Anti-seismic underground pipe gallery prefabricated structure and construction method thereof

By designing a buffer layer and shock-absorbing bracket in the prefabricated structure of the underground pipeline corridor, the problem of soil pressure concentration during vibration was solved, and the seismic performance was improved and the internal facilities were protected.

CN120625658APending Publication Date: 2025-09-12中交投资南京有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510924735.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-04
Publication Date
2025-09-12

AI Technical Summary

Technical Problem

The existing prefabricated structure of the underground pipeline gallery cannot effectively release the vibration force when vibrating, resulting in excessive pressure on the outer wall of the assembly unit frame and damage to the internal pipes and lines.

Method used

A buffer layer is designed between the rectangular outer frame and the inner frame. The buffer layer is equipped with a buffer partition and a buffer spring. A shock-absorbing bracket is provided inside the inner frame. The arch design disperses the vibration force, and cast partitions and air holes are set at both ends of the inner frame to release pressure.

Benefits of technology

It effectively disperses vibration force, reduces the concentrated effect of soil cover pressure on the rectangular outer frame, protects the pipes and lines in the inner frame, and improves seismic performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120625658A_ABST
    Figure CN120625658A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-seismic underground pipe gallery prefabricated structure and a construction method thereof, and relates to the field of constructions.The anti-seismic underground pipe gallery prefabricated structure comprises a rectangular outer frame, an inner frame is arranged in the rectangular outer frame, a buffer layer is reserved between the rectangular outer frame and the inner frame, a buffer component is arranged in the buffer layer, and the buffer component comprises a buffer interlayer; a plurality of sets of buffer springs are distributed between the buffer interlayer and the inner wall of the rectangular outer frame, the buffer layer covers the inner frame, a plurality of sets of damping supports are installed on the two side walls of the interior of the inner frame, and reinforcing rib plates are installed at the bottoms of the damping supports. The buffer components are distributed between the inner frame and the rectangular outer frame, the inner frame and the buffer components are designed to be in an arch shape, so that concentrated soil can cover the arch shape to be dispersed, the pressure after covering is reduced, the shock absorption effect in the inner frame is improved through the herringbone support, and pipelines and lines are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building technology, in particular to an earthquake-resistant underground pipe gallery prefabricated structure and a construction method thereof. Background Art

[0002] The core role of underground integrated pipeline corridors is to intensively manage urban pipelines, avoid repeated road excavation, and improve urban safety and operational efficiency. Specific functions can be summarized as follows: avoiding repeated road excavation and resource waste, extending pipeline life and reducing maintenance costs, intensively utilizing underground space and optimizing urban landscapes, improving urban safety and disaster prevention capabilities, and achieving economic and social benefits. In order to quickly lay underground comprehensive pipeline corridors, prefabrication is usually adopted, that is, the underground comprehensive pipeline corridor is split into assembly units one by one. When laying the underground comprehensive pipeline corridor, the complete underground comprehensive pipeline corridor can be laid by assembling the prefabricated assembly units. For the existing prefabricated underground comprehensive pipeline corridor assembly units, they are usually rectangular frames cast in cement. When laying the underground pipeline corridor, first, a foundation pit is excavated, and then the prefabricated assembly units are assembled one by one at the foundation pit through lifting equipment, and the pipes, lines, etc. are installed in the assembled underground pipeline corridor, and then waterproofing is done. Finally, backfill construction is carried out. Finally, the entire soil will cover the outside of the prefabricated rectangular assembly frame. When it is vibrated, the prefabricated underground pipeline corridor assembly unit cannot release the excess vibration force, resulting in excessive pressure on the outer wall of the assembly unit frame, and the pipes, lines, etc. arranged inside are also affected by the vibration. For this reason, we propose an earthquake-resistant underground pipeline corridor prefabricated structure and a construction method thereof. Summary of the Invention

[0003] The purpose of the present invention is to provide a seismic-resistant underground pipe gallery prefabricated structure and a construction method thereof to solve the problems raised in the above-mentioned background technology.

[0004] To achieve the above-mentioned objectives, the present invention provides the following technical solutions: a seismic-resistant underground pipe gallery prefabricated structure and a construction method thereof, comprising a rectangular outer frame, an inner frame being arranged inside the rectangular outer frame, a buffer layer being reserved between the rectangular outer frame and the inner frame, a buffer component being arranged inside the buffer layer, and the buffer component comprising a buffer interlayer, and a plurality of groups of buffer springs being distributed between the buffer interlayer and the inner wall of the rectangular outer frame, the buffer layer covering the inner frame, and a plurality of groups of shock-absorbing brackets being installed on both side walls inside the inner frame, and a reinforcing rib being installed at the bottom of the shock-absorbing bracket, and the reinforcing rib and the shock-absorbing bracket being installed in a herringbone shape on the inner wall of the inner frame.

