Construction method of turnover type post-cast strip support
Through modular design and optimization of construction technology, efficient installation and reuse of the post-pouring belt support system is achieved, and the problems of waste of materials, low efficiency, difficulty in ensuring quality and great environmental impact in traditional construction are solved, which significantly reduces construction costs and construction periods, and improves construction quality and adaptability.
Patent Information
- Application Number
- CN202411678283.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-22
- Publication Date
- 2025-03-25
AI Technical Summary
In the construction of traditional post-pouring belts, there are problems such as serious material waste, low construction efficiency, difficult quality protection and great environmental impact. The existing turnover support system has complex structure, large weight, long installation time, low applicability and short service life.
The modular design of the turnable rear casting tape supports construction method is adopted. Through efficient installation and reuse of the design support system, modular steel frames and lightweight formwork are selected, and the quick connections and positioning pins are used for precise installation. Combined with layered casting and vibration processes, the concrete is ensured.
It realizes efficient installation and reuse of the support system, reduces construction costs and construction periods, improves construction quality, has significant economic and environmental benefits, strong adaptability, and extends component life.
Abstract
Description
Technical Field
[0001] The invention relates to a construction method, in particular to a construction method for a rotatable post-casting strip support, and belongs to the technical field of building construction. Background Art
[0002] Post-cast strips are a common construction method in construction projects. They are mainly used to deal with temperature stress and uneven settlement problems in concrete structures. They form a strong connection through later pouring. However, in traditional post-cast strip construction, disposable wooden formwork or simple steel formwork is generally used for support. This method has the following technical defects: Serious waste of materials: Disposable wooden and steel formworks usually cannot be reused after use and are easily damaged during dismantling, resulting in a large amount of construction waste and increasing construction costs.
[0003] Low construction efficiency: The traditional support system requires manual adjustment and assembly on site, which is complicated and time-consuming, and can easily delay the construction progress.
[0004] Quality is difficult to guarantee: Due to insufficient rigidity of the support system or low installation precision, the formwork is prone to deformation, resulting in quality problems such as loose joints or leakage of concrete after construction of the post-cast zone.
[0005] The environmental impact is large: the use of disposable formwork not only consumes a large amount of wood or steel, but also generates a large amount of garbage, causing environmental pollution.
[0006] In response to the above problems, the industry has gradually explored the use of turnaround formwork and support systems to optimize the post-casting construction process, but the existing technology still has the following shortcomings: the turnaround support system has a complex structure and heavy weight, and on-site installation still requires a lot of manpower and time; some designs lack modular concepts, and the support system has low applicability and cannot meet the needs of different project scales; the support system is susceptible to wear and tear during repeated use, the number of turnovers is limited, and the service life is short.
[0007] Based on the above problems, the present invention provides a construction method for a recyclable post-cast strip support. Through modular design and optimized construction process, efficient installation and reuse of the support system can be achieved, which not only reduces construction costs and shortens construction period, but also improves the construction quality of the post-cast strip, and has significant economic and environmental benefits. Summary of the invention
[0008] The purpose of the present invention is to provide a construction method for a recyclable post-cast strip support, so as to achieve efficient installation and reuse of the support system through modular design and optimized construction process, which not only reduces construction costs and shortens construction period, but also improves the construction quality of the post-cast strip. It has the advantages of significant economic and environmental benefits, and solves the problems raised by the above-mentioned background technology.
[0009] To achieve the above object, the present invention provides the following technical solution: a construction method for a rotatable post-casting belt support, comprising the following steps: S1. Design and assembly of support system: Calculate the position and size of the post-casting strip according to the design drawings, design the post-casting strip support system according to the construction drawings, and select modular steel frames and lightweight formwork; S2. On-site support installation: Install a revolving support frame at the post-casting zone, and adjust the height and width of the frame to match the construction requirements. Assemble the support system at the construction site, and use the level adjuster and positioning pins to ensure the accuracy of the frame; S3. Reservation of post-casting zone area: Install the load-bearing formwork on the support system and pour concrete on both sides to reserve the post-casting zone area; S4. Reuse: After the concrete of the post-cast zone is poured and reaches the designed strength, the support frame is dismantled and recycled to achieve the turnover use of the support system.
[0010] As a preferred technical solution of the present invention, the support frame is of modular design and is spliced together from high-strength steel components. It has the ability to bear high loads. The modular design allows the support frame to be quickly disassembled and assembled, and can be flexibly adjusted according to the shape of the post-casting strip to reduce material waste. Each module is equipped with an anti-slip gasket to ensure the stability of the support system.
