Scaffold erecting and disassembling method
Through the combination of inner slider and column footrest, the time-consuming and labor-intensive installation of columns in the prior art is solved, rapid installation positioning is achieved, and installation efficiency and practicality are improved.
Patent Information
- Application Number
- CN202510560587.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-30
- Publication Date
- 2025-06-27
AI Technical Summary
In the prior art, when installing the column, the column needs to be inserted into the receiving groove and then fixed by the third locking member, which makes the column installation time-consuming and labor-intensive and cannot be quickly positioned.
The inner slider is combined with column footrests, and the column footrest is adjusted by sliding the inner slider, and the column footrest is fixed using rubber jacks and slots to achieve rapid installation and positioning.
Through the combination of inner slider and column footrest, the column installation efficiency is significantly improved, the cumbersome installation process is avoided, time and energy are saved, and it is more practical.
Smart Images

Figure CN120211470A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of scaffolding, and in particular relates to a scaffolding erection and dismantling method. Background Art
[0002] The Chinese patent, application number 202421778627.5, discloses an auxiliary device for erecting and dismantling a scaffold, which is connected by sliding between a longitudinal guide rail and a transverse guide rail, and a positioning block is connected by sliding between the transverse guide rail. According to the positions of the four columns in the scaffold, the positioning blocks are respectively adjusted to appropriate positions, and then after the positions of the positioning blocks are fixed, when erecting the scaffold, the positions of the columns can be respectively fixed by the positioning blocks. Specifically, when in use, the bottom ends of the columns can be respectively inserted into the receiving grooves, and then the positions of the columns can be fixed by rotating the third threaded rod until the third threaded rod is pressed against the columns, so that when installing diagonal braces or connecting rods between the columns, the scaffold will not collapse suddenly; and when dismantling the scaffold, the positions of the columns can also be respectively fixed by the positioning blocks;
[0003] However, when installing the column, the device needs to insert the column into the receiving groove and then fix the column by the third locking member. Due to the large number of columns, it is time-consuming and labor-intensive to install the columns using this method, and the columns cannot be installed and positioned quickly, so the practicality is poor. Summary of the invention
[0004] In order to solve the problem of inconvenience in quickly positioning and installing columns in the above-mentioned prior art, the present invention provides a scaffold erection and dismantling method, which adopts an inner slider in combination with a column pad foot to insert the column into the column pad foot and complete the effect of quick installation and positioning. The specific technical scheme is: a scaffold erection and dismantling method, characterized in that it includes the following steps: S1, positioning and laying out the line as required, placing two pads on the positioning line respectively, and arranging the column pad feet on the pads, and a sliding connection mechanism is arranged between the pads and the column pad feet; S2, inserting the column into the column pad feet, and arranging longitudinal and transverse sweeping rods between the columns; S 3. Erection of scaffolding, which is divided into longitudinal horizontal bar structure erection and transverse horizontal bar structure erection. The longitudinal horizontal bars and transverse horizontal bars are laid from bottom to top; S4. Install scaffolding boards, footboards and guardrails; S5. Continuously erect scissors braces and diagonal bars. The integral tie rods such as scissors braces and diagonal bars are set up at the same time as the erected frame; S6. Install wall connecting rods, which are fixed to the horizontal bars and vertical bars by fasteners; S7. Dismantle the scaffolding, which is dismantled layer by layer from top to bottom; S8. The dismantled rod accessories are concentrated on the adjacent undismantled frame surface, tied up and then hoisted down.
