A cooling and heating pipe installation device and installation process

By adopting the design of telescopic hanger and sliding bracket in the installation of cooling and heating pipes, the insulation layer cracks and bracket damage caused by the expansion and displacement of the riser are solved, and a stable installation with a long life is achieved.

CN119778556APending Publication Date: 2025-04-08CHENGDU ORIENTAL GUANGYI INVESTMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411861124.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-17
Publication Date
2025-04-08

AI Technical Summary

Technical Problem

In the prior art, the expansion and displacement of the riser tube can easily affect the riser insulation layer and bracket, resulting in cracks in the insulation layer and damage to the bracket.

Method used

The heating and cooling pipe installation device including a telescopic hanger and a sliding bracket is adopted. The telescopic hanger is connected to the transverse pipe through screws and elastic parts, and the sliding bracket is connected to the riser through an annular tube support and a ball slider, allowing the riser to move smoothly when expanding and contracting, avoiding damage caused by displacement.

Benefits of technology

Effectively support and fix the heating and cooling pipes, avoid cracks in the insulation layer of the riser and bracket damage, and extend the service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119778556A_ABST
    Figure CN119778556A_ABST
Patent Text Reader

Abstract

The present invention discloses a cooling and heating pipe installation device and installation process, and relates to the technical field of cooling and heating pipe installation. The cooling and heating pipe installation device includes a telescopic hanger for limiting the horizontal pipe and a sliding bracket for limiting the vertical pipe. The telescopic hanger includes a fixing piece connected to the roof, the fixing piece is connected to a screw, the lower end of the screw is provided with an elastic piece, the elastic piece is connected to a hanger, the hanger is provided with a sleeve ring 1 connected to the horizontal pipe, the sliding bracket includes a bracket body, a sleeve ring 2 and an annular pipe support, the bracket body is fixed to the wall, the annular pipe support is fixedly connected to the vertical pipe, the annular pipe support is elastically deformed by force after the vertical pipe expands, a plurality of sliders are provided on the outside of the annular pipe support, and a plurality of balls rolling on the surface of the sliders are provided on the inside of the sleeve ring 2. The installation process includes the steps of design, manufacture, installation, fastening and heat preservation treatment, testing, and delivery. The cooling and heating pipe installation device and the installation process can not only play the role of support and fixation, but also are not easy to be damaged, and have the advantage of long service life.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of cooling and heating pipe installation, and in particular to a cooling and heating pipe installation device and an installation process. Background Art

[0002] The difference between the installation of cold and hot water pipes for air conditioners is that the temperature difference between the cold water temperature of the air conditioner and the ambient temperature is about 22-32℃, the cold contraction of the pipe is often small, and the requirements for cold insulation materials and thickness are based on the principle of preventing the pipe from generating condensation during use. The cold water pipe support and hanger need to prevent the generation of cold bridges. The temperature difference between hot water and ambient temperature is about 40-50℃, and the thermal expansion of the hot water pipe of the air conditioner is large. The insulation materials and thickness require that the temperature of the insulation shell meets the energy-saving and safety requirements, and there is no concern about the generation of condensation. Therefore, the focus of the support and hanger is the impact of thermal expansion on the building and others.

[0003] In the prior art, since the supporting points of the pipes are often at the bottom of the pipes and the convection transfer of heat is upward, the hot water pipes do not consider the transfer of thermal bridges. In the current installation process, the cold water pipe installation method is often used. The horizontal cross pipe can still solve the thermal expansion and contraction by the swinging method of the hanger, and the vertical pipe is generally only fixed to the wall by a clamp and an insulated pipe support. After a period of use, the vertical pipe will be displaced due to expansion and contraction. If it moves in the insulated pipe support, cracks will easily occur in the vertical pipe insulation layer on the inside of the insulated pipe support, and if the insulated pipe support is tight to the pipe, the bracket will be easily damaged.

[0004] Therefore, the prior art needs to be improved. Summary of the invention

[0005] The technical problem to be solved by the present invention is that the expansion and displacement of the riser in the prior art easily affect the insulation layer and the bracket of the riser. The purpose is to provide a cold and heating pipe installation device and installation process, which adopts corresponding technical means to deal with the thermal expansion and contraction of the cold and heating pipes, which can not only play a supporting and fixing role, but also is not easy to be damaged, and has the advantage of a long service life.

