A method, system and medium for DC collection power supply of distributed power sources in a transformer substation.

By introducing a common DC bus and back-to-back DC remote power supply equipment into the low-voltage distribution area, the network topology was reconstructed and an optimized scheduling model was built. This solved the problem of unbalanced three-phase power supply caused by disordered AC grid connection of distributed photovoltaic power, improved voltage quality, reduced losses, and enhanced grid interaction efficiency.

CN123073685APending Publication Date: 2026-11-10YUNNAN POWER GRID CO LTD ELECTRIC POWER RES INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611396520.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-09
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Existing technologies are insufficient to effectively address the problems of three-phase power supply imbalance, reduced voltage quality, and increased overall losses caused by disordered AC grid connection of distributed photovoltaic systems. In particular, in low-voltage distribution areas, traditional reactive power compensation methods are difficult to adapt to changes in photovoltaic output, leading to a decline in grid interaction efficiency.

Method used

By introducing a common DC bus and back-to-back DC remote power supply equipment into the low-voltage distribution area, the network topology is reconstructed, and the distributed photovoltaic grid connection mode is changed from AC to DC aggregation. A comprehensive objective function and an optimized scheduling model are constructed to achieve power balance and voltage optimization control.

Benefits of technology

It achieves symmetry in three-phase power distribution, improves voltage quality, reduces overall losses, enhances energy efficiency in interaction with the upstream power grid, and strengthens the system's adaptability and reliability under multiple operating conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123073685A_ABST
    Figure CN123073685A_ABST
Patent Text Reader

Abstract

This application discloses a method for DC aggregation power supply of distributed power sources in a transformer substation, belonging to the field of smart grid technology. The method includes: acquiring the network topology and basic parameters of each electrical device in the transformer substation; reconstructing the network topology to obtain a reconstructed network topology; determining the power balance constraint of the common DC bus based on the reconstructed network topology and basic parameters; constructing a comprehensive objective function based on the basic parameters; determining the optimal scheduling model of the transformer substation based on the reconstructed network topology, basic parameters, power balance constraint, and comprehensive objective function; acquiring real-time operating data of the transformer substation and inputting it into the optimal scheduling model for solving, obtaining the power target values ​​corresponding to the back-to-back DC remote power supply equipment and photovoltaic converters, and optimizing the power supply control of the transformer substation based on the power target values. By implementing this application, the three-phase balance of power supply, voltage safety, and the economy and reliability of the distribution network can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of smart grid technology, and in particular to a method, system and medium for DC collection and power supply of distributed power sources in a transformer substation. Background Technology

[0002] Distribution transformer substations are a crucial link connecting the power system and end users. With the widespread integration of distributed renewable energy and diverse loads, unprecedented challenges have arisen for three-phase power supply balance, power quality, and operational control. Achieving flexible, efficient, low-carbon, and high-quality power supply in low-voltage substations remains a technical challenge both domestically and internationally. For example, the degree of three-phase power supply balance directly affects the operating efficiency and lifespan of electrical equipment in the substation and even the medium-voltage system. As the scale of distributed photovoltaic (PV) installations on the user side continues to expand, the direct connection of single-phase PV power generation systems to substations via AC lines is becoming increasingly common. Because PV output is significantly random and intermittent due to the influence of sunlight intensity, and because the connection phases of various PV systems lack unified coordination, the active power distribution on each phase line of the substation frequently deviates from a symmetrical state. This low-voltage imbalance not only further leads to reduced voltage quality, increased overall losses, and decreased energy efficiency in interaction with the upstream power grid, but also weakens the substation's ability to accommodate distributed renewable energy and new loads, increasing additional losses in transformer power transmission. Meanwhile, under the disturbance and impact of massive distributed resources on power quality, the complexity of efficient power supply and power quality coordination in distribution areas has reached more than 100 times that of the main grid side, becoming a core bottleneck restricting the safe and economical operation of distribution areas.

[0003] Existing technologies typically involve installing static var generators (SVMs) or parallel capacitor banks at the busbars or feeders of low-voltage distribution areas to monitor the system's reactive power demand in real time and inject inductive or capacitive reactive current into the grid. This supports the busbar voltage and indirectly affects the current distribution of each phase. This approach relies on rapid tracking of the system's reactive power deficit, adjusting reactive power output to change the voltage drop on transmission lines, thereby adjusting the distribution ratio of active current in each phase. However, the effectiveness of this method is limited by the matching degree between the device's installation location and the system's equivalent impedance. When the output or load of distributed photovoltaic systems changes, the equivalent impedance of each phase changes accordingly. Pre-set reactive power output strategies are difficult to adapt to actual phase compensation requirements, and cannot simultaneously address multiple optimization objectives such as voltage over-limit suppression, minimizing overall losses, and improving energy efficiency with the upstream grid. Therefore, how to optimize the power supply control of disordered AC grid connection of low-voltage distributed photovoltaic systems to improve voltage quality, reduce overall losses, and enhance interaction efficiency with the upstream grid is a pressing technical problem that needs to be solved. Summary of the Invention

[0004] This application provides a DC collection power supply method, system, and medium for distributed power sources in low-voltage distribution areas, which optimizes the power supply control for disordered AC grid connection of distributed photovoltaic power in low-voltage distribution areas, thereby improving voltage quality, reducing overall losses, and improving energy efficiency in interaction with the upstream power grid.

