Prefabricated inspection well and construction method thereof

Through the prefabricated inspection well and its construction method, the combination of ring beam, first wellbore, second wellbore and adjustment prefabricated blocks is used to solve the traffic impact and resource waste caused by traditional inspection well maintenance methods, and efficient maintenance and rapid adjustment are achieved.

CN119531414AActive Publication Date: 2025-02-28SHANGHAI CONSTRUCTION GROUP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411776288.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-05
Publication Date
2025-02-28
Estimated Expiration
2044-12-05

AI Technical Summary

Technical Problem

Traditional inspection well maintenance methods lead to long-term closure of local locations, affecting normal traffic traffic, and prone to traffic accidents and serious waste of resources.

Method used

The prefabricated inspection well and its construction method are adopted. Through the combination of ring beam, first wellbore, second wellbore and adjustable prefabricated block, the height of the first wellbore is adjusted to match the ups and downs of the inspection well, and rapid adjustment and repair are achieved.

Benefits of technology

It improves the maintenance and construction efficiency of inspection wells, reduces road blockage time, avoids waste of resources, and reduces the risk of traffic accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

The invention provides a prefabricated inspection well and a construction method thereof. The prefabricated inspection well comprises a ring beam, a first shaft and a second shaft. Wherein the first shaft comprises a first spiral step shaft, a second spiral step shaft and a plurality of adjusting prefabricated blocks, and a part of rotating steps on the edge of the first spiral step shaft and a part of rotating steps on the edge of the second spiral step shaft are complementary; the adjusting precast blocks with the corresponding number are selected according to the number of the remaining steps, the adjusting precast blocks are embedded between the non-complementary steps of the adjusting precast blocks and the remaining steps so as to make up the gap between the adjusting precast blocks and the remaining steps, and the adjusting precast blocks and the remaining steps are assembled to form the first shaft. The construction process is easy to operate, cast-in-place concrete is not needed, the maintenance construction efficiency is effectively improved, the road blocking time is shortened, meanwhile, the inspection well is prevented from being replaced, and resources are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of inspection wells, and in particular to a prefabricated inspection well and a construction method thereof. Background Art

[0002] Various types of inspection wells located within the carriageway are subject to vehicle loads for a long time, and uneven settlement often occurs between the inspection wells and the surrounding road structure layers; the traditional treatment method is to close the traffic, partially dismantle the inspection well shaft, repair and maintain the cast-in-place concrete, and open the traffic after the concrete strength reaches the standard. This method will lead to long-term closure of local locations, affecting normal traffic and easily causing traffic accidents.

[0003] Therefore, how to improve the maintenance and construction efficiency of inspection wells and avoid waste of resources is a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0004] The object of the present invention is to provide a prefabricated inspection well and a construction method thereof, which can improve the maintenance and construction efficiency of the inspection well and avoid waste of resources.

[0005] In order to solve the above technical problems, the present invention provides a prefabricated inspection well, which comprises: a ring beam, a first wellbore, and a second wellbore, wherein one end of the first wellbore is vertically fixed on the ring beam, and the other end is sleeved in the second wellbore;

[0006] The first shaft comprises: a first spiral step shaft, a second spiral step shaft, and a plurality of adjustment prefabricated blocks, the rotation steps at the edge of a portion of the first spiral step shaft are complementary to the rotation steps at the edge of the second spiral step shaft; a corresponding number of adjustment prefabricated blocks are selected according to the number of the remaining steps, and are embedded between the non-complementary steps of the two to fill the gap between the two, and the first shaft is assembled;

[0007] Between the rotating step at the edge of the first spiral step wellbore of the assembled first wellbore and the rotating step at the edge of the second spiral step wellbore, each increase / decrease of an adjustment prefabricated block can correspondingly increase / decrease the height of the assembled first wellbore by one step.

[0008] Optionally, the prefabricated inspection well further includes: a first steel bar, a second steel bar and a steel bar sleeve, each second steel bar embedded in the wall of the second shaft and partially exposed is connected to the first steel bar passing through the wall of the first shaft through the steel bar sleeve, so that the first steel bar and the second steel bar are coaxial to fix the first shaft and the second shaft to the ring beam.

[0009] Optionally, in the prefabricated inspection shaft, the wall of the first shaft is provided with steel bar installation holes at even intervals along its circumference, and the position of each steel bar installation hole corresponds to the position of the second steel bar embedded in the wall of the second shaft.

[0010] Optionally, in the prefabricated inspection well, each steel bar installation hole passes through a rotation step on the edge of the first spiral step shaft and a rotation step on the edge of the second spiral step shaft at a corresponding position.