[0006] The present invention is achieved through the following technical solutions:

[0007] In a first aspect, the present invention provides a cooling and heating pipe installation device, which includes a telescopic hanger for limiting a horizontal pipe and a sliding bracket for limiting a vertical pipe, the telescopic hanger includes a fixing part connected to a roof, the fixing part is connected to a screw, the lower end of the screw is provided with an elastic part, the elastic part is connected to a hanger, the hanger is provided with a sleeve 1 connected to the horizontal pipe, the sliding bracket includes a bracket body, a sleeve 2 and an annular pipe support, the bracket body is fixed to a wall, the annular pipe support is fixedly connected to the vertical pipe, the annular pipe support is elastically deformed by force after the vertical pipe expands, a plurality of sliders are provided on the outer side of the annular pipe support, a plurality of balls rolling on the surface of the slider are provided on the inner side of the sleeve 2.

[0008] Furthermore, in the present invention, the above-mentioned fixing part is configured as a channel steel, the channel steel is provided with a through hole for the screw to pass through, the screw is provided with a nut abutting the upper surface of the channel steel, the upper surface of the channel steel is provided with a curved groove connected to the through hole, and the nut is provided with a curved head that deflects and slides in the curved groove.

[0009] Furthermore, in the present invention, the elastic member includes a connecting member, the connecting member is provided with two through holes for the screw rod to pass through, the screw rod is provided with two nuts for fixing the connecting member, the connecting member is provided with a first spring, and the suspension rod is connected to the first spring.

[0010] Furthermore, in the present invention, the above-mentioned first spring is arranged inside the connecting piece, the suspension rod passes through the middle of the first spring, the suspension rod is provided with a nut three connected to the top of the first spring, the top of the first spring is provided with a pad connected to the nut three, and the bottom of the first spring is provided with a pad connected to the connecting piece.

[0011] Furthermore, in the present invention, rotating shafts are arranged on both sides of the above-mentioned ball, a groove for embedding the rotating shaft is arranged on the inner side of the ring sleeve 2, an anti-slip pattern 1 is arranged on the surface of the ball, a rolling groove is arranged on the surface of the slider, and an anti-slip pattern 2 cooperating with the anti-slip pattern 1 is arranged in the rolling groove.

[0012] Furthermore, in the present invention, a retaining ring is provided on the inner wall of the second ring sleeve, the vertical pipe is provided with a retaining rod passing through the annular pipe support, and a second spring is provided between the retaining rod and the retaining ring.

[0013] Furthermore, in the present invention, the inner wall of the above-mentioned sleeve ring 1 is provided with a heat insulating ring, the annular pipe support and the heat insulating ring are both configured as rubber rings, and the sleeve ring 1 and the sleeve ring 2 are both configured as clamps.

[0014] In a second aspect, the present invention further provides a cooling and heating pipe installation process, which uses the cooling and heating pipe installation device and also includes the following method:

[0015] S1. Based on the designed 3D architectural drawing, each designed pipeline including the cooling and heating pipe installation device according to claim 1 is reflected on the drawing;

[0016] S2. Reserve casing and embedded parts during the civil construction process according to the 3D architectural drawing;

[0017] S3. Make or purchase cooling and heating pipe installation devices according to the 3D architectural drawings, and design and number the cooling and heating pipe installation devices;

[0018] S4. Fix the cooling and heating pipe installation device on the wall or roof, and connect the horizontal pipe and vertical pipe to the cooling and heating pipe installation device;

[0019] S5. Connect the horizontal pipes and vertical pipes, and install valves and instruments;

[0020] S6. Perform water pressure test on horizontal pipes and vertical pipes, and flush the pipes after the test;

[0021] S7. Re-tighten the flange connections of the horizontal pipe and vertical pipe, and then perform insulation treatment;

[0022] S8. In summer, introduce chilled water into the horizontal pipes and vertical pipes for trial operation;

[0023] S9. After the horizontal pipes and vertical pipes operate normally in both summer and winter, organize the five parties to conduct acceptance and delivery.

