Fabricated house building component hoisting equipment
By designing a housing component lifting equipment including a connecting mechanism, a beam assembly, a traction mechanism and a wiring assembly, the problems of poor stability and limitations in the prior art are solved, and a lifting effect with high stability and flexibility is achieved.
Patent Information
- Application Number
- CN202510024401.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-07
- Publication Date
- 2025-03-04
- Estimated Expiration
- 2045-01-07
AI Technical Summary
The prior art has poor stability and limitations in lifting of building components. The suspender structure is complex and cumbersome to debug, so it is impossible to flexibly adapt to different lifting points.
A prefabricated house building component hoisting equipment is designed, including a connecting mechanism, a beam assembly, a traction mechanism and a wiring assembly. By adjusting the position of the connecting mechanism and beam assembly, the lifting points of the traction mechanism and the building component are flexibly matched, and the limiting function is provided through the wiring assembly to ensure stability and flexibility.
It realizes the universality and flexibility of lifting while ensuring stability, and adapts to different types of building components, simplifies the lifting process and reduces the complexity of operation.
Smart Images

Figure CN119551545A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of prefabricated component hoisting, and in particular relates to a prefabricated building component hoisting device. Background Art
[0002] Prefabricated building components refer to building components that are prefabricated in factories and then assembled and connected on site to form a complete building. This method transfers the traditional on-site construction process to a factory environment, thereby improving construction efficiency, reducing costs, reducing environmental pollution, and improving building quality.
[0003] At present, for the hoisting of building construction components, they can be hoisted by directly connecting them to the components through multiple hoisting ropes, or by using special hoists to hoist the components.
[0004] However, although the method of lifting by rope is simple to operate, low in cost and highly flexible, this method has the problem of poor stability; and although the stability is improved by lifting by slings, the slings are relatively complex in structure during use, the assembly process is relatively cumbersome and requires constant debugging to match the corresponding building components for use, and a type of sling can usually only be used to lift a few specific types of building components, which has great limitations in use. Summary of the invention
[0005] In view of the above problems, an embodiment of the present application provides an assembled building component lifting equipment, which can flexibly adjust the traction mechanism according to the position of the lifting point on the building component, thereby improving the universality of lifting while ensuring stability.
[0006] In order to achieve the above-mentioned purpose, the embodiment of the present application provides the following technical solutions: The present invention provides a prefabricated building component lifting equipment, including a connecting mechanism, on which four crossbeam assemblies distributed in an X shape are arranged, on which a traction mechanism is arranged, and on which a wire harness assembly is also arranged to cooperate with the traction mechanism to limit the building component. The connecting mechanism includes two upper and lower connecting seats in a disc structure, the two connecting seats are rotatably connected by a connecting shaft, and a first locking assembly is arranged between the two connecting seats, two symmetrical arc grooves are provided on the outer side wall of the connecting seat, a first guide rod in an arc structure is fixedly arranged in the arc groove, the first guide rod is connected to the corresponding crossbeam assembly, and a second locking assembly is arranged on the connecting seat to limit the crossbeam assembly. A cavity connected to two adjacent arc grooves is formed inside the connecting seat, and a through hole connected to the cavity is formed on the surface of the connecting seat on a side away from the connecting shaft, and the second locking assembly includes a locking plate slidably arranged in the cavity, a pressing column is fixedly arranged on the side of the locking plate close to the through hole, one end of the pressing column is slidably connected to the through hole, and a plurality of second springs are fixedly arranged on the side of the locking plate away from the through hole, and one end of the second spring away from the locking plate is fixedly connected to the inner wall of the cavity, a connecting plate is provided on the crossbeam assembly, a positioning hole is formed on the surface of the connecting plate, and a plurality of second positioning pins are provided at a position opposite to each arc groove on the side of the locking plate close to the through hole, and the plurality of second positioning pins are evenly distributed along the arc direction of the arc groove, and the positioning holes are slidably plugged into the second positioning pins.
[0007] According to a preferred embodiment, the first locking assembly includes a plurality of second guide rods, which are fixedly arranged on the lower side wall of the upper connecting seat and evenly distributed along the circumferential direction of the connecting seat; a locking ring is slidably connected between the plurality of second guide rods; a plurality of first positioning pins evenly distributed along its circumferential direction are fixedly arranged on the edge of the lower side wall of the locking ring; a plurality of positioning grooves evenly distributed along its circumferential direction are provided on the edge of the upper side wall of the lower connecting seat; the first positioning pins are slidably plugged into the positioning grooves; a plurality of first springs evenly distributed along the circumferential direction of the locking ring are fixedly connected between the upper side wall of the locking ring and the lower side wall of the upper connecting seat.
