Flue gas desulfurization and denitrification purification treatment packed tower

By designing filler mechanisms and material replacement mechanisms in the flue gas desulfurization and denitrification filler tower, the rapid replacement of filler is achieved, and the gas-liquid contact area is improved through the design of liquid separation parts, solving the problem of cumbersome filler replacement in traditional filler towers, and improving the efficiency and effect of purification treatment.

CN119819106AActive Publication Date: 2025-04-15XIAN THREE DIMENSIONAL ENERGY & ENVIRONMENTAL PROTECTION TOWER TECH ENG CO LTD

Patent Information

Application Number
CN202510107864.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-23
Publication Date
2025-04-15
Estimated Expiration
2045-01-23

AI Technical Summary

Technical Problem

After the flue gas desulfurization and denitrification purification operation, the filler is prone to scale corrosion, sinking and aging, resulting in a decline in physical and chemical properties. It requires frequent replacement of the filler, but the replacement process is cumbersome, which affects the use effect.

Method used

A flue gas desulfurization and denitrification purification packing tower is designed, using a combination of a filler mechanism and a material exchange mechanism to achieve rapid disassembly and replacement of fillers. Through the design of liquid separation parts, the chemical agents are evenly distributed and the gas-liquid contact area is improved.

Benefits of technology

The rapid replacement of fillers is achieved without affecting the desulfurization and denitrification purification treatment effect of flue gas, improving the efficiency of the use of filler towers, and improving the effectiveness of purification treatment by evenly distributing chemical agents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119819106A_ABST
    Figure CN119819106A_ABST
Patent Text Reader

Abstract

The invention discloses a flue gas desulfurization and denitrification purification treatment packed tower, and particularly relates to the technical field of flue gas purification treatment.The flue gas desulfurization and denitrification purification treatment packed tower comprises a supporting bottom frame, a bottom ring support is fixedly installed at the top end of the supporting bottom frame, a connecting inner frame is fixedly installed on the inner side of the bottom ring support, and a tower body is fixedly installed in the middle of the connecting inner frame; an air inlet pipe opening is fixedly formed in the bottom of the tower body, a liquid inlet pipe opening is fixedly formed in the top of the tower body, a liquid separation part is fixedly arranged at the inner end of the liquid inlet pipe opening, a plurality of filling mechanisms are uniformly distributed between the air inlet pipe opening and the liquid inlet pipe opening, and a material changing mechanism is arranged between the bottom ring support and the plurality of filling mechanisms. The packing mechanism is arranged and is matched with the material changing mechanism, so that the flue gas can be subjected to desulfurization and denitrification purification treatment, the packing can be quickly disassembled and replaced, the desulfurization and denitrification purification treatment of the packed tower on the flue gas cannot be influenced, and the use effect of the whole packed tower is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of flue gas purification treatment, in particular to a flue gas desulfurization and denitrification purification treatment packed tower. Background Art

[0002] Flue gas desulfurization and denitrification treatment is to remove sulfur dioxide (SO 2 ), nitrogen oxides (NOx) and other harmful substances to reduce air pollution and protect the environment. Among them, the packed tower is an important equipment for the contact reaction between gas and liquid. It is widely used in wet desulfurization and denitrification systems. It mainly includes structural components such as tower body and packing. The flue gas enters from the bottom of the tower and meets the liquid (such as desulfurization liquid or denitrification liquid) in the tower. The liquid is evenly distributed to the packing layer from the top of the tower, and a thin film is formed through the packing layer to increase the contact area between gas and liquid. SO in the flue gas 2 Or NOx reacts chemically with the reactant in the liquid (such as lime slurry or ammonia water) to generate soluble compounds, thereby achieving the purpose of desulfurization and denitrification. The flue gas after the reaction is discharged from the top of the tower and usually contains lower concentrations of pollutants; When the packed tower performs desulfurization and denitrification operations on flue gas for a period of time, the internal packing will show scaling, corrosion, sinking and aging, resulting in a decrease in its physical and chemical properties. The packing needs to be replaced to prevent it from affecting the normal desulfurization and denitrification operations of the flue gas. However, traditional packing replacement requires disassembly and replacement one level at a time, and the packing bracket, liquid distributor, etc. must be disassembled one by one, which makes disassembly more troublesome and affects the overall use effect. For this reason, we propose a flue gas desulfurization and denitrification purification packed tower to solve the above problems. Summary of the invention

[0003] The object of the present invention is to provide a flue gas desulfurization and denitrification purification treatment packed tower to solve the problems raised in the above background technology.

