Wall drilling and grouting device for house building
The design of the adjustment mechanism and sliding block of the wall drilling and grouting device for house construction solves the problems of poor sealing and low efficiency in traditional drilling and grouting, realizes automatic sealing and efficient grouting, and meets the needs of emergency repairs.
Patent Information
- Application Number
- CN202511100769.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-07
- Publication Date
- 2025-09-05
- Estimated Expiration
- 2045-08-07
AI Technical Summary
During the traditional drilling and grouting process, the hole diameter and depth drilled by the drilling device are prone to deviations, the seal is not compatible, causing the grouting liquid to leak out, affecting the grouting quality and repair efficiency, and the separate operations lead to low efficiency.
A wall drilling and grouting device for house construction is used. The sealing sleeve and the sliding block are driven by an adjustment mechanism to achieve automatic sealing during the drilling process, ensuring a tight connection between the grouting pipe and the hole wall. The sliding block can be telescopically controlled by the cooperation of an air bag and a spring, thereby improving the sealing effect and grouting efficiency.
Automatic sealing is achieved during the drilling process, which improves the grouting quality and repair efficiency, simplifies the operation steps, and meets emergency repair needs.
Smart Images

Figure CN120592492A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building drilling and grouting equipment, and in particular to a wall drilling and grouting device for building construction. Background Art
[0002] When repairing a leaking wall, a drilling device is first used to drill grouting holes in the area of the wall corresponding to the leak, and then a grouting device is used to inject grout into the holes. Currently, the grouting device includes a grouting pipe, which is connected to a liquid pump via a pipeline. Before grouting the wall, a corresponding tubular seal is inserted into the grouting hole using a corresponding tool. This seal seals the gap between the grouting pipe and the hole wall during the subsequent grouting process.
[0003] However, the traditional drilling and grouting process relies on manual operation, and the hole diameter and hole depth drilled by the drilling device are prone to deviations. During the subsequent insertion of the seal, the specifications of the seal are not suitable for the hole diameter of the grouting hole, and gaps are prone to occur. As a result, the grouting process does not reach the rated pressure, and the slurry flows out of the grouting hole, affecting the quality of the grouting and reducing the effect of the wall repair. In addition, the sealing and grouting processes are operated separately, and the work content is large, which leads to reduced efficiency in wall repair and makes it difficult to adapt to the situation of completing emergency repairs of leaking walls within the rated time. Summary of the Invention
[0004] The present application proposes a wall drilling and grouting device for house construction, which has the advantages of improving the sealing effect while improving the repair efficiency, and is used to solve the problems of poor sealing of grouting pipes and low efficiency of drilling and grouting operations caused by manual drilling and grouting.
[0005] To achieve the above-mentioned purpose, the present application adopts the following technical solution: a wall drilling and grouting device for building construction, comprising a mounting seat, a No. 2 movable seat being slidably provided on one side of the top of the mounting seat, a grouting pipe being fixedly provided on the top of the No. 2 movable seat, a sealing sleeve being provided on one side of the grouting pipe, a flexible pad being provided on one side of the movable sleeve of the sealing sleeve, a movable ring being provided on one side of the movable sleeve of the sealing sleeve, an inner tube being provided on the inner side of the grouting pipe, a No. 2 partition being capable of allowing slurry to pass through being fixedly sleeved on one side of the sealing sleeve, and a sliding block being provided on one side of the sliding sleeve of the inner tube; It also includes an adjustment mechanism, which can drive the moving ring to approach the corresponding distance of the sealing sleeve according to the moving position of the No. 2 moving seat, and cooperate with the sealing sleeve to extrude the two side end faces of the flexible pad. The adjustment mechanism can drive the sliding block to retract toward the inner tube after the No. 2 moving seat grouting action moves forward to its position, and can drive the sliding block to reset and extend out of the inner tube during the resetting process of the No. 2 moving seat.
[0006] Furthermore, the adjustment mechanism includes a No. 1 partition, which is fixedly connected to the grouting pipe and the inner pipe. The No. 1 partition is provided with a through hole that is controlled to open and close by a control valve. A movable sleeve on one side of the sealing sleeve is provided with a movable ring. A movable sleeve is threadedly sleeved on one side of the outer side of the sealing sleeve. A rotating ring is slidably sleeved on the outer side of the movable sleeve. A movable block that can be sleeved with the sealing sleeve is provided on one side of the grouting pipe wall. A through hole for slurry to pass through is provided on the No. 2 partition, and a No. 1 movable seat is slidably provided on one side of the top of the mounting seat, and a drilling mechanism is fixedly provided on the top of the No. 1 movable seat.