[0005] Preferably, the buffer interlayer is arched, and the outside of the inner frame is designed to be an arch similar to the buffer interlayer, and the inside of the inner frame is a rectangular through groove, the rectangular through groove inside the inner frame is embedded in the arch, and three groups of casting sections are assembled at the arch and rectangular through groove of the inner frame.

[0006] Preferably, the length of the rectangular outer frame is greater than that of the inner frame and greater than that of the buffer layer, and cast partitions are provided at both ends of the inner frame. The cast partitions are filled in the gaps between the inner frame and the ends of the rectangular outer frame by pouring cement.

[0007] Preferably, the casting partition is provided with a plurality of air holes, the air holes are evenly distributed on each casting section, and the air holes are expanded when opening toward the outer shape.

[0008] Preferably, the upper part of the cast partition is composed of two deformation zones, which are composed of deformation grooves. The deformation grooves are curved arc segments, and the radius of the deformation grooves gradually increases from the inner frame to the rectangular outer frame. The material hardness of the deformation zone is lower than the material hardness of the bottom of the cast partition.

[0009] Preferably, a positioning piece is provided at one end of the inner frame. The positioning piece is an outwardly protruding portion of the inner frame. The positioning piece is designed to be arched in imitation of the buffer interlayer, and the positioning piece fits with one end of the buffer interlayer.

[0010] Preferably, a plurality of pouring channels are distributed on the inner frame, and each pouring channel is connected by a pouring pipe, the pipe radius of the pouring channel is twice the pipe radius of the pouring channel, and the pouring pipes are distributed along the arch of the inner frame.

[0011] Preferably, a plurality of corrugated grooves are distributed on the outside of the rectangular outer frame, the corrugated grooves are semicircular depressions, and a lifting groove is provided on the rectangular outer frame.

[0012] Preferably, the top of the shock-absorbing bracket is provided with multiple anti-slip textures.

[0013] A construction method used for a seismic-resistant underground pipe gallery prefabricated structure: A: Splice individual underground pipe gallery prefabricated parts, push the buffer layer into the rectangular frame, and securely connect the buffer spring and the inner wall of the rectangular frame by pouring; B: Inner frame pouring: push the inner frame into the buffer layer and pour along the pouring path so that the inner frame and the buffer layer fit together; C: Encapsulate and install the brackets, encapsulate the two cast partitions at both ends of the inner frame, and assemble the shock-absorbing brackets inside the inner frame; D: Excavate the foundation pit and lift the prefabricated parts of the underground pipe gallery. Use an excavator to excavate the foundation pit, and use the lifting equipment to lift the assembled prefabricated parts of the underground pipe gallery into the excavated foundation pit; E: Lay pipes and wires on shock-absorbing brackets; F: Waterproofing and backfilling the pit.

[0014] Compared with the prior art, the present invention has the following beneficial effects: The present invention prefabricates an underground pipe gallery into three different components, with the outermost layer being a rectangular outer frame and the innermost layer being an inner frame for placing pipes and lines. Buffer components are distributed between the inner frame and the rectangular outer frame. By designing the inner frame and the buffer components into an arch shape, it is beneficial to disperse the concentrated soil covering the arch, thereby reducing the pressure after covering. At the same time, by designing the brackets supporting the pipes and lines inside the inner frame into a herringbone bracket, the shock absorption effect inside the inner frame is increased, which is beneficial to protecting the pipes and lines inside the inner frame.

[0015] The present invention designs multiple corrugated grooves on the outside of the rectangular outer frame, thereby evenly dividing the upper covering layer of the rectangular outer frame into the multiple corrugated grooves, so that the soil covering force on the rectangular outer frame is not too concentrated.

[0016] The present invention forms an elastic support between the inner frame and the rectangular outer frame by designing a cast partition, while also isolating and protecting the buffer component. The air holes on the cast partition are conducive to releasing the squeezed gas formed in the buffer layer. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall structure of the present invention.

[0018] Figure 2 It is a schematic diagram of the overall explosion structure of the present invention.

[0019] Figure 3 It is a structural schematic diagram of the buffer component of the present invention.

[0020] Figure 4 It is a structural schematic diagram of the rectangular mine building and buffer components of the present invention.

