Method for disengaging steel roof truss sling
By installing temporary support devices, including hydraulic jacks and sliding supports, between the steel roof truss placement end and the supporting structure, the problem of unstable load transfer during the unloading process of the steel roof truss was solved, thus achieving the safety and placement accuracy of the steel roof truss.
Patent Information
- Application Number
- CN202611515399.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-28
- Publication Date
- 2026-11-10
AI Technical Summary
In existing technologies, the load transfer during unloading of steel roof truss lifting slings is not stable, which can easily cause impact damage to the steel roof truss and supporting structure, and the positioning accuracy is difficult to guarantee.
A temporary support device, including hydraulic jacks and sliding supports, is installed between the positioning end of the steel roof truss and the supporting structure. The lifting force of the slings is reduced slowly and synchronously, and the steel roof truss is actively lifted by the hydraulic jacks. The load at the positioning end is gradually transferred to the temporary support device. The slings are temporarily fixed before unloading.
The process of unloading steel roof truss slings was made smooth and safe, avoiding sudden load changes and impact damage, and ensuring positioning accuracy.
Smart Images

Figure CN123061871A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of nuclear island plant roof installation technology, and in particular to a method for detaching steel roof truss slings. Background Technology
[0002] With the rapid development of large-span, large-space public and industrial buildings, steel roof trusses, with their characteristics of light weight, high strength, strong span capacity, factory processing, and prefabrication, are widely used in the roof structures of stadiums, convention centers, airport terminals, and large factories. They are showing a trend towards larger spans and heavier individual structures, with large steel roof trusses with spans exceeding 36 meters and weights exceeding 200 tons becoming increasingly common in projects. The installation of steel roof trusses typically involves hoisting them as a whole or in sections using lifting equipment and slings. After the steel roof truss is in place, it needs to be smoothly converted from a suspended state to a permanently supported state. The unloading and disengagement of the slings are critical and high-risk aspects of steel roof truss construction.
[0003] Currently, the unloading and detachment of slings after a steel roof truss is hoisted into place typically employs the following methods: One is direct unloading, where the crane directly lowers the hooks or loosens the slings all at once after the truss is in place, rapidly discharging the load in a short time. Another is staged unloading, where the load is gradually reduced according to pre-defined unloading stages until the slings are completely unloaded before detachment. Additionally, there is a method using temporary support frames to support the steel roof truss, and during unloading, the entire truss is slowly lowered by gradually removing the support frames or using sandboxes to release sand and lowering jacks. In these processes, the unloading of the load relies mainly on the operator's experience to control the lowering speed, and real-time monitoring of the load transfer and deformation at the positioned end of the steel roof truss is generally lacking.
[0004] However, all of the above methods have certain shortcomings. For steel roof trusses with large spans and heavy weights, the lifting capacity of the slings often reaches hundreds or even thousands of tons. When using the direct unloading method, the lifting capacity is released rapidly in a short period of time, and the load is suddenly transferred to the supporting structure, which will impact the steel roof truss and the supporting structure, causing sudden changes in internal forces, deformation, or even local instability of the steel roof truss. Although the staged unloading and jig unloading methods alleviate the sudden changes in load to some extent, due to the lack of quantitative control over the synchronicity between the unloading of the lifting capacity and the increase of the temporary support force, the rates of the two are still prone to mismatch during the unloading process, resulting in unstable load transfer at the positioning end. At the same time, before the slings are completely unloaded, the positioning end of the steel roof truss lacks reliable temporary constraints, and the positioning accuracy after unloading is difficult to guarantee and adjust. The deformation and stress state during the unloading process lack real-time monitoring, and it is difficult to detect and deal with any abnormalities in a timely manner. Summary of the Invention
[0005] The main purpose of the present application is to provide a steel roof truss sling disengagement method, aiming to solve the technical problems of unstable load transfer, easy impact damage to the steel roof truss and supporting structure, and difficult to guarantee the accuracy of the steel roof truss sling unloading process, improve the safety, stability and accuracy of the steel roof truss sling unloading process.
[0006] To achieve the above purpose, in the first aspect, the present application provides a steel roof truss sling disengagement method, comprising the following steps: A temporary support device is installed between the just-in-place end of the steel roof truss and the supporting structure; wherein the temporary support device comprises a hydraulic jack and a slidable support, the jacking force of the hydraulic jack is 1.1 to 1.3 times the counterforce of the self-weight of the end of the steel roof truss, and the sliding direction of the slidable support is consistent with the length direction of the steel roof truss; Synchronously and slowly reduce the lifting load of the sling, while the hydraulic jack actively jacks up the just-in-place end of the steel roof truss at a matching speed, so that the load of the just-in-place end of the steel roof truss is gradually transferred from the sling to the temporary support device; wherein the synchronization deviation of the lifting load reduction and the active jacking is controlled within 5%; When the lifting load of the sling is reduced to a preset safe disengagement force threshold, stop reducing the lifting load of the sling, and temporarily fix and connect the just-in-place end of the steel roof truss and the supporting structure; After the temporary fixed connection is completed, continue to reduce the lifting load of the sling until the sling is completely unloaded, and then disengage the sling from the steel roof truss.
[0007] The technical scheme of the present application installs a temporary support device between the in-place end of the steel roof truss and the support structure, so that the in-place end of the steel roof truss always obtains reliable temporary vertical bearing during the unloading process of the hoisting device, and avoids the in-place end from being suspended or directly impacting the support structure after the unloading of the hoisting force; wherein the temporary support device comprises a hydraulic jack and a slidable support, the hydraulic jack can actively and continuously jack up the in-place end of the steel roof truss during the unloading process, and the slidable support provides support for the in-place end to allow horizontal sliding, and the two cooperate to make the temporary support device have both vertical active bearing capacity and horizontal deformation adaptability; by setting the jacking force of the hydraulic jack to 1.1-1.3 times the corresponding end reaction force of the self-weight of the steel roof truss, the hydraulic jack always has a bearing margin at any stage of the entire unloading process and will not lose stability or fail due to insufficient bearing capacity; by making the sliding direction of the slidable support consistent with the length direction of the steel roof truss, the horizontal displacement of the steel roof truss along the length direction caused by changes in stress state or temperature changes during the unloading process is freely released, avoiding additional horizontal constraints and secondary internal forces on the in-place end; by simultaneously and slowly reducing the hoisting force of the hoisting device, and the hydraulic jack actively jacking up the in-place end of the steel roof truss at a matching speed, the load of the in-place end of the steel roof truss is gradually transferred from the hoisting device to the temporary support device, and the synchronization deviation between the reduction of the hoisting force and the active jacking is controlled within 5%, so that the release amount of the hoisting force and the growth amount of the temporary support force maintain a corresponding relationship at each moment during the unloading process, and the load transfer process is continuous, smooth and without sudden changes, thereby reducing the stress fluctuation and deformation fluctuation of the steel roof truss during the unloading process, and avoiding impact damage to the steel roof truss and the support structure; by stopping reducing the hoisting force of the hoisting device when the hoisting force is reduced to a preset safe disengagement force threshold, and temporarily fixing and connecting the in-place end of the steel roof truss and the support structure, the in-place end of the steel roof truss is temporarily fixed and constrained before the hoisting device is completely unloaded, avoiding uncontrollable displacement or rotation of the in-place end when the remaining hoisting force is continuously unloaded, and providing stable boundary conditions for subsequent complete unloading; by continuing to reduce the hoisting force of the hoisting device after the temporary fixing and connecting is completed until the hoisting device is completely unloaded, and then disengaging the hoisting device from the steel roof truss, the steel roof truss is already under the protection of the temporary support device and the temporary fixing and connecting when the hoisting device is disengaged, and the residual hoisting force of the hoisting device can be released smoothly without causing stress changes in the steel roof truss. In summary, through the setting of the temporary support device, the synchronous control of the reduction of the hoisting force and the active jacking of the hydraulic jack, and the phased temporary fixing and complete unloading, the load of the in-place end of the steel roof truss is smoothly, continuously and controllably transferred from the hoisting device to the support structure, avoiding load sudden changes and impact during the unloading process, reducing the damage risk of the steel roof truss and the support structure caused by unloading, and ensuring the in-place accuracy of the steel roof truss, thereby solving the technical problems of unstable load transfer, easy impact damage and difficult to ensure in-place accuracy in the prior art. BRIEF DESCRIPTION OF DRAWINGS
[0008] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the following will briefly introduce the drawings needed to be used in the embodiments or prior art description. Obviously, the drawings described below only show some of the embodiments of the present application, and the person skilled in the art can obtain other drawings according to the structures shown in the drawings without any creative effort.
[0009] Figure 1 The flow chart of the steel roof truss sling disengagement method provided by the present application.
[0010] The implementation, functional features and advantages of the present application will be further described with reference to the embodiments and the accompanying drawings. DETAILED DESCRIPTION
[0011] The technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only some of the embodiments of the present application, not all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by the person skilled in the art without any creative effort are within the protection scope of the present application.
[0012] It should be noted that if the embodiments of the present application involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement condition, etc. between the components in a certain posture, and if the certain posture changes, the directional indications also change accordingly.