[0011] Optionally, in the prefabricated inspection well, the diameter of the steel bar installation hole is larger than the diameter of the first steel bar.

[0012] Optionally, in the prefabricated inspection well, a thread is provided on the outer side of one end of each first steel bar adjacent to the ring beam, and one end of the first shaft is vertically fixed to the ring beam by a nut engaging the thread on the first steel bar.

[0013] Optionally, in the prefabricated inspection well, the first wellbore is a hollow cylinder.

[0014] Optionally, in the prefabricated inspection well, the second wellbore is a hollow main body with a gap between one end of the first wellbore and the gap is filled after the first wellbore and the second wellbore are connected.

[0015] The present invention also provides a construction method for a prefabricated inspection well, the construction method for the prefabricated inspection well comprising:

[0016] Determine the current sinking and floating situation of the inspection well, and carry out corresponding steps according to the sinking and floating situation;

[0017] When the inspection well sinks and needs to be lifted, the second spiral step well shaft is fixed, and the first spiral step well shaft is rotated counterclockwise by a predetermined angle, and a corresponding number of adjustment prefabricated blocks are added between the second spiral step well shaft and the first spiral step well shaft to increase the height of the first well shaft;

[0018] When the inspection well floats and the height of the inspection well needs to be lowered, the second spiral step wellbore is fixed, and the first spiral step wellbore is rotated clockwise by a predetermined angle, and a corresponding number of adjustment prefabricated blocks are reduced between the second spiral step wellbore and the first spiral step wellbore to lower the height of the first wellbore.

[0019] In the prefabricated inspection well and its construction method provided by the present invention, the prefabricated inspection well ring beam, the first wellbore, the second wellbore and the adjusting prefabricated block, one end of the first wellbore is vertically fixed on the ring beam, and the other end is sleeved in the second wellbore; wherein, the first wellbore includes: a first spiral step wellbore, a second spiral step wellbore, and a plurality of adjusting prefabricated blocks, the rotating steps on the edge of part of the first spiral step wellbore are complementary to the rotating steps on the edge of the second spiral step wellbore; according to the number of remaining steps, a corresponding number of adjusting prefabricated blocks are selected, embedded between the non-complementary steps of the two to fill the gap between the two, and assembled to form the first wellbore, based on the structural design of the first wellbore of the present invention, according to the sinking and floating conditions of the inspection well, the number of adjusting prefabricated blocks in the first wellbore is adjusted to adjust the height of the first wellbore to match the current construction needs, the entire construction process is simple to operate, since all prefabricated parts are used, there is no need for cast-in-place concrete for repair and maintenance, which effectively improves the maintenance construction efficiency, reduces the road blocking time, and avoids the replacement of the inspection well, thereby realizing resource conservation. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The above and other objects, features and advantages of the present disclosure will become more apparent through a more detailed description of exemplary embodiments of the present disclosure in conjunction with the accompanying drawings, wherein like reference numerals generally represent like components throughout the exemplary embodiments of the present disclosure.

[0021] Figure 1 is a schematic diagram of a prefabricated inspection well in one embodiment of the present invention;

[0022] Figure 2 is a schematic diagram of the splitting of the first wellbore in one embodiment of the present invention;

[0023] Figure 3 is a three-dimensional schematic diagram of a first wellbore in one embodiment of the present invention;

[0024] Figure 4a yes Figure 3 The main view;

[0025] Figure 4b yes Figure 3 Rear view of

[0026] Figure 4c yes Figure 3 Left view of

[0027] Figure 4d yes Figure 3 A top view of

[0028] Figure 5 It is a structural schematic diagram after adding an adjustment prefabricated block between the rotating step at the edge of the first spiral step wellbore and the rotating step at the edge of the second spiral step wellbore of the assembled first wellbore.

[0029] In the figure:

[0030] 1-ring beam; 2-first shaft; 3-second shaft; 4a-first steel bar; 4b-second steel bar; 5-steel sleeve; 6-first spiral step shaft; 7-adjustment prefabricated block; 8-second spiral step shaft; 9-steel installation hole. DETAILED DESCRIPTION

[0031] The following is a further detailed description of the prefabricated inspection well and its construction method proposed by the present invention in conjunction with the accompanying drawings and specific embodiments. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.

[0032] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.

[0033] In the description of the invention, it is necessary to understand that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.

[0034] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0035] In the invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the invention can be understood according to the specific circumstances.