[0024] Furthermore, in the present invention, ultrasonic vibrators are provided on the outer walls of the horizontal pipe and the vertical pipe, and in the step S6, the ultrasonic vibrators operate during flushing.

[0025] Furthermore, in the present invention, during the heat preservation treatment process in step S7, a shell is used to cover the flange connections of the horizontal pipe and the vertical pipe, and heat preservation material is filled into the shell.

[0026] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0027] The horizontal pipes of the cold and heating pipes are connected and fixed by telescopic hangers, and the vertical pipes of the cold and heating pipes are connected and fixed by sliding brackets. When the vertical pipes are displaced up and down due to thermal expansion and contraction, the annular pipe support also moves along due to its fixed connection with the vertical pipe, avoiding displacement between the vertical pipe and the annular pipe support and causing cracks in the vertical pipe insulation layer. At this time, due to the contact between the slider and the ball, the ball can roll on the surface of the slider, facilitating the movement of the annular pipe support and the vertical pipe, and preventing the bracket body from being damaged due to the tightness between the annular pipe support and the bracket body, thereby extending the service life. Therefore, the cold and heating pipe installation device and installation process of the present invention can not only play the role of support and fixation, but also are not easy to be damaged, and have the advantage of long service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:

[0029] Figure 1 It is a schematic diagram of the cooling and heating pipe installation device of the present invention;

[0030] Figure 2 is a schematic diagram of a sliding bracket of the present invention;

[0031] Figure 3 for Figure 1 The enlarged schematic diagram of point A in the middle;

[0032] Figure 4 for Figure 1 The enlarged schematic diagram of point B in the middle;

[0033] Figure 5 A schematic diagram of a ball and a slider of the present invention;

[0034] Figure 6 It is a cross-sectional schematic diagram of the riser and the second ring sleeve of the present invention;

[0035] Figure 7 It is a schematic diagram of the ball and rolling groove of the present invention.

[0036] The markings and corresponding parts names in the accompanying drawings are: 1-telescopic hanger, 101-fixing part, 1011-through hole one, 1012-curved groove, 102-screw, 1021-nut one, 1022-curved head, 1023-nut two, 103-hanging rod, 1031-nut three, 2-sliding bracket, 201-bracket body, 202-ring sleeve two, 203-annular pipe support, 204-blocking ring, 3-elastic part, 301-connecting part, 302-first spring, 303-pad, 4-ring one, 5-slider, 501-rolling groove, 502-anti-slip pattern two, 6-ball, 601-rotating shaft, 602-anti-slip pattern one, 7-blocking rod, 8-second spring. DETAILED DESCRIPTION

[0037] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with the embodiments and drawings. The schematic implementation mode of the present invention and its description are only used to explain the present invention and are not intended to limit the present invention. The following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention.

[0038] It should be noted that similar numbers and letters represent similar items in the following figures. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures. In the description of the embodiments of the present invention, it should also be noted that unless otherwise clearly specified and limited, the terms "setting", "installation" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, and it can be the internal connection of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0039] Example 1

[0040] Please refer to Figures 1 to 7 , shown is a cooling and heating pipe installation device according to an embodiment of the present invention, and the specific structure and principle are described as follows.

[0041] Combination Figure 1 As shown, the existing heating and cooling pipes are generally composed of horizontal transverse pipes and vertical risers. In order to achieve fixed installation of the transverse pipes and the risers, the heating and cooling pipe installation device of the present invention mainly includes two parts: a telescopic hanger 1 and a sliding bracket 2, wherein the telescopic hanger 1 is used to connect the transverse pipe, and the sliding bracket 2 is used to connect the risers.

[0042] In some implementations of this embodiment, Figure 1 As shown, the telescopic hanger 1 of this embodiment 1 mainly includes three parts: a fixing member 101, a screw rod 102 and a hanger rod 103, wherein the fixing member 101 is made of channel steel, and the open side of the channel steel faces the vertical wall during installation, and the fixing member 101 is fixedly connected to the floor (roof) by expansion screws.