[0004] To achieve the above-mentioned objectives, the present invention provides the following technical solutions: a flue gas desulfurization and denitrification purification treatment packed tower, comprising a supporting base frame, a bottom ring bracket is fixedly installed on the top of the supporting base frame, a connecting inner frame is fixedly installed on the inner side of the bottom ring bracket, a tower body is fixedly installed on the middle part of the connecting inner frame, an air inlet pipe port is fixedly installed on the bottom of the tower body, a liquid inlet pipe port is fixedly installed on the top of the tower body, a liquid separator is fixedly installed on the inner end of the liquid inlet pipe port, a plurality of evenly distributed packing mechanisms are arranged between the air inlet pipe port and the liquid inlet pipe port, a plurality of the packing mechanisms are installed on the tower body, and a material changing mechanism is arranged between the bottom ring bracket and the plurality of packing mechanisms.

[0005] Preferably, the packing mechanism comprises a packing transverse frame, a first longitudinal tube is fixedly installed in the middle of the top end of the packing transverse frame, a second longitudinal tube is fixedly installed in the middle of the bottom end of the packing transverse frame, the first longitudinal tube and the second longitudinal tube are fixedly installed on the tower body and are connected to the tower body, the first longitudinal tube and the second longitudinal tube are connected to each other, the inner sides of the first longitudinal tube and the second longitudinal tube are fixedly provided with an inner sealing longitudinal tube, two packing longitudinal tubes are movably provided in the packing transverse frame, one of the packing longitudinal tubes is vertically corresponding to the first longitudinal tube and the second longitudinal tube, a top ring frame is detachably provided at the top end of the packing longitudinal tube, a bottom ring frame is movably provided at the bottom end of the packing longitudinal tube, and the top ring frame in one of the packing longitudinal tubes The upper surface and the top position correspond to the lower surface of the inner sealing longitudinal tube in contact, the lower surface of the bottom ring frame in one of the filling longitudinal tubes contacts the upper surface of the inner sealing longitudinal tube in contact with the bottom position, a liquid separation top pressure plate is fixedly installed in the top ring frame, and a bottom support plate is fixedly installed in the bottom ring frame, and a connecting cross frame is fixedly installed on the top and bottom of the two filling longitudinal tubes, and the connecting cross frames are respectively slidably connected to the top and bottom of the filling cross frame, and bottom grooves are opened on both sides of the bottom end of the filling cross frame, and top grooves are opened on both sides of the top end of the filling cross frame, and a bottom support seat is movably provided in the bottom groove, and the upper surface of the bottom support seat contacts the lower surface of the corresponding bottom ring frame, and a top sealing cover is detachably provided in the top groove.

[0006] Preferably, a plurality of smoke separation arc plates are integrally formed on the top end of the bottom support plate, and a plurality of smoke separation grooves are evenly distributed on the smoke separation arc plates.

[0007] Preferably, side frame covers are fixedly installed on both ends of the filling transverse frame, telescopic cylinders are fixedly installed at the four corners of the side frame covers, driving ends of the telescopic cylinders extend into the filling transverse frame, mounting seats are fixedly installed on the driving ends of the telescopic cylinders, and the mounting seats are fixedly installed on the corresponding connecting transverse frames.

[0008] Preferably, the material changing mechanism comprises a plurality of connecting longitudinal frames, and a plurality of the connecting longitudinal frames are fixedly mounted on a bottom ring bracket, a top ring bracket is fixedly mounted on the top ends of the plurality of connecting longitudinal frames, a plurality of lifting screws are rotatably mounted between the top ring bracket and the bottom ring bracket, a lifting ring frame corresponding to the filling mechanism is provided between the top ring bracket and the bottom ring bracket, the lifting ring frame is threadedly mounted on the outside of the plurality of lifting screws, a rotating ring seat is rotatably clamped in the lifting ring frame, the second longitudinal tube passes through the rotating ring seat, two groups of symmetrically distributed mounting bases are fixedly mounted on the top end of the rotating ring seat, and the bottom support seat is fixedly mounted on the top end of the corresponding mounting base.

[0009] Preferably, a first gear is provided on one side of the lifting ring frame, a first longitudinal axis is fixedly installed in the middle of the first gear, the first longitudinal axis is rotatably installed on the lifting ring frame, a first gear ring is provided at the bottom of the rotating ring seat for use with the first gear, the first gear and the first gear ring are meshingly connected, a first motor is fixedly installed on one side of the bottom end of the lifting ring frame close to the first gear, and the driving end of the first motor is fixedly installed on the bottom end of the first longitudinal axis.

[0010] Preferably, a second gear is fixedly installed on the top of the lifting screw, and a second gear ring is meshed and connected between multiple second gears. A rotating snap ring is integrally formed with the middle part of the second gear ring, and the rotating snap ring is rotatably clamped in the middle part of the top ring bracket. A third gear is provided on one side of the top ring bracket, and the third gear is meshed and connected with the outer side of the second gear ring. A second longitudinal axis is fixedly installed in the middle part of the third gear, and the second longitudinal axis is rotatably installed on one side of the top ring bracket. A second motor is fixedly installed on the side of the bottom end of the top ring bracket close to the third gear, and the driving end of the second motor and the bottom end of the second longitudinal axis are fixedly installed.