[0013] In addition, if the embodiments of the present application involve descriptions of "first", "second", etc., the descriptions of "first", "second", etc. are only for description purpose, and cannot be understood as indicating or implying the relative importance of the indicated technical features or implicitly indicating the number of the indicated technical features. Therefore, the features limited by "first", "second" can explicitly or implicitly include at least one of the features. In addition, "and / or" or "and / or" appearing throughout the text means that the three parallel schemes are included, for example, "A and / or B" includes A scheme, or B scheme, or A and B are satisfied at the same time. In addition, the technical solutions of each embodiment can be combined with each other, but it must be based on the person skilled in the art can be realized, when the combination of technical solutions appears contradictory or cannot be realized, it should be considered that the combination of technical solutions does not exist, and is not within the protection scope of the present application.
[0014] The main solution of the present application is that a temporary support device is installed between the in-place end of the steel roof truss and the support structure, wherein the temporary support device comprises a hydraulic jack and a slidable support, the jacking force of the hydraulic jack is 1.1 to 1.3 times the counterforce of the self-weight of the steel roof truss at the corresponding end, and the sliding direction of the slidable support is consistent with the length direction of the steel roof truss; the lifting load of the sling is synchronously and slowly reduced, and at the same time the in-place end of the steel roof truss is actively jacked up by the hydraulic jack at a matching speed, so that the load of the in-place end of the steel roof truss is gradually transferred from the sling to the temporary support device, wherein the synchronous deviation between the reduction of the lifting load and the active jacking is controlled within 5%; when the lifting load of the sling is reduced to a preset safe disengagement force threshold, the reduction of the lifting load of the sling is stopped, and the in-place end of the steel roof truss is temporarily fixed and connected with the support structure; after the temporary fixed connection is completed, the lifting load of the sling is continuously reduced until the sling is completely unloaded, and then the sling is disengaged from the steel roof truss.
[0015] Currently, the unloading after the hoisting and positioning of the steel roof truss usually adopts the modes of direct hooking reduction one-time unloading, staged unloading or temporary jig unloading, and the removal of the lifting load mainly relies on the experience control of the operators, lacking quantitative control of the synchronization between the removal of the lifting load and the increase of the temporary support force, and the load mutation and unstable load transfer are prone to occur in the unloading process, thereby causing impact damage to the steel roof truss and the support structure and affecting the positioning accuracy of the steel roof truss.
[0016] The present application overcomes the technical defects of load mutation and impact damage caused by the sudden removal of the lifting load and poor synchronization by setting the temporary support device composed of the hydraulic jack and the slidable support, combining the synchronous control of the lifting load reduction and the active jacking of the hydraulic jack, and the phased temporary fixing and complete unloading, so that the load of the in-place end of the steel roof truss is stably and continuously transferred from the sling to the temporary support device and the support structure, the positioning accuracy of the steel roof truss is ensured, and the safety and reliability of the sling unloading process of the steel roof truss are improved.
[0017] It should be noted that the steel roof truss refers to a truss type roof bearing structure composed of chord bars, web bars and other bar members through node connection, and the steel roof truss in the present application can be a whole hoisted steel roof truss or a segmented hoisted and assembled whole steel roof truss. The sling refers to the general term of the hoisting tools such as hooks, slings, hoisting beams and shackle connected between the hoisting equipment and the steel roof truss in the hoisting operation. The in-place end refers to the end connected with the support structure during the installation of the steel roof truss. The support structure refers to the column, corbel, support and other lower structures for supporting the steel roof truss.
[0018] It should be noted that the execution subject of the embodiment can be a hoisting device and its control system of a construction unit, or a control device in communication connection with the hoisting device and the hydraulic jack and capable of executing the steps of the method, or an engineering management personnel who organizes the construction according to the method, and the embodiment does not make specific limitation thereon. The embodiment and the following embodiments are described below by taking the example of the construction unit implementing the method by using the hoisting device control system and the hydraulic jack.
[0019] The application provides a steel roof truss sling disengagement method.
[0020] Please refer to Figure 1 , in order to facilitate understanding, the steel roof truss sling disengagement method comprises the following steps: S100, installing a temporary support device between the in-place end of the steel roof truss and the support structure; wherein the temporary support device comprises a hydraulic jack and a slidable support, the jacking force of the hydraulic jack is 1.1 times to 1.3 times of the end reaction force corresponding to the self-weight of the steel roof truss, and the sliding direction of the slidable support is consistent with the length direction of the steel roof truss.
[0021] It should be noted that the temporary support device refers to a device that temporarily replaces the in-place end of the steel roof truss supported by the sling during the sling unloading process. In the embodiment, the temporary support device comprises a hydraulic jack and a slidable support, wherein the hydraulic jack refers to a jacking device that uses hydraulic oil as a power medium and extends the piston rod to jack up the weight, which can actively and continuously adjust the jacking force during the unloading process; the slidable support refers to a supporting device that allows the supported member to slide horizontally. The temporary support device is installed between the in-place end of the steel roof truss and the support structure, that is, between the bottom surface of the bottom chord of the in-place end and the top surface of the support structure, so that the in-place end of the steel roof truss always obtains reliable vertical bearing during the unloading process.
[0022] The jacking force of the hydraulic jack refers to the rated bearing capacity of the hydraulic jack. The end reaction force corresponding to the self-weight of the steel roof truss refers to the support reaction force of the in-place end of the steel roof truss under the action of the self-weight, which is determined according to the structure form of the steel roof truss through structure calculation. For a steel roof truss symmetrically supported at both ends, the end reaction force of the in-place end is generally half of the self-weight of the steel roof truss. The jacking force of the hydraulic jack is set to 1.1 times to 1.3 times of the end reaction force, so that the hydraulic jack has a bearing margin of 1.1 times or more at any stage of the entire unloading process. Even if temporary load fluctuation occurs during the unloading process, the hydraulic jack will not be unstable or fail due to insufficient bearing capacity. For example, the self-weight of a certain steel roof truss is 2400kN, and the structure calculation shows that the end reaction force of the in-place end is 1200kN, so the jacking force of the hydraulic jack should be selected as 1320kN~1560kN, and the hydraulic jack of 1500kN is selected in the embodiment.
[0023] The sliding direction of the slidable support is consistent with the length direction of the steel roof truss, which means that the slidable support only allows the in-place end of the steel roof truss to slide horizontally along the length direction of the steel roof truss (i.e., the longitudinal direction of the lower chord of the steel roof truss), and provides constraint in the direction perpendicular to the length direction. During the unloading process, the stress state of the steel roof truss gradually changes from the hoisting suspended state to the supported state, and meanwhile, the temperature may change. The steel roof truss will generate horizontal displacement along the length direction. By setting the sliding direction of the slidable support to be consistent with the length direction of the steel roof truss, the horizontal displacement can be freely released, so as to avoid additional horizontal constraint and secondary internal force generated at the in-place end.
[0024] In a feasible embodiment, the slidable support can be first installed on the top surface of the support structure, and then the hydraulic jack is placed on the slidable support. In another feasible embodiment, the hydraulic jack and the slidable support can be assembled into an integral whole, and then the integral whole is installed between the in-place end of the steel roof truss and the support structure. In yet another feasible embodiment, the temporary support device can also be installed synchronously with the hoisting progress during the hoisting and placing process of the steel roof truss, for example, the installation is completed after the steel roof truss is hoisted to the in-place position and before the unloading is started. The above are only several feasible installation modes of the temporary support device provided by the present embodiment, and the present embodiment does not specifically limit this.
[0025] S200, simultaneously and slowly reduce the hoisting load of the hoisting sling, and the hydraulic jack actively jacks up the in-place end of the steel roof truss at a matching speed, so that the load of the in-place end of the steel roof truss is gradually transferred from the hoisting sling to the temporary support device; wherein the synchronization deviation between the reduction of the hoisting load and the active jacking is controlled within 5%.
[0026] It should be noted that the hoisting load refers to the vertical lifting force exerted by the hoisting sling on the steel roof truss, which can be measured in real time by a hoisting load sensor. The synchronization means that the reduction of the hoisting load and the jacking of the hydraulic jack are coordinated on the same time axis, that is, for every amount of reduction of the hoisting load, the jacking force of the hydraulic jack increases by an amount, and there is no disconnection in time between the two. Slow means that the reduction process of the hoisting load is carried out at a preset low speed, so as to avoid the rapid release of the hoisting load in a short time. The matching speed means that the jacking speed of the hydraulic jack matches the reduction speed of the hoisting load, so that the reduction rate of the hoisting load and the growth rate of the jacking force of the hydraulic jack remain consistent in value, so as to keep the total reaction force borne by the in-place end of the steel roof truss basically constant during the unloading process, and realize the smooth transfer of the load.