[0007] Furthermore, the outer wall of the movable sleeve is a regular polygon, the adjustment mechanism also includes a shrinkage bag, the side of the sliding block away from the axis of the inner tube is an inclined surface, the sliding block is located in the inner tube and is slidably connected to a connecting rod on one side, the connecting rod is T-shaped, one end of the connecting rod is fixedly connected to the shrinkage bag, the end of the connecting rod close to the axis of the inner tube is slidably sleeved with a fixed block, the fixed block is fixedly connected to the inner tube, and a spring is provided between the fixed block and the sliding block.
[0008] Furthermore, the adjustment mechanism also includes an air cylinder, which is fixedly connected to the No. 2 movable seat, a vent hole is opened on one side of the air cylinder, a sliding plug is slidably provided on the inner side of the air cylinder, an air inlet pipe is fixedly provided on the other side of the air cylinder, an air outlet pipe is fixedly provided on one side of the air cylinder, a one-way valve is fixedly provided on the air inlet pipe, a connecting pipe is fixedly connected to one side of the inner tube, the air outlet pipe is connected to the connecting pipe through a pipeline, a pressure relief pipe is fixedly connected to one side of the inner tube, an electromagnetic valve is fixedly provided on the pressure relief pipe, and the tube hole of the inner tube is connected to the cavity of the contraction bag.
[0009] Furthermore, a sealing block for sealing the corresponding through hole is slidably sleeved on one side of the second partition, and a spring is fixedly connected between the sealing block and the end of the sealing sleeve.
[0010] Furthermore, the adjustment mechanism also includes a guide rod, which is fixedly connected to the air cylinder, and an adjustment rod is slidably sleeved on the outer side of the guide rod, and a spiral adjustment groove is provided on the rod body of the adjustment rod. A transmission mechanism is provided on one side of the No. 2 movable seat, and the transmission mechanism is connected to an adjustment block. A contact switch is fixedly provided on one end of the guide rod close to the air cylinder, and the contact switch is electrically connected to the solenoid valve of the pressure relief pipe. A spring is movably provided on the side of the sliding plug close to the air inlet pipe, and a moving rod is fixedly connected to one side of the sliding plug.
[0011] Furthermore, the transmission mechanism includes an external gear and a ratchet gear, both of which are rotatably connected to the No. 2 movable seat, and a stopping claw is provided on the inner side of the external gear for rotation, and a spring is fixedly connected between the stopping claw and the external gear, and the stopping claw cooperates with the corresponding spring to enable the ratchet gear to drive the external gear to rotate in one direction, and the ratchet gear is fixedly connected to the adjustment block, and the adjustment block is slidably connected to the adjustment slot.
[0012] Furthermore, a connecting gear is rotatably provided on one side of the grouting pipe, a transmission ring is fixedly connected to one side of the connecting gear, a transmission key is fixedly provided on the inner side of the transmission ring, the transmission ring and the rotating ring are slidingly connected, a connecting groove is opened on one side of the rotating ring, and the transmission key is slidably connected to the connecting groove.
[0013] Furthermore, a spring is provided between the rotating ring and the connecting gear, a spring is provided between the movable block and the grouting pipe for pushing the movable block close to the sealing sleeve, and the connecting gear and the external gear are meshed with each other.
[0014] The beneficial effects of the present invention are as follows: The present application provides a wall drilling and grouting device for house construction. The adjusting rod drives the adjusting rod to rotate when the No. 2 movable seat approaches the wall, and the transmission mechanism drives the connecting gear to rotate in one direction. The connecting gear drives the movable sleeve to screw into the end of the sealing sleeve, so that the flexible pad is squeezed to seal the gap between the grouting hole and the sealing sleeve during the process of inserting the sealing sleeve into the grouting hole, so that the drilling and grouting device can seal when the inner wall of the drilled hole is uneven, and the sealing effect is improved.