[0011] Preferably, the liquid separating component includes an outer ring frame, a middle ring frame is provided in the middle of the outer ring frame, an inner ring frame is provided in the middle of the middle ring frame, the outer ring frame, the middle ring frame and the inner ring frame are concentrically arranged, and a connecting main pipe is integrally formed between the outer ring frame, the middle ring frame and the inner ring frame, one end of the connecting main pipe is fixedly clamped on the inner end of the liquid inlet pipe port, and a plurality of evenly distributed liquid drainage grooves are provided at the bottom ends of the outer ring frame, the middle ring frame and the inner ring frame.

[0012] Preferably, a liquid discharge pipe opening is fixedly mounted on the bottom of the tower body, a material control valve is fixedly mounted on the liquid discharge pipe opening, and the air inlet pipe opening is located above the liquid discharge pipe opening.

[0013] Preferably, an exhaust pipe opening is fixedly mounted on the top of the tower body.

[0014] Compared with the prior art, the present invention has the following beneficial effects: 1. By setting up a packing mechanism and using a material changing mechanism, the flue gas can be desulfurized and denitrated, and the packing can be quickly disassembled and replaced without affecting the desulfurization and denitration purification of the flue gas by the packing tower, thereby improving the use effect of the entire packing tower.

[0015] 2. By setting up a packing mechanism and using a liquid separator, the chemical agents can be effectively and evenly distributed, and the flue gas can be effectively and evenly distributed, so that the flue gas and the chemical agents can undergo a contact chemical reaction over an effective area, thereby improving the effect of flue gas desulfurization and denitrification purification treatment. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 It is a schematic diagram of the structure of the present invention.

[0018] Figure 2 It is a schematic diagram of the structural connection between the tower body and the packing mechanism in the present invention.

[0019] Figure 3 It is a structural schematic diagram of the packing mechanism in the present invention.

[0020] Figure 4 For the present invention Figure 3 Enlarged view of point A in the middle.

[0021] Figure 5 It is a schematic diagram of the structure of the packing longitudinal tube in the present invention.

[0022] Figure 6 It is a structural schematic diagram of the material changing mechanism in the present invention.

[0023] Figure 7 For the present invention Figure 6 Enlarged view of point B in the middle.

[0024] Figure 8 It is a structural schematic diagram of the liquid separation component in the present invention.

[0025] In the figure: 1, supporting base frame; 11, bottom ring bracket; 12, connecting inner frame; 2, tower body; 21, air inlet; 22, liquid inlet; 23, liquid discharge; 231, material control valve; 24, exhaust; 25, liquid separation; 251, outer ring frame; 252, middle ring frame; 253, inner ring frame; 254, connecting main pipe; 201, liquid discharge groove; 3, packing mechanism; 4, material changing mechanism; 31, packing cross frame; 311, first longitudinal pipe; 312, second longitudinal pipe; 313, inner sealing longitudinal pipe; 32, packing longitudinal pipe; 321, top ring frame; 3211, liquid top pressure plate; 322, bottom ring frame; 3221, bottom support plate; 3222, Smoke arc separating plate; 3223, smoke separating groove; 33, connecting horizontal frame; 34, side frame cover; 341, telescopic cylinder; 342, mounting seat; 301, bottom groove; 3011, bottom support seat; 302, top groove; 3021, top sealing cover; 41, connecting vertical frame; 42, top ring bracket; 43, lifting screw; 431, second gear; 432, second gear ring; 433, rotating snap ring; 434, third gear; 435, second longitudinal axis; 436, second motor; 44, lifting ring frame; 45, rotating ring seat; 451, mounting base; 46, first gear; 461, first longitudinal axis; 462, first gear ring; 463, first motor. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] Example: Figure 1-8 As shown, the present invention provides a flue gas desulfurization and denitrification purification treatment packed tower, comprising a supporting base frame 1, a bottom ring bracket 11 is fixedly installed on the top of the supporting base frame 1, a connecting inner frame 12 is fixedly installed on the inner side of the bottom ring bracket 11, a tower body 2 is fixedly installed in the middle of the connecting inner frame 12, an air inlet pipe port 21 is fixedly installed at the bottom of the tower body 2, when in use, the flue gas to be purified is introduced into the tower body 2 from the bottom of the tower body 2 through the air inlet pipe port 21, a liquid inlet pipe port 22 is fixedly installed on the top of the tower body 2, and a liquid separator 25 is fixedly installed at the inner end of the liquid inlet pipe port 22; The liquid separation member 25 includes an outer ring frame 251, a middle ring frame 252 is provided in the middle of the outer ring frame 251, an inner ring frame 253 is provided in the middle of the middle ring frame 252, the outer ring frame 251, the middle ring frame 252 and the inner ring frame 253 are concentrically arranged, and a connecting main pipe 254 is integrally formed between the outer ring frame 251, the middle ring frame 252 and the inner ring frame 253, one end of the connecting main pipe 254 is fixedly clamped on the inner end of the liquid inlet pipe 22, and a plurality of evenly distributed drainage grooves 201 are provided at the bottom ends of the outer ring frame 251, the middle ring frame 252 and the inner ring frame 253, and the chemical agents for desulfurization and denitrification enter the top of the tower body 2 through the liquid inlet pipe 22 and are introduced into the outer ring frame 251, the middle ring frame 252 and the inner ring frame 253 through the connecting main pipe 254, and then are evenly discharged into the tower body 2 through the plurality of drainage grooves 201, and then evenly introduced into the packing mechanism 3; A liquid discharge pipe opening 23 is fixedly installed at the bottom of the tower body 2, a material control valve 231 is fixedly installed on the liquid discharge pipe opening 23, and the air inlet pipe opening 21 is located above the liquid discharge pipe opening 23; an exhaust pipe opening 24 is fixedly installed at the top of the tower body 2, and the flue gas is purified by multiple packing mechanisms 3 and discharged through the exhaust pipe opening 24, and the chemical agent flows to the bottom of the tower body 2, and by opening the material control valve 231, the chemical agent is discharged through the liquid discharge pipe opening 23; A plurality of evenly distributed packing mechanisms 3 are provided between the air inlet 21 and the liquid inlet 22 . The plurality of packing mechanisms 3 are installed on the tower body 2 . A material changing mechanism 4 is provided between the bottom ring bracket 11 and the plurality of packing mechanisms 3 .