[0027] The synchronization deviation refers to the absolute value of the difference between the actual increase amount of the jacking force of the hydraulic jack and the actual reduction amount of the hoisting load within a preset verification time step, which accounts for a percentage of the planned load transfer amount within the time step. The calculation formula of the synchronization deviation can be expressed as:
[0028] Where δ is the synchronization deviation. This represents the actual increase in the lifting force of the hydraulic jacks within that time step. The actual reduction in lifting capacity during this time step ( For negative values, | (Take its absolute value) This represents the planned load transfer amount within that time step. In this embodiment, the synchronization deviation is controlled within 5%. For example, if the planned load transfer amount within a certain time step is 96kN, and the actual measured lifting force decreases by 94kN while the hydraulic jack lifting force increases by 96kN, then the synchronization deviation is... delta =|96 94|÷96×100%≈2.1%, which is less than 5%, thus meeting the synchronization control requirements. Synchronization deviation can be controlled by adjusting the lifting speed of the hydraulic jack or the lowering speed of the lifting equipment; the specific adjustment method will be further detailed in Example 2.
[0029] In one feasible implementation, the synchronization deviation can be checked every minute, and the lifting speed or lowering speed of the next time step can be adjusted according to the check result; in another feasible implementation, the synchronization deviation can be checked every 30 seconds; in yet another feasible implementation, the synchronization deviation can be checked every time the lifting force decreases by a preset increment.
[0030] S300. When the lifting force of the sling is reduced to a preset safe release force threshold, the reduction of the lifting force of the sling is stopped, and the positioning end of the steel roof truss is temporarily fixedly connected to the supporting structure.
[0031] It should be noted that the preset safe release force threshold is a limit for determining whether the lifting force of the slings has been reduced to a level where subsequent operations can be safely carried out, and thus deciding whether to stop reducing the lifting force. The preset safe release force threshold can be pre-set in the lifting equipment control system. When the reading of the lifting force sensor drops to the preset safe release force threshold, the lifting equipment control system automatically stops lowering the hook, or issues a warning signal for the operator to stop lowering the hook. Stopping the reduction of the lifting force means maintaining the lifting force of the slings at the current level and not continuing to lower them. The specific value of the preset safe release force threshold will be further detailed in Example Six. In this example, the self-weight of a steel roof truss is 2400kN, and the preset safe release force threshold is 5% of the self-weight of the steel roof truss, i.e., 120kN.
[0032] Temporary fixed connections refer to the temporary connection between the positioned end of a steel roof truss and the supporting structure using temporary fasteners, thereby providing temporary fixation to the positioned end of the steel roof truss. Temporary fixed connections differ from subsequent permanent fixed connections. Their purpose is to limit any possible displacement or rotation of the positioned end of the steel roof truss before the lifting slings are completely unloaded, providing stable boundary conditions for further reduction of the lifting load.
[0033] When the lifting force of the slings is reduced to the preset safe release force threshold, the hydraulic jack has already borne most of the load at the steel roof truss placement end. At this time, the lifting force is reduced and a temporary fixing connection is made. The stress state at the steel roof truss placement end is close to the design state, and the temporary fixing connection is in a low stress state, so that the temporary fixing connection operation can be completed in a safe environment.
[0034] S400. After the temporary fixed connection is completed, continue to reduce the lifting force of the sling until the sling is completely unloaded, and then detach the sling from the steel roof truss.
[0035] It should be noted that complete unloading means that the lifting capacity of the slings is reduced to zero, and the slings no longer bear any load. Disengagement means removing the hook of the sling from the lifting lug of the steel roof truss, thus physically separating the slings from the steel roof truss. After the temporary fixing connection is completed, during the continued reduction of the lifting capacity, the load at the positioned end of the steel roof truss is further transferred from the slings to the temporary support device and the temporary fixing connection; when the lifting capacity is reduced to zero, the slings are in a relaxed state, and at this point, disengaging the slings from the steel roof truss will not cause a sudden change in the stress on the steel roof truss. The specific implementation method for further reducing the lifting capacity will be further detailed in Example 7.
[0036] In this embodiment, by installing a temporary support device between the positioning end of the steel roof truss and the supporting structure, the positioning end of the steel roof truss always receives reliable temporary vertical bearing during the unloading process of the slings, avoiding the positioning end being suspended or directly impacting the supporting structure after the lifting force is removed. The temporary support device includes hydraulic jacks and sliding supports. The hydraulic jacks can actively and continuously lift the positioning end of the steel roof truss during unloading, while the sliding supports provide support that allows horizontal sliding of the positioning end. Together, these components give the temporary support device both vertical active bearing capacity and horizontal deformation adaptability. The lifting force of the hydraulic jacks is set to 1.1 to 1.3 times the reaction force at the end corresponding to the self-weight of the steel roof truss. This ensures that the hydraulic jacks maintain a load-bearing margin at any stage of the unloading process, preventing instability or failure due to insufficient load-bearing capacity. By aligning the sliding direction of the sliding supports with the length direction of the steel roof truss, the horizontal displacement along the length direction caused by changes in stress or temperature during unloading is freely released, avoiding additional horizontal constraints and secondary internal forces at the placement end. Simultaneously and slowly reducing the lifting force of the slings, the hydraulic jacks actively adjust their speed accordingly. The lifting of the steel roof truss at its positioning end gradually transfers the load from the slings to the temporary support device. The synchronization deviation between reducing the lifting force and the active lifting is controlled within 5%, ensuring a consistent relationship between the release of the lifting force and the increase in the temporary support force at every moment during the unloading process. This continuous, smooth, and abrupt load transfer reduces stress and deformation fluctuations in the steel roof truss during unloading, preventing impact damage to the truss and supporting structure. The lifting force is stopped when it reaches a preset safe release force threshold, and the steel roof truss is then lifted into position. The positioning end is temporarily fixed to the supporting structure, so that the steel roof truss is temporarily fixed and constrained at the positioning end before the slings are completely unloaded. This prevents uncontrollable displacement or rotation at the positioning end when the remaining lifting force continues to be unloaded, and provides stable boundary conditions for subsequent complete unloading. After the temporary fixed connection is completed, the lifting force of the slings is further reduced until complete unloading, and then the slings are detached from the steel roof truss. When the slings are detached, the steel roof truss is under the dual protection of the temporary support device and the temporary fixed connection. The residual lifting force of the slings can be released smoothly without causing sudden stress changes in the steel roof truss. In summary, this application, through the installation of temporary support devices, the synchronous control of load reduction and active jacking by hydraulic jacks, and the phased temporary fixing and complete unloading, enables the load at the positioning end of the steel roof truss to be transferred smoothly, continuously, and controllably from the slings to the supporting structure. This avoids sudden load changes and impacts during the unloading process, reduces the risk of damage to the steel roof truss and supporting structure caused by unloading, and ensures the positioning accuracy of the steel roof truss. Thus, it solves the technical problems of unstable load transfer, easy impact damage, and difficulty in guaranteeing positioning accuracy in the prior art.
[0037] In one embodiment, step S200 includes: S210. The lifting equipment control system of the slings reduces the lifting force of the hook at a preset unloading rate; wherein the preset unloading rate is 3% to 5% of the self-weight of the steel roof truss per minute.
[0038] It should be noted that the lifting equipment control system refers to the control system on the lifting equipment used to control actions such as lifting, luffing, and slewing. The lifting equipment control system may include a torque limiter, a lifting force sensor, and a main controller. A hook refers to a hook-shaped component on the lifting equipment used to suspend slings. The preset unloading rate refers to the pre-set rate at which the lifting force is reduced. In this embodiment, the preset unloading rate is 3% to 5% of the steel roof truss's self-weight per minute, meaning the lifting force is reduced by 3% to 5% of the steel roof truss's self-weight per minute. For example, if a steel roof truss has a self-weight of 2400 kN, and the preset unloading rate is 4% of its self-weight per minute, then the lifting force is reduced by 96 kN per minute.
[0039] The preset unloading rate is set to 3% to 5% of the steel roof truss's self-weight per minute, so that the rate of reduction of the lifting force matches the size of the steel roof truss: for steel roof trusses with greater self-weight, the rate of reduction of the lifting force is correspondingly greater, thereby ensuring that the unloading process of steel roof trusses of different sizes has a considerable degree of stability; at the same time, this rate range avoids both excessively fast unloading rate causing sudden load changes and excessively slow unloading rate causing construction period extension and temporary support devices to be in a high-load state for a long time.
[0040] In one feasible implementation, the preset unloading rate can remain constant during the unloading process; in another feasible implementation, the preset unloading rate can take a larger value in the early stage of unloading and a smaller value in the later stage of unloading; in yet another feasible implementation, the preset unloading rate can also be set in segments according to the change in load ratio. The above are only a few feasible ways to set the preset unloading rate provided in this embodiment, and this embodiment does not make specific limitations on them.
[0041] S220. Read the load force sensor values of the slings and the pressure sensor values of the hydraulic jacks in real time, and calculate the load proportion borne by the slings and the load proportion borne by the temporary support device at the positioning end of the steel roof truss.
[0042] It should be noted that a lifting force sensor is a sensor used to measure the lifting force of slings and can be installed on the hook pulley block, sling, or lifting beam; a pressure sensor is a sensor used to measure the oil pressure in the hydraulic jack circuit, and can be installed on the hydraulic jack circuit or valve block. The load ratio refers to the percentage of the load borne by the slings or temporary support devices relative to the total reaction force at the steel roof truss's placement end.