[0015] The present application provides a wall drilling and grouting device for house construction, in which a sliding block is extended and retracted in cooperation with a corresponding spring, a shrinkage bag and a connecting rod. When the sealing sleeve is pre-sleeved on the grouting pipe, the sliding block is driven to remain extended, so that when the No. 2 partition passes through the sliding block, the inclined surface is pushed to drive the slider to retract, and the subsequent extension of the sliding block is used to limit the axial movement of the sealing sleeve. After the sealing sleeve is inserted, the shrinkage bag is inflated to drive the sliding block to extend, thereby improving the overall drilling and grouting efficiency while allowing the sealing sleeve to remain in the grouting hole after grouting to serve as a seal for the grouting hole. The sealing during the grouting process is completed in cooperation with the transmission mechanism, thereby further improving the reliability of the drilling and grouting equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are only embodiments of the present invention. Those skilled in the art can also derive other drawings based on the provided drawings without inventive work. Figure 1This is a schematic diagram of the overall structure of this application; Figure 2 This is a structural diagram of the second mobile seat of this application; Figure 3 This is a structural diagram of the transmission mechanism of this application; Figure 4 This is a schematic diagram of the structural cross-section of the grouting pipe in this application; Figure 5 For this application Figure 4 A magnified view of the structure at point A; Figure 6 This is a structural diagram of the rotating ring of this application; Figure 7 This is a structural diagram of the sliding block of this application; Figure 8 This is a schematic diagram of the ratchet gear structure of this application; Figure 9 This is a schematic cross-sectional diagram of the structure of the gas cylinder in this application; Figure 10 This is a schematic diagram of the structure of the adjustment rod in this application.
[0017] In the figure: 1. Mounting seat; 2. No. 1 movable seat; 3. Drilling mechanism; 4. No. 2 movable seat; 5. Grouting pipe; 6. Sealing sleeve; 7. Flexible pad; 8. Transmission mechanism; 801. External gear; 802. Ratchet gear; 803. Stop pawl; 9. Rotating ring; 10. Transmission ring; 11. Connecting gear; 12. Moving sleeve; 13. No. 1 partition; 14. Inner pipe; 15. No. 2 partition; 16. Moving ring; 17. Connecting Connecting groove; 18. Transmission key; 19. Movable block; 20. Sealing block; 21. Shrinkage bag; 22. Sliding block; 23. Connecting rod; 24. Fixed block; 25. Adjusting rod; 26. Adjusting groove; 27. Adjusting block; 28. Guide rod; 29. Contact switch; 30. Air cylinder; 31. Sliding plug; 32. Moving rod; 33. Vent; 34. Inlet pipe; 35. Outlet pipe; 36. Pressure relief pipe; 37. Connecting pipe. DETAILED DESCRIPTION
[0018] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0019] Example 1, as Figure 1-Figure 7 and Figure 9A wall drilling and grouting device for building construction includes a mounting base 1, which is used to carry a drilling and grouting assembly. The mounting base 1 is installed on a horizontal linear guide rail module supporting a lifting platform, so that the mounting base 1 can adjust its height and horizontal position. For example, the supporting lifting platform is configured as a working trolley, and a lifting base is provided on the working trolley. The lifting base is driven up and down by an electric push rod. When the working trolley drives the mounting base 1 to move to the working position, the horizontal linear guide rail module drives the mounting base 1 to move horizontally, which is used to switch the corresponding positions of the drilling assembly, the grouting assembly and the wall. For example, the horizontal linear guide rail module is configured as a lead screw and a linear guide rail driven by a motor, and the lead screw transmission drives the mounting base 1 to move along the linear guide rail.
[0020] A No. 1 movable seat 2 is slidably provided on one side of the top of the mounting seat 1, and a drilling mechanism 3 is fixedly provided on the top of the No. 1 movable seat 2. The No. 1 movable seat 2 is driven by an electric push rod to move horizontally relative to the mounting seat 1 to adjust the distance between the drilling mechanism 3 and the wall. The drilling mechanism 3 is used to drill holes in the wall. For example, the drilling mechanism 3 can be set as a drill barrel driven by a motor. A No. 2 movable seat 4 is slidably provided on one side of the top of the mounting seat 1. The No. 2 movable seat 4 is driven by an electric push rod to move horizontally relative to the mounting seat 1. A grouting pipe 5 is fixedly provided on the top of the No. 2 movable seat 4. The grouting pipe 5 is connected to the liquid pump through a pipeline. Figure 4 A partition plate 13 is fixedly sleeved on one side of the grouting pipe 5. The partition plate 13 is provided with a through hole for the slurry to pass through. A control valve is provided on the through hole to control the opening and closing of the through hole.
