heat exchanger is set on the heat usage area pipe, a waste heat collection pipe is set in the thermoelectric conversion area, the exterior wall structure unit of the heat dissipation area is made of a material with thermal insulation performance, the exterior wall structure unit of the heat usage area is made of a material with heat insulation performance, and the exterior wall structure unit of the thermoelectric conversion area is made of a material with sealing performance.

[0047] Compared with the prior art, the beneficial effects of the present invention are that the energy-saving technology and design using lightweight materials can reduce energy consumption and carbon emissions, have good thermal insulation properties, help reduce energy loss inside the building, and adopt intelligent construction solutions through factory prefabrication and unitized assembly of exterior wall structures to shorten the construction period and reduce construction costs.

[0048] In particular, the exterior wall reduces heat transfer losses in ultra-low energy consumption building structures, utilizes renewable energy such as solar energy, reduces dependence on traditional energy, helps maintain indoor temperature stability, and improves comfort.

[0049] In particular, the step S2 calculates the thickness of the outer wall corresponding to the building base point according to the building base point coordinates to obtain the outer wall thickness dimension, so as to ensure the stability of the ultra-low energy consumption building structure and meet the design requirements.

[0050] In particular, the step S3 performs a stress analysis on the plate buckle structure of the exterior wall structure unit according to the building base point coordinates, the exterior wall thickness and the exterior wall structure unit information to obtain an unstable exterior wall structure unit, so as to facilitate targeted reinforcement and optimization design of the ultra-low energy consumption building structure to ensure the overall structural safety of the ultra-low energy consumption building structure.

[0051] In particular, the step S4 performs environmental index analysis based on the building environment information, and adjusts the process of stress analysis of the plate buckle structure of the exterior wall structural unit based on the analysis results, so as to accurately evaluate the stability and safety of the exterior wall structural unit under different environmental conditions, thereby taking effective reinforcement or optimization measures.

[0052] In particular, step S5 performs an environmental service analysis based on the user's required service life, and adjusts the environmental indicator analysis process based on the analysis results, so as to accurately predict the performance changes and potential risks of the exterior wall structural unit during long-term use, and provide support for optimizing the reinforcement plan.

[0053] In particular, the step S6 performs plate buckle reinforcement on the unstable exterior wall structure unit so as to enhance the stability, bearing capacity and durability of the exterior wall structure unit, thereby ensuring the overall safety of the ultra-low energy consumption building structure and extending its service life.

[0054] In particular, the step S7 performs stress simulation on the plate buckle reinforcement, and provides feedback on the plate buckle reinforcement according to the simulation results, so as to verify the effectiveness and safety of the reinforcement design and ensure that the reinforced exterior wall structural unit can meet the use requirements;

[0055] The step S8 adjusts the plate buckle reinforcement process according to the feedback result, so as to ensure that the reinforced exterior wall structural unit has good mechanical properties and stability and meets the use requirements of ultra-low energy consumption building structures.

[0056] In particular, step S9 performs thermal analysis on the exterior wall structure unit according to the user's building thermal habits, and sets the fresh air heat recovery system and the exterior wall structure unit property distribution according to the thermal analysis results, so as to improve the energy efficiency of the ultra-low energy consumption building structure, ensure the comfort of the indoor environment, and reduce energy consumption. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] Figure 1 This is a schematic diagram of the structure of an ultra-low energy consumption building structure based on lightweight materials in this embodiment;

[0058] Figure 2 This is a schematic diagram of the structure of the exterior wall of this embodiment;

[0059] Figure 3 Schematic diagram of the process of the intelligent construction method of the ultra-low energy consumption building structure based on lightweight materials in this embodiment. DETAILED DESCRIPTION

[0060] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0061] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.

[0062] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0063] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0064] See also Figure 1 As shown, it is a structural schematic diagram of an ultra-low energy consumption building structure based on lightweight materials in this embodiment, and the ultra-low energy consumption building structure includes:

[0065] External wall 1, which is installed on the outer surface of the ultra-low energy consumption building structure, directly contacts the external environment, and is used for heat preservation and insulation, and controls the exchange of indoor and outdoor heat;

[0066] The window 2 is composed of a window frame 3, a glass 4 and a sealing strip 5. The window frame 3 is installed at the periphery of the window 2 and connected to the outer wall 1 to fix the window 2 and support the overall weight of the window 2. The glass 4 is installed in the middle of the window 2 and connected to the window frame 3 to be used for heat insulation. The sealing strip 5 is installed between the window frame 3 and the glass 4 and between the window frame 3 and the outer wall 1 to fill the gap and provide sealing;