[0043] Further, combined with Figure 1 and Figure 3 As shown, a through hole 1011 is provided on the bottom plate of the fixing member 101, and a curved groove 1012 is provided on the top surface of the bottom plate of the fixing member 101, and the curved groove 1012 is connected with the through hole 1011. The top end of the screw rod 102 passes through the through hole 1011 and the curved groove 1012 in sequence, and a nut 1021 is threadedly connected on the screw rod 102, and the bottom of the nut 1021 has a curved head 1022, which is in a hemispherical shape, and the surface of the curved head 1022 fits the surface of the curved groove 1012, so that the curved head 1022 can slide along the curved groove 1012, thereby facilitating the deflection of the screw rod 102.

[0044] It should be noted that after the nut 1021 is rotated, it can move up and down along the screw rod 102, which is convenient for adjusting the suspension height of the cross pipe and has a better use effect.

[0045] Furthermore, combined Figure 1 and Figure 4 As shown, the screw rod 102 and the suspension rod 103 are connected by an elastic member 3. The elastic member 3 mainly includes a connecting member 301 and a first spring 302. The connecting member 301 can be made of square steel, and an opening is provided at the bottom of the connecting member 301 for the top end of the suspension rod 103 to pass through. A through hole 2 is provided at the top of the connecting member 301, and the bottom end of the screw rod 102 passes through the through hole 2, and then the top of the connecting member 301 is clamped by two nuts 1023 on the screw rod 102, which plays a fixing role.

[0046] It should be noted that a gasket is installed between the nut 1023 and the top of the connecting piece 301 to achieve a better fixing effect.

[0047] In some implementations of this embodiment, Figure 1 and Figure 4 As shown, the first spring 302 is vertically installed inside the connecting member 301, and a pad 303 is installed on the top of the first spring 302. The pad 303 has a round hole for the suspension rod 103 to pass through. The bottom of the first spring 302 is also installed with a pad 303. The size of the pad 303 is larger than the bottom opening of the connecting member 301, and it also has a round hole for the suspension rod 103 to pass through. The suspension rod 103 is a threaded rod. After the top of the suspension rod 103 vertically passes through the two pads 303, a nut 3 1031 is installed on the top of the suspension rod 103. The nut 3 1031 cannot pass through the pad 303 on the top, thereby limiting the suspension rod 103. The first spring 302 has deformation ability, thereby adapting to the expansion and contraction deformation caused by the horizontal pipe and the vertical pipe.

[0048] Further, the collar 104 is fixed at the bottom end of the suspension rod 103, and the collar 104 is sleeved on the outside of the transverse tube, and the collar 104 is a clamp. A heat insulating ring is arranged inside the collar 104, and the heat insulating ring is in direct contact with the transverse tube. The heat insulating ring is a rubber ring made of rubber material, which has good heat insulating performance, avoids affecting the collar 104, and has elasticity to adapt to the expansion and contraction deformation of the transverse tube.

[0049] In some implementations of this embodiment, Figure 1 and Figure 2 As shown, the sliding bracket 2 mainly includes three parts: a bracket body 201, a second ring sleeve 202 and an annular pipe support 203. The bracket body 201 can be made of channel steel. When installed, the opening side of the channel steel faces the roof. The bracket body 201 is fixedly connected to the vertical wall through expansion screws. An opening is opened on the side of the bracket body 201 away from the vertical wall. The second ring sleeve 202 is installed at the opening position, and the vertical pipe is installed inside the second ring sleeve 202.

[0050] Further, combined with Figure 2 and Figure 5 As shown, the ring sleeve 202 adopts a clamp, and the two halves of the clamp are respectively clamped to the outer plate of the bracket body 201 by bolts, and the riser is fixed. A hemispherical groove is provided inside the ring sleeve 202, and a ball 6 coated with lubricating grease is installed in the groove. The ball 6 adopts a steel ball. The annular pipe support 203 is sleeved on the outside of the riser and fixedly connected to the riser. A slider 5 is installed on the outer surface of the annular pipe support 203. Six sliders 5 are evenly arranged around the center of the annular pipe support 203, and the corresponding balls 6 are also evenly arranged around. The six sliders 5 and the six balls 6 are aligned one by one. When the riser moves in the vertical direction due to expansion or contraction, the annular pipe support 203 also moves, and the balls 6 roll on the surface of the slider 5 to avoid damaging the sliding bracket 2.