[0005] This application provides a method for DC collection and power supply of distributed power sources in a transformer substation, including: Obtain the network topology of the transformer area and the basic parameters of each electrical device; The network topology is reconstructed to obtain a reconstructed network topology; wherein the reconstructed network topology includes a common DC bus, back-to-back DC remote power supply equipment, transformers, photovoltaic converters, and energy storage devices; Based on the reconstructed network topology and the basic parameters, the power balance constraints of the common DC bus are determined. Based on the aforementioned fundamental parameters, a comprehensive objective function is constructed; the comprehensive objective function includes a three-phase imbalance objective function, an operating cost objective function, and a voltage deviation objective function. Based on the reconstructed network topology, the basic parameters, the power balance constraints, and the comprehensive objective function, the optimal scheduling model for the transformer area is determined. The real-time operating data of the transformer substation is obtained; the real-time operating data is input into the optimization scheduling model for solution to obtain the power target values ​​corresponding to the back-to-back DC remote power supply equipment and the photovoltaic converter, so as to optimize the power supply control of the transformer substation based on the power target values.

[0006] This application provides a data foundation for subsequent grid connection reconfiguration and optimization scheduling model construction by acquiring the network topology and basic parameters of each electrical device in the distribution area. Based on this, the original network topology of the distribution area is reconfigured by adding a common DC bus to change the grid connection mode of distributed photovoltaics from localized AC grid connection to DC convergence. This eliminates the power injection disorder caused by the random connection of single-phase photovoltaics to each AC phase line, suppresses the conditions for three-phase imbalance in physical structure, and shortens the electrical distance for photovoltaic power transmission to the load side, reducing power transmission losses on AC lines. Based on the reconstructed network topology and fundamental parameters, a power balance constraint for the common DC bus is established to ensure that the DC power conservation relationship has a clear mathematical boundary at the optimization modeling level. A comprehensive objective function consisting of three-phase imbalance, operating cost, and voltage deviation is constructed, quantifying voltage quality improvement, loss reduction, and energy efficiency optimization in interaction with the upper-level power grid as a unified optimization objective. Furthermore, an optimization scheduling model is determined based on the network topology, fundamental parameters, power balance constraints, and comprehensive objective function. This ensures that minimizing three-phase imbalance, operating cost, and voltage deviation becomes an inherent objective that the optimization model must actively satisfy during the solution process, rather than a post-event indicator evaluated after the optimization results are generated. Real-time operating data of the distribution areas is acquired and input into the optimization scheduling model for solution. Back-to-back DC remote power supply equipment adjusts the three-phase power distribution between the AC main grid and the common DC bus according to the obtained power target value. Photovoltaic converters adjust their power output according to the power target value. The synergistic effect of both makes the power distribution of each phase tend to be symmetrical again, and the node voltage distribution tends to be stable. Compared with the existing end-of-pipe treatment method that makes ex-post adjustments through reactive power compensation, this application starts from reconstructing the grid connection mode of distributed photovoltaics, internalizing voltage quality improvement, comprehensive loss reduction and energy efficiency optimization of interaction with the upper-level power grid as the solution objectives of the optimization model, and realizing coordinated control from source suppression to real-time correction.

[0007] Further, the process of reconstructing the network topology to obtain a reconstructed network topology includes: The common DC bus is connected to the DC side of the back-to-back DC remote power supply equipment; wherein, there may be several back-to-back DC remote power supply equipment. Determine the AC busbar connected to the low-voltage side of the transformer, and connect the main port of the back-to-back DC remote power supply equipment to the AC busbar; Identify the load-side node with the highest voltage imbalance in the transformer area, and connect the slave port of the back-to-back DC remote power supply equipment to the load-side node. Each photovoltaic power generation system is connected to the common DC bus through the DC port of its corresponding photovoltaic converter to obtain the reconstructed network topology.