[0021] A sealing sleeve 6 is provided on one side of the grouting pipe 5, and a flexible pad 7 is provided on one side of the sealing sleeve 6. The sealing sleeve 6 is used to cooperate with the flexible pad 7 to seal the gap between the grouting pipe 5 and the grouting hole. A movable sleeve 16 is provided on one side of the sealing sleeve 6. The movable sleeve 16 is located on one side of the flexible pad 7 and is used to cooperate with one end face of the sealing sleeve 6 to clamp the two ends of the flexible pad 7. A movable sleeve 12 is threaded on one side of the outer side of the sealing sleeve 6. The movable sleeve 12 can be screwed into the side close to the flexible pad 7 by rotating. Figure 6 The outer wall of the movable sleeve 12 is a regular polygon, and the outer side of the movable sleeve 12 is slidably sleeved with a rotating ring 9. The inner wall shape of the rotating ring 9 is adapted to the outer wall shape of the movable sleeve 12. The rotating ring 9 drives the movable sleeve 12 to rotate while the movable sleeve 12 can move axially relative to the rotating ring 9.
[0022] A movable block 19 is provided on one side of the wall of the grouting pipe 5. Figure 7The movable block 19 can be inserted into the end of the sealing sleeve 6 and slidably connected to the sealing sleeve 6. The movable block 19 is used to limit the rotation of the sealing sleeve 6 relative to the grouting pipe 5. The inner tube 14 is fixedly connected to the middle position of the No. 1 partition 13. The No. 2 partition 15 is fixedly connected to one side of the sealing sleeve 6. The No. 2 partition 15 is provided with a through hole for the passage of slurry. The number of through holes corresponding to the No. 2 partition 15 is set to a number, see Figure 5 A shrinkage bag 21 is provided on one side of the wall of the inner tube 14. The shrinkage bag 21 has a tendency to shrink. A sliding block 22 is provided on one side of the sliding sleeve of the inner tube 14. The number of sliding blocks 22 is set to at least one. The sliding blocks 22 are arranged at the outer side of the inner tube 14 in a uniformly spaced manner. The side of the sliding block 22 away from the axis of the inner tube 14 is an inclined surface. The sliding block 22 is used to limit the axial movement of the No. 2 partition 15 away from the grouting pipe 5, thereby limiting the axial movement of the sealing sleeve 6 in the corresponding direction relative to the grouting pipe 5.
[0023] The sliding block 22 is located on one side of the inner tube 14 and is slidably connected to a connecting rod 23. The connecting rod 23 is T-shaped. The connecting rod 23 can move radially relative to the sliding block 22 in the inner tube 14 without separating from the sliding block 22. One end of the connecting rod 23 is fixedly connected to the shrinkage bag 21, and the end of the connecting rod 23 close to the axis of the inner tube 14 is slidably sleeved with a fixed block 24. The fixed block 24 is fixedly connected to the inner tube 14. A spring is provided between the fixed block 24 and the sliding block 22. The spring is used to push the sliding block 22 out of the inner tube 14. The shrinkage bag 21 can overcome the spring force corresponding to the sliding block 22 to drive the sliding block 22 to shrink into the inner tube 14, and the No. 2 partition 15 is movably sleeved with the inner tube 14.
[0024] When the cam 16 is in the state of being threadedly sleeved with the sealing sleeve 6, the movable ring 16 and the sealing sleeve 6 cooperate to be in the state of clamping the flexible pad 7. At this time, the flexible pad 7 remains flat, and the sealing sleeve 6 is sleeved on the grouting pipe 5 in advance, so that the movable block 19 is sleeved with the sealing sleeve 6, and the sealing sleeve 6 and the end face of the grouting pipe 5 form a seal. At this time, the rotating ring 9 and the movable sleeve 12 are sleeved together. During the sleeve connection process of the sealing sleeve 6, the sealing sleeve 6 drives the second partition 15 to sleeve on the outer side of the inner tube 14. When the second partition 15 contacts the inclined surface of the sliding block 22, the sliding block 22 is driven to overcome the corresponding spring force to retract toward the inner tube 14 until the sealing sleeve 6 is sleeved in place. At this time, the second partition 15 is out of contact with the sliding block 22, and the corresponding spring pushes the sliding block 22 to extend. The sliding block 22 limits the axial movement of the second partition 15 relative to the grouting pipe 5 to complete the pre-sleeving of the sealing sleeve 6, thereby simplifying the installation steps of the seal, improving the efficiency of the overall grouting, and saving manpower.
