Tunnel plan generation method and tunnel visualization system for railway construction
By obtaining and processing the planning and progress data related to tunnel construction, an intuitive tunnel plan is automatically generated, which solves the problem of difficulty in displaying the spatial distribution of tunnel construction sites and real-time update of construction progress in the existing technology, and effectively manages and adjusts the project progress.
Patent Information
- Application Number
- CN202510024252.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-07
- Publication Date
- 2025-06-10
AI Technical Summary
The prior art is difficult to intuitively display the spatial distribution of multiple work points in tunnel construction, and it is impossible to update the planning information and construction progress related to each work point in real time.
By obtaining guiding construction plan and work site structure information, an implementation construction plan is generated, and the construction log data is automatically extracted. The total project construction period under the current construction progress is deduced by interpolation method, and an intuitive tunnel plan is automatically generated to display the construction site structure information, construction progress and construction period deduction results under multi-dimensional indicators.
It realizes an intuitive display of the structural information of tunnel engineering construction points, updates the construction progress and planning information of each construction point in real time, and provides the results of the total project construction period deduction under multi-dimensional indicators to help construction units adjust their plans in a timely manner to ensure that the project is completed on time.
Smart Images

Figure CN120124838A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of computers and graphic visualization, and particularly to a method for generating a tunnel plan view for railway construction and a tunnel visualization system. Background Art
[0002] During the tunnel construction process for railway construction, when the management unit prepares the tunnel construction organization plan, it is necessary to have an overview of the overall engineering structure of the tunnel design and the construction organization plan arrangements of each unit; when controlling the project progress, it is necessary to automatically obtain a stable and reliable source of project progress data; during the process of adjusting the tunnel construction organization plan, it is necessary to refer to the current construction progress of each work point, make adjustments to the construction organization plan without affecting the critical path, and be able to refer to the existing design structure to adjust to a reasonable position during the adjustment process to make the adjustment reasonable.
[0003] Visual overview diagrams that can visually display the overall engineering structure of the tunnel design and the construction organization plan arrangements of each unit include slope diagrams, bar charts, network diagrams, etc. Among them, the slope diagram can show one of the work points during the tunnel construction process and its time and mileage distribution. However, for multiple work points, especially the specific situations of multiple work points at the same mileage and their related information, it is easy to overlap in the display of this slope diagram, and the spatial distribution of different work points and their related information cannot be visually displayed. The bar chart and the network diagram can only clearly show the precedence relationship of each work point in time, but cannot show the spatial distribution of each work point. The prior art also cannot display various types of information such as the plans related to each work point and update them in real time. Summary of the Invention
[0004] In view of this, embodiments of the present invention provide a method for generating a tunnel plan view for railway construction and a tunnel visualization system to eliminate or improve one or more defects existing in the prior art.
[0005] One aspect of the present invention provides a method for generating a tunnel plan view for railway construction, the method comprising:
[0006] Obtaining a guiding construction organization plan, the guiding construction organization plan including the total project duration, the overall start and end mileage of the project determined based on the overall structure of the tunnel project, and at least one critical path;
[0007] Obtain the work point structure information, where the work point structure information includes multiple work points decomposed based on the overall structure of the tunnel project, the construction line, the surrounding rock information of different grades and types distributed within each work point, and the start and end mileage of the construction plan for each surrounding rock. Generate an implementation construction organization plan based on the work point structure information and the guiding construction organization plan. The implementation construction organization plan includes the start and end times of the construction plans for each work point and its surrounding rocks that match the work point structure information, and the total project duration of the implementation construction organization plan does not exceed the total project duration of the guiding construction organization plan;
[0008] Obtain the construction log data, automatically extract the daily construction progress data of each work point from the construction log data based on the work point structure information, and automatically verify the daily construction progress data of each work point based on the preset construction logic relationship. The daily construction progress data of each work point includes the daily construction progress data of each surrounding rock distributed within each work point;
[0009] Calculate the cumulative quantity of each work point currently based on the verified daily construction progress data of each work point, and use interpolation to deduce the current remaining construction duration of each work point under multi-dimensional indicators based on the cumulative quantity of each work point currently, so as to obtain the deduction result of the total project duration based on the current construction progress. The multi-dimensional indicators include guiding construction organization plan indicators, implementation construction organization plan indicators, and a certain project duration progress indicator;
[0010] Automatically generate a tunnel plan based on the guiding construction organization plan, the work point structure information, the implementation construction organization plan, the construction log data, and the deduction result of the total project duration based on the current construction progress under multi-dimensional indicators. The display content of the tunnel plan includes at least multiple non-overlapping and interconnected work point frames for displaying the spatial distribution of the work point structure information, the specific content included in the guiding construction organization plan and the implementation construction organization plan, the current construction progress and construction status of each work point and its surrounding rocks, and the deduction result of the total project duration based on the current construction progress under multi-dimensional indicators.
[0011] In some embodiments of the present invention, the step of automatically verifying the daily construction progress data of each work point based on the preset construction logic relationship includes:
[0012] Calculate the cumulative quantity of each work point currently every day based on the daily construction progress data of each work point;
[0013] Use a verification function to verify the cumulative quantity of each work point currently every day. If the cumulative quantity currently every day is not less than the cumulative quantity of the previous day, it means that the obtained daily construction progress data is normal. If the cumulative quantity currently every day is less than the cumulative quantity of the previous day, it means that the obtained daily construction progress data is abnormal, and further trace and correct the obtained daily construction progress data.