[0008] According to a favorable embodiment, the beam assembly includes a first beam, one end of the first beam close to the connecting seat is slidably arranged in a corresponding arc groove, and a connecting plate is fixedly connected to the end surface of the first beam in the arc groove, the first guide rod is slidably connected to the corresponding first beam, a first slide groove is provided on the lower side of the first beam, a guide column is fixedly provided in the first slide groove, and a second beam is slidably arranged in the first slide groove, a second slide groove is provided on the second beam, the guide column is slidably arranged in the second slide groove, and a first screw is rotatably arranged in the second slide groove, and the first screw is threadedly connected to the guide column.
[0009] According to a favorable embodiment, a turntable is rotatably provided at one end of the second cross beam away from the connecting seat, and the turntable is fixedly connected to one end close to the first screw rod. Guide holes connected to the first sliding groove are provided on the longer side walls of the first cross beam, and a limit pin is slidably connected in the guide hole, and the limit pin is fixedly connected to the side wall of the second cross beam.
[0010] According to a favorable embodiment, a moving channel extending along its length direction and having a rectangular structure is provided on the second crossbeam, a sliding hole is provided on the lower side of the moving channel, two groups of symmetrically distributed first tooth plates of the same length as the moving channel are fixedly provided on the lower inner wall of the moving channel, a sliding seat is slidably connected in the moving channel, two groups of symmetrically distributed second tooth plates are fixedly provided on the lower side wall of the sliding seat, the second tooth plates are clamped with the first tooth plates therebelow, and the sliding seat is connected to the traction mechanism.
[0011] According to a favorable embodiment, the traction mechanism includes two mounting columns fixedly connected to the lower side wall of the slide seat, a pulley block is provided between the two mounting columns, a driving assembly is provided on the pulley block, and a connecting buckle is also provided on the pulley block.
[0012] According to a favorable embodiment, the pulley block includes two pulley seats symmetrically arranged in an upper and lower direction, a rotating shaft is rotatably arranged on the pulley seat, two pulley bodies are fixedly arranged on the rotating shaft, a traction rope is commonly sleeved between the four pulley bodies, one end of the traction rope is fixedly connected to any one of the upper pulley bodies, and the traction rope is slidably sleeved on the other three pulley bodies, and the other end of the traction rope is fixedly connected to the lower side wall of the upper pulley seat, and the connecting buckle is fixedly connected to the lower side wall of the lower pulley seat.
[0013] According to a favorable embodiment, the drive assembly includes a worm wheel fixedly connected to one end of the upper rotating shaft, the worm wheel is meshed with a worm screwed on the side wall of the upper pulley seat and rotatably arranged through a connecting plate, a motor is fixedly arranged on a mounting column close to the worm screw, and the output shaft of the motor is fixedly connected to one end of the worm screw.
[0014] According to a favorable embodiment, the cable harness assembly includes four second screws rotatably arranged on the lower side wall of the lower connecting seat, and the cable harness seat is threadedly connected between the four second screws. The cable harness seat is provided with four circumferentially arranged matching grooves, and a circular ring is fixedly provided on the outer wall of the cable harness seat. A lifting rope is slidably connected to the circular ring segment in each matching groove, and one end of the lifting rope is fixedly connected to the corresponding connecting buckle. A locking buckle is provided on the surface of the lifting rope, and a limiting rope is fixedly provided between two adjacent locking buckles. A locking bolt is threadedly provided on the surface of the locking buckle, and the end of the locking bolt contacts the surface of the lifting rope.
[0015] According to a preferred embodiment, a first gear is fixedly provided on the upper end side wall of the third screw rod, and a second gear is rotatably provided at the middle position of the lower side wall of the lower connecting seat and meshes with the four first gears, and a plurality of pushing seats are fixedly provided on the lower side wall of the second gear.