[0043] In this embodiment, the formula for calculating the proportion of the load borne by the slings at the positioning end of the steel roof truss can be expressed as:
[0044] The formula for calculating the proportion of the load borne by temporary support devices at the positioning end of the steel roof truss can be expressed as:
[0045] in, The proportion of the load borne by the slings. The proportion of the load borne by the temporary support device. The lifting force is measured by the lifting force sensor. The load borne by the temporary support device. It can be calculated based on the oil pressure measured by the pressure sensor. The calculation formula can be expressed as: ,in, This refers to the number of hydraulic jacks. The mechanical efficiency of the hydraulic jack is typically taken as 0.90 to 0.95. p The oil pressure is measured by a pressure sensor. A This refers to the effective area of the hydraulic jack piston. For example, if the diameter of a hydraulic jack piston is 0.28m, then the effective area of the piston is... A =π×0.28×0.28÷4≈0.0616m²; At a certain moment during unloading, the pressure sensor measured the oil pressure. p The pressure is 12.5 MPa, and the number of hydraulic jacks is [number missing]. n The mechanical efficiency is 1. Taking 0.92, the load borne by the temporary support device =1×0.92×12.5×1000×0.0616≈708kN; the lifting force measured by the lifting force sensor at this moment is... If the load is 492kN, then the proportion of the load borne by the slings is... =492÷(492+708)×100%=41%, the proportion of the load borne by the temporary support device. =708÷(492+708)×100%=59%. It can be seen that by reading sensor values in real time and calculating the load ratio, the progress of load transfer can be monitored at any time. The above values for hydraulic pressure and lifting force are all actual sensor readings during the unloading process, and the load ratio is calculated from the actual readings using the above formula.
[0046] S230. Dynamically adjust the descent speed of the lifting equipment and the lifting speed of the hydraulic jack according to the load ratio to keep the load transfer rate of the two consistent.
[0047] It should be noted that the descent speed of the lifting equipment refers to the descent speed of the hook, while the lifting speed of the hydraulic jack refers to the extension speed of the hydraulic jack piston rod. Consistent load transfer rate means that the amount of load released by the slings per unit time is equal to the amount of load increased by the temporary support device; that is, the total reaction force at the positioning end remains constant during unloading, without any instantaneous accumulation or loss of load.
[0048] In this embodiment, the actual rate of decrease in lifting force and the actual rate of increase in lifting force of the hydraulic jack can be calculated based on the load ratio, and then compared with the preset unloading rate. If the rate of increase in lifting force of the hydraulic jack is lower than the rate of decrease in lifting force, it indicates that the hydraulic jack is lagging behind and the load transfer to the temporary support device is too slow; in this case, the lifting speed of the hydraulic jack should be increased. If the rate of increase in lifting force of the hydraulic jack is higher than the rate of decrease in lifting force, it indicates that the hydraulic jack is ahead of schedule; in this case, the lifting speed of the hydraulic jack should be reduced. If the two rates are basically the same, the current speed should be maintained to continue unloading. For example, within a certain minute, the actual lifting force decreases by 92kN, which is lower than the preset unloading rate of 96kN, while the actual lifting force of the hydraulic jack increases by 99kN, indicating a synchronization deviation. delta =|99 92|÷96×100%≈7.3%, which is greater than 5%, indicating that the hydraulic jack is lifting ahead of schedule. At this time, the lifting speed of the hydraulic jack should be reduced so that the increase in the lifting force of the hydraulic jack in the next minute is reduced to a level that matches the reduction in the lifting force. The synchronization deviation should be checked again until the synchronization deviation is restored to within 5%.
[0049] In one feasible implementation, the adjustment cycle can be 1 minute, and the speed of the next cycle can be adjusted according to the load ratio change of the previous cycle. In another feasible implementation, the adjustment cycle can be 1 preset increment for each reduction in the lifting force. In yet another feasible implementation, the correspondence between load ratio change and speed adjustment can be pre-written into the lifting equipment control system, and the control system can automatically complete the dynamic adjustment.
[0050] In one embodiment, step S100 includes: S110. Place the slidable support at the predetermined support position of the support structure; wherein, the slidable support includes a lower slide plate and an upper slide plate, the lower slide plate is fixed to the support structure, a polytetrafluoroethylene slider is provided between the upper slide plate and the lower slide plate, and the top surface of the upper slide plate is provided with an arc groove.
[0051] It should be noted that the predetermined support position refers to the pre-determined location on the support structure for supporting the steel roof truss at its placement end, usually a column top corbel or support platform. A pre-embedded steel plate is generally provided at the predetermined support position. The sliding support includes a lower sliding plate and an upper sliding plate. The lower sliding plate is fixed to the support structure, and the upper sliding plate is stacked on top of the lower sliding plate. A polytetrafluoroethylene (PTFE) slider is provided between the upper and lower sliding plates, and the top surface of the upper sliding plate has an arc-shaped groove.
[0052] The lower sliding plate can be made of steel plate and can be fixed to the pre-embedded steel plate on the top surface of the supporting structure by welding or bolting, providing a stable foundation for the entire sliding support. The upper sliding plate is stacked on top of the lower sliding plate and can slide horizontally relative to the lower sliding plate. A PTFE slider is set between the upper and lower sliding plates. PTFE is a self-lubricating material with an extremely low coefficient of friction. The coefficient of friction between the PTFE slider and the steel plate is generally 0.03~0.05, and no additional lubrication is required, thus ensuring smooth sliding of the upper sliding plate relative to the lower sliding plate and allowing the horizontal displacement of the steel roof truss's positioning end along the length direction to be released smoothly. The arc-shaped groove on the top surface of the upper sliding plate is used to accommodate the bottom of the hydraulic jack. The shape of the arc-shaped groove is adapted to the shape of the bottom of the hydraulic jack, allowing the hydraulic jack to adaptively adjust its posture with the slight rotation of the lower chord of the steel roof truss, ensuring that the lifting force is transmitted along the normal direction of the contact surface and avoiding uneven loading of the hydraulic jack.
[0053] It should be noted that the thickness, area, and plate thickness of the upper and lower sliding plates of the PTFE slider can be calculated based on the magnitude of the design reaction force at the steel roof truss placement end. This embodiment does not impose specific limitations on these parameters. For example, in this embodiment, the design reaction force at the placement end is 1200kN. The PTFE slider is 20mm thick with an area of 0.4m². Its average vertical compressive stress is approximately 1200÷0.4=3000kPa=3MPa, which is far below the allowable compressive stress of PTFE material and can meet the requirements for long-term load-bearing. The above compressive stress is calculated based on the design reaction force at the placement end and the slider area. The design reaction force at the placement end is determined based on the steel roof truss structure.
[0054] S120. The hydraulic jack is placed in the arc groove of the upper sliding plate; wherein, the top of the piston rod of the hydraulic jack is equipped with an arc-shaped top head, and the curvature of the arc-shaped top head matches the bottom curvature of the lower chord of the steel roof truss.
[0055] It should be noted that the piston rod of the hydraulic jack is fitted with an arc-shaped jack head, the curvature of which matches the curvature of the bottom surface of the steel roof truss's lower chord. The arc-shaped jack head is the curved component on the top of the hydraulic jack's piston rod used to contact the bottom surface of the steel roof truss's lower chord. Matching the curvature of the arc-shaped jack head to the bottom surface of the lower chord ensures surface contact rather than point contact, increasing the contact area and distributing the lifting force evenly across the contact surface. This prevents stress concentration due to an insufficient contact area, which could damage the bottom surface of the lower chord. The lower chord of the steel roof truss is generally a round tube or a welded box-shaped section of steel plate, and its bottom curvature can be determined based on the cross-sectional shape of the lower chord. The curvature of the arc-shaped jack head can be machined to conform to the bottom curvature of the lower chord during fabrication.
[0056] In this embodiment, the lower chord of the steel roof truss has a circular tube cross-section with an outer diameter of 0.5m and a bottom surface curvature radius of 0.25m. The curved top end is machined with a curvature radius of 0.25m to achieve surface contact between the curved top end and the bottom surface of the lower chord. The contact stress between the curved top end and the bottom surface of the lower chord can be calculated using the formula... The verification is performed, where σ is the contact stress and F is the lifting force of the hydraulic jack. This refers to the projected area of the contact surface of the curved top. In this embodiment, the projected area of the contact surface of the curved top is... The area is 0.0707 m², and the maximum lifting force F of the hydraulic jack is 1500 kN. Therefore, the contact stress σ = 1500 ÷ 0.0707 ≈ 21.2 MPa, which is much less than the local bearing capacity of the steel, ensuring the safety of the contact surface. The above contact stress is calculated based on the maximum lifting force of the hydraulic jack and the projected area of the contact surface of the arc-shaped jack. The projected area of the contact surface is determined based on the geometric dimensions of the arc-shaped jack.
[0057] S130. Adjust the height of the hydraulic jack so that the arc-shaped jack head contacts the bottom surface of the lower chord of the steel roof truss and applies an initial preload; wherein the initial preload is 50kN~100kN.