[0014] In some embodiments of the present invention, in the step of using interpolation to deduce the current remaining construction duration of each construction site under multi-dimensional indicators based on the cumulative quantity of each construction site at present, and obtaining the deduced result of the total project duration based on the current construction progress,
[0015] Using interpolation, respectively deduce the current remaining construction duration of each level and each type of surrounding rock distributed within each construction site under a certain project duration progress indicator of the project and the implementation construction organization plan indicator, and obtain the deduced result of the total project duration under the current construction progress;
[0016] Using interpolation, deduce the current remaining construction duration of each level and each type of surrounding rock distributed within each construction site under the guiding construction organization plan indicator, and obtain the deduced result of the total project duration under the current construction progress.
[0017] In some embodiments of the present invention, the critical path includes the traveling route with a relatively long time-consuming and high construction difficulty during the tunnel engineering construction process.
[0018] In some embodiments of the present invention, the multiple construction sites include the main tunnel and auxiliary adits, and the auxiliary adits at least include horizontal adits, inclined shafts, cross tunnels and vertical shafts.
[0019] In some embodiments of the present invention, the method further includes:
[0020] If the deduced result of the current remaining construction duration corresponding to at least one construction site exceeds the construction plan end time of the implementation construction organization plan, or the deduced result of the total project duration based on the current construction progress exceeds the total project duration of the implementation construction organization plan, adjust at least one of the construction plan start and end times and the construction plan start and end mileage of the non-critical path of the implementation construction organization plan, so that the total project duration of the adjusted implementation construction organization plan does not exceed the total project duration of the guiding construction organization plan and the adjusted implementation construction organization plan meets the construction continuity of each construction site;
[0021] Update the construction log data based on the adjusted implementation construction organization plan, and continue to execute the steps of verification, deduction and floor plan generation, and automatically update the construction site structure information, the specific content included in the implementation construction organization plan, the current construction progress and construction status of each construction site and its surrounding rocks, and the deduced result of the total project duration based on the current construction progress under multi-dimensional indicators in the display content of the tunnel floor plan.
[0022] In some embodiments of the present invention, the method further includes:
[0023] Calculate the leading line mileage based on the total project duration and the overall start and end mileage of the project of the guiding construction organization plan or the implementation construction organization plan.
[0024] If the total mileage of the current project construction is not less than the mileage of the leading line, output the automatically generated tunnel plan view;
[0025] If the total mileage of the current project construction is less than the mileage of the leading line, adjust at least one of the start and end time of the construction plan and the start and end mileage of the construction plan for each work point on the non-critical line of the implementable construction plan, so that the total project duration of the adjusted implementable construction plan does not exceed the total project duration of the guiding construction plan and the adjusted implementable construction plan meets the construction continuity of each work point;
[0026] Update the construction log data based on the adjusted implementable construction plan, and continue to execute the steps of verification, deduction and plan view generation, and automatically update the work point structure information, the specific content included in the implementable construction plan, the current construction progress and construction status of each work point and its surrounding rocks, and the deduction result of the total project duration based on the current construction progress under multi-dimensional indicators in the display content of the tunnel plan view.
[0027] In some embodiments of the present invention, the method further includes:
[0028] Calculate the corresponding leading line mileage based on the total project duration and the total start and end mileage of the guiding construction plan and the implementable construction plan respectively;
[0029] If the total mileage of the current project construction is not less than the larger value of the leading line mileage, output the automatically generated tunnel plan view;
[0030] If the total mileage of the current project construction is less than the larger value of the leading line mileage, adjust at least one of the start and end time of the construction plan and the start and end mileage of the construction plan for each work point on the non-critical line of the implementable construction plan, so that the total project duration of the adjusted implementable construction plan does not exceed the total project duration of the guiding construction plan and the adjusted implementable construction plan meets the construction continuity of each work point;
[0031] Update the construction log data based on the adjusted implementable construction plan, and continue to execute the steps of verification, deduction and plan view generation, and automatically update the work point structure information, the specific content included in the implementable construction plan, the current construction progress and construction status of each work point and its surrounding rocks, and the deduction result of the total project duration based on the current construction progress under multi-dimensional indicators in the display content of the tunnel plan view.
[0032] Another aspect of the present invention provides a tunnel visualization system, which includes: a computer device, the computer device includes a processor and a memory, computer instructions are stored in the memory, and the processor is used to execute the computer instructions stored in the memory. When the computer instructions are executed by the processor, the system implements the steps of the aforementioned tunnel plan drawing generation method for railway construction.
[0033] Another aspect of the present invention provides a computer-readable storage medium, on which a computer program is stored. When the program is executed by a processor, it implements the steps of the aforementioned tunnel plan drawing generation method for railway construction.
[0034] Another aspect of the present invention provides a computer program product, including computer instructions. When the computer instructions are executed by a processor, it implements the steps of the aforementioned tunnel plan drawing generation method for railway construction.
[0035] The tunnel plan drawing generation method for railway construction and the tunnel visualization system of the present invention automatically obtain the guiding construction organization plan and work point structure information, and based on the work point structure information, obtain the implementation construction organization plan and the construction log data of each work point and its surrounding rocks. It automatically generates a tunnel plan drawing that can intuitively and real-time display the work point structure information of the tunnel project, the spatial distribution information of each work point, and the actual construction progress of each work point, various construction organization plans such as guiding and implementation, the engineering total duration deduced under multi-dimensional indicators such as guiding construction organization plan indicators, implementation construction organization plan indicators, and engineering progress indicators at a certain construction period, etc. Data, and can realize real-time comparison of various progress data, for construction units and on-site construction personnel to refer to and adjust the construction progress of the implementation construction organization plan and the construction quantity of each work point and its surrounding rocks in a timely manner, ensure the rationality of the adjustment, and enable the tunnel project to be completed as scheduled or in advance according to the guiding construction organization plan overall.
[0036] The additional advantages, objectives, and features of the present invention will be partially described below, and will become partially obvious to those of ordinary skill in the art after studying the following text, or can be learned according to the practice of the present invention. The objectives and other advantages of the present invention can be achieved and obtained through the structures specifically pointed out in the description and the drawings.