[0016] Compared with the prior art, the prefabricated building component hoisting equipment provided by the embodiment of the present invention has the following beneficial effects:
[0017] 1. In the present invention, the first locking assembly and the second locking assembly provided in the connecting mechanism cooperate, and the two crossbeam assemblies on the connecting seat can not only rotate with the connecting seat at the same time, but also rotate around the connecting seat while the connecting seat remains stationary to adjust the position of the traction mechanism, so that the four traction mechanisms can match the appropriate lifting points on the building components as much as possible to perform stable lifting operations, with good stability and good lifting flexibility, and better adaptability.
[0018] 2. In the present invention, the first beam and the second beam arranged in the beam assembly can slide relative to each other for adjustment, and the slide seat on the second beam can drive the traction mechanism to perform secondary movement adjustment relative to the second beam, further improving the flexibility of the traction mechanism during lifting.
[0019] 3. In the present invention, the hoisting rope and the limiting rope in the cable harness assembly can cooperate to automatically press against the outer wall of the building component when tightened, thereby limiting the position of the building component, thereby making the building component more stable during hoisting. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is the external overall three-dimensional structure diagram of the present invention.
[0021] Figure 2 It is a bottom-up stereoscopic structural diagram of the connecting seat of the present invention.
[0022] Figure 3 It is a cross-sectional structural diagram of the connecting mechanism in the present invention.
[0023] Figure 4It is a planar cross-sectional structural diagram of the crossbeam assembly in the present invention.
[0024] Figure 5 It is a partial planar cross-sectional structural diagram of the crossbeam assembly in the present invention.
[0025] Figure 6 It is a planar structural diagram of the traction mechanism in the present invention.
[0026] Figure 7 This is a front cross-sectional structural diagram of the locking buckle.
[0027] Figure 8 It is a schematic diagram of the present invention when hoisting a columnar building component.
[0028] Fig. 9 It is a schematic diagram of the present invention when the panel is hoisted horizontally.
[0029] Reference numerals in the figure: 1, connecting mechanism; 11, connecting seat; 111, arc groove; 112, cavity; 12, connecting shaft; 13, first locking assembly; 131, second guide rod; 132, locking ring; 133, first positioning pin; 134, first spring; 14, first guide rod; 15, second locking assembly; 151, locking plate; 152, pressing column; 153, second spring; 154, connecting plate; 155, second positioning pin; 2, beam assembly; 21, first beam; 22, guide column; 23, second beam; 24, first screw; 25, turntable; 2 6. Limit pin; 27. Moving channel; 28. First tooth plate; 29. Sliding seat; 30. Second tooth plate; 3. Traction mechanism; 31. Mounting column; 32. Pulley block; 321. Pulley seat; 322. Rotating shaft; 323. Pulley body; 324. Traction rope; 33. Driving assembly; 331. Worm gear; 332. Worm; 333. Motor; 34. Connecting buckle; 4. Cable harness assembly; 41. Second screw rod; 42. Cable harness seat; 43. Ring; 44. Lifting rope; 45. Locking buckle; 46. Limit rope; 47. First gear; 48. Second gear; 49. Pushing seat. DETAILED DESCRIPTION
[0030] The following is combined with Figure 1-9 The present application is further described in detail.
[0031] Please refer to Figure 1 and Figure 8, a prefabricated building component hoisting equipment, including a connecting mechanism 1, on which four X-shaped beam assemblies 2 are arranged, on which a traction mechanism 3 is arranged, and on which a wire harness assembly 4 is also arranged for cooperating with the traction mechanism 3 to limit the building component. The four beam assemblies 2 are mounted on the connecting mechanism 1 in an X shape, and after the traction mechanism 3 is connected to an external fixing part (a special hook or other clamps adapted to the building component), the external fixing part is locked with the building component, and the traction mechanism 3 is guided by the wire harness assembly 4, so that the four traction mechanisms 3 can cooperate with each other to hoist the building component.
[0032] See also Figure 1 , Figure 2 , Figure 3 The connection mechanism 1 includes two upper and lower connection seats 11 in a disc structure, the two connection seats 11 are connected to each other by a connecting shaft 12, and a first locking assembly 13 is provided between the two connection seats 11. Two symmetrical arc grooves 111 are provided on the outer wall of the connection seat 11, and a first guide rod 14 in an arc structure is fixedly provided in the arc groove 111. The first guide rod 14 is connected to the corresponding cross beam assembly 2, and a second locking assembly 15 for limiting the cross beam assembly 2 is provided on the connection seat 11. The first locking assembly 13 locks the relative positions of the upper and lower connection seats 11 so that the two cannot rotate relative to each other, and the second locking assembly 15 can limit the cross beam assembly 2 and lock it on the connection seat 11.