[0036] Please refer to Figures 1 to 4dThe prefabricated inspection well includes: a ring beam 1, a first wellbore 2, and a second wellbore 3. One end of the first wellbore 2 is vertically fixed on the ring beam 1, and the other end is sleeved in the second wellbore 3. The first wellbore 2 includes: a first spiral step wellbore 6, a second spiral step wellbore 8, and a plurality of adjustment prefabricated blocks 7. The rotating steps at the edge of the first spiral step wellbore are complementary to the rotating steps at the edge of the second spiral step wellbore. According to the number of remaining steps, a corresponding number of adjustment prefabricated blocks 7 are selected and embedded between the non-complementary steps of the two to fill the gap between the two, and the first wellbore 2 is assembled. The assembled first wellbore 2 is a hollow column.

[0037] Specifically, Figure 1 As shown, the second wellbore 3 is a hollow main body, and there is a gap between one end of the first wellbore 2 , and the gap is filled after the first wellbore 2 and the second wellbore 3 are connected.

[0038] Please refer to Figure 5 Between the rotating step at the edge of the first spiral step shaft 6 of the assembled first shaft 2 and the rotating step at the edge of the second spiral step shaft 8, each increase / decrease of an adjusting prefabricated block 7 can correspondingly increase / decrease the height of the assembled first shaft 2 by one step.

[0039] In this embodiment, two adjustment prefabricated blocks 7 are used to fill the gap between the rotating step at the edge of the first spiral step shaft and the rotating step at the edge of the second spiral step shaft. The specific results are as follows: Figures 2 to 4d If the first shaft 2 is to be increased in height by one step, the second spiral step shaft 8 needs to be fixed first, and the first spiral step shaft 6 needs to be rotated counterclockwise by a predetermined angle, and an adjustment prefabricated block 7 is added at a position adjacent to the adjustment prefabricated block 7 between the second spiral step shaft 8 and the first spiral step shaft 6, so as to increase the height of the first shaft 2 by one step. Figure 5 shown.

[0040] like Figure 1 As shown, the prefabricated inspection well also includes: a first steel bar 4a, a second steel bar 4b and a steel bar sleeve 5. Each second steel bar 4b embedded in the wall of the second shaft 3 and partially exposed is connected to the first steel bar 4a that passes through the wall of the first shaft 2 through the steel bar sleeve 5, so that the first steel bar 4a and the second steel bar 4b are coaxial to fix the first shaft 2 and the second shaft 3 on the ring beam 1.

[0041] Specifically, the wall of the first shaft 2 is provided with steel bar installation holes 9 at uniform intervals along its circumference, and the position of each steel bar installation hole 9 corresponds to the position of the second steel bar 4b embedded in the wall of the second shaft 3; wherein each steel bar installation hole 9 passes through a rotation step on the edge of the first spiral step shaft 6 and a rotation step on the edge of the second spiral step shaft 8 at the corresponding position.

[0042] It can be understood that the diameter of the steel bar installation hole 9 described here is larger than the diameter of the first steel bar 4a, so that the first steel bar 4a passes through the steel bar installation hole 9 on the wall of the first shaft 2 and docks with the second steel bar 4b embedded in the wall of the second shaft 3. A steel bar sleeve 5 is arranged on the plane where the first shaft 2 and the second shaft 3 dock, so as to facilitate the replacement of the first steel bar 4a when the height of the prefabricated inspection well is adjusted, and the first steel bar 4a and the second steel bar 4b are connected as a coaxial whole. Based on the first steel bar 4a being fixed on the ring beam 1, the first shaft 2 and the second shaft 3 are indirectly installed and fixed on the ring beam 1 as a whole, so as to ensure the overall stability and firmness of the prefabricated inspection well. In addition, since the height of each inspection well lifting is fixed, the steel bar length of the first steel bar 4a is also modular, which is convenient for manufacturing.

[0043] Better, such as Figure 1 As shown, a thread is provided on the outer side of one end of each first steel bar 4a adjacent to the ring beam 1, and one end of the first shaft 2 is vertically fixed to the ring beam 1 by a nut cooperating with the thread on the first steel bar 4a.

[0044] Accordingly, this embodiment also provides a construction method for a prefabricated inspection well. Figures 1 to 5 The construction method of the prefabricated inspection well described in this embodiment is described in detail.

[0045] First, execute step S1 to determine the current sinking and floating conditions of the inspection well, and carry out corresponding steps according to the sinking and floating conditions;

[0046] Next, step S2 is executed. When the inspection well sinks and needs to be lifted, the second spiral step shaft 8 is fixed, and the first spiral step shaft 6 is rotated counterclockwise by a predetermined angle, and a corresponding number of adjustment prefabricated blocks 7 are added between the second spiral step shaft 8 and the first spiral step shaft 6 to increase the height of the first shaft 2;

[0047] When the inspection well floats and the height of the inspection well needs to be lowered, the second spiral step wellbore 8 is fixed, and the first spiral step wellbore 6 is rotated clockwise by a predetermined angle, and a corresponding number of adjustment prefabricated blocks 7 are reduced between the second spiral step wellbore 8 and the first spiral step wellbore 6 to lower the height of the first wellbore 2.