[0037] Those skilled in the art will understand that the objectives and advantages that can be achieved by the present invention are not limited to the above specific descriptions, and the above and other objectives that the present invention can achieve will be more clearly understood according to the following detailed description. Description of the Drawings
[0038] The drawings described herein are used to provide a further understanding of the present invention, form a part of this application, and do not limit the present invention.
[0039] Figure 1 Schematic flowchart of an implementation manner of the tunnel plan drawing generation method for railway construction according to the present invention;
[0040] Figure 2 Tunnel plane of the present invention Figure 1 Schematic diagram of an example;
[0041] Figure 3 Schematic diagram of another example of the tunnel plan drawing of the present invention;
[0042] Figure 4 Schematic diagram of another example of the tunnel plan drawing of the present invention;
[0043] Figure 5 Schematic diagram of another example of the tunnel plan drawing of the present invention. Specific implementation manner
[0044] To make the objectives, technical solutions and advantages of the present invention clearer and more understandable, the present invention will be further described in detail below in conjunction with the implementation manners and the accompanying drawings. Herein, the illustrative implementation manners of the present invention and their descriptions are used to explain the present invention, but do not limit the present invention.
[0045] Herein, it should also be noted that in order to avoid obscuring the present invention due to unnecessary details, only the structures and / or processing steps closely related to the solution according to the present invention are shown in the drawings, while other details less related to the present invention are omitted.
[0046] It should be emphasized that the term "including / comprising" when used herein refers to the presence of features, elements, steps or components, but does not exclude the presence or addition of one or more other features, elements, steps or components.
[0047] Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. In the drawings, the same reference numerals represent the same or similar components, or the same or similar steps.
[0048] Regarding the display of the construction progress of tunnel projects for railway construction, existing visualization graphics displays such as slope charts, bar charts, network charts, etc. have the following problems: they cannot intuitively display the spatial distribution of each construction point of the project, nor can they display in real time and overview multiple index information such as the planned quantity and completed quantity of each construction point in the tunnel project under various plans, so as to assist the construction unit and its construction personnel, provide a reference for the actual construction work of the construction unit and its construction personnel, and thus ensure the smooth completion of the tunnel project within the plan. To address this problem, the embodiments of the present invention provide a tunnel plan drawing generation method for railway construction, which can be implemented by a railway engineering management platform.
[0049] The railway engineering management platform may include a tunnel visualization system, an electronic construction log system, and an engineering breakdown system. Among them, the engineering breakdown system decomposes the overall structure of the tunnel project to obtain work point structure information, which includes multiple work points, different grades and types of surrounding rock information distributed within each work point, and the start and end mileage of the construction plan for each surrounding rock. The electronic construction log system stores the construction log data of each work point and different grades and types of surrounding rock distributed within each work point, etc. The tunnel visualization system can automatically obtain the work point structure information decomposed by the engineering breakdown system, and automatically obtain and call the corresponding construction log data in the electronic construction log system according to the work point structure information, so as to obtain the daily construction progress data of each work point and its surrounding rock, and further obtain the cumulative amount or construction progress of each work point and its surrounding rock in the current construction period, and based on this, deduce the remaining construction period and the total project period of each work point and its surrounding rock under the current construction progress of multi-dimensional indicators. The tunnel visualization system can also automatically call the relevant data of the guiding construction organization plan in the railway engineering management platform, generate the relevant data of the implementation construction organization plan based on the automatically obtained work point structure information and the guiding construction organization plan, and finally automatically generate a tunnel plan view that can display the work point structure with non-overlapping spatial distribution according to the called guiding construction organization plan, work point structure information, implementation construction organization plan, construction log data, and the relevant data of the deduction result of the total project period of multi-dimensional indicators. It can also intuitively and clearly display the current construction progress and construction status of each work point and each surrounding rock within each work point, the relevant information of the guiding construction organization plan and the implementation construction organization plan, and the current remaining construction period and the total project period of each work point and its surrounding rock deduced under various indicators such as the guiding construction organization plan, the implementation construction organization plan, and the construction progress index of a certain construction period of the project. The tunnel plan view that can compare the deduced construction period result with the construction periods of the guiding construction organization plan and the implementation construction organization plan in real time to determine whether there will be a construction period delay is provided for the construction unit and on-site construction personnel to refer to and find a reasonable range for adjustment, and timely adjust the construction progress of the implementation construction organization plan and the construction quantity of each work point and its surrounding rock to ensure that the tunnel project can be completed on schedule or ahead of schedule according to the guiding construction organization plan overall.
[0050] Figure 1 is a schematic flow chart of a method for generating a tunnel plan view for railway construction according to an embodiment of the present invention. Refer to Figure 1 In this embodiment, the method for generating a tunnel plan view for railway construction includes the following steps:
[0051] Step S110, obtain a guiding construction organization plan, where the guiding construction organization plan includes the total project period, the overall start and end mileage of the project, and at least one critical line determined based on the overall structure of the tunnel project.
[0052] In the embodiments of the present invention, the guiding construction organization plan is prepared by the construction unit and stored in the railway engineering management platform. The critical path includes the progress route with a relatively long construction time and high construction difficulty during the construction process of the tunnel project. During the construction process, the construction of the tunnel project needs to be completed strictly in accordance with the guiding construction organization plan or earlier than this plan, and the critical path cannot be changed or adjusted.
[0053] Step S120: Obtain the work point structure information. The work point structure information includes multiple work points decomposed based on the overall structure of the tunnel project, the construction route, the surrounding rock information of different grades and types distributed in each work point, and the start and end mileage of the construction plan for each surrounding rock. Generate an implementation construction organization plan based on the work point structure information and the guiding construction organization plan. The implementation construction organization plan includes the start and end time of the construction plan for each work point and its surrounding rocks that match the work point structure information. The total project duration of the implementation construction organization plan does not exceed the total project duration of the guiding construction organization plan.