[0005] Preferably, the sliding connection mechanism comprises:
[0006] A vertical block, a vertical block is installed at the center of the top end of the backing plate, and the vertical block is of a rectangular structure;
[0007] Chute grooves, two chute grooves are symmetrically opened on the outer walls on both sides of the vertical block, and the chute grooves are rectangular grooves;
[0008] Inner sliders, inner sliders are slidably connected in the chute grooves, and the four corners of the inner sliders are of smooth arc structures;
[0009] Side sliding plates, one end of the inner slider extends out of the chute groove, and a side sliding plate is welded to the extended end of the inner slider, and the side sliding plate is attached to the vertical block;
[0010] Support plates, support plates are welded to the top ends of the two side sliding plates, reinforcing ribs are welded between the support plates and the side sliding plates, the column foot pads are welded to the top ends of the support plates, and the support plates are slidably attached to the vertical blocks;
[0011] Grooves, a plurality of grooves are opened on the top inner wall and the bottom inner wall of the chute groove, and the upper and lower chute grooves correspond to each other;
[0012] Rubber clamping heads, rubber clamping heads are fixedly installed in the grooves, and the round heads of the rubber clamping heads extend out of the grooves;
[0013] Card slots, card slots are opened at the center points of the top end and the bottom end of the inner slider, and the card slots are adapted to the rubber clamping heads.
[0014] Preferably, the S1 is specifically:
[0015] S1.1, the perimeter scaffolding starts from a corner and extends and laps around both sides; the one-way scaffolding starts from one end and extends and laps to the other end.
[0016] Preferably, the S2 is specifically:
[0017] S2.1, the vertical poles are erected in sequence according to the positioning, and the vertical poles are connected and fixed to the longitudinal and transverse bottom bars.
[0018] Preferably, the S3 is specifically:
[0019] S3.1, install the first-step longitudinal and transverse horizontal bars, fix them after correcting the verticality of the vertical poles, and continue to erect upward;
[0020] S3.2, the longitudinal horizontal bars are lengthened by using butt joints with fasteners, the joint positions are arranged staggeredly, and the joints of two adjacent longitudinal horizontal bars are arranged on different spans;
[0021] S3.3, set a transverse horizontal bar at the main node and connect it with a right-angle fastener;
[0022] S3.4, the scaffolding columns for steel structure installation are set on the base plates of the columns, and other scaffolding columns are erected on wooden cushion plates;
[0023] S3.5, for the extension of the vertical poles, lap joints are used at the top layer, and butt fasteners are used for the joints of each layer and each step for the rest. The butt fasteners on the vertical poles are arranged staggeredly.
[0024] Preferably, the said S4 is specifically:
[0025] S4.1, the scaffolding boards are laid flat and stable and are tied and fixed; the scaffolding boards are laid flat by butting.
[0026] Preferably, the said S5 is specifically:
[0027] S5.1, the double-row scaffolding is provided with cross braces and transverse diagonal bars for support;
[0028] S5.2, the overall tie rods such as cross braces and diagonal bars are set up together with the erected scaffold.
[0029] In addition, the scaffolding erection and dismantling method in the above technical solution provided by the present invention may also have the following features: the said S7 is specifically:
[0030] S7.1, the demolition sequence layer by layer is: safety net, toe board, guardrail, scaffolding board, cross brace, small cross bar, large cross bar and vertical pole, and then the above sequence is cycled;
[0031] S7.2, turn up the scaffolding board from the outside to the inside and stand it upright;
[0032] S7.3, after retaining the vertical pole, then remove the last two fasteners;
[0033] S7.4, first remove the fasteners in the middle of the large cross bar, diagonal brace and cross brace, then support the middle part, and then untie the end fasteners;
[0034] S7.5, first use a temporary support column for support, and then remove the outrigger;
[0035] S7.6, timely remove and transport away the loosened rod fittings.