[0033] See also Figure 3The first locking assembly 13 includes a plurality of second guide rods 131, which are fixedly arranged on the lower side wall of the upper connecting seat 11 and are evenly distributed along the circumferential direction of the connecting seat 11; a locking ring 132 is slidably connected between the plurality of second guide rods 131; a plurality of first positioning pins 133 evenly distributed along its circumferential direction are fixedly arranged on the edge of the lower side wall of the locking ring 132; a plurality of positioning grooves evenly distributed along its circumferential direction are provided on the edge of the upper side wall of the lower connecting seat 11; the first positioning pins 133 are slidably plugged into the positioning grooves; a plurality of first springs 134 evenly distributed along the circumferential direction of the locking ring 132 are fixedly connected between the upper side wall of the locking ring 132 and the lower side wall of the upper connecting seat 11. The upper and lower connecting seats 11 rotate through the connecting shaft 12, and the locking ring 132 moves downward under the action of the first spring 134, so that the first locating pin 133 is inserted into the locating groove on the upper side wall surface of the lower connecting seat 11, so that the two are locked. When necessary, the operator can push the locking ring 132 upward to disengage the first locating pin 133 from the locating groove, thereby releasing the lock on the connecting seat 11, so that the upper connecting seat 11 can be rotated to adjust the position, and after adjusting to the appropriate position, release the locking ring 132, so that the first locating pin 133 on the locking ring 132 can be inserted into the corresponding locating groove again for locking.
[0034] See also Figure 1 , Figure 2 , Figure 3 and Figure 4A cavity 112 communicating with two adjacent arc grooves 111 is provided inside the connecting seat 11, and a through hole communicating with the cavity 112 is provided on the surface of the connecting seat 11 on the side away from the connecting shaft 12. The second locking assembly 15 includes a locking plate 151 slidably arranged in the cavity 112, and a pressing column 152 is fixedly arranged on the side of the locking plate 151 close to the through hole, and one end of the pressing column 152 is slidably connected with the through hole. A plurality of second springs 153 are fixedly arranged on the side of the locking plate 151 away from the through hole, and one end of the second spring 153 away from the locking plate 151 is fixedly connected to the inner wall of the cavity 112. A connecting plate 154 is provided on the crossbeam assembly 2, and a positioning hole is provided on the surface of the connecting plate 154. A plurality of second positioning pins 155 are provided at a position facing each arc groove 111 on the side of the locking plate 151 close to the through hole, and the plurality of second positioning pins 155 are evenly distributed along the arc direction of the arc groove 111, and the positioning holes are slidably plugged with the second positioning pins 155. The locking disk 151 is acted upon by the second spring 153 so that the second locating pin 155 on the locking disk 151 can be plugged into the locating hole on the corresponding connecting plate 154, so that the connecting plate 154 cannot rotate, and the beam assembly 2 connected to the connecting plate 154 cannot rotate independently. When the staff pushes the end of the pressing column 152 with force, the pressing column 152 drives the locking disk 151 to slide in the cavity 112, so that the second locating pin 155 originally inserted into the locating hole slides and finally separates the second locating pin 155 from the locating hole, thereby releasing the limit of the beam assembly 2, so that the beam assembly 2 can rotate around the center of the circle of the connecting seat 11, thereby adjusting the position of the traction mechanism 3 on the beam assembly 2 independently.
[0035] In order to facilitate the adjustment of the traction mechanism 3 according to the position of the hoisting point on the building component, when the hoisting point on the building component is a symmetrical point, the first locking component 13 is used to release the limit between the upper and lower connecting seats 11, so that the upper and lower connecting seats 11 can rotate relative to each other, driving the two symmetrical beam assemblies 2 on the connecting seats 11 to rotate together, and adjusting the position of the beam assembly 2 to a suitable position; when the hoisting point on the building component is asymmetrical, the second locking component 15 is used to release the limit of the corresponding beam assembly 2, so that the corresponding beam assembly 2 can rotate and adjust the angle with the center of the connecting seat 11, thereby adjusting the position of the corresponding traction mechanism 3, so that the hoisting point of the traction mechanism 3 has a higher degree of freedom.