[0051] It should be noted that the annular pipe support 203 is a rubber ring, which has the function of heat insulation and can be deformed to adapt to the expansion and contraction deformation of the vertical pipe.

[0052] In some implementations of this embodiment, Figure 6 As shown, a second spring 8 is provided to support the vertical expansion and contraction of the riser. Figure 6 As shown, the retaining ring 204 is annular, and the retaining ring 204 is fixedly connected to the inner wall of the ring sleeve 202, and the two retaining rings 204 are respectively located on the upper side and the lower side of the ball 6. The retaining rod 7 is a metal rod, and one end of the retaining rod 7 is fixedly connected to the outer wall of the vertical tube, and the other end of the retaining rod 7 passes through the annular tube support 203. The second spring 8 is sleeved on the outside of the annular tube support 203, and the ends of the second spring 8 are respectively in contact with the retaining rod 7 and the retaining ring 204. When the vertical tube moves downward, the upper second spring 8 is compressed, and when the vertical tube moves upward, the lower second spring 8 is compressed.

[0053] Further, combined with Figure 6 and Figure 7 As shown, in order to make the ball 6 roll better, a rotating shaft 601 is fixedly connected on both sides of the ball 6, and a clamping groove is provided inside the ring sleeve 202. The clamping groove is located on both sides of the groove for installing the ball 6, and the rotating shaft 601 is embedded in the clamping groove. A strip-shaped anti-skid pattern 1 602 is provided on the surface of the ball 6, and the curve of any anti-skid pattern 1 602 is in the same plane as the rotating shaft 601. A rolling groove 501 is provided on the surface of the slider 5, and an anti-skid pattern 2 502 is provided on the surface of the rolling groove 501. The anti-skid pattern 2 502 and the anti-skid pattern 1 602 abut against each other to increase friction, so that the rolling effect of the ball 6 is better.

[0054] Example 2

[0055] This embodiment provides a cooling and heating pipe installation process, using the cooling and heating pipe installation device of Example 1, and also includes the following method.

[0056] According to the designed 3D building drawing, the designed pipelines, including the heating and cooling pipe installation device of Example 1, are reflected on the drawing, and the telescopic hanger 1 and the sliding bracket 2 are numbered, and the unreasonable parts are adjusted to ensure that the pipes are free of collision, easy to operate, easy to repair or replace wearing parts, and the channels and spaces meet the user requirements, ensuring that there is no adverse effect on fire protection facilities and lighting, and that the building structure should not be affected after the upgrade space of various systems is reserved. After the design is completed, it will be confirmed by the design department before implementation.

[0057] According to the 3D architectural drawing, reserved casings and embedded parts are arranged in the civil engineering process. When the civil engineering conditions are ripe, the lines are laid out and holes are drilled to install expansion bolts before the roof is plastered, ensuring that the drilling will reduce the pollution to the civil engineering during the subsequent installation process.

[0058] Make or purchase the heating and cooling pipe installation device, horizontal pipe, and vertical pipe according to the 3D architectural drawing. If the telescopic hanger 1 and the sliding bracket 2 are made by the production method, sufficient time must be left to ensure that the paint of the heating and cooling pipe installation device is fully dried before installation. The finished product of the heating and cooling pipe installation device must be properly wrapped to prevent contamination during placement, and the surface of the heating and cooling pipe installation device must be numbered for easy installation.