[0008] By defining the connection of the main port of the back-to-back DC remote power supply equipment to the low-voltage side bus of the transformer, the secondary port to the load-side node, and the DC side to the common DC bus, as well as the connection of distributed photovoltaic power to the common DC bus via photovoltaic converters, the physical channels for bidirectional power flow in the reconstructed back-end area are clarified: the main port establishes a power exchange interface between the DC collection side and the AC main grid, enabling surplus photovoltaic power to have a physical path to feed to the upper-level grid; the secondary port forms the terminal channel for local consumption of DC power, shortening the electrical distance for photovoltaic power to supply power to the load; the DC side uses the common DC bus as the collection node for various distributed power sources; and the connection of the photovoltaic converter to the common DC bus ensures that the power injection of single-phase photovoltaic power no longer directly acts on the AC phase lines, but first enters the DC side for unified collection and then is distributed as needed. Thus, the disorder of power injection caused by the random connection of single-phase photovoltaic power to the AC phase lines is eliminated in the physical structure, providing a structural basis for the coordinated mutual assistance of three-phase power.

[0009] Furthermore, the transformer includes an additional transformer or other substation power supply transformer, and connecting the main port of the back-to-back DC remote power supply equipment to the AC busbar further includes: Connect the high-voltage side of the added transformer to the upstream medium-voltage line; The main port of the back-to-back DC remote power supply equipment is connected to the low-voltage AC bus of the added transformer; wherein, the back-to-back DC remote power supply equipment adjusts the active power and reactive power of the added transformer respectively, so that the three-phase imbalance of the added transformer is limited to a preset range.

[0010] By limiting the main port of the back-to-back DC remote power supply equipment to connect to the upper-level medium-voltage distribution area via an additional transformer, and establishing a connection between the main port of the back-to-back DC remote power supply equipment and the additional transformer, excess photovoltaic power is directly fed back to the upper-level medium-voltage distribution area via the main port and the additional transformer. This avoids the reverse transmission of excess power on the distribution transformer in the distribution area, reducing the operating burden on the distribution transformer. Through separate adjustment of the active and reactive power of each phase of the additional transformer via the main port, and with the secondary current of each phase of the additional transformer as the direct control object, three-phase independent control is implemented. This limits the three-phase imbalance of the additional transformer itself to within the allowable range. Simultaneously, this is coordinated with the three-phase imbalance management of the distribution transformer in the distribution area via the slave port, achieving synchronous management of the three-phase imbalance of the existing transformer and the additional transformer. The additional transformer operates independently of the existing distribution transformer, and the two are not coupled, further enhancing the system's adaptability and reliability under various operating conditions.

[0011] Further, determining the power balance constraints of the common DC bus based on the reconstructed network topology and the basic parameters includes: Based on the reconstructed network topology, each power injection device and each power outflow device connected to the common DC bus is determined. Based on the aforementioned basic parameters, the injected power value of each power injection device and the outflow power value of each power outflow device are determined. The power balance constraint is determined based on each of the injected power values ​​and each of the outflow power values.

[0012] By identifying the injecting and consuming devices connected to the common DC bus based on the reconstructed network topology, the scope of DC bus power balance calculation was established, clarifying which devices inject power into the bus and which devices draw power from the bus, providing a physical topology basis for subsequent constraint construction. Injected and consuming power values ​​were determined based on fundamental parameters, quantifying the device power data into specific numerical boundaries of the constraints, thus providing calculable input parameters for the power balance relationship. Power balance constraints were determined based on the injected and consuming power values, establishing an equation on the common DC bus where the sum of injected power equals the sum of consuming power. This constraint serves as a mandatory boundary condition for the optimized scheduling model, ensuring that any power command derived from the optimization solution satisfies the power conservation law of the DC bus. This mathematically guarantees the physical executability of the optimization results and avoids invalid scheduling schemes with power imbalances.

[0013] Furthermore, the basic parameters include the three-phase output current of the transformer, and the objective function for determining the three-phase unbalance includes: Determine the maximum and minimum current values ​​among the three-phase output currents of the transformer; Determine the current direction of the three-phase output current; The objective function for the three-phase unbalance is determined based on the current direction, the maximum current value, and the minimum current value.

[0014] By determining the maximum and minimum values ​​of the three-phase output current of the transformer, two extreme parameters characterizing the current amplitude deviation are extracted from the measured data of the three-phase current, providing a quantifiable data basis for the degree of amplitude asymmetry of the three-phase current. The current direction of the three-phase output current is determined, and the positive and negative polarities of each phase current are used as the basis for segmented calculations. This allows the construction of the objective function to distinguish between different operating conditions of forward current flow and reverse injection, avoiding evaluation distortion caused by using a single calculation formula in bidirectional power flow scenarios. Based on the current direction, maximum current value, and minimum current value, the objective function for three-phase imbalance is determined, integrating the current extreme values ​​and direction information into a unified mathematical expression. This allows the amplitude deviation and directional difference of the three-phase current to be characterized by the same quantitative index. This objective function is directly used as an optimization objective in the subsequent optimization scheduling model, making the minimization of three-phase imbalance a goal that the optimization model must actively pursue during the solution process, rather than a post-event indicator evaluated after the optimization results are generated.