[0054] In the embodiments of the present invention, the above work points specifically include two categories: the main tunnel (main tunnel) and auxiliary adits. The auxiliary adits include at least parallel adits, inclined shafts, cross tunnels, and vertical shafts. The work points can include, for example, the 1# cross passage of Kangding No. 2 Tunnel, the 1st cross tunnel of Kangding No. 2 Tunnel, the large mileage of the parallel adit at the large mileage of the 1st cross tunnel of Kangding No. 2 Tunnel, the 2# inclined shaft of Kangding No. 2 Tunnel, the large mileage of the parallel adit at the large mileage of the 2# inclined shaft of Kangding No. 2 Tunnel, etc. The construction route is composed of multiple work points and the construction sequence and direction of each work point. The implementation construction organization plan is prepared by the construction unit according to the guiding construction organization plan prepared by the construction unit and stored in the railway engineering management platform. In this embodiment, the implementation construction organization plan is also generated according to the automatically obtained work point structure information. The work point structure information is obtained by decomposing the overall structure of the tunnel project by the engineering decomposition system. In the work point structure information, the start and end mileage of the construction plan for each work point can be obtained through the start and end mileage of the construction plan for each surrounding rock distributed in each work point.
[0055] Step S130: Obtain the construction log data. Automatically extract the daily construction progress data of each work point from the construction log data based on the work point structure information, and automatically verify the daily construction progress data of each work point based on the preset construction logical relationship. The daily construction progress data of each work point includes the daily construction progress data of each surrounding rock distributed in each work point.
[0056] In the embodiments of the present invention, the construction log data is specifically obtained from the electronic construction log system. The construction log data includes the construction status of each work point (including status such as not started, started, under construction, and completed), the daily construction progress data of each work point (i.e., the daily construction volume or construction mileage of each work point), etc. Here, the daily construction progress data of each work point includes the daily construction progress data of each grade and type of surrounding rock distributed in each work point.
[0057] In an embodiment of the present invention, the specific steps of automatically verifying the daily construction progress data of each construction site based on the preset construction logical relationship in step S130 include: calculating the cumulative amount of each construction site per day based on the daily construction progress data of each construction site; using a verification function to verify the cumulative amount of each construction site per day. If the cumulative amount per day is not less than that of the previous day, it indicates that the obtained daily construction progress data is normal. If the cumulative amount per day is less than that of the previous day, it indicates that the obtained daily construction progress data is abnormal, and further trace and correct the obtained daily construction progress data.
[0058] Specifically, the daily construction progress data obtained on the jth day is t j , then the cumulative amount on the Nth day is The set of cumulative amounts obtained on the Nth day is {p 1 , p 2 ,..., p N-1 , p N}, and the verification function is as follows:
[0059] f(p 1 , p 2 ,..., p N-1 , p N ) = (p 1 ≤ p 2 ) & (p 2 ≤ p 3 )... & (p N-1 ≤ p N )
[0060] Among them, if the value of the verification function is 1, it indicates that the obtained daily construction progress data is normal; if the value of the verification function is 0, it indicates that the obtained daily construction progress data is abnormal.
[0061] In the embodiment of the present invention, the deduction result of the total project duration based on the current construction progress is the sum of the actual duration used for the constructed mileage / constructed quantity of each construction site (each surrounding rock within each construction site) and the deduction result of the construction duration still required for the unconstructed mileage / unconstructed quantity of each construction site (each surrounding rock within each construction site).
[0062] Step S140, calculate the cumulative amount of each construction site based on the verified daily construction progress data of each construction site, and use the interpolation method to deduce the current remaining construction duration of each construction site under multi-dimensional indicators based on the cumulative amount of each construction site, and obtain the deduction result of the total project duration based on the current construction progress. The multi-dimensional indicators include the guiding construction organization plan indicators, the implementation construction organization plan indicators, and the project construction duration progress indicators.
[0063] In one embodiment of the present invention, in step S140, the specific steps of using the interpolation method to deduce the current remaining construction period of each construction point under multi-dimensional indicators based on the cumulative quantity of each construction point currently, and obtaining the deduced result of the total project duration based on the current construction progress are as follows:
[0064] Using the interpolation method, based on the cumulative quantity of each construction point currently, deduce the current remaining construction period of each level and type of surrounding rock distributed within each construction point under a certain project duration progress indicator of the project and the implementation construction organization plan indicator, and obtain the deduced result of the total project duration under the current construction progress;
[0065] Using the interpolation method, based on the cumulative quantity of each construction point currently, deduce the current remaining construction period of each level and type of surrounding rock distributed within each construction point under the guiding construction organization plan indicator, and obtain the deduced result of the total project duration under the current construction progress.
[0066] In an embodiment of the present invention, specifically, for this dimension indicator of a certain project duration progress indicator, for example, using the construction progress indicator of the recent 6 months, deduce the total project duration under the current construction progress according to the following formula:
[0067]
[0068] where, v i represents the construction speed of each level of surrounding rock distributed within each construction point actually completed in the recent 6 months of the project, S i represents the construction mileage or excavation distance (cumulative quantity) of each level of surrounding rock distributed within each construction point actually completed in the recent 6 months of the project, t i represents the completion time of the constructed quantity of each level of surrounding rock distributed within each construction point actually completed in the recent 6 months of the project, L i represents the remaining construction mileage or remaining excavation distance of each level of surrounding rock distributed within each construction point, T ′ represents the already constructed duration of each level of surrounding rock currently, T 结束日期(6个月指标) represents the total project duration deduced under this dimension indicator, i represents each surrounding rock grade distributed within each construction point, i = [1, 6].