[0011] As a preferred technical solution of the present invention, the support frame is installed by fast connectors and positioning pins, which has high connection accuracy, reduces assembly time, and ensures the overall rigidity and load-bearing capacity of the support system.
[0012] As a preferred technical solution of the present invention, the bearing template is made of corrosion-resistant aluminum alloy material, and the surface is covered with a polymer anti-stick coating. The template can be used multiple times and is easy to clean, thereby extending the service life of the template.
[0013] As a preferred technical solution of the present invention, before the construction of the post-cast strip, a rubber water stop is installed in the formwork, and an interface treatment agent is used to clean the concrete surface on both sides of the post-cast strip to ensure the subsequent connection strength and waterproof performance.
[0014] As a preferred technical solution of the present invention, support feet with adjustable heights are installed at the bottom of the support frame, and the height is adjusted to adapt to uneven terrain to ensure the horizontality of the support system.
[0015] As a preferred technical solution of the present invention, after the support frame is dismantled, the surface of the components is subjected to anti-corrosion treatment, concrete residues are removed, and a protective coating is applied to extend the turnover times and service life of the support system.
[0016] As a preferred technical solution of the present invention, when pouring the post-cast zone concrete, a layered pouring and vibration process is adopted, and the vibration time of each layer is not less than 30 seconds to ensure the compactness and overall quality of the concrete.
[0017] As a preferred technical solution of the present invention, the support frame adopts modular numbering management, which is convenient for zoning and rapid installation at the construction site, thereby improving construction efficiency. After repeated use, the support system needs to be inspected regularly and damaged components need to be replaced or repaired to ensure that the support system always meets the requirements of construction safety and structural stability.
[0018] Compared with the related art, the construction method of a revolving post-casting belt support provided by the present invention has the following beneficial effects: (1) Turnover use to save costs: The support system adopts modular design, the materials are strong and durable, and can be repeatedly disassembled and recycled, which greatly reduces the use of disposable support materials and saves construction costs; (2) Efficient construction and shortened construction period: The modular and quick-connect design of the support frame makes installation and removal more convenient, while reducing the workload and time during the construction process, significantly improving construction efficiency; (3) Reliable quality and stable structure: The supporting frame structure is reasonably designed, with high bearing capacity and stability. Combined with high-precision installation technology, it effectively guarantees the concrete quality and construction safety in the post-casting zone area. (4) Environmentally friendly materials, reducing waste: The support system mainly uses recyclable materials such as steel and aluminum alloy, which has a long service life; compared with traditional disposable wooden formwork and support systems, it reduces the generation of construction waste and is beneficial to environmental protection; (5) Strong adaptability and flexibility: The support frame can adjust the height and width to meet the construction requirements of post-casting strips of different shapes and sizes. It has a wide range of application scenarios and is suitable for complex construction environments. (6) Significant anti-seepage effect: During the construction of the post-casting strip, the waterproof performance of the later structure is ensured and leakage problems are avoided by setting water stop strips and precise interface treatment technology; (7) Extend component life and reduce long-term costs: Regular maintenance and surface anti-corrosion treatment of the support system extend the service life of the components, enable more turnover and further reduce the total cost of the project; (8) Improved safety and reduced risks: The design of the support system fully considers the construction safety. The anti-slip pads, positioning pins and other components are used to improve the stability and anti-slip performance of the system, reducing the possibility of construction accidents. (9) Modular management for easy maintenance: The support frame adopts a numbering management mode to facilitate the transportation, storage and on-site arrangement of components, avoiding the problem of confusion or loss in traditional support systems; (10) Promoting the concept of green construction: The present invention meets the requirements of green construction and sustainable development in the field of modern construction, can achieve a more efficient and environmentally friendly construction process while reducing resource consumption, and has great social benefits and economic value. DETAILED DESCRIPTION
[0019] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0020] The present invention provides a construction method for a rotatable post-casting belt support, comprising the following steps: The following steps are involved: S1. Design and assembly of support system: Calculate the position and size of the post-casting strip according to the design drawings, design the post-casting strip support system according to the construction drawings, and select modular steel frames and lightweight formwork; S2. On-site support installation: Install a revolving support frame at the post-casting zone, and adjust the height and width of the frame to match the construction requirements. Assemble the support system at the construction site, and use the level adjuster and positioning pins to ensure the accuracy of the frame. S3. Reservation of post-casting zone area: Install the load-bearing formwork on the support system and pour concrete on both sides to reserve the post-casting zone area; S4. Reuse: After the concrete of the post-cast zone is poured and reaches the designed strength, the support frame is dismantled and recycled to achieve the turnover use of the support system.