[0028] The packing mechanism 3 includes a packing transverse frame 31, a first longitudinal tube 311 is fixedly installed at the middle of the top end of the packing transverse frame 31, a second longitudinal tube 312 is fixedly installed at the middle of the bottom end of the packing transverse frame 31, the first longitudinal tube 311 and the second longitudinal tube 312 are fixedly installed on the tower body 2 and communicate with the tower body 2, and the first longitudinal tube 311 and the second longitudinal tube 312 are communicated with each other; The inner sides of the first longitudinal tube 311 and the second longitudinal tube 312 are fixedly provided with an inner sealing longitudinal tube 313, and the packing cross frame 31 is movably provided with two packing longitudinal tubes 32, one of which is vertically corresponding to the first longitudinal tube 311 and the second longitudinal tube 312, and a top ring frame 321 is detachably provided at the top of the packing longitudinal tube 32 to facilitate the disassembly of the top ring frame 321, and a bottom ring frame 322 is movably provided at the bottom end of the packing longitudinal tube 32, and the upper surface of the top ring frame 321 in one of the packing longitudinal tubes 32 contacts the lower surface of the inner sealing longitudinal tube 313 at the top position, and the lower surface of the bottom ring frame 322 in one of the packing longitudinal tubes 32 contacts the upper surface of the inner sealing longitudinal tube 313 at the bottom position, so as to achieve sealed communication between the first longitudinal tube 311 and the second longitudinal tube 312 and one of the packing longitudinal tubes 32 to prevent smoke leakage, and a liquid separation top is fixedly installed in the top ring frame 321 The pressure plate 3211 and the bottom ring frame 322 are fixedly installed with a bottom support plate 3221, and a plurality of smoke arc plates 3222 are integrally formed at the top of the bottom support plate 3221. The smoke arc plates 3222 are provided with a plurality of smoke separation grooves 3223 evenly distributed. A filler is installed between the liquid separation top pressure plate 3211 and the bottom support plate 3221. When the uniformly discharged chemical agent passes into the filler mechanism 3 from top to bottom, it will be evenly distributed again through the liquid separation top pressure plate 3211, and then evenly introduced into the corresponding filler longitudinal tube 32, and a thin film will be formed through the filler to increase the contact area between the flue gas and the chemical agent. When the flue gas passes into the filler mechanism 3 from bottom to top, it will be evenly distributed through the plurality of smoke separation grooves 3223 on the plurality of smoke arc plates 3222, so that the flue gas is evenly introduced into the filler longitudinal tube 32 to carry out a contact chemical reaction with the chemical agent in an effective area, thereby improving the effect of flue gas desulfurization and denitrification purification treatment; The top and bottom of the two stuffing longitudinal tubes 32 are fixedly installed with connecting transverse frames 33, and the connecting transverse frames 33 are slidably connected to the top and bottom of the stuffing transverse frame 31 respectively; the two ends of the stuffing transverse frame 31 are fixedly installed with side frame covers 34, and the four corners of the side frame covers 34 are fixedly installed with telescopic cylinders 341, and the driving ends of the telescopic cylinders 341 extend into the stuffing transverse frame 31, and the driving ends of the telescopic cylinders 341 are fixedly installed with mounting seats 342, and the mounting seats 342 are fixedly installed on the corresponding connecting transverse frames 33. By controlling the opening of the telescopic cylinder 341, the stuffing transverse frame 31 is driven to slide horizontally in the connecting transverse frame 33, thereby controlling the two stuffing longitudinal tubes 32 to slide horizontally in the connecting transverse frame 33, and flexibly adjusting the positions of the stuffing longitudinal tubes 32 on both sides, it is convenient for the subsequent disassembly and replacement of the stuffing in one of the stuffing longitudinal tubes 32 without affecting the use of the stuffing in the other stuffing longitudinal tube 32.