[0069] For this dimension indicator of the implementation construction organization plan indicator, deduce the total project duration under the current construction progress according to the following formula:
[0070]
[0071] where, L i represents the remaining construction mileage or remaining excavation distance of each level of surrounding rock distributed within each construction point, v i represents the standard construction speed or standard excavation speed corresponding to each level of surrounding rock distributed within each construction point under the implementation construction organization plan, T ′It represents the currently constructed construction period of surrounding rocks at all levels, T 结束日期(实施性指标) It represents the total project construction period deduced under this dimensional index. i represents each surrounding rock grade distributed within each work point, and i = [1, 6].
[0072] For this dimensional index of the guiding construction organization plan index, the total project construction period under the current construction progress is deduced according to the following formula:
[0073]
[0074] Among them, T s It represents the starting time of the overall project of the guiding construction organization plan, S s It represents the starting mileage of the overall project of the guiding construction organization plan, S l It represents the ending mileage of the overall project of the guiding construction organization plan, S ′ It represents the actual constructed mileage (cumulative amount) under the current construction progress, T ′ It represents the currently constructed construction period of the overall project, It represents the average construction speed or average excavation speed under the current construction progress, T 结束日期(指导性指标) It represents the total project construction period deduced under this dimensional index.
[0075] Step S150, automatically generate a tunnel plan view based on the guiding construction organization plan, the work point structure information, the implementation construction organization plan, the construction log data, and the deduction result of the total project construction period based on the current construction progress under multi-dimensional indexes. The display content of the tunnel plan view includes at least multiple non-overlapping and interconnected work point frames for displaying the spatial distribution of work point structure information, the specific content included in the guiding construction organization plan and the implementation construction organization plan, the current construction progress and construction status of each work point and its surrounding rocks, and the deduction result of the total project construction period based on the current construction progress under multi-dimensional indexes.
[0076] In the embodiments of the present invention, through the above tunnel plan view, the construction site structure information of the tunnel project can be comprehensively and real-time displayed, and the spatial distribution of each construction site in the construction site structure can be clearly shown, as well as the information of the guiding construction organization plan and the implementation construction organization plan of the project. Under multiple dimensions such as these planned indicators and a certain construction period progress indicator of the project, the remaining progress of the current project, the remaining construction period of the current project, and the total construction period of the project can be deduced, as well as the current construction progress information and the critical path of each construction site in the construction site structure. The tunnel plan view can also real-time display the comparison of the construction period information under various plans respectively and the construction period deduction results under multiple indicators such as the actual progress at a certain construction period, the guiding construction organization plan, and the implementation construction organization plan, etc., which can be used for the construction unit and construction personnel to timely understand the current construction progress of each construction site, and further estimate and judge whether the project can be successfully completed or completed ahead of schedule according to the comparison results, and make a judgment on whether to delay the construction period. The tunnel plan view can provide a more intuitive reference basis for the construction progress evaluation of the construction unit and construction personnel, which is conducive to timely adjusting the plan and ensuring the completion of the construction task on time. The construction site structure information is displayed by a plurality of non-overlapping and interconnected construction site frames with spatial distribution on the tunnel plan view.
[0077] In one embodiment of the present invention, the method for generating a tunnel plan view for railway construction may further include the following steps:
[0078] Step S161, if the deduction result of the current remaining construction period corresponding to at least one construction site exceeds the construction plan end time of the implementation construction organization plan, or the deduction result of the total construction period of the project based on the current construction progress exceeds the total construction period of the implementation construction organization plan, adjust at least one of the start and end time of the construction plan and the start and end mileage of the construction plan of each construction site on the non-critical path of the implementation construction organization plan, so that the total construction period of the adjusted implementation construction organization plan does not exceed the total construction period of the guiding construction organization plan and the adjusted implementation construction organization plan meets the construction continuity of each construction site;
[0079] Step S162, update the construction log data based on the adjusted implementation construction organization plan, and continue to execute the steps of verification, deduction, and plan view generation to automatically update the construction site structure information, the specific content included in the implementation construction organization plan, the current construction progress and construction status of each construction site and its surrounding rocks, and the deduction result of the total construction period of the project based on the current construction progress under multiple dimensions in the display content of the tunnel plan view.
[0080] In the embodiments of the present invention, in the deduction results of different dimensional indicators, if the deduction result of the construction period (remaining construction period) of the unconstructed mileage of one or more work points exceeds the construction plan completion time of the corresponding work point in the implementation construction organization plan, or if the deduction result of the total project construction period under the current actual construction progress exceeds the total project construction period of the implementation construction organization plan, that is, when it is estimated that the project progress lags behind, according to the project structure, the surrounding rock grades and types of each work point distribution, etc., adjust the start and end time and / or start and end mileage of the construction plan of each work point and its surrounding rock of the non-critical line of the implementation construction organization plan, so that the total project construction period of the adjusted implementation construction organization plan does not exceed the total project construction period of the guiding construction organization plan, and based on the work point structure layout shown in the tunnel plan, make the adjusted implementation construction organization plan meet the construction continuity of each work point (the start time of each work point is later than the start date of the previous work point, and the completion date of each work point is earlier than the start date of the next work point), and does not affect the construction period and construction sequence of the critical line, ensuring the rationality of the construction plan adjustment. Then, construct according to the adjusted implementation construction organization plan, update the construction log data such as the daily construction progress data of each work point. At the same time, the tunnel plan can automatically update the relevant content indicators shown according to the adjusted implementation construction organization plan and the updated construction progress data, so that the construction personnel can obtain the latest information of the displayed content and the actual progress of each work point of the project in real time, and can adjust the construction plan in time once a possible delay occurs, ensuring that the project is completed on schedule or even ahead of schedule according to the plan.