[0021] Figure 5 It is a schematic diagram of the transverse cross-section structure of the inner frame of the present invention.

[0022] Figure 6 It is a schematic diagram of the longitudinal cross-section structure of the inner frame of the present invention.

[0023] Figure 7 This is a structural diagram of the partition casting of the present invention.

[0024] Figure 8 It is a structural schematic diagram of the shock-absorbing bracket of the present invention.

[0025] In the figure: 1- rectangular outer frame; 2- inner frame; 3- buffer layer; 4- buffer component; 5- casting partition; 6- air hole; 7- deformation groove; 8- positioning piece; 11- corrugated groove; 12- lifting groove; 21- casting channel; 22- casting pipe; 41- buffer partition; 42- buffer spring; 43- shock-absorbing bracket; 44- reinforcing rib; 45- anti-slip texture. DETAILED DESCRIPTION

[0026] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0027] See also Figure 1-8 The present invention provides a technical solution: a seismic-resistant underground pipe gallery prefabricated structure. This solution is used to solve the problem that the prefabrication of existing underground pipe galleries is not convenient for seismic resistance and is easy to cause damage to pipes and lines in the underground pipe gallery. The solution mainly includes a rectangular outer frame 1, which is made of cement as a whole. A plurality of corrugated grooves 11 are distributed on the outside of the rectangular outer frame 1, and a lifting groove 12 is provided on the rectangular outer frame 1. When casting the rectangular outer frame 1, two rectangular frame plates are used as casting templates, wherein the template serving as the outer frame is provided with grooves for casting to form the corrugated grooves 11. The corrugated grooves 11 are used to disperse the fill to the corrugated grooves 11 during subsequent backfilling, thereby reducing the concentration of the fill on the outside of the rectangular outer frame 1, which is beneficial to reducing the pressure of the fill on the rectangular outer frame 1. A lifting groove 12 is excavated on the outer wall of the rectangular outer frame 1. A hook is hung on the lifting groove 12 by a lifting device such as a crane, thereby lifting the prefabricated components of the underground pipe gallery into the excavated foundation pit.

[0028] As attached Figure 1-2As shown in the figure, an inner frame 2 is provided in the rectangular outer frame 1, a buffer layer 3 is reserved between the rectangular outer frame 1 and the inner frame 2, a buffer component 4 is provided in the buffer layer 3, the buffer component 4 includes a buffer interlayer 41, and a plurality of groups of buffer springs 42 are distributed between the buffer interlayer 41 and the inner wall of the rectangular outer frame 1, the buffer layer 3 covers the inner frame 2, the buffer interlayer 41 is arched, and the outer part of the inner frame 2 is designed to be an arch similar to the buffer interlayer 41, and the inner part of the inner frame 2 is a rectangular through groove, the rectangular through groove inside the inner frame 2 is embedded in the arch, and three groups of casting sections are assembled at the arch and the rectangular through groove of the inner frame 2. By designing the buffer interlayer 3 and the outer part of the inner frame 2 to be arched, the effect is achieved. The pressure is released. When the rectangular outer frame 1 is subjected to force, the corrugated groove 11 on the top of the rectangular outer frame 1 can first distribute and release part of the soil pressure, thereby avoiding the soil pressure from being too concentrated on the top of the rectangular outer frame 1. When the external covering soil is distributed on the top of the rectangular outer frame 1, the rectangular outer frame 1 is under pressure, and the pressure acts on the internal buffer spring 42, and then acts on the buffer interlayer 41 through the buffer spring 42, thereby releasing the pressure on the rectangular outer frame 1 and reducing the pressure on the inner frame 2. At the same time, since the buffer interlayer 41 and the inner frame 2 are both designed with arches, it is convenient to release the concentrated stress, which is better than the existing plate-shaped underground pipeline corridor to release the concentrated soil pressure.

[0029] In order to facilitate the laying of pipes and cables inside the inner frame 2, multiple groups of shock-absorbing brackets 43 are installed on the inner side walls of the inner frame 2. The design of the shock-absorbing brackets 43 is as shown in the attached figure. Figure 8 As shown in FIG, the bottom of the shock-absorbing bracket 43 is equipped with reinforcing ribs 44. The reinforcing ribs 44 and the shock-absorbing bracket 43 are mounted in a herringbone pattern on the inner wall of the inner frame 2. The top of the shock-absorbing bracket 43 is provided with multiple anti-slip textures 45. After the pipes and cables are arranged on the shock-absorbing bracket 43, they are tied along the anti-slip textures 45 with straps or other fixing methods to secure the pipes and cables to the shock-absorbing bracket 43.