[0029] Bottom grooves 301 are provided on both sides of the bottom end of the filling cross frame 31, and top grooves 302 are provided on both sides of the top end of the filling cross frame 31. A bottom support seat 3011 is movablely provided in the bottom groove 301 to facilitate the bottom support seat 3011 to move downward and separate from the bottom groove 301. The upper surface of the bottom support seat 3011 contacts the lower surface of the corresponding bottom ring frame 322, and a top cover 3021 is detachably provided in the top groove 302 to facilitate the removal of the top cover 3021.

[0030] The material changing mechanism 4 includes a plurality of connecting longitudinal frames 41, and the plurality of connecting longitudinal frames 41 are fixedly mounted on the bottom ring bracket 11. A top ring bracket 42 is fixedly mounted on the top of the plurality of connecting longitudinal frames 41. A plurality of lifting screws 43 are rotatably mounted between the top ring bracket 42 and the bottom ring bracket 11. A lifting ring frame 44 corresponding to the filling mechanism 3 is arranged between the top ring bracket 42 and the bottom ring bracket 11. The lifting ring frame 44 is threadedly mounted on the outside of the plurality of lifting screws 43. A rotating ring seat 45 is rotatably clamped in the lifting ring frame 44. The second longitudinal tube 312 passes through the rotating ring seat 45. The top of the rotating ring seat 45 is fixedly mounted. Two groups of symmetrically distributed mounting bases 451 are fixedly installed, and the bottom support seat 3011 is fixedly installed on the top of the corresponding mounting base 451. By driving the multiple lifting screws 43 to rotate synchronously, the multiple lifting ring frames 44 are driven to descend synchronously, thereby controlling the synchronous descent of the bottom support seats 3011 in the multiple filling mechanisms 3, so that the bottom ring frames 322 and bottom support plates 3221 corresponding to the positions of the filling longitudinal tubes 32 in the multiple filling mechanisms 3 are automatically descended, and the filling follows the bottom ring frames 322 and the bottom support plates 3221 to descend and detach from the filling mechanism 3 for automatic disassembly of the filling, which is convenient for the subsequent replacement of the filling; A first gear 46 is provided on one side of the lifting ring frame 44, and a first longitudinal axis 461 is fixedly installed in the middle of the first gear 46, and the first longitudinal axis 461 is rotatably installed on the lifting ring frame 44. A first gear ring 462 used in conjunction with the first gear 46 is provided at the bottom of the rotating ring seat 45, and the first gear 46 and the first gear ring 462 are meshed and connected. A first motor 463 is fixedly installed on one side of the bottom end of the lifting ring frame 44 close to the first gear 46, and a driving end of the first motor 463 is fixedly installed with the bottom end of the first longitudinal axis 461. When the filler is automatically removed, the first motor 463 is controlled to start driving the first longitudinal axis 461 to drive the first gear 46 to drive the first gear 46 to drive the first gear ring 462 to rotate, thereby controlling the rotating ring seat 45 to rotate horizontally in the lifting ring frame 44, so that the old filler and the filler mechanism 3 are misaligned, so as to facilitate the filler to be removed from the bottom support plate 3221 from the material replacement mechanism 4 , and install the new filler on the bottom support plate 3221 to install the new filler. After the new filler is installed, the first motor 463 is controlled to start again to drive the first longitudinal axis 461 to drive the first gear 46 to drive the first gear ring 462 to rotate in the opposite direction and reset, thereby controlling the rotating ring seat 45 to rotate in the opposite direction and reset horizontally in the lifting ring frame 44, so that the new filler and the filler mechanism 3 correspond. Subsequently, the multiple lifting screws 43 are driven again to rotate in the opposite direction synchronously, driving the multiple lifting ring frames 44 to move up synchronously, thereby controlling the bottom support seats 3011 and the new filler in the multiple filler mechanisms 3 to move up synchronously, so that the new filler is reinstalled in the corresponding filler longitudinal tube 32, so that the new filler can be directly replaced and used later, thereby realizing the rapid disassembly and replacement of the filler, and will not affect the desulfurization and denitrification purification treatment of the flue gas by the filling tower, thereby improving the use effect of the entire filling tower.