[0081] In one embodiment of the present invention, the method for generating a tunnel plan for railway construction may further include the following steps:
[0082] Step S171, calculate the leading line mileage based on the total project construction period and the overall start and end mileage of the guiding construction organization plan or the implementation construction organization plan;
[0083] Step S172, if the current total project construction mileage is not less than the leading line mileage, output the automatically generated tunnel plan;
[0084] Step S173, if the current total project construction mileage is less than the leading line mileage, adjust at least one of the start and end time and start and end mileage of the construction plan of each work point on the non-critical line of the implementation construction organization plan, so that the total project construction period of the adjusted implementation construction organization plan does not exceed the total project construction period of the guiding construction organization plan and the adjusted implementation construction organization plan meets the construction continuity of each work point;
[0085] Step S174: Update the construction log data based on the adjusted implementation plan for construction organization, and continue to execute the steps of verification, deduction, and floor plan generation to automatically update the work point structure information in the display content of the tunnel floor plan, the specific content included in the implementation plan for construction organization, the current construction progress and construction status of each work point and its surrounding rocks, and the deduction results of the total project duration based on the current construction progress under multi-dimensional indicators.
[0086] In an embodiment of the present invention, the method for generating a tunnel floor plan for railway construction may further include the following steps:
[0087] Step S181: Calculate the corresponding front line mileage based on the total project duration and the overall start and end mileage of the guiding plan for construction organization and the implementation plan for construction organization respectively.
[0088] Step S182: If the current total construction mileage of the project is not less than the larger value of the front line mileage, output the automatically generated tunnel floor plan.
[0089] Step S183: If the current total construction mileage of the project is less than the larger value of the front line mileage, adjust at least one of the start and end time of the construction plan and the start and end mileage of the construction plan for each work point on the non-critical line of the implementation plan for construction organization, so that the total project duration of the adjusted implementation plan for construction organization does not exceed the total project duration of the guiding plan for construction organization and the adjusted implementation plan for construction organization meets the construction continuity of each work point.
[0090] Step S184: Update the construction log data based on the adjusted implementation plan for construction organization, and continue to execute the steps of verification, deduction, and floor plan generation to automatically update the work point structure information in the display content of the tunnel floor plan, the specific content included in the implementation plan for construction organization, the current construction progress and construction status of each work point and its surrounding rocks, and the deduction results of the total project duration based on the current construction progress under multi-dimensional indicators.
[0091] In an embodiment of the present invention, the front line mileage is the planned construction mileage that should be reached at the current construction period or progress, and is specifically calculated according to the start and end time (total project duration) and start and end mileage of the project as a whole in the guiding plan for construction organization or the implementation plan for construction organization according to the following formula:
[0092]
[0093] where, T s represents the start time of the project as a whole in the guiding plan for construction organization or the implementation plan for construction organization, T l represents the end time of the project as a whole in the guiding plan for construction organization or the implementation plan for construction organization, S s represents the start mileage of the project as a whole in the guiding plan for construction organization or the implementation plan for construction organization, Sl Indicates the end mileage of the overall project for the guiding construction organization plan or the implementation construction organization plan, T ′ Indicates the construction duration of the current overall project, S 前锋线 Indicates the mileage of the leading line.
[0094] Exemplarily, refer to Figure 2 , Figure 2 In the tunnel plan view for visualization shown in , each horizontal yellow wireframe represents specific spatial distribution information and each construction point frame with non-overlapping spatial distributions. Each vertical yellow wireframe connecting two rows of construction point frames and each construction point frame together constitute at least one construction line. The lengths of the horizontally arranged construction point frames represented by yellow wireframes schematically represent the distances of the start and end mileage of each construction point's construction. The horizontally arranged and interconnected construction point frames can be used to display the names of each construction point and its surrounding rocks, the progress ratio of the construction completion volume / excavation engineering volume, the completion percentage of the construction completion volume / excavation engineering volume, the status of the construction point (including status such as not started, started, under construction, and completed), the start and completion times, the construction duration of each construction point and the total project duration of the implementation construction organization plan and the guiding construction organization plan, the remaining construction duration of each construction point and the total project duration deduced under the three-dimensional indicators of the implementation construction organization plan indicators, the guiding construction organization plan indicators, and the actual progress indicators in the past 6 months, as well as information such as the mileage of the leading line. The horizontally arranged and connected construction point frames represented by yellow wireframes and the arrows therein respectively represent the construction sequence and construction direction of each construction point. The green highlighted display layer represents the current actual construction progress. The position of the red vertical line represents the guiding construction organization plan, and the position of the blue vertical line represents the implementation construction organization plan. These two vertical lines can be compared with the green highlighted display layer in real time.
[0095] The Figure 2 X and Y selection boxes in the upper left corner of can scale the tunnel plan view in two directions respectively, facilitating the viewing of detailed information of the construction points. Since there are many construction points in the cross-passage and they are densely displayed on the drawing, the cross-passage can be checked or hidden in the cross-passage checkbox, which is convenient for controlling the overall layout.
[0096] The Figure 2 In the upper right corner of , there are progress indicator checkbox options for three different dimensions of indicators, namely the actual construction progress indicators in the past 6 months, the guiding construction organization plan indicators, and the implementation construction organization plan indicators, used to deduce the current remaining construction duration and the total project duration. There are also two indicator checkbox options for the guiding construction organization plan and the implementation construction organization plan used to compare with the current actual construction progress respectively.
[0097] Refer to Figure 3 , Figure 3The tunnel plan view can also display the critical path set by the construction unit. After checking, the construction path of the critical path can be highlighted in yellow on the tunnel plan view, specifically showing the work point information of multiple critical paths and the current construction progress. By checking different critical paths, independent displays can be made in the tunnel plan view, and the progress direction is the arrow pointing within the yellow work point box highlighted in yellow.