[0067] The fresh air heat recovery system 6 is composed of a heat exchange system 7, a power system 8, a filtering system 9, a box 10, and a control system 11. The heat exchange system 7 is installed at the intersection of the air ducts of the air intake and exhaust, and is used to recover the cold and heat in the exhaust air, and preheat and precool the intake air. The power system 8 includes an air intake fan and an exhaust fan, which are connected to the heat exchange system 7, and are used to drive the air intake and exhaust generated by the fan. The filtering system 9 is installed at the air inlet of the air intake fan, and is used to remove harmful substances in the intake air. The box 10 is the outer shell of the fresh air heat recovery system 6, which is used to protect the fresh air heat recovery system 6. The control system 11 is installed in the equipment room, and is used to monitor and adjust the temperature, humidity and air volume in the system in real time.

[0068] Specifically, the ultra-low energy consumption building structure is insulated through the exterior wall, thereby improving the stability and durability of the ultra-low energy consumption building structure, reducing the transmission and loss of indoor and outdoor heat, and improving the thermal insulation performance of the building. The ultra-low energy consumption building structure optimizes the heat transfer path through windows, thereby reducing the heating, cooling and ventilation energy consumption of the building, reducing heat loss, preventing moisture from invading the room, avoiding wall mildew and structural damage. The ultra-low energy consumption building structure is sealed and soundproofed through window frames, thereby isolating external noise and improving indoor quietness. The ultra-low energy consumption building structure is illuminated through glass, thereby introducing natural light and providing a good field of view. The ultra-low energy consumption building structure is waterproof and dustproof through sealing strips, thereby preventing external pollutants such as rainwater and dust from entering the room and keeping the indoor environment clean and dry. The ultra-low energy consumption building structure is sealed and soundproofed through window frames, thereby isolating external noise and improving indoor quietness. The heat recovery system ventilates, purifies the air and adjusts the indoor environment, thereby reducing the energy consumption of the air-conditioning system and maintaining a stable indoor temperature. The ultra-low energy consumption building structure maintains stable indoor temperature and humidity through a heat exchange system, thereby improving indoor air quality. The ultra-low energy consumption building structure drives the fan in the fresh air heat recovery system through a power system, thereby achieving the discharge of indoor polluted air and the introduction of outdoor fresh air. The ultra-low energy consumption building structure removes large particles and impurities in the air through a filtration system, thereby reducing pollution and wear on the fresh air heat recovery system and extending its service life. The ultra-low energy consumption building structure reduces noise through sound insulation and noise reduction of the box body, thereby reducing the noise generated during the operation of the fresh air heat recovery system, providing users with a more peaceful living environment. The ultra-low energy consumption building structure achieves intelligent control through a control system, thereby improving the living comfort of users.

[0069] The air intake fan refers to a device that delivers processed fresh air into each room through pipes to ensure the circulation and renewal of indoor air. The exhaust fan refers to a device that extracts dirty air from the room and discharges it to the outside through a heat exchange system to achieve circulation and purification of indoor air. Harmful substances in the incoming air include dust and bacteria.

[0070] It is understandable that this embodiment does not limit the installation location of the control system, and those skilled in the art can freely set it according to actual conditions as long as the control requirements are met, such as being set in an equipment room or a control room.

[0071] Specifically, the ultra-low energy consumption building structure can reduce energy consumption and carbon emissions by adopting energy-saving technology and design using lightweight materials, has good thermal insulation properties, and helps reduce energy losses inside the building.

[0072] See also Figure 2 As shown, it is a schematic diagram of the structure of the exterior wall of this embodiment, and the exterior wall includes:

[0073] A structural layer 12, which is installed at the innermost layer of the outer wall and is used to provide stability and support for the ultra-low energy consumption building structure;

[0074] A heat insulation layer 13, which is installed on the second layer of the exterior wall and is used to isolate the temperature difference between the indoor and outdoor environments of the ultra-low energy consumption building structure;

[0075] A waterproof layer 14, which is installed on the third layer of the exterior wall to isolate rainwater erosion and penetration;

[0076] Insulation layer 15, the insulation layer is installed on the fourth layer of the outer wall, and is used to control the transfer of heat inside and outside the ultra-low energy consumption building structure;

[0077] A decorative layer 16, which is installed on the outermost layer of the exterior wall and is used to provide an appearance design for the ultra-low energy consumption building structure and withstand external physical impacts;

[0078] The plate buckle structure 17 is installed at the edge of the external wall and is formed by the first flange 19, the second flange 21 and the first groove 18, the second groove 20 of the two plates engaging with each other to provide stability and durability.