[0059] When installing the installation device for the horizontal pipe, vertical pipe, and heating and cooling pipe, the environment and the installer should be kept clean, and the numbers of the telescopic hanger 1, the sliding bracket 2, etc. should be checked to prevent rework caused by installation errors. The sliding bracket 2 should be installed on the solid structure of the building, such as a beam or a shear wall. The slider 5 is embedded in the annular pipe support 203, and the spacing between adjacent sliders 5 is kept within 60 mm. Each slider 5 is arranged at an equal distance, and the length of the slider 5 is determined according to the maximum distance allowed for the vertical pipe to move. The ring sleeve 202 drills two semicircular holes up and down at the corresponding position of the installation ball 6 as a steel ball nest. When installing, first apply grease in the steel ball nest or on the surface of the ball 6, and then embed the ball 6 into the steel ball nest. In order to ensure that the ball 6 does not fall off during installation, a magnet can be placed at the steel ball nest position outside the ring sleeve 202, and the magnet can be removed after the installation is completed.

[0060] When installing the cold and heating pipes, first connect and weld some horizontal pipes, vertical pipes or elbows, then install valves and various instruments (such as pressure gauges) on the pipes, and then assemble them on the telescopic hanger 1 and sliding bracket 2. However, the weight and lifting capacity of the cold and heating pipes after assembly must be fully considered to ensure safety and efficiency. The supply and return water cold and heating pipes should not be installed at the same elevation, with the supply water on the top and the return water on the bottom. This will not only minimize the mutual influence of the surface temperature of the cold and heating pipes on the temperature inside the pipes, but also prevent the pipes from turning over each other at the tee, avoiding air blockage and reducing hydraulic losses.

[0061] The water pressure test of the cooling and heating pipes requires clean, non-corrosive water, such as city tap water. The test requires a special pressure test pump, two 1.6-level pressure gauges (the maximum pressure value of the gauge is about twice the test pressure), a calibrated safety valve (the calibration pressure of the safety valve is the strength test pressure plus 0.02MPa), a check valve, a stop valve, and the required water inlet and drain pipes. The pressure test is based on the system's low pressure. When the pressure reaches 30% of the test pressure, the pressure rise rate should be controlled and should not be too fast. The strength test time is controlled within 10 minutes, and multiple strength tests are prohibited. The tightness test pressure is the same as the designed working pressure, the test time is more than 2 hours, and the test data is based on meeting the design and specifications. After the water pressure test is passed, the cooling and heating pipes are painted with anti-corrosion paint. After the paint is dry, the cooling and heating pipes are flushed and the pipes are insulated.

[0062] After the water pressure test, the pressure is reduced but the water is not released. A magnetic ultrasonic vibrator set is placed next to the weld of the heating and cooling pipes. The spacing between the ultrasonic vibrators is less than 100 mm. The ultrasonic generator is turned on and runs for 4-5 minutes. During this period, a rubber hammer is used to knock near the weld of the heating and cooling pipes to vibrate off the attachments adsorbed on the weld in the pipe. Then the water pump is used to self-circulate for 1 hour, and then water is filled while draining until the water is clear. After that, the filter at the water inlet of the water pump is removed and cleaned, and finally the heating and cooling pipes are filled with clean water. When flushing, the water volume should exceed 70% of the rated working flow.

[0063] Since the flange bolts of the cold and heating pipes will expand during hot operation, the flange connection will become loose, which is very likely to leak. Therefore, the flange bolts of the cold and heating pipes must be further tightened during hot operation to ensure long-term continuous normal operation. After the flange bolts are tightened, the part is insulated. During the insulation process, the flange is covered with an outer shell and the inner shell is filled with insulation material.

[0064] After the insulation is completely completed and the outdoor temperature reaches the hottest season of the year, the chilled water test operation can be carried out until it meets the design requirements and acceptance specifications. After normal operation in summer and winter, the five parties will be organized to conduct acceptance and handover.