[0031] A second gear 431 is fixedly installed on the top of the lifting screw 43, and a second gear ring 432 is meshed and connected between multiple second gears 431. A rotating snap ring 433 is integrally formed in the middle of the second gear ring 432, and the rotating snap ring 433 is rotatably clamped in the middle of the top ring bracket 42. A third gear 434 is provided on one side of the top ring bracket 42, and the third gear 434 is meshed and connected with the outer side of the second gear ring 432. A second longitudinal axis 435 is fixedly installed in the middle of the third gear 434, and the second longitudinal axis 435 is rotatably installed on one side of the top ring bracket 42. A second motor 436 is fixedly installed on one side of the bottom of the top ring bracket 42 close to the third gear 434, and the driving end of the second motor 436 is fixedly installed on the bottom end of the second longitudinal axis 435. When in use, the second motor 436 is controlled to start driving the second longitudinal axis 435 to drive the third gear 434 to drive the second gear ring 432 to rotate, thereby driving multiple second gears 431 to rotate, and then controlling multiple lifting screws 43 to rotate synchronously.

[0032] Working principle: When in use, the flue gas to be purified is introduced into the tower body 2 from the bottom of the tower body 2 through the air inlet port 21, and the chemical agent for desulfurization and denitrification enters the top of the tower body 2 through the liquid inlet port 22 and is introduced into the outer ring frame 251, the middle ring frame 252 and the inner ring frame 253 through the connecting main pipe 254, and then is evenly discharged into the tower body 2 through multiple drainage grooves 201. A filler is installed between the liquid separation top pressure plate 3211 and the bottom support plate 3221; When the uniformly discharged chemical agent passes into the packing mechanism 3 from top to bottom, it will be evenly distributed again through the liquid separation pressure plate 3211, and then evenly introduced into the corresponding packing longitudinal tube 32, and a thin film will be formed through the packing to increase the contact area between the flue gas and the chemical agent. When the flue gas passes into the packing mechanism 3 from bottom to top, it will be evenly distributed through the multiple smoke separation grooves 3223 on the multiple smoke separation arc plates 3222, so that the flue gas is evenly introduced into the packing longitudinal tube 32 and the chemical agent to carry out a contact chemical reaction with an effective area, thereby improving the effect of flue gas desulfurization and denitrification purification treatment; After being purified by multiple packing mechanisms 3, the flue gas is discharged through the exhaust pipe port 24, and the chemical agent flows to the bottom of the tower body 2, and by opening the material control valve 231, the chemical agent is discharged through the liquid discharge pipe port 23; When the packing tower needs to be disassembled and replaced after being used for a period of time, it is only necessary to control the opening of the telescopic cylinder 341 to drive the packing horizontal frame 31 to slide horizontally in the connecting horizontal frame 33, thereby controlling the two packing longitudinal tubes 32 to slide horizontally in the connecting horizontal frame 33, and moving the other packing longitudinal tube 32 with new packing to between the first longitudinal tube 311 and the second longitudinal tube 312, so as to quickly disassemble and replace the new packing without affecting the desulfurization and denitrification purification treatment of flue gas by the packing tower, thereby improving the use effect of the entire packing tower; At this time, the filler longitudinal pipe 32 with the old filler is moved to the position of one of the bottom grooves 301; Subsequently, the second motor 436 is controlled to start driving the second longitudinal shaft 435 to drive the third gear 434 to drive the second gear ring 432 to rotate, thereby driving the plurality of second gears 431 to rotate, and then controlling the plurality of lifting screws 43 to rotate synchronously, driving the plurality of lifting ring frames 44 to descend synchronously, thereby controlling the plurality of bottom support seats 3011 in the plurality of filling mechanisms 3 to descend synchronously, so that the bottom ring frames 322 and the bottom support plates 3221 at the positions of the filling longitudinal tubes 32 in the plurality of filling mechanisms 3 automatically descend, and the filling follows the bottom ring frames 322 and the bottom support plates 3221 to descend and detach from the filling mechanisms 3 for automatic disassembly of the filling; After the filler is automatically removed, the first motor 463 is controlled to start driving the first longitudinal shaft 461 to drive the first gear 46 to drive the first gear ring 462 to rotate, thereby controlling the rotating ring seat 45 to rotate horizontally in the lifting ring frame 44, so that the old filler and the filler mechanism 3 are misaligned, so that the filler can be removed from the bottom support plate 3221 from the material replacement mechanism 4, and the new filler can be installed on the bottom support plate 3221 to install the new filler. After the new filler is installed, the first motor 463 is controlled to start again to drive the first longitudinal shaft 461 to drive the first gear 46 to drive the first gear ring 462 to rotate in the opposite direction to reset, so as to The rotating ring seat 45 is controlled to rotate horizontally in the reverse direction in the lifting ring frame 44 to reset, so that the new filler and the filler mechanism 3 correspond to each other. Subsequently, the multiple lifting screws 43 are driven again to rotate in the reverse direction synchronously, driving the multiple lifting ring frames 44 to move up synchronously, thereby controlling the bottom support seats 3011 and the new filler in the multiple filler mechanisms 3 to move up synchronously, so that the new filler is reinstalled in the corresponding filler longitudinal tube 32, so that the new filler can be directly replaced and used later, thereby realizing rapid disassembly and replacement of the filler without affecting the desulfurization and denitrification purification treatment of the flue gas by the filling tower, thereby improving the use effect of the entire filling tower.