[0058] It should be noted that the initial preload refers to the lifting force applied to the bottom surface of the lower chord of the steel roof truss by the hydraulic jack before the lifting load is reduced. The initial preload is 50kN~100kN. During the installation of temporary support devices, the steel roof truss is still suspended by slings. There may be an initial gap between the curved jack head and the bottom surface of the lower chord, or a contact gap between the sliding support and the support structure. By adjusting the height of the hydraulic jack to make the curved jack head contact the bottom surface of the lower chord and applying an initial preload of 50kN~100kN, the aforementioned initial gaps can be eliminated. This ensures that the temporary support device establishes a reliable force connection with the steel roof truss before unloading begins, guaranteeing that the temporary support device immediately participates in bearing the load at the start of unloading and avoiding impact or slippage due to gap closure during the initial load transfer phase.
[0059] In this embodiment, the initial preload is set to 60 kN. The initial preload of the hydraulic jack can be controlled based on the hydraulic pressure reading. The calculation formula can be expressed as Fpreload = ηefficiency × p × A, where Fpreload is the initial preload, ηefficiency is the mechanical efficiency of the hydraulic jack, p is the oil pressure, and A is the effective piston area. In this embodiment, the effective piston area A is 0.0616 m², and the mechanical efficiency ηefficiency is 0.92. Therefore, the oil pressure required to apply the 60 kN initial preload is p = 60 ÷ (0.92 × 0.0616) ≈ 1059 kPa ≈ 1.06 MPa. Since the initial preload is relatively small, the oil pressure reading is in the low-pressure range of the pressure sensor. To improve the accuracy of the initial preload application, a pressure sensor with low-pressure, high-precision characteristics can be used to read the oil pressure, or a force sensor can be temporarily installed between the arc-shaped top head and the bottom surface of the lower chord to directly read the preload. In one embodiment, step S300 includes: S310. An adjusting shim is inserted between the bottom plate of the steel roof truss at its positioning end and the embedded steel plate of the supporting structure; wherein the thickness of the adjusting shim is determined according to the difference between the actual elevation and the design elevation of the steel roof truss at its positioning end.
[0060] It should be noted that the positioning end base plate refers to the base plate at the bottom of the steel roof truss's positioning end used for connection with the supporting structure; it can also be called the support base plate. The embedded steel plate refers to the steel plate pre-embedded in the top surface of the supporting structure for connection with the positioning end base plate. The adjusting shim refers to the thin steel plate shim placed between the positioning end base plate and the embedded steel plate to compensate for the elevation difference between them.
[0061] The thickness of the adjusting shims is determined based on the difference between the actual elevation and the design elevation of the steel roof truss's installation end. The actual elevation refers to the measured elevation of the top surface of the installation end's base plate or the reference point at the installation end, which can be obtained using a level. The design elevation refers to the installation elevation specified in the design drawings. When the actual elevation is lower than the design elevation, adjusting shims of equal thickness to the elevation difference are inserted between the installation end's base plate and the embedded steel plate to bring the installation end to the design elevation. When the actual elevation is higher than the design elevation, this can be addressed by grinding the bottom surface of the installation end's base plate or by using a combination of adjusting shims. Standard shims of thicknesses such as 0.5mm, 1mm, 2mm, and 5mm can be combined to accommodate different elevation differences.
[0062] In this embodiment, the actual elevation of the top surface of the base plate at the positioning end of the steel roof truss, as measured by a level, is 6mm lower than the design elevation. Therefore, two adjusting shims with thicknesses of 5mm and 1mm are inserted between the base plate at the positioning end and the embedded steel plate to bring the elevation of the positioning end to the design elevation. The aforementioned elevation difference is obtained by measuring the elevation control point at the positioning end using a level.
[0063] S320. Connect the positioning end base plate to the pre-embedded steel plate using temporary bolts; wherein the diameter of the temporary bolts is 2mm to 4mm smaller than the diameter of the designed permanent bolts, and the number of temporary bolts is not less than 50% of the number of designed permanent bolts.
[0064] It should be noted that temporary bolts refer to bolts used in the temporary fixing connection stage, while permanent bolts refer to bolts used in the permanent fixing connection stage as specified in the design drawings. The diameter of temporary bolts is 2mm to 4mm smaller than that of permanent bolts, and the number of temporary bolts shall not be less than 50% of the number of permanent bolts.
[0065] The diameter of the temporary bolts is set to be 2mm to 4mm smaller than that of the designed permanent bolts. This allows the temporary bolts to be easily inserted into the bolt holes reserved for the permanent bolts, while maintaining a gap between the bolt and the hole wall. This facilitates rapid installation during the temporary fixing phase and prevents damage to the permanent bolt holes and their walls during the installation and removal of the temporary bolts, ensuring the quality of the subsequent installation of the designed permanent bolts. The number of temporary bolts is set to be no less than 50% of the number of designed permanent bolts. This ensures that the temporary fixing connection has sufficient load-bearing capacity to withstand the reaction force at the steel roof truss's placement end after the slings are completely unloaded, and provides load-bearing assurance for the smooth transfer of load when the temporary support device is subsequently removed.
[0066] In this embodiment, 12 M30 high-strength bolts are designed as permanent bolts, and 8 M27 high-strength bolts (12 × 50% + 2, not less than 50% of the designed permanent bolt count) are used as temporary bolts. The diameter of the temporary bolts is 3mm smaller than the designed permanent bolt diameter, falling within the range of 2mm to 4mm. The total preload of the 8 M27 high-strength bolts is approximately 8 × 200 = 1600kN, which is greater than the designed reaction force of 1200kN at the placement end, thus meeting the load-bearing capacity requirements of the temporary fixed connection. The above preload value is calculated based on the nominal stress cross-sectional area of the bolt and the bolt performance grade. The nominal stress cross-sectional area of the bolt is determined by referring to a table based on the thread specification.
[0067] S330. Tighten the temporary bolts so that the gap between the positioning end base plate and the embedded steel plate does not exceed 1mm.
[0068] It should be noted that the gap between the positioning end base plate and the embedded steel plate refers to the gap remaining between the bottom surface of the positioning end base plate and the top surface of the embedded steel plate in the area where no adjustment shims were installed after inserting the adjusting shims and installing the temporary bolts. By tightening the temporary bolts, the positioning end base plate, adjusting shims, and embedded steel plate are made to fit tightly together, controlling the gap to within 1mm. This ensures a tight contact surface and reliable force transmission, preventing loosening or additional displacement of the positioning end during subsequent unloading and adjustment due to insufficient contact.
[0069] Temporary bolts can be tightened in two symmetrical stages using a torque wrench. The first tightening is to 50% of the design preload, and the second tightening is to the design preload, to reduce uneven stress on the bolts. In this embodiment, the tightening torque of the M27 high-strength bolt is calculated using the formula T=K×F×d, where T is the tightening torque, K is the torque coefficient (taken as 0.2), F is the bolt preload, and d is the nominal bolt diameter. In this embodiment, F is taken as 200kN, and d is taken as 0.027m, so the tightening torque T=0.2×200×0.027=1.08kN·m. After tightening, a feeler gauge is used to check the gap between the base plate at the installation end and the embedded steel plate. The measured gap is 0.6mm, which does not exceed 1mm and meets the requirements.
[0070] In one embodiment, prior to step S200, the method further includes: S500. Install tilt sensors and deflection monitoring points at the positioning end and mid-span position of the steel roof truss, respectively.
[0071] It should be noted that an inclination sensor is a sensor used to measure the tilt angle of steel roof truss members or nodes, and it can be installed at the chord or node at the positioned end of the steel roof truss. A deflection monitoring point is a location set on the steel roof truss to monitor deflection changes. It can be set at the mid-span lower chord node of the steel roof truss, and equipped with observation markers such as prisms or reflectors, and observed in conjunction with a total station. The inclination sensor can be a dual-axis inclination sensor with a range of not less than ±5° and an accuracy of not less than 0.01°. Deflection monitoring can be carried out by continuously observing the mid-span monitoring point using a measuring robot or a total station, with an angle measurement accuracy of not less than 1″ and a distance measurement accuracy of not less than 1mm + 1ppm.
[0072] S600. During the process of the lifting slings detaching, the changes in the tilt angle and deflection of the steel roof truss are monitored in real time.
[0073] It should be noted that the change in tilt angle refers to the change in the tilt angle of the steel roof truss relative to the start of unloading during the unloading process; the change in deflection refers to the change in the vertical displacement of the steel roof truss relative to the start of unloading during the unloading process. The change in tilt angle can be measured in real time by tilt sensors, and the change in deflection can be obtained by real-time observation and calculation of deflection monitoring points using a total station. Monitoring data can be collected at a sampling frequency of 1Hz and transmitted in real time to the monitoring terminal for construction personnel to view at any time.
[0074] S700. If the change in tilt angle exceeds 0.5° or the change in deflection exceeds 20% of the design allowable deflection, unloading shall be stopped immediately. The cause shall be identified and the abnormality eliminated before the unloading operation is continued.