[0036] See also Figure 1 , Figure 2 , Figure 3 and Figure 4The beam assembly 2 includes a first beam 21, one end of the first beam 21 close to the connecting seat 11 is slidably set in the corresponding arc groove 111, and a connecting plate 154 is fixedly connected to the end surface of the first beam 21 in the arc groove 111, the first guide rod 14 is slidably connected to the corresponding first beam 21, a first slide groove is opened on the lower side of the first beam 21, a guide column 22 is fixedly set in the first slide groove, and a second beam 23 is slidably set in the first slide groove, a second slide groove is opened on the second beam 23, the guide column 22 is slidably set in the second slide groove, and a first screw rod 24 is rotatably set in the second slide groove, and the first screw rod 24 is threadedly connected to the guide column 22. A turntable 25 is rotatably provided at one end of the second beam 23 away from the connection seat 11, and the turntable 25 is fixedly connected to one end close to the first screw rod 24. Guide holes connected to the first slide groove are provided on both the longer side walls of the first beam 21, and a limit pin 26 is slidably connected in the guide hole, and the limit pin 26 is fixedly connected to the side wall of the second beam 23. The limit pin 26 can move synchronously in the guide hole when the second beam 23 slides, and when the second beam 23 moves to the limit position, the second beam 23 is prevented from completely moving out of the first beam 21. The staff controls the turntable 25 to rotate so that the first screw rod 24 rotates, thereby driving the second beam 23 to slide relative to the first beam 21, and adjusting the position of the traction mechanism 3.
[0037] See also Figure 4 and Figure 5 The second crossbeam 23 is provided with a moving channel 27 extending along its length and having a rectangular structure. A sliding hole is provided at the lower side of the moving channel 27. Two groups of first tooth plates 28 symmetrically distributed and equal in length to the moving channel 27 are fixedly arranged on the lower inner wall of the moving channel 27. A slide seat 29 is slidably connected in the moving channel 27. Two groups of second tooth plates 30 symmetrically distributed are fixedly arranged on the lower side wall of the slide seat 29. The second tooth plates 30 are engaged with the first tooth plates 28 below, and the slide seat 29 is connected to the traction mechanism 3. The staff lifts the slide seat 29 upwards by using a tool, so that the second tooth plate 30 below the slide seat 29 is separated from the first tooth plate 28 below, and then controls the slide seat 29 to move and adjust to a suitable position in the moving channel 27, and then puts the slide seat 29 down again, so that the second tooth plate 30 below the slide seat 29 is engaged with the first tooth plate 28 in the moving channel 27 again, so as to limit the slide seat 29.
[0038] In order to further facilitate the adjustment of the traction mechanism 3 according to the position of the lifting point of the building component, the traction mechanism 3 is installed on the slide 29, and the slide 29 can move on the second beam 23. At the same time, the second beam 23 itself can also move relative to the first beam 21. The traction mechanism 3 on each beam assembly 2 can slide in two stages, so that the traction mechanism 3 can be adjusted more flexibly according to the position of the lifting point of the building component.
[0039] See also Figure 1 , Figure 4 , Figure 5 and Figure 6 The traction mechanism 3 includes two mounting posts 31 fixedly connected to the lower side wall of the slide seat 29, a pulley block 32 is commonly arranged between the two mounting posts 31, a driving assembly 33 is arranged on the pulley block 32, and a connecting buckle 34 is also arranged on the pulley block 32. The pulley block 32 includes two pulley seats 321 symmetrical in upper and lower directions, a rotating shaft 322 is rotatably arranged on the pulley seat 321, two pulley bodies 323 are fixedly arranged on the rotating shaft 322, a traction rope 324 is commonly sleeved between the four pulley bodies 323, one end of the traction rope 324 is fixedly connected to any one of the upper pulley bodies 323, and the traction rope 324 is slidably sleeved on the other three pulley bodies 323, and the other end of the traction rope 324 is fixedly connected to the lower side wall of the upper pulley seat 321, and the connecting buckle 34 is fixedly connected to the lower side wall of the lower pulley seat 321. The driving assembly 33 includes a worm wheel 331 fixedly connected to one end of the upper rotating shaft 322, and a worm 332 is meshed on the worm wheel 331 and is rotatably arranged on the side wall of the upper pulley seat 321 through a connecting plate. A motor 333 is fixedly arranged on the mounting column 31 near the worm 332, and the output shaft of the motor 333 is fixedly connected to one end of the worm 332. The first end of the traction rope 324 is fixed to one of the upper pulley bodies, and then the traction rope 324 is sleeved on the surface of the pulley body 323 directly below it, and then the traction rope 324 is sleeved on the surface of another upper pulley body 323, passes through the pulley body 323, and then sleeved on the surface of the pulley body 323 below it, and then the end of the traction rope 324 is fixed to the lower side wall of the upper pulley seat 321. The worm 332 is driven to rotate by the motor 333, so that the worm wheel 331 drives the rotating shaft 322 on the upper pulley seat 321 to rotate. Since one end of the traction rope 324 is fixedly connected to one of the pulley bodies 323 on the rotating shaft 322, the traction rope 324 is wound around the pulley body 323 along with the body of the rotating shaft 322. At the same time, the other three pulley bodies 323 cooperate to gradually move the lower pulley seat 321 upward, thereby pulling the corresponding lifting point to tilt up. The building component can be controlled to be lifted in an inclined posture during lifting.