[0033] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A flue gas desulfurization and denitrification purification treatment packed tower, comprising a supporting frame (1), characterized in that: A bottom ring bracket (11) is fixedly mounted on the top of the supporting bottom frame (1), a connecting inner frame (12) is fixedly mounted on the inner side of the bottom ring bracket (11), a tower body (2) is fixedly mounted in the middle of the connecting inner frame (12), an air inlet pipe opening (21) is fixedly mounted on the bottom of the tower body (2), a liquid inlet pipe opening (22) is fixedly mounted on the top of the tower body (2), a liquid separator (25) is fixedly mounted on the inner end of the liquid inlet pipe opening (22), a plurality of evenly distributed packing mechanisms (3) are arranged between the air inlet pipe opening (21) and the liquid inlet pipe opening (22), the plurality of packing mechanisms (3) are mounted on the tower body (2), and a material replacement mechanism (4) is arranged between the bottom ring bracket (11) and the plurality of packing mechanisms (3).

2. A flue gas desulfurization and denitrification purification treatment packed tower according to claim 1, characterized in that: The packing mechanism (3) comprises a packing transverse frame (31), a first longitudinal tube (311) being fixedly mounted at the middle of the top end of the packing transverse frame (31), a second longitudinal tube (312) being fixedly mounted at the middle of the bottom end of the packing transverse frame (31), the first longitudinal tube (311) and the second longitudinal tube (312) being fixedly mounted on the tower body (2) and communicating with the tower body (2), the first longitudinal tube (311) and the second longitudinal tube (312) being communicated with each other, and the first longitudinal tube (311) and the second longitudinal tube (312) being fixedly mounted on the tower body (2) and communicating with each other. The inner side of each of the filling longitudinal tubes (312) is fixedly provided with an inner sealing longitudinal tube (313), the movable card in the filling transverse frame (31) is provided with two filling longitudinal tubes (32), one of the filling longitudinal tubes (32) vertically corresponds to the first longitudinal tube (311) and the second longitudinal tube (312), the top of each of the filling longitudinal tubes (32) is detachably provided with a top ring frame (321), the bottom of each of the filling longitudinal tubes (32) is movablely provided with a bottom ring frame (322), the top ring frame (321) in one of the filling longitudinal tubes (32) is The upper surface of the inner sealing longitudinal tube (313) contacts with the lower surface of the inner sealing longitudinal tube (313) at the top position, the lower surface of the bottom ring frame (322) in one of the packing longitudinal tubes (32) contacts with the upper surface of the inner sealing longitudinal tube (313) at the bottom position, the top ring frame (321) is fixedly mounted with a liquid separation top pressure plate (3211), the bottom ring frame (322) is fixedly mounted with a bottom support plate (3221), the tops and bottoms of the two packing longitudinal tubes (32) are fixedly mounted with connecting transverse frames (33), the connecting The connecting transverse frame (33) is respectively slidably connected to the top and bottom of the filling transverse frame (31); bottom grooves (301) are provided on both sides of the bottom end of the filling transverse frame (31); top grooves (302) are provided on both sides of the top end of the filling transverse frame (31); a bottom support seat (3011) is movably provided in the bottom groove (301); the upper surface of the bottom support seat (3011) contacts the lower surface of the corresponding bottom ring frame (322); and a top cover (3021) is detachably provided in the top groove (302).

3. A flue gas desulfurization and denitrification purification treatment packed tower according to claim 2, characterized in that: A plurality of smoke arc separation plates (3222) are integrally formed on the top end of the bottom support plate (3221), and a plurality of smoke arc separation grooves (3223) are evenly distributed on the smoke arc separation plates (3222).