[0075] It should be noted that the design allowable deflection refers to the permissible deflection value of the steel roof truss determined according to relevant specifications and design requirements. For steel roof truss structures, the design allowable deflection is generally taken as 1 / 400 of the steel roof truss span, or it can be taken according to the specific provisions of the design drawings, specifically determined according to the relevant provisions and design requirements of the "Steel Structure Design Standard". In this embodiment, the steel roof truss span is 42m, and the design allowable deflection is taken as 1 / 400 of the span, i.e., 105mm. Therefore, the deflection change threshold is 105mm × 20% = 21mm, and the tilt angle change threshold is 0.5°.
[0076] During unloading, if the change in tilt angle exceeds 0.5° or the change in deflection exceeds 21mm, it indicates that the deformation of the steel roof truss has deviated from the normal unloading state. This may be due to asynchronous unloading, loosening of temporary support devices, or abnormal initial deformation of the steel roof truss. In this case, unloading should be stopped immediately, i.e., the lowering of the hooks of the lifting equipment and the raising of the hydraulic jacks should be stopped. The current load state should be maintained, and technical personnel should be organized to find out the cause and eliminate the abnormality before unloading can continue. For example, during one unloading process in this embodiment, the change in mid-span deflection was detected to suddenly increase from 8mm to 24mm in a short period of time, exceeding the threshold of 21mm. The construction personnel immediately stopped unloading. Upon inspection, it was found that the pad under the sliding support on one side was not dense enough, causing the support to sink. After the pad was filled and the monitoring data was checked and restored to normal, unloading was completed.
[0077] In one embodiment, the preset safe release force threshold is 5% to 10% of the self-weight of the steel roof truss; When the lifting force of the slings decreases to the preset safe release force threshold, the load borne by the temporary support device is 90% to 95% of the design reaction force at the placement end of the steel roof truss.
[0078] It should be noted that the preset safe release force threshold is 5% to 10% of the steel roof truss's self-weight. The formula for calculating the preset safe release force threshold can be expressed as: F_threshold = G × (5% to 10%), where F_threshold is the preset safe release force threshold and G is the self-weight of the steel roof truss. In this embodiment, the self-weight G of the steel roof truss is 2400 kN, so the preset safe release force threshold is 120 kN to 240 kN.
[0079] The preset safe release force threshold determines when to stop reducing the lifting capacity and implement temporary fixing connections. If the threshold is too high, the residual lifting capacity of the slings will still be large when the load reduction stops, requiring temporary fixing connections to be implemented at a high lifting capacity level, and the subsequent load increment after complete unloading will be large. If the threshold is too low, the time to stop the load reduction is delayed, and the temporary support device will be under high load for a long time. Setting the preset safe release force threshold to 5%~10% of the steel roof truss's self-weight ensures that the residual lifting capacity of the slings is at a low level when the load reduction stops, and most of the load at the steel roof truss's positioning end has been transferred to the temporary support device, providing a stable stress environment for the implementation of temporary fixing connections.
[0080] When the lifting capacity of the slings decreases to the preset safe release force threshold, the load borne by the temporary support device is 90% to 95% of the design reaction force at the steel roof truss placement end. It should be noted that the design reaction force at the steel roof truss placement end refers to the design support reaction force at the placement end of the steel roof truss under its own weight and corresponding load combination. In this embodiment, the design reaction force R at the steel roof truss placement end is 1200kN, and the preset safe release force threshold is taken as 5% of the steel roof truss's own weight, i.e., 120kN. At this time, the lifting capacity F_lift of the slings is 120kN, and the load F_support borne by the temporary support device is 1200kN. 120 = 1080 kN, which is 1080 ÷ 1200 × 100% = 90% of the design reaction force at the in-situ end, falling within the range of 90% to 95%. The aforementioned design reaction force at the in-situ end is determined based on calculations for the steel roof truss structure.
[0081] It should be noted that the proportion of the load borne by the temporary support device to the design reaction force at the placement end is related to the value of the preset safe release force threshold and the relationship between the design reaction force at the placement end and the self-weight of the steel roof truss. In this embodiment, the design reaction force at the placement end is half the self-weight of the steel roof truss. When the preset safe release force threshold is 5% of the self-weight of the steel roof truss (i.e., 10% of the design reaction force), the bearing ratio of the temporary support device is 90%. When the structural form of the steel roof truss makes the proportion of the design reaction force at the placement end to the self-weight of the steel roof truss higher, the bearing ratio of the temporary support device will be further increased under the same threshold value, up to a maximum of 95%. During project implementation, the preset safe release force threshold can be determined within the range of 5% to 10% of the self-weight of the steel roof truss, combined with the relationship between the design reaction force at the placement end and the self-weight, so that the load borne by the temporary support device reaches 90% to 95% of the design reaction force at the placement end when the load reduction stops, thereby ensuring that the temporary fixed connection is implemented under conditions close to the design stress state.
[0082] In one embodiment, step S400 includes: S410. Continue to reduce the lifting capacity of the slings at a fine unloading rate that is slower than the preset unloading rate; wherein the fine unloading rate is 30% to 50% of the preset unloading rate.
[0083] It should be noted that the fine unloading rate refers to the unloading rate used to further reduce the lifting force after the temporary fixed connection is completed. The fine unloading rate is 30% to 50% of the preset unloading rate. In this embodiment, the preset unloading rate is 4% of the steel roof truss's self-weight per minute, i.e., 96 kN / min. Therefore, the fine unloading rate is 96 × 30% to 96 × 50%, i.e., 28.8 kN / min to 48 kN / min. In this embodiment, the fine unloading rate is taken as 38.4 kN / min, which is 40% of the preset unloading rate.
[0084] After the temporary fixing connection is completed, the load at the steel roof truss's positioned end is borne simultaneously by the temporary support device and the temporary fixing connection. The temporary bolts in the temporary fixing connection have already begun to bear the load. If the unloading continues at the preset unloading rate, the load will increase rapidly in the temporary bolts, making it difficult to observe and control the stress state of the temporary fixing connection. By adopting a fine unloading rate that is slower than the preset unloading rate, the release of the residual lifting force is made more gradual, the load increase process in the temporary bolts is more controllable, and sufficient reaction time is allowed for the detection after each stage of unloading.
[0085] S420. After each increment of the lifting force of the sling is reduced, pause for 30s to 60s and detect the change in bolt stress at the temporary fixed connection and the change in displacement of the steel roof truss.
[0086] It should be noted that the increment refers to the amount of load reduction in the lifting force during each fine unloading process. The magnitude of the increment can be determined based on the fine unloading rate and the pause duration. For example, the increment can be set to be equal to the product of the fine unloading rate and the 1-minute unloading duration. In this embodiment, the increment is 40kN, meaning that the lifting force is paused once after each 40kN reduction. Bolt stress change refers to the stress difference of the temporary bolts at the temporary fixed connection before and after the current unloading increment. It can be measured by strain gauges attached to the temporary bolts. The strain gauges are collected in real time by a strain acquisition instrument at a sampling frequency of not less than 1Hz. The bolt stress is calculated by multiplying the strain by the elastic modulus of the steel. Steel roof truss displacement change refers to the displacement difference of the steel roof truss end before and after the current unloading increment. It can be measured by a dial gauge or displacement gauge set between the base plate and the embedded steel plate at the end of the end, or by observing the monitoring points at the end of the end using a total station.
[0087] After each increment of the lifting force, a pause of 30-60 seconds was taken to allow the steel roof truss and temporary fixed connections to stabilize under the new load level. Then, bolt stress and displacement changes were monitored. If the bolt stress change did not exceed a preset stress change threshold and the displacement change did not exceed a preset displacement change threshold, no abnormality was confirmed. If the thresholds were exceeded, unloading was immediately stopped and the cause investigated. In this embodiment, the preset stress change threshold was 15 MPa, and the preset displacement change threshold was 1 mm. During the unloading process in this embodiment, the lifting force was reduced from 120 kN to 0 in three stages, with a reduction of 40 kN per stage, followed by a 45-second pause after each stage. The measured bolt stress change after each unloading stage was 8-11 MPa, and the displacement change was 0.3-0.5 mm, both within the corresponding thresholds, confirming no abnormality. The bolt stress changes were measured using strain gauges and calculated using strain gauges, while the displacement changes were measured using dial gauges.
[0088] S430. After confirming that there are no abnormalities, continue to reduce the lifting capacity of the slings until the slings are completely unloaded.
[0089] It should be noted that the next level of unloading can only be carried out after each level of unloading is completed and confirmed to be without any abnormalities. This process is repeated level by level until the lifting capacity is reduced to zero and the slings are completely unloaded.
[0090] In this embodiment, after each increment of the lifting force, the process is paused for 30-60 seconds to detect changes in bolt stress and displacement. Unloading continues only after confirming that there are no abnormalities. This makes the release of residual lifting force after the temporary fixed connection participates in the stress more gradual, verifiable, and controllable. The stress increase of the temporary bolts and the displacement change of the steel roof truss are verified after each stage of unloading, ensuring that the temporary fixed connection is safe and reliable during the complete unloading process, thereby further reducing the operational risks during the complete unloading stage.