[0079] Specifically, the flange refers to a ring-shaped or disc-shaped metal part that is installed around the edge of the exterior wall and protrudes outward, and the groove refers to a groove recessed in the surface of the exterior wall for connection and positioning.

[0080] Specifically, the ultra-low energy consumption building structure bears and supports the load through the structural layer, provides a solid support foundation for the subsequent thermal insulation layer, waterproof layer, thermal insulation layer and decorative layer, and ensures the overall stability and safety of the ultra-low energy consumption building structure. The ultra-low energy consumption building structure reduces heat transfer through the thermal insulation layer, reduces the energy consumption of the ultra-low energy consumption building structure in heating and cooling, effectively isolates the influence of external high or low temperature on the indoor temperature, and improves the energy efficiency of the building. The ultra-low energy consumption building structure prevents moisture penetration through the waterproof layer, protects the ultra-low energy consumption building structure from corrosion and mildew, and extends the service life. The ultra-low energy consumption building structure reduces indoor heat loss or external cold intrusion through the thermal insulation layer, maintains the indoor temperature stable and comfortable. The ultra-low energy consumption building structure is designed for appearance through the decorative layer, which protects the internal structural layer, thermal insulation layer, waterproof layer and thermal insulation layer to prevent them from being directly eroded by the external environment. The ultra-low energy consumption building structure enhances the connection stability between the plates through the plate buckle structure to prevent loosening or deformation caused by external force, and extend the service life of the ultra-low energy consumption building structure.

[0081] Specifically, the stability refers to the ability of the ultra-low energy consumption building structure to maintain its original properties, structure or function after being subjected to external interference. The supporting force refers to the force in the opposite direction of gravity generated by the elastic deformation of the ultra-low energy consumption building structure. The external physical impact includes wind and rain erosion and sunlight exposure.

[0082] It can be understood that the present embodiment does not limit the material of the structural layer, and those skilled in the art can freely set it according to actual conditions, and it only needs to meet the support requirements of the exterior wall, such as concrete material can be set. The present embodiment does not limit the material of the thermal insulation layer, and those skilled in the art can freely set it according to actual conditions, and it only needs to meet the temperature isolation requirements of the exterior wall, such as polymer coating can be set. The present embodiment does not limit the material of the waterproof layer, and those skilled in the art can freely set it according to actual conditions, and it only needs to meet the rainwater isolation requirements of the exterior wall, such as polymer coating can be set. The present embodiment does not limit the material of the thermal insulation layer, and those skilled in the art can freely set it according to actual conditions, and it only needs to meet the heat isolation requirements of the exterior wall, such as foam cement board can be set. The present embodiment does not limit the material of the decorative layer, and those skilled in the art can freely set it according to actual conditions, and it only needs to meet the physical impact bearing requirements of the exterior wall, such as color steel plate can be set.

[0083] Specifically, the exterior wall reduces heat transfer losses of ultra-low energy consumption building structures, utilizes renewable energy such as solar energy, reduces dependence on traditional energy, helps maintain indoor temperature stability, and improves comfort.

[0084] See also Figure 3As shown, it is a schematic diagram of the process of the intelligent construction method of the ultra-low energy consumption building structure based on lightweight materials in this embodiment, and the method includes:

[0085] Step S1, acquiring building size data, and locating the building base point according to the building size data to obtain the building base point coordinates;

[0086] Step S2, calculating the thickness of the outer wall corresponding to the building base point according to the building base point coordinates to obtain the outer wall thickness size;

[0087] Step S3, performing a stress analysis on the plate buckle structure of the exterior wall structural unit according to the building base point coordinates, the exterior wall thickness and the exterior wall structural unit information to obtain an unstable exterior wall structural unit;

[0088] Step S4, performing environmental index analysis according to the building environmental information, and adjusting the process of performing stress analysis on the plate buckle structure of the exterior wall structural unit according to the analysis results;

[0089] Step S5, performing environmental service analysis according to the user's required service life, and adjusting the environmental indicator analysis process according to the analysis results;

[0090] Step S6, reinforcing the unstable exterior wall structural unit with plate buckles;

[0091] Step S7, performing stress simulation on the plate buckle reinforcement, and providing feedback on the plate buckle reinforcement status according to the simulation results;

[0092] Step S8, optimizing the plate buckle reinforcement process according to the feedback result;

[0093] Step S9, performing a thermal analysis on the exterior wall structural unit according to the user's building thermal habits, and setting the fresh air heat recovery system and the exterior wall structural unit attribute distribution according to the thermal analysis results.