[0036] A scaffolding erection and dismantling method of the present invention, compared with the prior art, has the beneficial effects as follows:
[0037] 1. For this scaffolding erection and dismantling method, by sliding the inner slider, it is convenient to adjust the position of the column foot pad on the cushion plate. After the rubber chuck is snapped into the card slot, the inner slider is fixed in the chute, and the position of the column foot pad is fixed; when adjusting the position of the inner slider, by moving the inner slider, the inner slider presses the rubber chuck, causing the rubber chuck to retract into the card slot, and then the position of the inner slider in the chute can be moved, thereby adjusting the position of the column foot pad;
[0038] 2. By setting up column foot pads and inserting the columns into the column foot pads, it is convenient to quickly install and position the columns, avoiding cumbersome installation processes, saving time and effort, and having strong practicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 One of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0040] Figure 2 Two of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0041] Figure 3 Three of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0042] Figure 4 Four of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0043] Figure 5 Five of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0044] Figure 6 Six of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0045] Figure 7 Seven of the process flowcharts of the scaffolding erection and dismantling method provided by the present invention;
[0046] Figure 8 Schematic diagram of the three-dimensional structure of the backing plate provided by the present invention;
[0047] Figure 9 Partial cross-sectional view of the vertical block provided by the present invention;
[0048] Among them, Figures 8 to 9 The reference numerals in the drawings and the component names are: 1, backing plate; 2, vertical block; 3, sliding groove; 4, inner slider; 5, side sliding plate; 6, support plate; 7, reinforcing rib; 8, column foot pad; 9, slotted opening; 10, rubber chuck; 11, card slot. DETAILED DESCRIPTION OF THE EMBODIMENTS
[0049] The following further illustrates the present invention in conjunction with specific implementation cases and attached Figures 1 - 9 The present invention provides a technical solution: a scaffolding erection and dismantling method, characterized by including the following steps:
[0050] S1. Position and set out lines as required, place two backing plates 1 on the set-out lines respectively, and set column foot pads 8 on the backing plates 1. A sliding connection mechanism is provided between the backing plates 1 and the column foot pads 8;
[0051] S2, insert the column into the column pad 8, the column pad 8 is made of φ25 steel pipe and 150×150×5mm thick steel plate, which is compatible with the column; set longitudinal and transverse sweeping rods between the columns, the longitudinal sweeping rod is fixed to the column at a distance of no more than 200mm from the base by a right-angle fastener, and the transverse sweeping rod is fixed to the column close to the bottom of the longitudinal sweeping rod by a right-angle fastener;
[0052] S3, erecting the scaffolding structure, which is divided into erecting the longitudinal horizontal bar structure and erecting the transverse horizontal bar structure, and the longitudinal horizontal bars and the transverse horizontal bars are laid from bottom to top;
[0053] S4, install scaffolding, toeboards and guardrails;
[0054] S5, continuously erect scissor braces and diagonal bars, and the integral tie rods such as scissor braces and diagonal bars are set up simultaneously with the erected racks;
[0055] S6, setting a wall connecting rod, and fixing the wall connecting rod to the horizontal rod and the vertical rod through fasteners;
[0056] S7, dismantling the scaffolding, dismantling the scaffolding layer by layer from top to bottom, avoiding simultaneous operation of the upper and lower layers;
[0057] S8, the dismantled rod accessories are gathered on the adjacent undismantled rack surface, tied up and then hung down.
[0058] As a preferred solution, further, the sliding connection mechanism includes:
[0059] A vertical block 2 is installed at the top center of the pad 1, and the vertical block 2 is a rectangular structure;
[0060] Slide groove 3, two slide grooves 3 are symmetrically opened on the outer walls of both sides of the vertical block 2, and the slide groove 3 is a rectangular groove;
[0061] An inner slide block 4 is slidably connected in the slide groove 3, and the four corners of the inner slide block 4 are smooth arc-shaped structures;
[0062] A side slide plate 5, one end of the inner slide block 4 extends out of the slide groove 3, the extended end of the inner slide block 4 is welded with a side slide plate 5, and the side slide plate 5 is fitted with the vertical block 2;
[0063] Support plate 6, the top ends of the two side slide plates 5 are welded with support plates 6, reinforcing ribs 7 are welded between the support plate 6 and the side slide plates 5, and column pads 8 are welded on the top ends of the support plate 6, and the support plate 6 is slidably fitted with the vertical block 2;
[0064] Slots 9, multiple slots 9 are provided on the top wall and the bottom wall of the slide 3, and the upper and lower slide slots 9 correspond to each other one by one;
[0065] A rubber clamp 10 is fixedly installed in the slot 9, and a round head of the rubber clamp 10 extends out of the slot 9;
[0066] A clamping groove 11 is provided at the center points of the top and bottom ends of the inner slider 4 , and the clamping groove 11 is matched with the rubber clamp 10 .