[0030] The length of the rectangular outer frame 1 is greater than that of the inner frame 2 and the buffer layer 41. Casting partitions 5 are provided at both ends of the inner frame 2. The casting panels 5 are filled in the gaps between the inner frame 2 and the ends of the rectangular outer frame 1 by pouring cement.

[0031] The casting partition 5 is provided with a plurality of air holes 6 , which are evenly distributed on each casting section, and the air holes 6 have an expansion shape beyond the outer opening.

[0032] The upper part of the cast partition 5 is composed of two deformation zones, each of which is composed of a deformation groove 7. The deformation groove 7 is a curved arc segment, and the radius of the deformation groove 7 gradually increases from the inner frame 2 to the rectangular outer frame 1. The material hardness of the deformation zone is lower than the material hardness of the bottom of the cast partition 5.

[0033] A positioning piece 8 is provided at one end of the inner frame 2 . The positioning piece 8 is an outwardly protruding portion of the inner frame 2 . The positioning piece 8 is arched in shape to imitate the buffer layer 41 , and fits in place with one end of the buffer layer 41 .

[0034] A plurality of pouring channels 21 are distributed on the inner frame 2 , and each pouring channel 21 is connected by a pouring pipe 22 . The pipe radius of the pouring channel 21 is twice the pipe radius of the pouring channel 21 , and the pouring pipe 22 is distributed along the arch of the inner frame 2 .

[0035] The outside of the rectangular outer frame 1 is distributed with a plurality of corrugated grooves 11 , which are semicircular depressions, and the rectangular outer frame 1 is provided with lifting grooves 12 .

[0036] When used specifically: first, cast the rectangular outer frame 1, using two rectangular frame plates as casting templates, and cast the rectangular outer frame 1 shown in the figure. By inserting the buffer interlayer 41 into the interior of the rectangular outer frame 1, the bottom edge of the buffer interlayer 41 and the edge of the rectangular outer frame 1 fit together, and the buffer spring 42 just rests against the inner wall of the rectangular outer frame 1. At this time, cement pouring is used to cast the buffer spring 42 and the bottom of the buffer interlayer 41 into the rectangular outer frame 1. Finally, push the pre-cast inner frame 2 into the buffer interlayer 41 until the positioning piece 8 fits the outside of the buffer interlayer 41. At this time, pour along the pouring channel 21, and convey multiple pouring channels 21 at the same time through multiple pouring pipes 22, so that the inner frame 2 and the buffer interlayer 41 form a casting layer.

[0037] A construction method used for a seismic-resistant underground pipe gallery prefabricated structure. A: Splice a single underground pipe gallery prefabricated part, push the buffer layer 3 into the rectangular frame, and fix the buffer spring 42 to the inner wall of the rectangular frame by pouring; B: Casting of the inner frame 2: Push the inner frame 2 into the buffer layer 3 and cast along the pouring path 21 so that the inner frame 2 and the buffer layer 3 fit together. C: Encapsulate and install the brackets, encapsulate the two cast partitions 5 at both ends of the inner frame 2, and assemble the shock-absorbing bracket 43 inside the inner frame 2; D: Excavate the foundation pit and lift the prefabricated parts of the underground pipe gallery. Use an excavator to excavate the foundation pit, and use the lifting equipment to lift the assembled prefabricated parts of the underground pipe gallery into the excavated foundation pit; E: Laying pipes and wires on the shock-absorbing bracket 43; F: Waterproofing and backfilling the pit.

[0038] After the three components of the prefabricated parts are assembled into one assembly unit respectively, it is necessary to lay multiple assembled prefabricated parts. First, a foundation pit is dug out using an excavator or other equipment, and the hook of the crane is hung on the lifting groove 12 of the rectangular outer frame 1 to lift the assembled rectangular outer frame 1. The rectangular outer frame 1 is placed in the foundation pit, and then multiple rectangular outer frames 1 are placed in sequence. By bundling cables and the like on the shock-absorbing bracket 43, the laying of the entire underground pipeline corridor prefabrication is completed.

[0039] It should be noted that, in this document, relational terms such as first and second, etc., are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus.

[0040] While embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions, and variations may be made to these embodiments without departing from the principles and spirit of the invention, and that the scope of the invention is defined by the appended claims and their equivalents.