[0094] Specifically, in step S1, when obtaining the building base point coordinates, the building dimension data is obtained according to the ultra-low energy consumption building structure design drawings, and the building base point coordinates are manually input and located.

[0095] Specifically, the building dimension data refers to various dimensional information of the geometric shape and positional relationship of the ultra-low energy consumption building structure, such as the dimensional information obtained through architectural design drawings. The building base point refers to the reference point used to determine the main structure and construction position of the ultra-low energy consumption building structure during the construction process. This embodiment does not limit the positioning method of the building base point. Technical personnel in this field can freely set it according to actual conditions as long as the positioning requirements are met. For example, a satellite positioning method such as GPS can be set.

[0096] Specifically, step S1 locates the building base point according to the building dimension data, so as to ensure that the overall position, size and shape of the ultra-low energy consumption building structure meet the design requirements, provide accurate reference points for subsequent construction, and help improve construction efficiency and quality.

[0097] Specifically, in step S2, the thickness of the outer wall corresponding to the building base point coordinates (x, y, z) is calculated:

[0098]

[0099] Among them, H is the thickness of the outer wall, T is the temperature value obtained through real-time monitoring, T0 is the preset temperature, z is the height of the outer wall, z0 is the preset height of the outer wall, B is the noise value obtained through real-time monitoring, and B0 is the preset noise value that affects the thickness of the outer wall.

[0100] Specifically, the thickness of the exterior wall corresponding to the building base point coordinates (x, y, z) refers to the thickness of the exterior wall at the location of the building base point coordinates (x, y, z). The present embodiment does not limit the monitoring method of the temperature value. Those skilled in the art can freely set it according to actual conditions, and only need to meet the monitoring requirements. For example, a thermal resistor temperature measurement can be set. The thermal resistor temperature measurement refers to temperature measurement through the different resistance values ​​of the coating material at different temperatures. The preset temperature refers to a preset value that affects the thickness of the exterior wall. The exterior wall height refers to the vertical height of the exterior wall corresponding to the building base point coordinates. The preset exterior wall height refers to a preset temperature value that affects the thickness of the exterior wall. The present embodiment does not limit the monitoring method of the noise value. Those skilled in the art can freely set it according to actual conditions, and only need to meet the monitoring requirements. For example, a noise sensor can be set, and the preset noise value refers to a preset noise value that affects the thickness of the exterior wall.

[0101] Specifically, the step S2 calculates the thickness of the outer wall corresponding to the building base point according to the building base point coordinates to obtain the outer wall thickness dimension, so as to ensure the stability of the ultra-low energy consumption building structure and meet the design requirements.

[0102] Specifically, in step S3, when the plate buckle structure of the external wall structure unit is subjected to stress analysis, a stress strength analysis is performed according to the building base point coordinates, the external wall thickness and the external wall structure unit information, and the stress strength N of the plate buckle structure is compared with the preset stress strength NO. The stability of the external wall structure unit is judged according to the comparison result, wherein:

[0103] When N>NO, the exterior wall structural unit is determined to be stable;

[0104] When N≤NO, the exterior wall structural unit is determined to be unstable and marked as an unstable unit.

[0105] Specifically, the exterior wall structure unit refers to the basic component of the exterior wall structure of an ultra-low energy consumption building structure, such as an EPS (polystyrene foam) insulation board exterior wall. This embodiment does not limit the force analysis method of the exterior wall structure unit. Technical personnel in this field can freely set it according to actual conditions, and only need to meet the force analysis requirements. For example, finite element analysis (FEA) software can be set, and the three-dimensional modeling graphics of the plate buckle structure can be imported into the FEA software, and meshing and load application are performed. After the solution is completed, stress and strain data are output. The preset force intensity refers to the maximum stress and load that the plate buckle structure needs to withstand under normal use conditions. The unstable unit refers to a structural unit that exhibits low stability and low bearing capacity during the force analysis of the ultra-low energy consumption building structure.

[0106] Specifically, step S3 performs a stress analysis on the plate buckle structure of the exterior wall structure unit according to the building base point coordinates, the exterior wall thickness and the exterior wall structure unit information to obtain an unstable exterior wall structure unit, so as to facilitate targeted reinforcement and optimization design of the ultra-low energy consumption building structure to ensure the overall structural safety of the ultra-low energy consumption building structure.