[0091] In one embodiment, the span of the steel roof truss is not less than 36m, and the weight of the steel roof truss is not less than 200 tons; The lifting slings include at least two lifting devices, each of which lifts different points of the steel roof truss. The unloading operations of each lifting device are carried out synchronously, with a synchronization time deviation of no more than 3 seconds.
[0092] It should be noted that the span of the steel roof truss is not less than 36m, and the weight of the steel roof truss is not less than 200 tons. The span of the steel roof truss refers to the distance between the two end support points of the steel roof truss. Large steel roof trusses with a span of not less than 36m and a weight of not less than 200 tons have huge hoisting loads, relatively small structural stiffness, and a large impact range of load transfer during unloading. Using the unloading method of this application can effectively avoid unloading impact and structural damage. The method of this application has outstanding applicability to this type of steel roof truss. In this embodiment, the span of the steel roof truss is 42m, and the weight is about 240 tons (self-weight about 2400kN), which meets the above specifications. The span of the steel roof truss is determined according to the design drawings, and the self-weight is calculated based on the cross-sectional dimensions of the steel roof truss members and the weight of the steel, and determined by repeated weighing.
[0093] The lifting slings consist of at least two lifting devices, each lifting different points on the steel roof truss. A lifting point refers to the location where the slings connect to the steel roof truss during lifting; the number and location of these points are determined based on the span, weight, and lifting plan of the steel roof truss. Using at least two lifting devices to lift different points distributes the self-weight load of the steel roof truss across multiple points, reducing the lifting capacity of a single lifting device and minimizing structural internal forces caused by single-point lifting. The unloading operations of each lifting device are performed synchronously, with a synchronization time deviation not exceeding 3 seconds. Synchronization time deviation refers to the maximum time difference between the start times of the unloading operation (hooking down) of each lifting device. For example, if two lifting devices are agreed to start lowering the hook at the same time, and the actual start times of the two devices differ by 2.1 seconds, which does not exceed 3 seconds, the synchronization time deviation requirement is met.
[0094] The unloading operations of each lifting device are carried out synchronously to avoid uneven stress on the steel roof truss due to asynchronous unloading at different lifting points, thereby preventing out-of-plane torsion, lateral deformation, or even instability of the steel roof truss. In this embodiment, the initial lifting capacity of both lifting devices is 1200kN. Each lifting device reduces the lifting capacity of its hook at a rate of 4% of the steel roof truss's own weight per minute (i.e., 96kN / min). If the starting time deviation between the two lifting devices is 3 seconds, the resulting difference in lifting capacity is 96÷60×3=4.8kN, which is only 4.8÷1200×100%=0.4% of the lifting capacity of a single lifting device. This is far less than the 5% synchronization deviation control requirement, indicating that when the synchronization time deviation does not exceed 3 seconds, the unloading process of each lifting point has sufficient synchronicity.
[0095] In one feasible implementation, synchronization of each lifting device can be achieved through a unified command signal (such as walkie-talkie instructions, flag signals, or audio-visual signals); in another feasible implementation, the control systems of each lifting device can be connected to a unified unloading control platform, which can simultaneously issue hook-lowering commands to each lifting device; in yet another feasible implementation, a linkage control method can be adopted in which one lifting device is the master and the other lifting devices are slaves.
[0096] In one embodiment, after the slings are completely unloaded, the method further includes: Keeping the temporary support device under load, remove the hook of the sling from the lug of the steel roof truss; The positioning end of the steel roof truss is precisely adjusted; wherein, the precise adjustment includes horizontal displacement adjustment and elevation adjustment, the horizontal displacement adjustment accuracy is ±2mm, and the elevation adjustment accuracy is ±1mm; After precise adjustment, the temporary support device is removed, and the positioned end of the steel roof truss is permanently fixed to the support structure.
[0097] It should be noted that lifting lugs refer to ear plates or lifting rings, etc., installed on the steel roof truss for connecting the slings during hoisting. After the slings are completely unloaded, the lifting capacity is zero, and the steel roof truss is supported by temporary support devices and temporary fixed connections. The temporary support devices are kept under load; that is, after the slings are completely unloaded, the hydraulic jacks continue to lift (pressure holding or mechanical locking) to ensure that the positioned end of the steel roof truss remains in a stable supported state. Then, the hook is removed from the lifting lug, completing the sling removal. Removing the hook at this point will not cause any load change; the steel roof truss structure is stable, and the hoisting equipment can be removed. Precise adjustment refers to the high-precision adjustment of the installation position of the positioned end of the steel roof truss after the slings are completely unloaded. Precise adjustment includes horizontal displacement adjustment and elevation adjustment; the accuracy of horizontal displacement adjustment is ±2mm, and the accuracy of elevation adjustment is ±1mm.
[0098] In one embodiment, the sliding support allows horizontal sliding during precise adjustment of the steel roof truss at its positioning end, and the horizontal sliding resistance of the sliding support is 5% to 10% of the horizontal force at the positioning end of the steel roof truss, so as to provide moderate horizontal constraint while allowing fine-tuning of position during adjustment.
[0099] The sliding bearing allows for horizontal sliding during precise adjustments at the positioning end of the steel roof truss. As mentioned earlier, a PTFE slider is provided between the upper and lower sliding plates of the sliding bearing. The upper sliding plate can slide horizontally relative to the lower sliding plate. Therefore, during the precise adjustment phase, the positioning end of the steel roof truss can be finely adjusted in horizontal position through the sliding of the sliding bearing without interrupting the vertical load.
[0100] It should be noted that the horizontal sliding resistance of the sliding support is 5% to 10% of the horizontal force at the steel roof truss placement end. The horizontal force at the steel roof truss placement end refers to the horizontal force acting along the length of the steel roof truss during unloading and precise adjustment, including the horizontal component generated by the redistribution of internal forces and the horizontal force generated by temperature effects; its magnitude is determined through structural calculations. The horizontal sliding resistance refers to the frictional resistance that the sliding support must overcome when it slides horizontally. The horizontal sliding resistance can be calculated using the formula F_resistance = μ × N, where F_resistance is the horizontal sliding resistance, μ is the coefficient of friction (0.03~0.05) between the PTFE slider and the steel plate, and N is the vertical pressure borne by the sliding support.
[0101] In this embodiment, the horizontal force at the steel roof truss placement end is determined to be 700kN based on structural calculations. During the precise adjustment stage, the vertical pressure N borne by the sliding support is approximately 1200kN, the design reaction force at the placement end. With a friction coefficient μ of 0.04, the horizontal sliding resistance F_resistance = 0.04 × 1200 = 48kN. The proportion of the horizontal sliding resistance to the horizontal force at the steel roof truss placement end is 48 ÷ 700 × 100% ≈ 6.9%, falling within the range of 5% to 10%. The aforementioned friction coefficient is within the conventional range for friction coefficients between PTFE and steel plates. The values of the vertical pressure and horizontal force are determined based on the steel roof truss structural calculations.
[0102] Setting the horizontal sliding resistance to 5%~10% of the horizontal force at the steel roof truss's positioning end ensures that the sliding support provides appropriate horizontal constraint to the positioning end during precise adjustment: the horizontal sliding resistance is not too large, ensuring smooth sliding and fine-tuning of the positioning end under the jacking of the horizontal jack, without generating additional internal forces in the steel roof truss due to excessive constraint; at the same time, the horizontal sliding resistance is not too small, preventing uncontrolled free sliding of the positioning end under the action of unloading residual horizontal force. Thus, the precise adjustment process is carried out under controllable constraint conditions, balancing the convenience of adjustment with the stability of the structure.
[0103] To verify the technical effectiveness of the steel roof truss sling release method provided in this application, two steel roof trusses of the same specifications were selected for a comparative unloading test in a large factory project. Both steel roof trusses had a span of 42m, a self-weight of approximately 2400kN, and identical structural form, member specifications, and support conditions. One steel roof truss (control example) was unloaded using the conventional direct unloading method, i.e., after hoisting into place, the lifting equipment was directly lowered to quickly and completely remove the load. After the load was completely removed, temporary bolts were used to temporarily fix the positioned end to the supporting structure. The specifications and quantity of the temporary bolts were the same as in the example, to compare the impact of the two unloading methods on the stress of the temporary fixed connection. The other steel roof truss (example) was unloaded using the methods described in Examples 1 to 10 of this application.
[0104] The monitoring content and data acquisition methods are as follows: A dual-axis tilt sensor (range ±5°, accuracy 0.01°) was installed at the end chord node of each of the two steel roof trusses. A deflection monitoring point was set at the mid-span lower chord node, and observations were conducted using a total station (angle accuracy 1″, distance accuracy 1mm+1ppm). A lifting force sensor (accuracy 0.5%FS) was installed at the lifting hook of the sling, and a pressure sensor (range 25MPa, accuracy 0.5%FS) was installed in the hydraulic jack circuit. Strain gauges were attached to the temporary bolts at the temporary fixed connection in the example, and bolt stress was monitored using a strain gauge. All monitoring data were collected synchronously at a sampling frequency of 1Hz. After noise reduction, the peak values during the entire unloading process were statistically analyzed. To ensure fairness in the comparison, the measuring points of the two steel roof trusses were arranged in the same locations, and the sensor models and calibration conditions were the same. The ambient temperature during the monitoring period was 20±2℃, and the wind speed was no greater than level three.