[0025] Adjust the mounting seat 1 to the corresponding position, drive the drilling mechanism 3 close to the wall, and drill the grouting hole on the wall. After the drilling is completed, drive the drilling mechanism 3 to break away from the contact with the wall, adjust the horizontal position of the mounting seat 1, and the mounting seat 1 drives the grouting pipe 5 to move and switch the corresponding position of the grouting pipe 5, so that the axis of the grouting pipe 5 is collinear with the axis of the grouting hole. The No. 2 moving seat 4 moves close to the wall through the electric push rod, and the No. 2 moving seat 4 drives the grouting pipe 5 close to the wall. The transmission drives the end of the sealing sleeve 6 to insert the rated length into the grouting hole, rotate the rotating ring 9, and the rotating ring 9 rotates with The movable sleeve 12 rotates, and the movable sleeve 12 rotates and screws in relative to the sealing sleeve 6. When it is screwed into place, the movable sleeve 12 is disengaged from the rotating ring 9. The movable sleeve 12 is screwed in and drives the movable ring 16 to approach the end of the sealing sleeve 6. The movable ring 16 cooperates with the sealing sleeve 6 to squeeze the flexible pad 7, so that the middle part of the flexible pad 7 is arched, thereby increasing the sealing pressure of the flexible pad 7 and expanding the sealing diameter of the flexible pad 7, so that the flexible pad 7 can form a seal with the irregular grouting hole on the inner wall and the grouting pipe 5, simplifying the sealing steps while improving the sealing effect and improving the reliability of the drilling grouting device.
[0026] A sealing block 20 for sealing the corresponding through hole is slidably sleeved on one side of the No. 2 partition 15. The position of the sealing block 20 corresponds to the through hole of the No. 2 partition 15. A spring is fixedly connected between the sealing block 20 and the end of the sealing sleeve 6. The spring corresponding to the sealing block 20 is used to push the sealing block 20 close to the No. 2 partition 15 to block the corresponding through hole. After the sealing is completed, the control valve corresponding to the No. 1 partition 13 is opened, and the slurry is extracted by the liquid pump through the grouting pipe 5 through the through hole corresponding to the No. 1 partition 13. The slurry overcomes the elastic force of the spring corresponding to the sealing block 20 and pushes the sealing block 20 away from the corresponding through hole. The slurry enters the grouting hole through the gap between the sealing block 20 and the sealing sleeve 6 until the pressure of the pumped slurry reaches the rated value and the slurry flows out through the leaking gaps in the wall. The grouting is completed, the pumping of the slurry is stopped, the control valve is closed, and the sealing block 20 closes the through hole of the No. 2 partition 15 under the push of the corresponding spring to prevent the slurry from flowing back when the grouting pipe 5 is withdrawn from the grouting hole.
[0027] A gas cylinder 30 is fixedly provided on one side of the second movable seat 4. Figure 9 A vent hole 33 is provided on one side of the cylinder 30, a sliding plug 31 is slidably provided on the inner side of the cylinder 30, an air inlet pipe 34 is fixedly provided on the other side of the cylinder 30, an air outlet pipe 35 is fixedly provided on one side of the cylinder 30, and a one-way valve is fixedly provided on the air inlet pipe 34 for gas to enter the cylinder 30 in one direction through the air inlet pipe 34, see Figure 4A connecting pipe 37 is fixedly connected to one side of the inner tube 14, and the air outlet pipe 35 is connected to the connecting pipe 37 through a pipeline. A pressure relief pipe 36 is fixedly connected to one side of the inner tube 14, and a solenoid valve is fixedly provided on the pressure relief pipe 36. The tube hole of the inner tube 14 is connected to the cavity of the contraction bag 21. The air inlet pipe 34 and the air outlet pipe 35 are located on one side of the sliding plug 31, and the vent hole 33 is located on the other side of the sliding plug 31.