Claims

1. A seismic-resistant underground pipe gallery prefabricated structure, comprising a rectangular outer frame (1), characterized in that: An inner frame (2) is provided in the rectangular outer frame (1), a buffer layer (3) is reserved between the rectangular outer frame (1) and the inner frame (2), a buffer component (4) is provided in the buffer layer (3), the buffer component (4) includes a buffer interlayer (41), and a plurality of groups of buffer springs (42) are distributed between the buffer interlayer (41) and the inner wall of the rectangular outer frame (1), the buffer layer (3) covers the inner frame (2), and a plurality of groups of shock-absorbing brackets (43) are installed on both side walls inside the inner frame (2), and a reinforcing rib (44) is installed at the bottom of the shock-absorbing bracket (43), and the reinforcing rib (44) and the shock-absorbing bracket (43) are installed on the inner wall of the inner frame (2) in a herringbone shape.

2. The seismic-resistant underground pipe gallery prefabricated structure according to claim 1, characterized in that: The buffer interlayer (41) is arched, and the outer portion of the inner frame (2) is designed to be arched in the same manner as the buffer interlayer (41), and the inner portion of the inner frame (2) is a rectangular through groove, the rectangular through groove inside the inner frame (2) being embedded in the arch, and three groups of casting sections are assembled at the arch and the rectangular through groove of the inner frame (2).

3. The seismic-resistant underground pipe gallery prefabricated structure according to claim 2, characterized in that: The length of the rectangular outer frame (1) is greater than the length of the inner frame (2) and greater than the length of the buffer layer (41). Casting partitions (5) are provided at both ends of the inner frame (2). The casting panels (5) are filled in the gaps between the two ends of the inner frame (2) and the rectangular outer frame (1) by pouring cement.

4. The seismic-resistant underground pipe gallery prefabricated structure according to claim 3 is characterized by: The casting partition (5) is provided with a plurality of air holes (6), the air holes (6) are evenly distributed on each casting section, and the air holes (6) are expanded when opening toward the outer shape.

5. The seismic-resistant underground pipe gallery prefabricated structure according to claim 3 is characterized by: The upper portion of the cast partition (5) is a two-section deformation zone, the deformation zone consisting of a deformation groove (7), the deformation groove (7) being a curved arc segment, and the radius of the deformation groove (7) gradually increasing from the inner frame (2) to the rectangular outer frame (1), and the material hardness of the deformation zone is lower than the material hardness of the bottom of the cast partition (5).

6. The seismic-resistant underground pipe gallery prefabricated structure according to claim 2, characterized in that: One end of the inner frame (2) is provided with a positioning piece (8), which is an outwardly protruding portion of the inner frame (2), and the positioning piece (8) is designed to be arched in the same manner as the buffer layer (41), and the positioning piece (8) is fitted with one end of the buffer layer (41).

7. The earthquake-resistant underground pipe gallery prefabricated structure according to claim 5, characterized in that: A plurality of pouring channels (21) are distributed on the inner frame (2), and each pouring channel (21) is connected through a pouring pipe (22), the pipe radius of the pouring channel (21) is twice the pipe radius of the pouring channel (21), and the pouring pipe (22) is distributed along the arch of the inner frame (2).

8. The seismic-resistant underground pipe gallery prefabricated structure according to claim 1, characterized in that: The rectangular outer frame (1) is provided with a plurality of corrugated grooves (11) on the outside, wherein the corrugated grooves (11) are semicircular depressions, and a lifting groove (12) is provided on the rectangular outer frame (1).

9. The earthquake-resistant underground pipe gallery prefabricated structure according to claim 1, characterized in that: The top of the shock-absorbing bracket (43) is provided with multiple anti-slip textures (45).

10. The construction method for a seismic-resistant underground pipe gallery prefabricated structure according to any one of claims 1 to 9, characterized in that: A: Splice a single underground pipe gallery prefabricated part, push the buffer layer (3) into the rectangular frame, and fix the buffer spring (42) and the inner wall of the rectangular frame by pouring; B: Casting of the inner frame (2): pushing the inner frame (2) into the buffer layer (3) and casting along the casting path (21) so that the inner frame (2) and the buffer layer (3) fit together; C: Encapsulating and installing the bracket, encapsulating the two cast partitions (5) at both ends of the inner frame (2), and assembling the shock-absorbing bracket (43) inside the inner frame (2); D: Excavate the foundation pit and lift the prefabricated parts of the underground pipe gallery. Use an excavator to excavate the foundation pit, and use the lifting equipment to lift the assembled prefabricated parts of the underground pipe gallery into the excavated foundation pit; E: Laying pipes and wires on the shock-absorbing bracket (43); F: Waterproofing and backfilling the pit.