[0021] In one embodiment of the present invention, the support frame is modularly designed and is made of high-strength steel components, which have the ability to bear high loads, and each module is equipped with an anti-slip pad to ensure the stability of the support system; The support frame is installed with quick connectors and positioning pins, which has high connection accuracy, reduces assembly time, and ensures the overall rigidity and load-bearing capacity of the support system; The bearing template is made of corrosion-resistant aluminum alloy material and the surface is covered with a polymer anti-stick coating. The template can be used multiple times and is easy to clean, extending the service life of the template; Before the construction of the post-cast strip, a rubber waterstop is installed in the formwork, and the interface treatment agent is used to clean the concrete surface on both sides of the post-cast strip to ensure the subsequent connection strength and waterproof performance; adjustable height support feet are installed at the bottom of the support frame to adapt to uneven terrain by adjusting the height to ensure the horizontality of the support system; after the support frame is dismantled, the surface of the components is treated with anti-corrosion, concrete residues are removed, and a protective coating is applied to extend the turnover number and service life of the support system; when pouring the concrete of the post-cast strip, a layered pouring and vibration process is adopted, and the vibration time for each layer is not less than 30 seconds to ensure the density and overall quality of the concrete; the support frame adopts modular numbering management to facilitate the zoning use and rapid installation of the construction site, and improve construction efficiency. After repeated turnover use, the support system needs to be inspected regularly and damaged components replaced or repaired to ensure that the support system always meets the construction safety and structural stability requirements.
[0022] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction method for a revolving post-casting belt support, characterized in that: The following steps are involved: S1. Design and assembly of support system: Calculate the position and size of the post-casting strip according to the design drawings, design the post-casting strip support system according to the construction drawings, and select modular steel frames and lightweight formwork; S2. On-site support installation: Install a revolving support frame at the post-casting zone, and adjust the height and width of the frame to match the construction requirements. Assemble the support system at the construction site, and use the level adjuster and positioning pins to ensure the accuracy of the frame; S3. Reservation of post-casting zone area: Install the load-bearing formwork on the support system and pour concrete on both sides to reserve the post-casting zone area; S4. Reuse: After the concrete of the post-cast zone is poured and reaches the designed strength, the support frame is dismantled and recycled to achieve the turnover use of the support system.
2. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: The support frame is modular in design and is made up of high-strength steel components. It has the ability to carry high loads, and each module is equipped with anti-slip pads to ensure the stability of the support system.
3. The construction method of a rotatable post-casting strip support according to claim 2 is characterized in that: The support frame is installed with quick connectors and positioning pins, which has high connection accuracy, reduces assembly time, and ensures the overall rigidity and load-bearing capacity of the support system.
4. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: The load-bearing template is made of corrosion-resistant aluminum alloy material and the surface is covered with a polymer anti-stick coating. The template can be used multiple times and is easy to clean, extending the service life of the template.
5. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: Before the construction of the post-cast strip, install a rubber waterstop in the formwork and use an interface treatment agent to clean the concrete surface on both sides of the post-cast strip to ensure the subsequent connection strength and waterproof performance.
6. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: Install height-adjustable support feet at the bottom of the support frame to adapt to uneven terrain and ensure the levelness of the support system.
7. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: After the support frame is removed, the components are subjected to surface anti-corrosion treatment, concrete residues are removed, and protective coatings are applied to extend the turnover rate and service life of the support system.
8. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: When pouring concrete in the post-cast zone, the layered pouring and vibration process is adopted, and the vibration time for each layer is not less than 30 seconds to ensure the density and overall quality of the concrete.
9. The construction method of a rotatable post-casting strip support according to claim 1 is characterized in that: The supporting frame adopts modular numbering management to facilitate zoning and rapid installation at the construction site, thereby improving construction efficiency.
10. The construction method of a rotatable post-casting strip support according to claim 1, characterized in that: After repeated use, the support system needs to be inspected regularly and damaged components replaced or repaired to ensure that the support system always meets the requirements of construction safety and structural stability.