[0098] See Figure 4 , Figure 4 The tunnel plan view of sets a dynamic deduction table option for the construction period progress after the critical path. By selecting three different progress indicators in the progress indicator checkbox, the remaining estimated completion time and total construction period of this line can be calculated in real time, specifically calculated through the deduction calculation formula described above. An indicator checkbox option is set behind the progress indicator checkbox option, and two types of plans, namely the guiding construction organization plan or the implementation construction organization plan, can be selected under this indicator checkbox option to dynamically display the data comparison between the actual completed project progress and the planned progress on the critical path.
[0099] Regarding the adjustment of the start and end times of the construction plan and / or the start and end mileage of the construction plan for each work point in the implementation construction organization plan, according to the tunnel engineering structure, the surrounding rock grades and types of each work point distribution, combined with the actual construction conditions, the construction quantities of any work point and the surrounding rock of each grade and type distributed within the work point are reasonably adjusted, and then the adjusted line is dynamically and vividly displayed on the tunnel plan view. The adjustment results of the construction mileage of each work point are mainly reflected in the length change of the yellow work point box. During the adjustment process, it does not affect the critical path and at the same time avoids the situation of discontinuous construction progress. For example, see Figure 5 , in Figure 5 In the critical path highlighted in purple shown, the pilot tunnel process of the No. 1 cross-passage will affect the start dates of several cross-passages beside the 19# cross-passage. If the construction start dates of the remaining cross-passages are earlier than the date when the pilot tunnel reaches the entrance of the 19# cross-passage, there will be a phenomenon of discontinuous construction progress. That is to say, when adjusting, attention should be paid to the start dates of the preceding work points of each work point and ensure that the completion date of its own work point is earlier than the start date of the succeeding work point.
[0100] In summary, the tunnel plan view can intuitively display the overall situation of the tunnel project, can vividly display the specific construction situation of the tunnel project in a lightweight manner, is convenient for controlling the work point structure and critical path, and clearly view the project progress warning when the deduced total construction period exceeds the planned total construction period and find the reasonable scope for adjusting the implementation construction organization plan.
[0101] Correspondingly, a tunnel visualization system according to an embodiment of the present invention includes a computer device, the computer device includes a processor and a memory, computer instructions are stored in the memory, and the processor is configured to execute the computer instructions stored in the memory. When the computer instructions are executed by the processor, the system implements the steps of the aforementioned method for generating a tunnel plan view for railway construction.
[0102] An embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, it implements the steps of the aforementioned method for generating a tunnel plan view for railway construction. The computer-readable storage medium may be a tangible storage medium, such as a random access memory (RAM), internal memory, read-only memory (ROM), electrically programmable ROM, electrically erasable programmable ROM, register, floppy disk, hard disk, removable storage disk, CD-ROM, or any other form of storage medium known in the art.
[0103] An embodiment of the present invention further provides a computer program product, including computer instructions, which implement the steps of the aforementioned method for generating a tunnel plan view for railway construction when the computer instructions are executed by a processor.
[0104] Those of ordinary skill in the art should understand that the various exemplary components, systems, and methods described in conjunction with the embodiments disclosed herein can be implemented in hardware, software, or a combination of both. Specifically, whether to implement in hardware or software depends on the specific application and design constraints of the technical solution. A professional technician can use different methods to implement the described functions for each specific application, but such implementation should not be considered to exceed the scope of the present invention. When implemented in hardware, it can be, for example, an electronic circuit, an application-specific integrated circuit (ASIC), appropriate firmware, a plug-in, a functional card, etc. When implemented in software, the elements of the present invention are programs or code segments used to perform the required tasks. The program or code segment can be stored in a machine-readable medium or transmitted via a data signal carried in a carrier wave on a transmission medium or a communication link.
[0105] It should be clear that the present invention is not limited to the specific configurations and processes described above and shown in the figures. For the sake of brevity, detailed descriptions of known methods are omitted here. In the above embodiments, several specific steps are described and shown as examples. However, the method process of the present invention is not limited to the specific steps described and shown. Those skilled in the art can make various changes, modifications, and additions, or change the order between steps after understanding the spirit of the present invention.
[0106] In the present invention, features described and / or illustrated for one embodiment can be used in the same way or in a similar way in one or more other embodiments, and / or combined with the features of other embodiments or replace the features of other embodiments.
[0107] The foregoing are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, various changes and modifications can be made to the embodiments of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.
Claims
1. A method for generating a tunnel plan for railway construction, characterized in that: The method comprises: Obtaining a guiding construction group plan, wherein the guiding construction group plan includes a total construction period determined based on the overall structure of the tunnel project, the overall starting and ending mileages of the project, and at least one key route; Acquire work site structure information, the work site structure information including multiple work sites, construction routes, surrounding rock information of different grades and types distributed in each work site and construction plan start and end mileages of each surrounding rock based on the overall structure decomposition of the tunnel project, generate an implementation construction group plan based on the work site structure information and the guiding construction group plan, the implementation construction group plan includes the construction plan start and end time of each work site and its surrounding rock that matches the work site structure information, and the total construction period of the implementation construction group plan does not exceed the total construction period of the guiding construction group plan; Acquire construction log data, automatically extract daily construction progress data of each work point from the construction log data based on the work point structure information, and automatically verify the daily construction progress data of each work point based on a preset construction logic relationship, wherein the daily construction progress data of each work point includes the daily construction progress data of each surrounding rock distributed in each work point; Based on the verified daily construction progress data of each construction point, the current cumulative opening amount of each construction point is calculated, and the current remaining construction period of each construction point under the multi-dimensional indicators is deduced by the interpolation method according to the current cumulative opening amount of each construction point, so as to obtain the deduction result of the total construction period of the project based on the current construction progress, wherein the multi-dimensional indicators include the guiding construction group plan indicators, the implementation construction group plan indicators and the progress indicators of a certain construction period of the project; A tunnel plan is automatically generated based on the guiding construction group plan, the work site structure information, the implementing construction group plan, the construction log data and the deduction results of the total construction period based on the current construction progress under multi-dimensional indicators. The display content of the tunnel plan includes at least a plurality of work site frames that are non-overlapping and interconnected in spatial distribution for displaying the work site structure information, the specific contents included in the guiding construction group plan and the implementing construction group plan, the current construction progress and construction status of each work site and its surrounding rock, and the deduction results of the total construction period based on the current construction progress under multi-dimensional indicators.