[0028] After the grouting is completed, the solenoid valve opens, the contraction bag 21 contracts, and the contraction bag 21 drives the connecting rod 23 to move, and the connecting rod 23 drives the sliding block 22 to move and shrink into the inner tube 14, and the limit of the No. 2 partition 15 is removed. The No. 2 moving seat 4 moves to drive the grouting pipe 5 to exit the grouting hole, and the grouting is completed. The sliding plug 31 is controlled by the driving component to move to the side close to the air outlet pipe 35, and the rated amount of gas is filled into the contraction bag 21. The contraction bag 21 expands, and cooperates with the movement of the connecting rod 23 to remove the pull on the sliding block 22. The spring corresponding to the sliding block 22 drives the sliding block 22 to reset.
[0029] Example 2, as Figures 1-10 On the basis of the first embodiment, one end of the air cylinder 30 is fixedly connected to a guide rod 28 at the midpoint, and an adjusting rod 25 is slidably sleeved on the outer side of the guide rod 28. The rod body of the adjusting rod 25 is provided with a spiral adjusting groove 26. A transmission mechanism 8 is provided on one side of the second moving seat 4. The transmission mechanism 8 includes an external gear 801 and a ratchet gear 802. The ratchet gear 802 and the external gear 801 are both rotatably connected to the second moving seat 4. Figure 8 A stop pawl 803 is provided on the inner side of the outer gear 801 for rotation, and a spring is fixedly connected between the stop pawl 803 and the outer gear 801. The stop pawl 803 cooperates with the corresponding spring to enable the ratchet gear 802 to drive the outer gear 801 to rotate in one direction. An adjustment block 27 is fixedly connected to the inner side of the ratchet gear 802, and the adjustment block 27 is slidably connected to the adjustment slot 26. A contact switch 29 is fixedly provided on one end of the guide rod 28 close to the air cylinder 30, and the contact switch 29 is electrically connected to the solenoid valve of the pressure relief pipe 36. A spring is movably provided on the side of the sliding plug 31 close to the air intake pipe 34.
[0030] One side of the sliding plug 31 is fixedly connected to a moving rod 32, and the moving rod 32 extends out of the air cylinder 30 with the rod body. The number of the moving rod 32 is set to at least one, and the moving rod 32 is fixedly connected to the adjusting rod 25. A connecting gear 11 is rotatably provided on one side of the grouting pipe 5, and a transmission ring 10 is fixedly connected to one side of the connecting gear 11. A transmission key 18 is fixedly provided on the inner side of the transmission ring 10, and the transmission ring 10 is slidingly sleeved with the rotating ring 9. A connecting groove 17 is provided on one side of the rotating ring 9, and the transmission key 18 is slidingly connected with the connecting groove 17. A spring is provided between the rotating ring 9 and the connecting gear 11, and the spring corresponding to the rotating ring 9 is used to push the rotating ring 9 to maintain the sleeve with the moving sleeve 12. The movable block 19 is slidably connected to the grouting pipe 5, and the movable block 19 can slide axially without disengaging the grouting pipe 5. A spring for pushing the movable block 19 close to the sealing sleeve 6 is provided between the movable block 19 and the grouting pipe 5, and the connecting gear 11 and the outer gear 801 are meshed with each other.
[0031] In the process of the No. 2 movable seat 4 driving the grouting pipe 5 close to the wall, the sealing sleeve 6 is inserted into the grouting hole. At this time, the end of the adjusting rod 25 contacts the wall, and the No. 2 movable seat 4 continues to move, so that the guide rod 28 and the ratchet gear 802 move relative to the adjusting rod 25. The inner wall of the adjusting groove 26 corresponding to the adjusting rod 25 presses against the adjusting rod 25, driving the adjusting rod 25 to rotate relative to the No. 2 movable seat 4. The adjusting rod 25 rotates the one-way transmission to drive the outer gear 801 to rotate, and the movement of the grouting pipe 5 drives the connecting gear 11 to move synchronously. The rotation of the outer gear 801 drives the connecting gear 11 to rotate, and the connecting gear 11 drives the transmission ring 10 to rotate. The transmission ring 10 drives the rotating ring 9 to rotate through the transmission key 18, thereby rotating the movable sleeve 12, and driving the flexible pad 7 to shrink and arch during the process of the sealing sleeve 6 being inserted into the grouting hole.