[0067] As a preferred solution, further, S1 is specifically:
[0068] S1.1, Perimeter scaffolding starts from one corner and extends to both sides to form a circle; Linear scaffolding starts from one end and extends to the other end.
[0069] As a preferred solution, further, S2 is specifically:
[0070] S2.1. Erect the vertical poles in sequence according to the positioning, and connect and fix the vertical poles with the longitudinal and transverse sweeping poles.
[0071] As a preferred solution, further, S3 is specifically:
[0072] S3.1, install the first step of longitudinal and transverse horizontal bars, correct the verticality of the vertical bars, fix them, and continue to erect upwards;
[0073] S3.2, the longitudinal horizontal bars are connected by butt fasteners or overlap. The joints are arranged in a staggered manner. The joints of two adjacent longitudinal horizontal bars are set at different spans. The horizontal distance between two adjacent joints of different spans is greater than 500mm. The distance from the center of each joint to the nearest node is less than 1 / 3 of the longitudinal span. The overlap length is not less than 1m. Three rotating fasteners are set at equal intervals. The distance from the edge of the end fastener cover plate to the end of the overlapped longitudinal horizontal bar is not less than 100mm.
[0074] S3.3, a horizontal bar is set at the main node, connected with right-angle fasteners and it is strictly forbidden to remove it. The center distance between the two right-angle fasteners at the main node is not more than 150mm. The horizontal bars at non-main nodes on the working layer are set at equal intervals according to the needs of supporting scaffolding boards, and the maximum spacing is not more than 1 / 2 of the longitudinal distance;
[0075] S3.4, scaffolding columns for steel structure installation are set on the bottom plate of the columns, and other scaffolding columns are placed on wooden pads, that is, a 5mm thick 150*150mm steel plate welded with a 20mm diameter and 200mm long steel pipe for protection;
[0076] S3.5. Connection of vertical poles. At the top layer, lap joint is used; for the rest of each layer and each step, butt fasteners are used for connection. The butt fasteners on the vertical poles are staggered. The joints of two adjacent vertical poles are not set within the same step. The distance between two separated joints of every other vertical pole within the same step is staggered by no less than 500 mm in the height direction; the distance from the center of each joint to the main node is not greater than 1 / 3 of the step distance; the lap length is not less than 1 m. Three rotary fasteners are used for fixation, and the distance from the edge of the end fastener cover plate to the end of the pole is not less than 100 mm; the transverse spacing of the vertical columns of the full hall scaffold is 1.8 m, and the step distance of the scaffold is 1.5 m; the longitudinal spacing of the vertical poles is 1.8 m; for the double-row scaffold, the longitudinal spacing of the vertical poles is 1.8 m, the transverse spacing of the vertical poles is 1.8 m, the step distance of the vertical poles is 1.5 m, and single vertical pipes are used for the vertical poles of the scaffold.
[0077] As a preferred solution, further, S4 is specifically as follows:
[0078] S4.1. The footboards are laid flat and stable and tied and fixed; the footboards are laid butt-joint flat; at the butt joint, the distance from the two supporting cross bars below it should be controlled between 100 and 150 mm; for the butt fasteners used to connect the main cross bars, avoid setting the openings upward to prevent rainwater from entering.
[0079] As a preferred solution, further, S5 is specifically as follows:
[0080] S5.1. The double-row scaffold is provided with scissors braces and transverse diagonal bars for support;
[0081] S5.2. The overall tie rods such as scissors braces and diagonal bars are set up together with the erected scaffold; the width of each scissors brace is not less than 4 spans and not less than 6 m, and the angle between the diagonal bar and the ground is between 45° and 60°.
[0082] As a preferred solution, further, S7 is specifically as follows:
[0083] S7.1. The demolition sequence layer by layer is: safety net, toe board, guardrail, footboard, scissors brace, small cross bar, large cross bar and vertical pole, and then cycle the above sequence;
[0084] S7.2. Turn up the footboards from the outside to the inside and stand them up;
[0085] S7.3. After keeping the vertical pole, then remove the last two fasteners;
[0086] S7.4. First remove the fasteners in the middle of the large cross bar, diagonal brace and scissors brace, then support the middle part, and then untie the end fasteners;
[0087] S7.5. First use temporary support columns for support, and then remove the cast braces;
[0088] S7.6. Timely remove and transport away the loosened rod fittings.