[0105] The results of the comparative experiment are shown in the table below:
[0106] As can be seen from the data in the table above, compared with the conventional direct unloading method, the method of this application extends the load release process to approximately 11 minutes, reducing the maximum fluctuation of the load transfer rate from ±21% to ±3.4%, the maximum change in the tilt angle at the placement end from 0.78° to 0.13°, the maximum change in mid-span deflection from 24mm to 8mm, the peak stress of the bolts at the temporary fixing connection from 231MPa to 156MPa, and the elevation deviation at the placement end after unloading from 5.2mm (exceeding the ±1mm accuracy requirement) to 0.8mm (meeting the ±1mm accuracy requirement). These data indicate that the method of this application enables the load at the placement end of the steel roof truss to be transferred smoothly and continuously from the slings to the supporting structure, significantly reducing deformation and stress fluctuations during the unloading process, avoiding impact damage to the steel roof truss and supporting structure from sudden load changes, and ensuring the placement accuracy of the steel roof truss.
[0107] It should be noted that the comparative test data mentioned above were obtained from on-site monitoring of the entire unloading process of two steel roof trusses of the same specification. The data was collected synchronously by the aforementioned tilt sensor, total station, load force sensor, pressure sensor, and strain gauge at a sampling frequency of 1Hz, and then processed for noise reduction and peak value statistics. The above comparative tests are merely exemplary tests listed to illustrate the technical effects of the technical solution of this application. This application does not limit the specific test conditions, test objects, or test results.
[0108] Finally, it should be noted that the calculation formulas, judgment criteria, and parameters in this specification are all theoretical models or design parameters. Their specific values should be determined based on the actual structural form, span, self-weight, design reaction force at the positioning end, support structure form, and construction site conditions of the steel roof truss. The specific values of parameters such as hydraulic jack lifting force, initial preload, preset unloading rate, synchronization deviation, preset safety release force threshold, shim thickness, temporary bolt specifications and quantity, tilt angle change threshold, deflection change threshold, fine unloading rate, unloading increment, pause duration, horizontal displacement adjustment accuracy, elevation adjustment accuracy, and horizontal sliding resistance ratio listed in the embodiments of this application are only used to illustrate the technical solution of this application and do not constitute a limitation on the scope of protection of this application. This invention does not involve limitations on specific test results.
[0109] The above description is merely an exemplary embodiment of this application and does not limit the scope of this application. Any equivalent structural transformations made based on the technical concept of this application and the contents of the application specification and drawings, or direct / indirect applications in other related technical fields, are included within the protection scope of this application.
Claims
1. A method for detaching slings from steel roof trusses, characterized in that, Includes the following steps: A temporary support device is installed between the positioning end of the steel roof truss and the supporting structure; wherein the temporary support device includes a hydraulic jack and a sliding support, the lifting force of the hydraulic jack is 1.1 to 1.3 times the reaction force at the end corresponding to the self-weight of the steel roof truss, and the sliding direction of the sliding support is consistent with the length direction of the steel roof truss. The lifting force of the slings is reduced synchronously and slowly, while the hydraulic jack actively lifts the positioning end of the steel roof truss at a matching speed, so that the load at the positioning end of the steel roof truss is gradually transferred from the slings to the temporary support device; wherein, the synchronous deviation between reducing the lifting force and actively lifting is controlled within 5%; When the lifting force of the sling is reduced to the preset safe release force threshold, the reduction of the lifting force of the sling is stopped, and the positioning end of the steel roof truss is temporarily fixedly connected to the supporting structure. After the temporary fixed connection is completed, continue to reduce the lifting force of the slings until the slings are completely unloaded, and then detach the slings from the steel roof truss.
2. The method for detaching steel roof truss slings as described in claim 1, characterized in that, The step of synchronously and slowly reducing the lifting force of the slings includes: The lifting equipment control system of the slings reduces the lifting force of the hook at a preset unloading rate; wherein the preset unloading rate is 3% to 5% of the self-weight of the steel roof truss per minute. The load sensor values of the slings and the pressure sensor values of the hydraulic jacks are read in real time to calculate the proportion of the load borne by the slings and the proportion of the load borne by the temporary support device at the positioning end of the steel roof truss. The descent speed of the lifting equipment and the lifting speed of the hydraulic jack are dynamically adjusted according to the load ratio to keep the load transfer rate of both consistent.
3. The method for detaching steel roof truss slings as described in claim 1, characterized in that, The step of installing a temporary support device between the positioned end of the steel roof truss and the supporting structure includes: The slidable support is placed at a predetermined support position on the support structure; wherein, the slidable support includes a lower slide plate and an upper slide plate, the lower slide plate is fixed to the support structure, a polytetrafluoroethylene slider is provided between the upper slide plate and the lower slide plate, and the top surface of the upper slide plate is provided with an arc groove; The hydraulic jack is placed in the arc groove of the upper sliding plate; wherein, the top of the piston rod of the hydraulic jack is equipped with an arc-shaped top head, and the curvature of the arc-shaped top head matches the bottom curvature of the lower chord of the steel roof truss. Adjust the height of the hydraulic jack so that the arc-shaped jack head contacts the bottom surface of the lower chord of the steel roof truss and applies an initial preload; wherein the initial preload is 50kN~100kN.
4. The method for detaching steel roof truss slings as described in claim 2, characterized in that, The step of temporarily fixing the positioned end of the steel roof truss to the supporting structure includes: An adjusting shim is inserted between the bottom plate of the steel roof truss at its placement end and the embedded steel plate of the supporting structure; wherein the thickness of the adjusting shim is determined according to the difference between the actual elevation and the design elevation of the steel roof truss at its placement end. The positioning end base plate is connected to the embedded steel plate using temporary bolts; wherein the diameter of the temporary bolts is 2mm to 4mm smaller than the diameter of the designed permanent bolts, and the number of temporary bolts is not less than 50% of the number of designed permanent bolts; Tighten the temporary bolts so that the gap between the positioning end base plate and the embedded steel plate does not exceed 1mm.
5. The method for detaching steel roof truss slings as described in claim 2, characterized in that, Prior to the step of synchronously and slowly reducing the lifting force of the slings, the method further includes: Inclination sensors and deflection monitoring points are installed at the positioning end and mid-span position of the steel roof truss, respectively; During the detachment of the slings, the changes in the tilt angle and deflection of the steel roof truss are monitored in real time. If the change in tilt angle exceeds 0.5° or the change in deflection exceeds 20% of the design allowable deflection, unloading should be stopped immediately. The cause should be identified and the abnormality eliminated before the unloading operation can continue.
6. The method for detaching steel roof truss slings as described in claim 2, characterized in that, The preset safe release force threshold is 5% to 10% of the self-weight of the steel roof truss; When the lifting force of the slings decreases to the preset safe release force threshold, the load borne by the temporary support device is 90% to 95% of the design reaction force at the placement end of the steel roof truss.
7. The method for detaching steel roof truss slings as described in claim 4, characterized in that, After the temporary fixing connection is completed, the step of continuing to reduce the lifting capacity of the slings until the slings are completely unloaded includes: The lifting capacity of the slings is further reduced at a fine unloading rate that is slower than the preset unloading rate; wherein the fine unloading rate is 30% to 50% of the preset unloading rate. After each increment of the lifting force of the slings, pause for 30 to 60 seconds and detect the changes in bolt stress at the temporary fixed connection and the displacement of the steel roof truss. After confirming that there are no abnormalities, continue to reduce the lifting capacity of the slings until the slings are completely unloaded.
8. The method for detaching steel roof truss slings as described in claim 1, characterized in that, The span of the steel roof truss is not less than 36m, and the weight of the steel roof truss is not less than 200 tons; The lifting slings include at least two lifting devices, each of which lifts different points of the steel roof truss. The unloading operations of each lifting device are carried out synchronously, with a synchronization time deviation of no more than 3 seconds.
9. The method for detaching the steel roof truss slings as described in any one of claims 1 to 8, characterized in that, After the slings are completely unloaded, the method further includes: Keeping the temporary support device under load, remove the hook of the sling from the lug of the steel roof truss; The positioning end of the steel roof truss is precisely adjusted; wherein, the precise adjustment includes horizontal displacement adjustment and elevation adjustment, the horizontal displacement adjustment accuracy is ±2mm, and the elevation adjustment accuracy is ±1mm; After precise adjustment, the temporary support device is removed, and the positioned end of the steel roof truss is permanently fixed to the support structure.
10. The method for detaching the steel roof truss slings as described in any one of claims 1 to 8, characterized in that, The sliding support allows horizontal sliding when the steel roof truss is precisely adjusted at its positioning end. The horizontal sliding resistance of the sliding support is 5% to 10% of the horizontal force at the positioning end of the steel roof truss, so as to provide appropriate horizontal constraint while allowing fine-tuning of position during the adjustment process.