[0107] Specifically, in step S4, when analyzing the environmental index according to the building environmental information, the environmental index A is compared with the preset environmental index A0, and the process of performing the stress analysis on the plate buckle structure of the exterior wall structural unit is adjusted according to the comparison result, wherein:

[0108] When A>AO, the environmental index is judged to be abnormal and the correction coefficient is set The preset force intensity NO is adjusted according to the correction coefficient. The adjusted preset force intensity is Na, and Na=N0×a is set;

[0109] When A≤AO, the environmental index is judged to be normal, and there is no need to adjust the stress analysis process of the plate buckle structure of the exterior wall structural unit.

[0110] Specifically, the building environment information refers to the sum of data and information of environmental elements around and inside the ultra-low energy consumption building structure, including but not limited to natural environment information, artificial environment information and indoor environment information. The natural environment information includes temperature, rainfall, solar radiation and vegetation coverage; the artificial environment information includes surrounding buildings, road traffic and public facilities; the indoor environment information includes pollutant concentration in indoor air, ventilation efficiency and indoor noise level; the environmental indicators refer to the measurement standards set for environmental elements for evaluating environmental quality; the preset environmental indicators refer to the expected goals and quantitative standards set for environmental indicators.

[0111] Specifically, step S4 performs environmental index analysis based on building environmental information, and adjusts the process of stress analysis of the plate buckle structure of the exterior wall structural unit based on the analysis results, so as to accurately evaluate the stability and safety of the exterior wall structural unit under different environmental conditions, thereby taking effective reinforcement or optimization measures.

[0112] Specifically, in step S5, when the environmental service analysis is performed according to the user's required service life, the required service life S is compared with the preset required service life S0, and the environmental service analysis is performed according to the comparison result, wherein:

[0113] When S>S0, it is difficult to judge the service environment, and the correction coefficient is set The preset environmental index A0 is adjusted according to the correction coefficient, and the adjusted environmental index is Aa, Aa = A0 × b;

[0114] When S≤S0, it is easy to determine the environmental service and there is no need to adjust the environmental indicator analysis process.

[0115] Specifically, the required service life refers to the time period during which users expect or require that ultra-low energy consumption building structures can meet their functional and safety requirements under normal conditions of use; the preset required service life refers to the period during which the exterior wall structural units and plate-fastened structures of ultra-low energy consumption building structures maintain their functional functions under normal maintenance conditions; and the environmental service analysis refers to the analysis and evaluation of the performance, lifespan, safety and other aspects of ultra-low energy consumption building structures during operation.

[0116] Specifically, step S5 performs an environmental service analysis based on the user's required service life, and adjusts the environmental indicator analysis process based on the analysis results, so as to accurately predict the performance changes and potential risks of the exterior wall structural unit during long-term use, and provide support for optimizing the reinforcement plan.

[0117] Specifically, in step S6, when the unstable exterior wall structural unit is reinforced with plate buckles, the plate buckle model is optimized, and the force strength level of the plate buckle model is divided into three levels: A, B, and C, wherein:

[0118] If the stress strength of the unstable exterior wall structure unit plate buckle model is A, the stress strength grade of the optimized plate buckle model is A;

[0119] If the stress strength of the unstable exterior wall structure unit plate buckle model is B, the stress strength level of the optimized plate buckle model is A;

[0120] If the stress strength of the unstable exterior wall structure unit plate buckle model is C, the stress strength grade of the optimized plate buckle model is B.

[0121] Specifically, the force strength grade A means that the force strength of the plate buckle model is high, and the force strength is 150-200N / m 2 The stress strength grade B means that the stress strength of the plate buckle model is medium, and the stress strength is 100-150N / m 2 The stress strength grade C means that the stress strength of the plate buckle model is low, and the stress strength is 50-100N / m 2 .

[0122] Specifically, the step S6 performs plate buckle reinforcement on the unstable exterior wall structure unit so as to enhance the stability, bearing capacity and durability of the exterior wall structure unit, thereby ensuring the overall safety of the ultra-low energy consumption building structure and extending its service life.

[0123] Specifically, in step S7, when feedback is given on the reinforcement of the plate buckle, a simulation model of the plate buckle structure is established using simulation software, and the stress strength is simulated and analyzed, the stress strength simulation result N1 is compared with the preset stress strength NO, and feedback is given on the reinforcement of the plate buckle according to the comparison result, wherein:

[0124] When N1>N0, the plate buckle reinforcement is determined to be effective;

[0125] When N1≤N0, the plate buckle reinforcement is determined to be invalid.