[0065] In summary, the present invention provides a cooling and heating pipe installation device, which includes a telescopic hanger 1 for limiting the horizontal pipe and a sliding bracket 2 for limiting the vertical pipe. The telescopic hanger 1 includes a fixing part 101 connected to the roof, the fixing part 101 is connected to a screw 102, the lower end of the screw 102 is provided with an elastic part 3, the elastic part 3 is connected to a hanger 103, the hanger 103 is provided with a sleeve 4 connected to the horizontal pipe, the sliding bracket 2 includes a bracket body 201, a ring sleeve 202 and an annular pipe support 203, the bracket body 201 is fixed to the wall, the annular pipe support 203 is fixedly connected to the vertical pipe, after the vertical pipe expands, the annular pipe support 203 is elastically deformed by force, a plurality of sliders 5 are provided on the outer side of the annular pipe support 203, and a plurality of balls 6 rolling on the surface of the slider 5 are provided on the inner side of the ring sleeve 202. The fixing member 101 is configured as a channel steel, and the channel steel is provided with a through hole 1011 for the screw rod 102 to pass through, and the screw rod 102 is provided with a nut 1021 that abuts against the upper surface of the channel steel. The upper surface of the channel steel is provided with a curved groove 1012 that communicates with the through hole 1011, and the nut 1021 is provided with a curved head 1022 that deflects and slides in the curved groove 1012. The elastic member 3 includes a connecting member 301, and the connecting member 301 is provided with a through hole 2 for the screw rod 102 to pass through, and the screw rod 102 is provided with a nut 2 1023 that fixes the connecting member 301, and the connecting member 301 is provided with a first spring 302, and the suspension rod 103 is connected to the first spring 302. The first spring 302 is arranged inside the connecting piece 301, the suspension rod 103 passes through the middle of the first spring 302, the suspension rod 103 is provided with a nut three 1031 connected to the top of the first spring 302, the top of the first spring 302 is provided with a pad 303 connected to the nut three 1031, and the bottom of the first spring 302 is provided with a pad 303 connected to the connecting piece 301. The inner wall of the collar 1 4 is provided with a heat insulation ring. The annular pipe support 203 and the heat insulation ring are both configured as rubber rings, and the collar 1 4 and the collar 2 202 are both configured as clamps.

[0066] The present invention also provides a cold and heating pipe installation process, and the cold and heating pipe installation device adopted by the invention also includes the following method: according to the designed 3D architectural drawing, the designed pipelines including the cold and heating pipe installation device of claim 1 are reflected on the drawing; according to the 3D architectural drawing, the sleeves and embedded parts are reserved in the civil engineering process; according to the 3D architectural drawing, the cold and heating pipe installation device is manufactured or purchased, and the cold and heating pipe installation device is designed and numbered; the cold and heating pipe installation device is fixed on the wall and the roof, and the horizontal pipe and the vertical pipe are connected to the cold and heating pipe installation device; the horizontal pipe and the vertical pipe sections are connected, and valves and instruments are installed; the horizontal pipe and the vertical pipe are subjected to water pressure testing, and the pipeline is flushed after the test; the flange connection of the horizontal pipe and the vertical pipe is re-tightened, and then the heat preservation treatment is performed; in summer, chilled water is introduced into the horizontal pipe and the vertical pipe for trial operation; after the horizontal pipe and the vertical pipe are operated normally in summer and winter, the five parties are organized to conduct acceptance and delivery. An ultrasonic vibrator is arranged on the outer wall of the horizontal pipe and the vertical pipe, and the ultrasonic vibrator works during flushing. During the insulation treatment process, an outer shell is used to cover the flange connections of the horizontal pipe and the vertical pipe, and insulation material is filled into the outer shell.

[0067] Therefore, the cold and heating pipe installation device and installation process of the present invention can not only play a supporting and fixing role, but also is not easy to be damaged, and has the advantage of a long service life.

[0068] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A cooling and heating pipe installation device, characterized in that: The invention comprises a telescopic hanger (1) for limiting a horizontal pipe and a sliding bracket (2) for limiting a vertical pipe. The telescopic hanger (1) comprises a fixing member (101) connected to a roof. The fixing member (101) is connected to a screw rod (102). The lower end of the screw rod (102) is provided with an elastic member (3). The elastic member (3) is connected to a suspension rod (103). The suspension rod (103) is provided with a first sleeve (4) connected to the horizontal pipe. The sliding bracket (2) comprises a bracket body (201), a second sleeve (202) and an annular pipe support (203). The bracket body (201) is fixed to a wall. The annular pipe support (203) is fixedly connected to the vertical pipe. After the vertical pipe expands, the annular pipe support (203) is subjected to force and elastically deforms. A plurality of sliding blocks (5) are provided on the outer side of the annular pipe support (203). A plurality of balls (6) rolling on the surface of the sliding block (5) are provided on the inner side of the second sleeve (202).