2. The method according to claim 1, characterized in that The step of automatically verifying the daily construction progress data of each work point based on the preset construction logic relationship includes: Calculate the current daily cumulative opening volume of each work site based on the daily construction progress data of each work site; The verification function is used to verify the current daily cumulative opening volume of each work point. If the current daily cumulative opening volume is not less than the previous day's cumulative opening volume, it means that the obtained daily construction progress data is normal. If the current daily cumulative opening volume is less than the previous day's cumulative opening volume, it means that the obtained daily construction progress data is abnormal, and the obtained daily construction progress data is further traced and corrected.
3. The method according to claim 1, characterized in that: In the step of using the interpolation method to deduce the current remaining construction period of each work point under the multi-dimensional indicators according to the current cumulative opening amount of each work point, and obtaining the deduction result of the total construction period of the project based on the current construction progress, Using the interpolation method, according to the current cumulative opening of each construction point, the current remaining construction period of each level and type of surrounding rock distributed in each construction point is deduced under a certain construction period progress index of the project and the implementable construction group plan index, and the deduction result of the total construction period of the project under the current construction progress is obtained; The interpolation method is used to deduce the current remaining construction period of each level and type of surrounding rock distributed in each work point according to the current cumulative amount of each work point under the guiding construction group plan indicators, and the deduction result of the total project period under the current construction progress is obtained.
4. The method according to claim 1, characterized in that: The key routes include routes that take a long time and are difficult to construct during the tunnel construction process; The multiple work sites include main tunnels and auxiliary tunnels, and the auxiliary tunnels include at least horizontal guides, inclined shafts, horizontal tunnels and vertical shafts.
5. The method according to any one of claims 1 to 4, characterized in that The method further comprises: If the deduced result of the current remaining construction period corresponding to at least one work site exceeds the planned construction end time of the implementable construction group plan, or the deduced result of the total construction period based on the current construction progress exceeds the total construction period of the implementable construction group plan, at least one of the planned construction start and end time and the planned construction start and end mileage of each work site of the non-critical line of the implementable construction group plan is adjusted, so that the adjusted total construction period of the implementable construction group plan does not exceed the total construction period of the guiding construction group plan and the adjusted implementable construction group plan satisfies the construction continuity of each work site; The construction log data is updated based on the adjusted implementation plan, and the verification, deduction and plan generation steps are continued to be performed. The work site structure information in the tunnel plan display, the specific content of the implementation plan, the current construction progress and construction status of each work site and its surrounding rock, and the deduction results of the total construction period based on the current construction progress under multi-dimensional indicators are automatically updated.
6. The method according to any one of claims 1 to 4, characterized in that The method further comprises: Calculate the forward line mileage based on the total construction period of the project and the overall starting and ending mileage of the project in the guiding construction group plan or the implementing construction group plan; If the total mileage of the current engineering construction is not less than the mileage of the front line, output the automatically generated tunnel plan; If the current total construction mileage is less than the front line mileage, at least one of the construction plan start and end time and the construction plan start and end mileage of each work point of the non-critical line of the implementation group plan is adjusted, so that the total construction period of the adjusted implementation group plan does not exceed the total construction period of the guiding group plan and the adjusted implementation group plan meets the construction continuity of each work point; The construction log data is updated based on the adjusted implementation plan, and the verification, deduction and plan generation steps are continued to be performed. The work site structure information in the tunnel plan display, the specific content of the implementation plan, the current construction progress and construction status of each work site and its surrounding rock, and the deduction results of the total construction period based on the current construction progress under multi-dimensional indicators are automatically updated.
7. The method according to any one of claims 1 to 4, characterized in that The method further comprises: Calculate the corresponding forward line mileage based on the total construction period and the overall starting and ending mileage of the project of the guiding construction group plan and the implementing construction group plan; If the total mileage of the current project construction is not less than the larger value of the forward line mileage, output the automatically generated tunnel plan; If the current total construction mileage is less than the larger value of the front line mileage, at least one of the construction plan start and end time and the construction plan start and end mileage of each work point of the non-critical line of the implementation group plan is adjusted, so that the total construction period of the adjusted implementation group plan does not exceed the total construction period of the guiding group plan and the adjusted implementation group plan meets the construction continuity of each work point; The construction log data is updated based on the adjusted implementation plan, and the verification, deduction and plan generation steps are continued to be performed. The work site structure information in the tunnel plan display, the specific content of the implementation plan, the current construction progress and construction status of each work site and its surrounding rock, and the deduction results of the total construction period based on the current construction progress under multi-dimensional indicators are automatically updated.
8. A tunnel visualization system, comprising a processor and a memory, characterized in that: The memory stores computer instructions, and the processor is used to execute the computer instructions stored in the memory. When the computer instructions are executed by the processor, the system implements the steps of the method as claimed in any one of claims 1 to 7.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are implemented.
10. A computer program product comprising computer instructions, characterized in that: When the computer instructions are executed by a processor, the steps of the method described in any one of claims 1 to 7 are implemented.
Citation Information
Patent Citations
Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model
CN106384191A
A field progress monitoring system and a method based on a three-dimensional model
CN109377066A
Construction period prediction method based on tunnel engineering progress slope diagram and compilation method
CN111241620A
BIM-based four-power construction group plan simulation and resource dynamic adjustment method and system
CN112365113A
Railway engineering construction period progress early warning management method and system and storage medium
CN114331066A