[0126] Specifically, this embodiment does not limit the type of simulation software. Technical personnel in this field can freely set it according to actual conditions, as long as the simulation requirements for force strength are met. For example, ANSYS software can be set, and the three-dimensional modeling graphics of the plate buckle structure can be imported into the ANSYS software, and meshing and load application can be performed. After the solution is completed, the force strength data can be output.

[0127] Specifically, the step S7 performs stress simulation on the plate buckle reinforcement, and provides feedback on the plate buckle reinforcement status according to the simulation results, so as to verify the effectiveness and safety of the reinforcement design and ensure that the reinforced exterior wall structural unit can meet the use requirements.

[0128] Specifically, in step S8, when optimizing the plate buckle reinforcement process according to the feedback results, when N1≤N0 and the plate buckle reinforcement is invalid, it is necessary to adjust the plate buckle reinforcement quantity S and set the correction coefficient c=1+0.1(N1-N0)+0.01(N1-N0) 2 , and adjust the number of plate buckle reinforcements S according to the correction coefficient. The adjusted number of plate buckle reinforcements is Sa, and Sa is set to S×c.

[0129] Specifically, the step S8 adjusts the plate buckle reinforcement process according to the feedback result, so as to ensure that the reinforced exterior wall structural unit has good mechanical properties and stability and meets the use requirements of the ultra-low energy consumption building structure.

[0130] Specifically, in step S9, when setting the attribute distribution of the fresh air heat recovery system and the exterior wall structure unit, the heat usage mode, heat usage days and average temperature parameters are input into the heat usage habit analysis model to obtain the output results of the heat usage habit analysis model, including the heat dissipation area, the heat usage area and the thermoelectric conversion area, which are used as the user's building heat usage habits, and thermal insulation materials are set on the heat dissipation area pipes, heat exchangers are set on the heat usage area pipes, and waste heat collection pipes are set in the thermoelectric conversion area. The exterior wall structure unit of the heat dissipation area uses materials with thermal insulation properties, the exterior wall structure unit of the heat usage area uses materials with heat insulation properties, and the exterior wall structure unit of the thermoelectric conversion area uses materials with sealing properties.

[0131] Specifically, the user's building heat usage habits refer to the user's heat usage location and heat usage method in the ultra-low energy consumption building structure. This embodiment does not limit the collection method of the user's building heat usage habits. Technical personnel in this field can freely set it according to actual conditions, as long as the collection needs are met. For example, manual collection can be set. The heat dissipation area refers to living spaces such as living rooms and bedrooms. Thermal insulation measures must be considered to reduce heat loss. The heat use area refers to heat use areas such as kitchens. A good ventilation system must be designed, and an efficient heat source and heat recovery system must be set up. At the same time, oil fume emissions must be considered. The thermoelectric conversion area refers to power use areas such as charging areas or air conditioning areas. These areas A large amount of heat will be generated in the field, which needs to be effectively dissipated and energy efficiency should be considered. This embodiment does not limit the use of ultra-low energy consumption building structures. Those skilled in the art can freely set it according to actual conditions, as long as the building needs are met. For example, a hospital can be set. This embodiment does not limit the construction process of the heat habit analysis model. Those skilled in the art can freely set it according to actual conditions, as long as the intelligent analysis needs of the user's building heat habits are met. For example, the heat mode, heat days and average temperature parameters can be set as indexes, and the user's building heat habits can be used as the index corresponding content of the data combination as the heat habit analysis model construction data, and 70% of the The data for constructing the thermal habit analysis model is divided into a model training set, and 30% of the data for constructing the thermal habit analysis model is divided into a model test set. The convolutional neural network model is trained according to the model training set, and the trained convolutional neural network model is tested according to the model test set. When the test accuracy reaches 98%, the trained convolutional neural network model is output as the thermal habit analysis model. When the test accuracy does not reach 98%, the trained convolutional neural network model continues to be trained until the test accuracy reaches 98%, and then it is output as the thermal habit analysis model. This embodiment does not limit the thermal insulation material. Technical personnel in the field can freely set it according to actual conditions, and only need to meet the thermal insulation requirements, such as glass wool can be set. This embodiment does not limit the type of waste heat collection pipes, and technical personnel in the field can freely set it according to actual conditions, and only need to meet the waste heat collection requirements. For example, a shell and tube heat exchanger can be set. This embodiment does not limit the thermal insulation material, and technical personnel in the field can freely set it according to actual conditions, and only need to meet the thermal insulation requirements. For example, a double-layer hollow glass curtain wall can be set. This embodiment does not limit the sealing material, and technical personnel in the field can freely set it according to actual conditions, and only need to meet the sealing requirements, such as a metal plate can be set.