[0089] The pad and rubber clamp in this case are prior art, and the pad has the same structure and connection method as in the cited document. As long as the pad and rubber clamp meet the requirements of this case, they are not limited to a single model.
[0090] Working principle: The electrical components in this application are all connected to the power supply and control switch when in use. After the present invention is installed, first check the installation and fixation of the present invention and the safety protection, and then it can be used; necessary preparations need to be made before construction. Before erection, the scaffolding pole accessories entering the site must be strictly inspected, and the use of pole accessories with unqualified specifications and quality is prohibited; wear life jackets when working on the dock platform, and each work point is equipped with monitoring and lifebuoys, life ropes, etc. Workers working on the scaffolding wear labor protection shoes and wear safety belts. The safety belts should be hung high and used low. For the convenience of operation and safety, at least three scaffolding boards are laid under the feet, and they are laid steadily. When the scaffolding cannot be laid temporarily for footing or grasping, the gripping rods should be stable frame parts; the free vertical poles located above the vertical pole joints are not used as gripping poles;
[0091] Seasonal construction protection measures: The construction period is the season when typhoons are less frequent in the local area, so typhoon prevention measures need to be taken. During the rainy season, operations should be carried out, mainly to prevent electric shock, lightning, collapse and strong winds. The power cord should use wires other than bare wires and plastic wires, and should not be in contact with the ground. The distribution box should be made of rainproof and waterproof materials, and the electrical layout should comply with regulations. Damaged electrical components should be repaired in time to avoid exposure of live electricity. The metal casing of electromechanical equipment should be grounded or zeroed for protection. When using hand-held power tools and mechanical equipment, qualified leakage protectors should be installed, and lightning protection devices should be installed on scaffoldings that are higher than buildings. In the thunderstorm season, anti-slip measures should be set for on-site scaffolding boards, ramp boards, and work platforms. Anti-slip adjustments should be set on ramp boards to prevent workers from slipping on rainy days. In windy weather, temporary buildings, scaffolding and other windproof safety measures at the construction site should be inspected and reinforced. Before re-construction, check the on-site equipment and facilities, especially special construction equipment and important facilities, and use them only after they are in good condition.
[0092] During construction, scaffolding is built from the ground around the equipment, and scaffolding work platforms are built according to the installation needs on site. The construction process is divided into ground-type scaffolding and suspended scaffolding.
[0093] The erection process of the floor-standing scaffold is as follows: Place the base plate 1 on the ground for installation protection, then determine the position of the passage opening. After determining the position of the passage opening, place the base and the bottom horizontal bar. After moving and fixing the position of the column foot pad 8, erect the columns one by one, and immediately fasten the columns to the bottom horizontal bar for temporary fixation. Then install the small bottom horizontal bar and fasten it to the column or the bottom horizontal bar. Install the first-step small horizontal bar, making the small horizontal bar fasten to each column. Install the first-step large horizontal bar, the second-step small horizontal bar and the second-step large horizontal bar. Then install the diagonal brace and the third and fourth-step small horizontal bars and large horizontal bars, connecting the diagonal brace and the third and fourth-step small horizontal bars and large horizontal bars to the columns. Then erect the cross bracing, lay the scaffold boards and build the ramp; The scaffold passage needs to be fully paved, and railings need to be set on both sides of the passage, with a gap less than 30 mm, and fixed at both ends, with an extension length of 15 - 20 cm;
[0094] The erection process of the suspended scaffold is as follows: Place the I-beam cantilever beam, and successively erect the bottom columns from the foot to both sides. The bottom end of the column is fastened and fixed to the longitudinal bottom horizontal bar. Then install the transverse bottom horizontal bar and fix it to the column. After erecting three to four columns on each side, immediately install the first-step longitudinal horizontal bar and the transverse horizontal bar. The first-step longitudinal horizontal bar is fastened and fixed to the column. Then correct the verticality of the column and the horizontality of the horizontal bar to meet the requirements, and tighten the fastener bolts forcefully to form the starting section of the framework. Then extend and erect forward in turn according to the above requirements until