[0032] When the sealing sleeve 6 is inserted, the adjusting rod 25 contacts and triggers the contact switch 29, and the contact switch 29 opens the corresponding solenoid valve, causing the contraction bag 21 to decompress and contract, and the transmission drives the sliding block 22 to contract, removing the limit on the No. 2 partition 15, to facilitate the subsequent withdrawal of the grouting pipe 5. When the No. 2 moving seat 4 drives the grouting pipe 5 to withdraw from the grouting hole, the spring corresponding to the sliding plug 31 drives the sliding plug 31 to slide and reset, and presses the air into the contraction bag 21 through the air outlet pipe 35, the connecting pipe 37 and the inner tube 14. When the sliding block 22 moves through the No. 2 partition 15, it drives the sliding block 22 to extend, thereby completing the telescopic control of the sliding block 22 and the end compression of the flexible pad 7 during the grouting process, further improving the efficiency of the grouting operation.
[0033] At the same time, the rotating ring 9 can move axially relative to the connecting gear 11, and the movable block 19 can move axially relative to the grouting pipe 5. When secondary grouting is required, the grouting pipe 5 is grouting based on the sealing sleeve 6 left during the first grouting of the sealing hole. When the movable sleeve 12 is loose, the movable sleeve 12 retreats a certain distance, and the grouting pipe 5 drives the rotating ring 9 to move. The rotating ring 9 rotates at the same time, so that the rotating ring 9 can resist the movable sleeve 12 and rotate, and the movable block 19 resists the sealing sleeve 6 and rotates, so that the rotating ring 9 is re-connected with the movable sleeve 12 of the retreated part, and the movable ring 16 is driven again to extrude the flexible pad 7 to ensure the sealing performance, improve the applicability of the drilling grouting device, and further improve the reliability of use.
[0034] The above description of the disclosed embodiments is intended to enable one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention is not limited to the embodiments shown herein but is intended to conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A wall drilling and grouting device for building construction, comprising a mounting seat (1), a second movable seat (4) being slidably provided on one side of the top of the mounting seat (1), characterized in that: A grouting pipe (5) is fixedly provided on the top of the No. 2 movable seat (4), a sealing sleeve (6) is provided on one side of the grouting pipe (5), a flexible pad (7) is provided on one side of the movable sleeve of the sealing sleeve (6), a movable ring (16) is provided on one side of the movable sleeve of the sealing sleeve (6), an inner pipe (14) is provided on the inner side of the grouting pipe (5), a No. 2 partition (15) capable of allowing slurry to pass through is fixedly sleeved on one side of the sealing sleeve (6), and a sliding block (22) is provided on one side of the sliding sleeve of the inner pipe (14); The adjusting mechanism further includes an adjusting mechanism, wherein the adjusting mechanism can drive the moving ring (16) to approach the sealing sleeve (6) by a corresponding distance according to the moving position of the No. 2 moving seat (4), and cooperate with the sealing sleeve (6) to squeeze the end faces of the flexible pad (7). The adjusting mechanism can drive the sliding block (22) to retract toward the inner tube (14) after the No. 2 moving seat (4) moves forward to the grouting position, and can drive the sliding block (22) to reposition and extend out of the inner tube (14) during the resetting process of the No. 2 moving seat (4).
2. A wall drilling and grouting device for building construction according to claim 1, characterized in that: The regulating mechanism comprises a No. 1 partition (13), the No. 1 partition (13) is fixedly connected to the grouting pipe (5) and the inner pipe (14), the No. 1 partition (13) is provided with a through hole controlled by a control valve, a movable sleeve on one side of the sealing sleeve (6) is provided with a movable ring (16), a movable sleeve (12) is threadedly sleeved on one side of the outer side of the sealing sleeve (6), and a rotating ring (9) is slidably sleeved on the outer side of the movable sleeve (12), a movable block (19) capable of being sleeved and connected with the sealing sleeve (6) is provided on one side of the wall of the grouting pipe (5), a through hole for slurry to pass through is opened on the No. 2 partition (15), a No. 1 movable seat (2) is slidably provided on one side of the top of the mounting seat (1), and a drilling mechanism (3) is fixedly provided on the top of the No. 1 movable seat (2).