[0132] Specifically, step S9 performs thermal analysis on the exterior wall structure unit according to the user's building thermal habits, and sets the fresh air heat recovery system and the exterior wall structure unit property distribution according to the thermal analysis results, so as to improve the energy efficiency of the ultra-low energy consumption building structure, ensure the comfort of the indoor environment, and reduce energy consumption.

[0133] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.

Claims

1. An ultra-low energy consumption building structure based on lightweight materials, characterized in that: include: External wall, which is installed on the outer surface of the ultra-low energy consumption building structure, directly contacts with the external environment, and is used for heat preservation and insulation, and controls the exchange of indoor and outdoor heat; The window is composed of a window frame, glass and a sealing strip. The window frame is installed at the periphery of the window and connected to the outer wall to fix the window and support the overall weight of the window. The glass is installed in the middle of the window and connected to the window frame to be used for heat insulation. The sealing strip is installed between the window frame and the glass and between the window frame and the outer wall to fill the gap and provide sealing; The fresh air heat recovery system is composed of a heat exchange system, a power system, a filtering system, a box, and a control system. The heat exchange system is installed at the intersection of the air ducts of the air intake and exhaust, and is used to recover the cold and heat in the exhaust air and preheat and precool the intake air. The power system includes an air intake fan and an exhaust fan, which are connected to the heat exchange system and are used to drive the air intake and exhaust generated by the fan. The filtering system is installed at the air inlet of the air intake fan and is used to remove harmful substances in the intake air. The box is the outer shell of the fresh air heat recovery system and is used to protect the fresh air heat recovery system. The control system is installed in the equipment room and is used to monitor and adjust the temperature, humidity and air volume in the system in real time.

2. The ultra-low energy consumption building structure based on lightweight materials according to claim 1 is characterized in that: The exterior wall comprises: A structural layer, which is installed in the innermost layer of the outer wall and is used to provide stability and support for the ultra-low energy consumption building structure; A heat-insulating layer installed on the second layer of the exterior wall to isolate the temperature difference between the indoor and outdoor environments of the ultra-low energy consumption building structure; A waterproof layer, which is installed on the third layer of the exterior wall and is used to isolate rainwater erosion and penetration; An insulation layer, which is installed on the fourth layer of the exterior wall and is used to control the transfer of heat inside and outside the ultra-low energy consumption building structure; A decorative layer, which is installed on the outermost layer of the exterior wall and is used to provide an appearance design of the ultra-low energy consumption building structure and withstand external physical impact; The plate buckle structure is installed at the edge of the external wall and is formed by the first flange, the second flange and the first groove, the second groove of two plates engaging with each other to provide stability and durability.

3. An intelligent construction method for an ultra-low energy consumption building structure based on lightweight materials as described in any one of claims 1 to 2, characterized in that: The method comprises: Step S1, acquiring building size data, and locating the building base point according to the building size data to obtain the building base point coordinates; Step S2, calculating the thickness of the outer wall corresponding to the building base point according to the building base point coordinates to obtain the outer wall thickness size; Step S3, performing a stress analysis on the plate buckle structure of the exterior wall structural unit according to the building base point coordinates, the exterior wall thickness and the exterior wall structural unit information to obtain an unstable exterior wall structural unit; Step S4, performing environmental index analysis according to the building environmental information, and adjusting the process of performing stress analysis on the plate buckle structure of the exterior wall structural unit according to the analysis results; Step S5, performing environmental service analysis according to the user's required service life, and adjusting the environmental indicator analysis process according to the analysis results; Step S6, reinforcing the unstable exterior wall structural unit with plate buckles; Step S7, performing stress simulation on the plate buckle reinforcement, and providing feedback on the plate buckle reinforcement status according to the simulation results; Step S8, optimizing the plate buckle reinforcement process according to the feedback result; Step S9, performing a thermal analysis on the exterior wall structural unit according to the user's building thermal habits, and setting the fresh air heat recovery system and the exterior wall structural unit attribute distribution according to the thermal analysis results.

4. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 3 is characterized in that: In step S2, the thickness of the outer wall corresponding to the building base point coordinates (x, y, z) is calculated: Among them, H is the thickness of the outer wall, T is the temperature value obtained through real-time monitoring, T0 is the preset temperature, z is the height of the outer wall, z0 is the preset height of the outer wall, B is the noise value obtained through real-time monitoring, and B0 is the preset noise value that affects the thickness of the outer wall.

5. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 4 is characterized in that: In step S3, when performing stress analysis on the plate buckle structure of the external wall structural unit, a stress strength analysis is performed based on the building base point coordinates, the external wall thickness and the external wall structural unit information, and the stress strength N of the plate buckle structure is compared with the preset stress strength NO. The stability of the external wall structural unit is judged based on the comparison result, wherein: When N>NO, the exterior wall structural unit is determined to be stable; When N≤NO, the exterior wall structural unit is determined to be unstable and marked as an unstable unit.

6. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 5 is characterized in that: In step S4, when analyzing the environmental index according to the building environmental information, the environmental index A is compared with the preset environmental index A0, and the process of performing the stress analysis on the plate buckle structure of the exterior wall structural unit is adjusted according to the comparison result, wherein: When A>AO, the environmental index is determined to be abnormal, a correction coefficient is set, and the preset force intensity NO is adjusted according to the correction coefficient. The adjusted preset force intensity is Na, and Na=N0×a is set; When A≤AO, the environmental index is judged to be normal, and there is no need to adjust the stress analysis process of the plate buckle structure of the exterior wall structural unit.

7. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 6 is characterized in that: In step S5, when the environmental service analysis is performed according to the user's required service life, the required service life S is compared with the preset required service life S0, and the environmental service analysis is performed according to the comparison result, wherein: When S>S0, it is difficult to judge the service environment, and the correction coefficient is set The preset environmental index A0 is adjusted according to the correction coefficient, and the adjusted environmental index is Aa, Aa = A0 × b; When S≤S0, it is easy to determine the environmental service and there is no need to adjust the environmental indicator analysis process.

8. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 7 is characterized in that: In step S6, when the unstable external wall structural unit is reinforced with plate buckles, the plate buckle model is optimized, and the force strength level of the plate buckle model is divided into three levels: A, B, and C, wherein: If the stress strength of the unstable exterior wall structure unit plate buckle model is A, the stress strength grade of the optimized plate buckle model is A; If the stress strength of the unstable exterior wall structure unit plate buckle model is B, the stress strength level of the optimized plate buckle model is A; If the stress strength of the unstable exterior wall structure unit plate buckle model is C, the stress strength grade of the optimized plate buckle model is B.

9. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 8, characterized in that: In step S7, when feedback is given on the reinforcement of the plate buckle, a simulation model of the plate buckle structure is established using simulation software, and the stress strength is simulated and analyzed, the stress strength simulation result N1 is compared with the preset stress strength NO, and feedback is given on the reinforcement of the plate buckle according to the comparison result, wherein: When N1>N0, the plate buckle reinforcement is determined to be effective; When N1≤N0, the plate buckle reinforcement is determined to be invalid; In step S8, when optimizing the plate buckle reinforcement process according to the feedback results, when N1≤N0 and the plate buckle reinforcement is invalid, it is necessary to adjust the plate buckle reinforcement quantity S and set the correction coefficient c=1+0.1(N1-N0)+0.01(N1-N0) 2 , and adjust the number of plate buckle reinforcements S according to the correction coefficient. The adjusted number of plate buckle reinforcements is Sa, and Sa is set to S×c.

10. The intelligent construction method of ultra-low energy consumption building structure based on lightweight materials according to claim 3, characterized in that: In step S9, when setting the attribute distribution of the fresh air heat recovery system and the exterior wall structure unit, the heat usage mode, heat usage days and average temperature parameters are input into the heat usage habit analysis model to obtain the output results of the heat usage habit analysis model, including the heat dissipation area, the heat usage area and the thermoelectric conversion area, which are used as the user's building heat usage habits, and an insulation layer is set on the heat dissipation area pipe, a heat exchanger is set on the heat usage area pipe, and a waste heat collection pipe is set in the thermoelectric conversion area. The exterior wall structure unit of the heat dissipation area is made of a material with thermal insulation performance, the exterior wall structure unit of the heat usage area is made of a material with heat insulation performance, and the exterior wall structure unit of the thermoelectric conversion area is made of a material with sealing performance.

Citation Information

Patent Citations

  • Low energy consumption fabricated building

    CN109138146A

Cited By

  • Fabricated wall construction method and structure

    CN120684018A

  • Construction method and structure for assembling a wall alignment device

    CN120684018B