the first erection is completed in a circle; After the circle is completed, comprehensively check the structural quality once, strictly ensure the design requirements and the structural quality, set the connecting wall bars, and erect the second step and the third step according to the procedures and requirements of the first step, and so on. Install the cross bracing in time during the erection process, erect the cross bars between the operation layers, lay the scaffold boards and erect the railings of the operation layer, and fully enclose the toe boards and the dense mesh; The suspended scaffold uses trapezoidal beam clamps and right-angle fasteners to fix the steel beam and the scaffold poles. The erection height of the scaffold platform is about 500 mm below the elevation of the top of the steel beam, the railing height is 1200 mm, and the height of the toe board is 180 mm; One inclined ladder is set for every 30 meters on the pipe gallery scaffold; After the erection of the first layer of the scaffold is completed, start erecting the second layer of the scaffold. The inclined ladder of the second layer of the scaffold is erected into a Z-shaped scaffold on the basis of the inclined ladder of the first layer, and complete the erection work of the above scaffolds in turn;
[0095] When demolishing the scaffold, before demolition, comprehensively inspect the scaffold to be demolished. According to the inspection results, draw up an operation plan. Before carrying out the demolition operation, establish a unified command and conduct technical safety disclosure to the operation personnel: the steps and methods of demolition, safety measures, material stacking location, labor organization arrangement, to ensure the safe and smooth progress of the demolition operation. The demolition sequence layer by layer is: safety net, toe board, safety railing, scaffold board, cross bracing, small horizontal bar, large horizontal bar, vertical pole. Cycle the above sequence. In case of special climates such as strong wind and rain, stop the demolition of the scaffold. It is strictly prohibited to demolish at night.
[0096] For those skilled in the art, it is obvious that the present invention is not limited to the details of the above-mentioned exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or basic characteristics of the present invention. Therefore, from any point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is defined by the appended claims rather than the above description. Therefore, all changes falling within the meaning and scope of the equivalent elements of the claims are intended to be included in the present invention. Any reference signs in the claims should not be construed as limiting the claimed rights involved.
[0097] In the description of the present invention, the term "a plurality of" means two or more unless otherwise clearly defined. The orientation or positional relationship indicated by terms such as "upper", "lower", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation of the present invention. The terms "connection", "installation", "fixation", etc. should all be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0098] In the description of the present invention, the description of terms such as "one embodiment", "some embodiments", "specific embodiments", etc. means that the specific features, structures, materials or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present invention. In the present invention, the schematic expressions of the above terms do not necessarily refer to the same embodiment or instance. Moreover, the specific features, structures, materials or characteristics described can be combined in a suitable manner in any one or more embodiments or examples.
[0099] The above are only the preferred embodiments of the present invention and are not used to limit the present invention. For those skilled in the art, the present invention can have various changes and modifications. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A scaffold erection and dismantling method, characterized in that: The following steps are involved: S1, positioning and laying out the lines as required, placing two pads (1) on the positioning lines respectively, and arranging column pads (8) on the pads (1), and a sliding connection mechanism is arranged between the pads (1) and the column pads (8); S2, inserting the columns into the column pads (8), and setting longitudinal and transverse sweeping rods between the columns; S3, erecting the scaffolding structure, which is divided into erecting the longitudinal horizontal bar structure and erecting the transverse horizontal bar structure, and the longitudinal horizontal bars and the transverse horizontal bars are laid from bottom to top; S4, install scaffolding, toeboards and guardrails; S5, continuously erect scissor braces and diagonal bars, and the integral tie rods such as scissor braces and diagonal bars are set up simultaneously with the erected racks; S6, setting a wall connecting rod, and fixing the wall connecting rod to the horizontal rod and the vertical rod through fasteners; S7, dismantling the scaffolding, dismantling the scaffolding layer by layer from top to bottom; S8, the dismantled rod accessories are gathered on the adjacent undismantled rack surface, tied up and then hung down.