4. A flue gas desulfurization and denitrification purification treatment packed tower according to claim 2, characterized in that: Side frame covers (34) are fixedly mounted on both ends of the filling transverse frame (31), telescopic cylinders (341) are fixedly mounted at four corners of the side frame cover (34), driving ends of the telescopic cylinders (341) extend into the filling transverse frame (31), and mounting seats (342) are fixedly mounted on the driving ends of the telescopic cylinders (341), and the mounting seats (342) are fixedly mounted on the corresponding connecting transverse frame (33).

5. A flue gas desulfurization and denitrification purification treatment packed tower according to claim 2, characterized in that: The material changing mechanism (4) comprises a plurality of connecting longitudinal frames (41), wherein the plurality of connecting longitudinal frames (41) are fixedly mounted on a bottom ring support (11), a top ring support (42) is fixedly mounted on the top ends of the plurality of connecting longitudinal frames (41), a plurality of lifting screws (43) are rotatably mounted between the top ring support (42) and the bottom ring support (11), a lifting ring frame (44) corresponding to the filling mechanism (3) is provided between the top ring support (42) and the bottom ring support (11), the lifting ring frame (44) is threadedly mounted on the outside of the plurality of lifting screws (43), a rotating ring seat (45) is rotatably clamped in the lifting ring frame (44), the second longitudinal tube (312) passes through the rotating ring seat (45), two groups of symmetrically distributed mounting bases (451) are fixedly mounted on the top ends of the rotating ring seats (451), and the bottom support seat (3011) is fixedly mounted on the top ends of the corresponding mounting bases (451).

6. A flue gas desulfurization and denitrification purification treatment packed tower according to claim 5, characterized in that: A first gear (46) is provided on one side of the lifting ring frame (44); a first longitudinal axis (461) is fixedly mounted in the middle of the first gear (46); the first longitudinal axis (461) is rotatably mounted on the lifting ring frame (44); a first gear ring (462) for use with the first gear (46) is provided at the bottom of the rotating ring seat (45); the first gear (46) and the first gear ring (462) are meshingly connected; a first motor (463) is fixedly mounted on one side of the bottom end of the lifting ring frame (44) close to the first gear (46); and a driving end of the first motor (463) is fixedly mounted on the bottom end of the first longitudinal axis (461).

7. A flue gas desulfurization and denitrification purification packed tower according to claim 5, characterized in that: A second gear (431) is fixedly mounted on the top of each of the lifting screw rods (43), and a second gear ring (432) is meshedly connected between the plurality of second gears (431). A rotating snap ring (433) is integrally formed in the middle of the second gear ring (432), and the rotating snap ring (433) is rotatably clamped in the middle of the top ring bracket (42). A third gear (434) is provided on one side of the top ring bracket (42), and the third gear (434) is meshedly connected to the outer side of the second gear ring (432). A second longitudinal axis (435) is fixedly mounted in the middle of the third gear (434), and the second longitudinal axis (435) is rotatably mounted on one side of the top ring bracket (42). A second motor (436) is fixedly mounted on the side of the bottom end of the top ring bracket (42) close to the third gear (434), and a driving end of the second motor (436) is fixedly mounted on the bottom end of the second longitudinal axis (435).

8. The flue gas desulfurization and denitrification purification packed tower according to claim 1, characterized in that: The liquid separation member (25) comprises an outer ring frame (251), a middle ring frame (252) is provided in the middle of the outer ring frame (251), an inner ring frame (253) is provided in the middle of the middle ring frame (252), the outer ring frame (251), the middle ring frame (252) and the inner ring frame (253) are arranged concentrically, a connecting main pipe (254) is integrally formed between the outer ring frame (251), the middle ring frame (252) and the inner ring frame (253), one end of the connecting main pipe (254) is fixedly clamped on the inner end of the liquid inlet pipe port (22), and a plurality of evenly distributed liquid drainage grooves (201) are provided at the bottom ends of the outer ring frame (251), the middle ring frame (252) and the inner ring frame (253).

9. A flue gas desulfurization and denitrification purification packed tower according to claim 1, characterized in that: A liquid discharge pipe opening (23) is fixedly mounted at the bottom of the tower body (2), a material control valve (231) is fixedly mounted on the liquid discharge pipe opening (23), and the air inlet pipe opening (21) is located above the liquid discharge pipe opening (23).

10. The flue gas desulfurization and denitrification purification treatment packed tower according to claim 1, characterized in that: An exhaust pipe opening (24) is fixedly mounted on the top of the tower body (2).

Citation Information

Patent Citations

  • Flue gas desulfurization, denitrification and purification treatment packed tower

    CN111644014A

  • Foreign matter removal device, reactor, flue gas treatment device and method for replacing filler

    JP2022021874A

Cited By

  • Tail gas-solid separation device for sodium sulfate pyrolyzing furnace

    CN120502191A