3. A wall drilling and grouting device for building construction according to claim 2, characterized in that: The outer wall of the movable sleeve (12) is a regular polygon, and the adjustment mechanism further includes a shrinkage bag (21). The side of the sliding block (22) facing away from the axis of the inner tube (14) is an inclined surface. The side of the sliding block (22) located in the inner tube (14) is slidably connected with a connecting rod (23). The connecting rod (23) is T-shaped. One end of the connecting rod (23) is fixedly connected to the shrinkage bag (21). The end of the connecting rod (23) close to the axis of the inner tube (14) is slidably connected with a fixed block (24). The fixed block (24) is fixedly connected to the inner tube (14), and a spring is provided between the fixed block (24) and the sliding block (22).
4. A wall drilling and grouting device for building construction according to claim 2, characterized in that: The regulating mechanism further comprises an air cylinder (30), the air cylinder (30) being fixedly connected to the second movable seat (4), a vent hole (33) being provided on one side of the air cylinder (30), a sliding plug (31) being slidably provided on the inner side of the air cylinder (30), an air inlet pipe (34) being fixedly provided on the other side of the air cylinder (30), an air outlet pipe (35) being fixedly provided on one side of the air cylinder (30), a one-way valve being fixedly provided on the air inlet pipe (34), a connecting pipe (37) being fixedly connected to one side of the inner tube (14), the air outlet pipe (35) being connected to the connecting pipe (37) through a pipeline, a pressure relief pipe (36) being fixedly connected to one side of the inner tube (14), a solenoid valve being fixedly provided on the pressure relief pipe (36), and a tube hole of the inner tube (14) being communicated with the cavity of the contraction bag (21).
5. A wall drilling and grouting device for building construction according to claim 4, characterized in that: A sealing block (20) for sealing the corresponding through hole is slidably sleeved on one side of the second partition plate (15), and a spring is fixedly connected between the sealing block (20) and the end of the sealing sleeve (6).
6. A wall drilling and grouting device for building construction according to claim 4, characterized in that: The regulating mechanism further comprises a guide rod (28), the guide rod (28) being fixedly connected to the air cylinder (30), an adjusting rod (25) being slidably sleeved on the outer side of the guide rod (28), a spiral regulating groove (26) being provided on the rod body of the regulating rod (25), a transmission mechanism (8) being provided on one side of the second movable seat (4), the transmission mechanism (8) being connected to an regulating block (27), a contact switch (29) being fixedly provided on one end of the guide rod (28) close to the air cylinder (30), the contact switch (29) being electrically connected to the solenoid valve of the pressure relief pipe (36), a spring being movably provided on one side of the sliding plug (31) close to the air inlet pipe (34), and a movable rod (32) being fixedly connected on one side of the sliding plug (31).
7. A wall drilling and grouting device for building construction according to claim 6, characterized in that: The transmission mechanism (8) comprises an external gear (801) and a ratchet gear (802), wherein the ratchet gear (802) and the external gear (801) are both rotatably connected to the second movable seat (4), a stop pawl (803) is provided on the inner side of the external gear (801), a spring is fixedly connected between the stop pawl (803) and the external gear (801), and the stop pawl (803) cooperates with the corresponding spring to enable the ratchet gear (802) to drive the external gear (801) to rotate in one direction, the ratchet gear (802) is fixedly connected to the adjustment block (27), and the adjustment block (27) is slidably connected to the adjustment slot (26).
8. A wall drilling and grouting device for building construction according to claim 7, characterized in that: A connecting gear (11) is rotatably provided on one side of the grouting pipe (5), a transmission ring (10) is fixedly connected to one side of the connecting gear (11), a transmission key (18) is fixedly provided on the inner side of the transmission ring (10), the transmission ring (10) is slidably sleeved with the rotating ring (9), a connecting groove (17) is provided on one side of the rotating ring (9), and the transmission key (18) is slidably connected to the connecting groove (17).
9. A wall drilling and grouting device for building construction according to claim 8, characterized in that: A spring is provided between the rotating ring (9) and the connecting gear (11), a spring for pushing the movable block (19) close to the sealing sleeve (6) is provided between the movable block (19) and the grouting pipe (5), and the connecting gear (11) and the external gear (801) are meshed with each other.
Citation Information
Patent Citations
Sequential slurry guide device for crack grouting and multifunctional slurry guide device for grouting
CN111927139A
Grouting method for coal mining
CN112855216A
Grouting and leaking stoppage auxiliary device and method for coping with water burst in underground construction
CN118498925A
Sealing device for goaf grouting
CN119663837A
Anti-blocking type side slope grouting drill bit
CN223088436U