2. The scaffolding erection and dismantling method according to claim 1, characterized in that: The sliding connection mechanism comprises: A vertical block (2), the vertical block (2) is installed at the center of the top end of the pad (1), and the vertical block (2) is a rectangular structure; Slide grooves (3), two slide grooves (3) are symmetrically provided on the outer walls of both sides of the vertical block (2), and the slide grooves (3) are rectangular grooves; An inner sliding block (4), the sliding groove (3) is slidably connected with the inner sliding block (4), and the four corners of the inner sliding block (4) are smooth arc-shaped structures; A side slide plate (5), one end of the inner slide block (4) extends out of the slide groove (3), the extended end of the inner slide block (4) is welded with a side slide plate (5), and the side slide plate (5) is fitted with the vertical block (2); A support plate (6), the top ends of the two side slides (5) are welded with a support plate (6), a reinforcing rib (7) is welded between the support plate (6) and the side slides (5), the top end of the support plate (6) is welded with the column pad (8), and the support plate (6) is slidably fitted with the vertical block (2); Grooves (9), the inner top wall and the inner bottom wall of the slide groove (3) are both provided with a plurality of slide grooves (9), and the upper and lower slide grooves (9) correspond to each other one by one; A rubber clamp (10), the rubber clamp (10) is fixedly installed in the slot (9), and the round head of the rubber clamp (10) extends out of the slot (9); A card slot (11) is provided at the center point of the top end and the bottom end of the inner sliding block (4), and the card slot (11) is adapted to the rubber card head (10).
3. The scaffolding erection and dismantling method according to claim 1, characterized in that: The S1 is specifically: S1.1, Perimeter scaffolding starts from one corner and extends to both sides to form a circle; Linear scaffolding starts from one end and extends to the other end.
4. The scaffolding erection and dismantling method according to claim 1, characterized in that: The S2 is specifically: S2.
1. Erect the vertical poles in sequence according to the positioning, and connect and fix the vertical poles with the longitudinal and transverse sweeping poles.
5. The scaffolding erection and dismantling method according to claim 1, characterized in that: The S3 is specifically: S3.1, install the first step of longitudinal and transverse horizontal bars, correct the verticality of the vertical bars, fix them, and continue to erect upwards; S3.2, the longitudinal horizontal bars are connected by butt fasteners, the joint positions are staggered, and the joints of two adjacent longitudinal horizontal bars are set at different spans; S3.3, a transverse horizontal bar is set at the main node and connected with right-angle fasteners; S3.4, scaffolding columns for steel structure installation are set on the base plate of the columns, and other scaffolding columns are set on wooden pads; S3.5, the vertical poles are extended, the top of the top layer adopts overlap joints, and the joints of the remaining layers and steps are connected with butt fasteners. The butt fasteners on the vertical poles are arranged in a staggered manner.
6. The scaffolding erection and dismantling method according to claim 1, characterized in that: The S4 is specifically: S4.1, Scaffolding boards shall be laid flat and firmly, and tied and fixed; Scaffolding boards shall be laid flat by butt joint.
7. The scaffolding erection and dismantling method according to claim 1, characterized in that: The S5 is specifically: S5.1, double-row scaffolding is provided with scissor braces and transverse diagonal bars for support; S5.
2. Integral tie rods such as scissor braces and diagonal rods shall be installed together with the erected racks.
8. The scaffolding erection and dismantling method according to claim 1, characterized in that: The S7 is specifically: S7.1, the order of dismantling layer by layer is: safety net, footboard, self-defense rail, scaffolding board, scissor brace, small crossbar, large crossbar and vertical pole, and then repeat the above order; S7.2, turn the scaffolding board from the outside to the inside and stand it upright; S7.3, after securing the pole, remove the last two buckles; S7.4, first remove the fasteners in the middle of the large crossbar, diagonal brace, and scissor brace, then hold the middle and unfasten the end fasteners; S7.5, first try to use temporary bracing props for support, and then remove the castors; S7.
6. Remove and transport loosened rod accessories promptly.
Citation Information
Patent Citations
Auxiliary device for erecting and disassembling scaffold
CN221627614U