2. The cooling and heating pipe installation device according to claim 1, characterized in that: The fixing member (101) is configured as a channel steel, the channel steel is provided with a through hole (1011) for the screw rod (102) to pass through, the screw rod (102) is provided with a nut (1021) abutting against the upper surface of the channel steel, the upper surface of the channel steel is provided with a curved groove (1012) connected to the through hole (1011), and the nut (1021) is provided with a curved head (1022) that deflects and slides in the curved groove (1012).

3. The cooling and heating pipe installation device according to claim 1, characterized in that: The elastic member (3) comprises a connecting member (301), the connecting member (301) being provided with a second through hole for the screw rod (102) to pass through, the screw rod (102) being provided with a second nut (1023) for fixing the connecting member (301), the connecting member (301) being provided with a first spring (302), and the suspension rod (103) being connected to the first spring (302).

4. The cooling and heating pipe installation device according to claim 3, characterized in that: The first spring (302) is arranged inside the connecting member (301), the suspension rod (103) passes through the middle of the first spring (302), the suspension rod (103) is provided with a nut three (1031) connected to the top of the first spring (302), the top of the first spring (302) is provided with a pad (303) connected to the nut three (1031), and the bottom of the first spring (302) is provided with a pad (303) connected to the connecting member (301).

5. The cooling and heating pipe installation device according to claim 1, characterized in that: Rotating shafts (601) are arranged on both sides of the ball (6), a slot for embedding the rotating shaft (601) is arranged on the inner side of the second ring sleeve (202), an anti-skid pattern (602) is arranged on the surface of the ball (6), a rolling groove (501) is arranged on the surface of the slider (5), and an anti-skid pattern (502) matching the anti-skid pattern (602) is arranged in the rolling groove (501).

6. The cooling and heating pipe installation device according to claim 1, characterized in that: The inner wall of the second ring sleeve (202) is provided with a retaining ring (204), the vertical pipe is provided with a retaining rod (7) passing through the annular pipe support (203), and a second spring (8) is provided between the retaining rod (7) and the retaining ring (204).

7. The cooling and heating pipe installation device according to claim 6, characterized in that: The inner wall of the sleeve ring 1 (4) is provided with a heat-insulating ring, the annular pipe support (203) and the heat-insulating ring are both configured as rubber rings, and the sleeve ring 1 (4) and the sleeve ring 2 (202) are both configured as clamps.

8. A process for installing cooling and heating pipes, characterized in that: The cooling and heating pipe installation device according to claim 1 further comprises the following method: S1. Based on the designed 3D architectural drawing, each designed pipeline including the cooling and heating pipe installation device according to claim 1 is reflected on the drawing; S2. Reserve casing and embedded parts during the civil construction process according to the 3D architectural drawing; S3. Make or purchase cooling and heating pipe installation devices according to the 3D architectural drawings, and design and number the cooling and heating pipe installation devices; S4. Fix the cooling and heating pipe installation device on the wall or roof, and connect the horizontal pipe and vertical pipe to the cooling and heating pipe installation device; S5. Connect the horizontal pipes and vertical pipes, and install valves and instruments; S6. Perform water pressure test on horizontal pipes and vertical pipes, and flush the pipes after the test; S7. Re-tighten the flange connections of the horizontal pipe and vertical pipe, and then perform insulation treatment; S8. In summer, introduce chilled water into the horizontal pipes and vertical pipes for trial operation; S9. After the horizontal pipes and vertical pipes operate normally in both summer and winter, organize the five parties to conduct acceptance and delivery.

9. The cooling and heating pipe installation process according to claim 8, characterized in that: Ultrasonic vibration heads are arranged on the outer walls of the horizontal pipe and the vertical pipe. In the step S6, the ultrasonic vibration heads are operated during flushing.

10. The cooling and heating pipe installation process according to claim 8, characterized in that: During the heat preservation treatment process in step S7, the flange connections of the horizontal pipe and the vertical pipe are covered with an outer shell, and heat preservation material is filled into the outer shell.