[0048] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.

[0049] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.

Claims

1. A prefabricated inspection well, characterized in that: include: A ring beam (1), a first wellbore (2), and a second wellbore (3), wherein one end of the first wellbore (2) is vertically fixed to the ring beam (1), and the other end is sleeved in the second wellbore (3); The first shaft (2) comprises: a first spiral step shaft (6), a second spiral step shaft (8), and a plurality of adjustment prefabricated blocks (7); the rotation steps at the edge of a portion of the first spiral step shaft are complementary to the rotation steps at the edge of the second spiral step shaft; a corresponding number of adjustment prefabricated blocks (7) are selected according to the number of the remaining steps, and are embedded between the non-complementary steps of the two to fill the gap between the two, and the first shaft (2) is assembled; Between the rotating step at the edge of the first spiral step shaft (6) of the assembled first shaft (2) and the rotating step at the edge of the second spiral step shaft (8), each time an adjustment prefabricated block (7) is added / reduced, the height of the assembled first shaft (2) can be increased / reduced by one step.

2. The prefabricated inspection well according to claim 1, characterized in that: Also includes: A first steel bar (4a), a second steel bar (4b) and a steel bar sleeve (5), each second steel bar (4b) pre-buried in the wall of the second shaft (3) and partially exposed is connected to the first steel bar (4a) penetrating the wall of the first shaft (2) through the steel bar sleeve (5), so that the first steel bar (4a) and the second steel bar (4b) are coaxial, so as to fix the first shaft (2) and the second shaft (3) on the ring beam (1).

3. The prefabricated inspection well according to claim 2, characterized in that: The wall of the first shaft (2) is provided with steel bar installation holes (9) at even intervals along its circumference, and the position of each steel bar installation hole corresponds to the position of the second steel bar (4b) embedded in the wall of the second shaft (3).

4. The prefabricated inspection well according to claim 3, characterized in that: Each steel bar installation hole (9) passes through a rotation step on the edge of the first spiral step shaft (6) and a rotation step on the edge of the second spiral step shaft (8) at a corresponding position.

5. The prefabricated inspection well according to claim 3, characterized in that: The diameter of the steel bar installation hole (9) is larger than the diameter of the first steel bar (4a).

6. The prefabricated inspection well according to claim 2, characterized in that: A thread is arranged on the outer side of one end of each first steel bar (4a) adjacent to the ring beam (1), and a nut is matched with the thread on the first steel bar (4a) to vertically fix one end of the first shaft (2) on the ring beam (1).

7. The prefabricated inspection well according to claim 1, characterized in that: The first shaft (2) is a hollow cylinder.

8. The prefabricated inspection well according to claim 1, characterized in that: The second wellbore (3) is a hollow main body, and has a gap with one end of the first wellbore (2). The gap is filled after the first wellbore (2) and the second wellbore (3) are butt-jointed.

9. A construction method for a prefabricated inspection well, characterized in that: include: Determine the current sinking and floating situation of the inspection well, and carry out corresponding steps according to the sinking and floating situation; When the inspection well sinks and needs to be raised, the second spiral step wellbore (8) is fixed, and the first spiral step wellbore (6) is rotated counterclockwise by a predetermined angle, and a corresponding number of adjustment prefabricated blocks (7) are added between the second spiral step wellbore (8) and the first spiral step wellbore (6) to increase the height of the first wellbore (2); When the inspection well floats up and the height of the inspection well needs to be lowered, the second spiral step wellbore (8) is fixed, and the first spiral step wellbore (6) is rotated clockwise by a predetermined angle, and a corresponding number of adjustment prefabricated blocks (7) are reduced between the second spiral step wellbore (8) and the first spiral step wellbore (6) to lower the height of the first wellbore (2).

Citation Information

Patent Citations

  • Prefabricated and assembled inspection well with adjustable elevation

    CN119061940A

  • Sectional type inspection well shaft

    CN210797640U

  • Integral concrete prefabricated inspection well for electric power

    CN222100950U

  • MANHOLE FOR TRAFFIC PAVEMENT AND METHOD FOR ADJUSTING THE HEIGHT OF SUCH A MANHOLE

    FR3061501A1