[0040] See also Figure 1 , Figure 2 , Figure 7 , Figure 8 and Fig. 9The cable assembly 4 includes four second screws 41 rotatably arranged on the lower side wall of the lower connecting seat 11, and a cable seat 42 is threadedly connected between the four second screws 41. The cable seat 42 is provided with four circumferentially arranged matching grooves, and a circular ring 43 is fixedly arranged on the outer wall of the cable seat 42. A lifting rope 44 is slidably connected to the circular ring 43 section in each matching groove, and one end of the lifting rope 44 is fixedly connected to the corresponding connecting buckle 34. A locking buckle 45 is sleeved on the surface of the lifting rope 44, and a limiting rope 46 is fixedly arranged between two adjacent locking buckles 45. A locking bolt is threadedly arranged on the surface of the locking buckle 45, and the end of the locking bolt contacts the surface of the lifting rope 44. The locking buckle 45 is fixed to the lifting rope 44 by the locking bolt, which is convenient for adjusting the specific position of the limiting rope 46. At the same time, the locking buckle 45 and the limiting rope 46 can be removed from the lifting rope 44 when not needed. A first gear 47 is fixedly provided on the upper side wall of the second screw rod 41 , and a second gear 48 is rotatably provided at the middle of the lower side wall of the lower connecting seat 11 and meshes with the four first gears 47 . A plurality of pushing seats 49 are fixedly provided on the lower side wall of the second gear 48 .
[0041] In order to further improve the stability of building components during hoisting, the staff can push any push seat 49 to rotate the second gear 48, thereby rotating the four first gears 47, controlling the lower cable tie seat 42 to move up or down, adjusting the distance between the cable tie seat 42 and the corresponding building component, and connecting one end of the lifting rope 44 to a fixing part (special hook or special clamp), and then locking it with the lifting point at the bottom of the building component. The upper connecting seat 11 is connected to the rope on the external crane, and the rope on the crane contracts to lift the traction mechanism 3, pulling the lifting rope 44 to tighten. The four lifting ropes 44 are brought closer to each other by the cable tie seat 42, so that the lifting rope 44 can be close to the surface of the building component to limit the position of the building component. At the same time, there is a limiting rope 46 between two adjacent lifting ropes 44, which is also attached to the surface of the building component to limit the position of the building component during hoisting, further improving the stability of the building component during hoisting. When the building component is a large pipe placed vertically or a large rectangular column, such as Figure 8 As shown, after the pipe is erected, the fixings on the lifting rope 44 are clamped on the lower edge of the pipe, and the fixings on the four lifting ropes 44 are connected to the pipe from different directions. When the traction mechanism 3 rises, the lifting rope 44 is tightened by the traction force. At this time, the lifting rope 44 will contact the surface of the pipe, and the limiting rope 46 between the adjacent lifting ropes 44 will fit on the surface of the pipe to limit the position. When the building component is a horizontally placed stone slab, such as Fig. 9 As shown, the fixings on the four lifting ropes 44 are fixedly connected to the lower part of the stone slab from different directions. When the traction mechanism 3 rises, the lifting ropes 44 are tightened by the traction force. At this time, the four lifting ropes 44 can respectively come into contact with the four side walls of the stone slab, thereby limiting the stone slab.
[0042] During specific operation, the four beam assemblies 2 are respectively installed on the connection mechanism 1, and the two connection seats 11 on the connection mechanism 1 are locked by the first locking assembly 13. When the first locking assembly 13 is unlocked, the relative positions of the four beam assemblies 2 can be adjusted, and the beam assembly 2 itself is connected to the connection seat 11 through the second locking assembly 15. When the second locking assembly 15 unlocks the beam assembly 2, the beam assembly 2 can be rotated independently to adjust the position of the corresponding traction mechanism 3. At the same time, the beam assembly 2 itself can be telescopically adjusted to further change the position of the traction mechanism 3, making the position adjustment of the traction mechanism 3 more flexible. After the traction mechanism 3 provided on the beam assembly 2 is connected to the external fixing part (special hook or other clamps compatible with the building component), the external fixing part is locked with the building component, and the traction mechanism 3 is guided by the wire harness assembly 4, so that the four traction mechanisms 3 can cooperate with each other to hoist the building component.
[0043] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A prefabricated building component lifting device, comprising a connecting mechanism (1), characterized in that: The connecting mechanism (1) is provided with four crossbeam assemblies (2) distributed in an X shape, the crossbeam assemblies (2) are provided with a traction mechanism (3), and the connecting mechanism (1) is also provided with a wire harness assembly (4) that cooperates with the traction mechanism (3) to limit the position of the building construction components; The connection mechanism (1) comprises two upper and lower connection seats (11) in the form of a disc structure and rotatably connected via a connection shaft (12); a first locking assembly (13) is commonly provided between the two connection seats (11); two symmetrical arc-shaped grooves (111) are provided on the outer side wall of the connection seat (11); a first guide rod (14) in the form of an arc-shaped structure is fixedly provided in the arc-shaped groove (111); the first guide rod (14) is connected to a corresponding crossbeam assembly (2); and a second locking assembly (15) for limiting the crossbeam assembly (2) is provided on the connection seat (11); The connection seat (11) is provided with a cavity (112) in communication with two adjacent arc-shaped grooves (111) on its interior; a through hole in communication with the cavity (112) is provided on a side surface of the connection seat (11) away from the connection shaft (12); the second locking assembly (15) comprises a locking plate (151) slidably arranged in the cavity (112); a pressing column (152) is fixedly arranged on a side of the locking plate (151) close to the through hole; one end of the pressing column (152) is slidably connected to the through hole; the locking plate (151) is provided with a pressing column (152) in a fixed manner; and one end of the pressing column (152) is slidably connected to the through hole. A plurality of second springs (153) are fixedly arranged on a side of the disk (151) away from the through hole, and one end of the second spring (153) away from the locking disk (151) is fixedly connected to the inner wall of the cavity (112). A connecting plate (154) is arranged on the crossbeam assembly (2), and a positioning hole is opened on the surface of the connecting plate (154). A plurality of second positioning pins (155) slidably connected to the corresponding positioning holes are arranged on a side of the locking disk (151) close to the through hole and facing each arc groove (111).
2. The prefabricated building component hoisting equipment according to claim 1, characterized in that: The first locking assembly (13) comprises a plurality of second guide rods (131), the plurality of second guide rods (131) are fixedly arranged on the lower side wall of the upper connecting seat (11) and are evenly distributed along the circumferential direction of the connecting seat (11), a locking ring (132) is slidably connected between the plurality of second guide rods (131), a plurality of first positioning pins (133) evenly distributed along the circumferential direction of the locking ring (132) are fixedly arranged on the edge of the lower side wall, a plurality of positioning grooves evenly distributed along the circumferential direction of the locking ring (132) are provided on the edge of the upper side wall of the lower connecting seat (11), the first positioning pins (133) are slidably plugged into the positioning grooves, and a plurality of first springs (134) evenly distributed along the circumferential direction of the locking ring (132) are fixedly connected between the upper side wall of the locking ring (132) and the lower side wall of the upper connecting seat (11).
3. The prefabricated building component hoisting equipment according to claim 2, characterized in that: The crossbeam assembly (2) comprises a first crossbeam (21), one end of the first crossbeam (21) close to the connecting seat (11) is slidably arranged in a corresponding arc groove (111), and a connecting plate (154) is fixedly connected to the end surface of the first crossbeam (21) in the arc groove (111), the first guide rod (14) is slidably connected to the corresponding first crossbeam (21), a first sliding groove is provided on the lower side of the first crossbeam (21), a guide column (22) is fixedly arranged in the first sliding groove, and a second crossbeam (23) is slidably arranged in the first sliding groove, a second crossbeam (23) is provided on the second crossbeam (23), the guide column (22) is slidably arranged in the second sliding groove, and a first screw rod (24) is rotatably arranged in the second sliding groove, and the first screw rod (24) is threadedly connected to the guide column (22).
4. The prefabricated building component hoisting equipment according to claim 3, characterized in that: A turntable (25) is rotatably provided at one end of the second cross beam (23) away from the connecting seat (11), and the turntable (25) is fixedly connected to the end close to the first screw rod (24). Guide holes connected to the first sliding groove are provided on the longer side walls of the first cross beam (21), and a limit pin (26) is slidably connected in the guide hole, and the limit pin (26) is fixedly connected to the side wall of the second cross beam (23).
5. The prefabricated building component hoisting equipment according to claim 3, characterized in that: The second crossbeam (23) is provided with a moving channel (27) extending along its length direction and having a rectangular structure, a sliding hole is provided on the lower side of the moving channel (27), two groups of symmetrically distributed first tooth plates (28) of the same length as the moving channel (27) are fixedly arranged on the lower inner wall of the moving channel (27), a sliding seat (29) is slidably connected in the moving channel (27), two groups of symmetrically distributed second tooth plates (30) are fixedly arranged on the lower side wall of the sliding seat (29), the second tooth plates (30) are clamped with the lower first tooth plates (28), and the sliding seat (29) is connected to the traction mechanism (3).
6. The prefabricated building component hoisting equipment according to claim 5, characterized in that: The traction mechanism (3) comprises two mounting columns (31) both fixedly connected to the lower side wall of the slide seat (29), a pulley block (32) being arranged between the two mounting columns (31), a driving assembly (33) being arranged on the pulley block (32), and a connecting buckle (34) being also arranged on the pulley block (32).
7. The prefabricated building component hoisting equipment according to claim 6, characterized in that: The pulley block (32) comprises two pulley seats (321) symmetrical in upper and lower directions, a rotating shaft (322) is rotatably arranged on the pulley seat (321), two pulley bodies (323) are fixedly arranged on the rotating shaft (322), a traction rope (324) is commonly sleeved between the four pulley bodies (323), one end of the traction rope (324) is fixedly connected to any one of the upper pulley bodies (323), and the traction rope (324) is slidably sleeved on the other three pulley bodies (323), and the other end of the traction rope (324) is fixedly connected to the lower side wall of the upper pulley seat (321), and the connecting buckle (34) is fixedly connected to the lower side wall of the lower pulley seat (321).
8. The prefabricated building component hoisting equipment according to claim 7, characterized in that: The driving assembly (33) comprises a worm wheel (331) fixedly connected to one end of the upper rotating shaft (322); the worm wheel (331) is meshed with a worm (332) rotatably arranged on the side wall of the upper pulley seat (321) via a connecting plate; a motor (333) is fixedly arranged on the mounting column (31) close to the worm (332); and an output shaft of the motor (333) is fixedly connected to one end of the worm (332).
9. The prefabricated building component hoisting equipment according to claim 6, characterized in that: The cable harness assembly (4) includes four second screw rods (41) rotatably arranged on the lower side wall of the lower connecting seat (11), and a cable harness seat (42) is commonly threadedly connected between the four second screw rods (41). The cable harness seat (42) is provided with four circumferentially arranged matching grooves, and a circular ring (43) is fixedly arranged on the outer wall of the cable harness seat (42). A lifting rope (44) is slidably connected to the circular ring (43) section in each matching groove, and one end of the lifting rope (44) is fixedly connected to the corresponding connecting buckle (34). A locking buckle (45) is sleeved on the surface of the lifting rope (44), and a limiting rope (46) is fixedly arranged between two adjacent locking buckles (45). A locking bolt is threadedly arranged on the surface of the locking buckle (45), and the end of the locking bolt contacts the surface of the lifting rope (44).
10. The prefabricated building component hoisting equipment according to claim 9, characterized in that: A first gear (47) is fixedly arranged on the upper side wall of the second screw rod (41), and a second gear (48) is rotatably arranged at the middle of the lower side wall of the lower connecting seat (11) and meshes with the four first gears (47), and a plurality of pushing seats (49) are fixedly arranged on the lower side wall of the second gear (48).
Citation Information
Patent Citations
Green energy-saving fabricated building and construction method
CN114086660A
Fabricated building hoisting equipment
CN116730185A