[0015] Further, determining the three-phase unbalance objective function based on the current direction, the maximum current value, and the minimum current value includes: When the current direction is positive, the current difference between the maximum current value and the minimum current value is determined, and the current difference is divided by the maximum current value to obtain the three-phase unbalance objective function. When the current direction is reversed, determine the first absolute value of the minimum current value and the second absolute value of the maximum current value, and divide the first absolute value by the second absolute value to obtain the three-phase unbalance objective function.

[0016] The objective function for three-phase unbalance is determined by selecting different calculation methods based on the current direction. When the current direction is positive, the difference is divided by the maximum value to characterize the dispersion of the three-phase current amplitude. When the current direction is reverse, the minimum absolute value of the current is divided by the maximum absolute value of the current to avoid calculation distortion caused by the negative sign. This ensures that the evaluation of three-phase unbalance can maintain the consistency of physical meaning under the complex working condition of bidirectional current flow, and ensures that the optimization model still has accurate optimization guidance in the power backfeed scenario, and will not output power commands that deviate from the actual balance requirements due to the distortion of evaluation indicators.

[0017] Furthermore, determining the optimal scheduling model for the transformer substation based on the reconstructed network topology, the basic parameters, the power balance constraints, and the three-phase imbalance objective function includes: Obtain the grid electricity price and the total electricity purchase amount; determine the electricity purchase cost based on the product of the grid electricity price and the total electricity purchase amount; Based on the reconstructed network topology and the basic parameters, the resistance and current of each branch in the transformer substation are determined; the line loss power of each branch is calculated according to the resistance value and the square of the current; the line loss power of each branch is accumulated to obtain the total line loss power of the transformer substation; the network loss cost is determined according to the product of the total line loss power and the grid electricity price. Based on the electricity purchase cost and the network loss cost, determine the objective function for operating costs; Based on the reconstructed network topology and the basic parameters, the voltage deviation between the actual voltage value and the rated voltage value of each node in the transformer area is determined; and a voltage deviation objective function is determined according to each voltage deviation. The comprehensive objective function is determined based on the three-phase imbalance objective function, the operating cost objective function, and the voltage deviation objective function. Based on the reconstructed network topology and the basic parameters, a set of constraints is determined; The optimized scheduling model is determined based on the comprehensive objective function and the set of constraints.

[0018] By constructing an objective function for operating costs including electricity purchase costs and network loss costs, an objective function for voltage deviations including phase voltage deviations at each node, and an objective function for three-phase imbalance, and then integrating these three functions into a weighted comprehensive objective function, multi-objective coordinated optimization of transformer area operation economy, voltage quality, and three-phase balance is achieved. The comprehensive objective function, together with a set of constraints consisting of three-phase power flow constraints, operational safety constraints, AC line power balance constraints, and common DC bus power balance constraints, constitutes the optimal scheduling model. This model uses the physical operating boundary of the transformer area as constraints and the multi-objective weighted function as the optimization guide. Under the premise of ensuring system safe operation, it simultaneously reduces the electricity purchase costs from the transformer area to the next higher level of the grid and the line loss costs during power transmission, reduces the deviation of phase voltages at each node from their rated values, and suppresses the imbalance of three-phase output current of transformers, achieving a synergistic improvement in transformer area power supply phase balance and operational economy. This model is a mixed-integer second-order cone programming form and a standard convex optimization model, which guarantees the convergence and optimality of the solution, providing a reliable computational foundation for online optimal scheduling of transformer areas.

[0019] Furthermore, determining the set of constraints based on the reconstructed network topology and the basic parameters includes: Based on the reconstructed network topology, the node connection relationships and branch connection relationships of the transformer area are determined, and the three-phase power flow constraints are determined according to the node connection relationships and branch connection relationships. Based on the aforementioned basic parameters, the voltage operating range of each node and the current operating range of each branch in the transformer substation are determined, and operational safety constraints are determined based on the voltage operating range and the current operating range. Based on the connection relationship between the main port of the back-to-back DC remote power supply equipment and the transformer, and the connection relationship between the slave port and the load-side node, the power balance constraints of the AC line are determined. Based on the three-phase power flow constraints, the operational safety constraints, the AC line power balance constraints, and the power balance constraints, the constraint condition set is determined.

[0020] By reconstructing the network topology, the node and branch connections of the distribution area are determined, thereby defining the three-phase power flow constraints. This transforms the physical topology of the power grid into power conservation boundary conditions that the optimization model must adhere to, ensuring that the power command obtained from the optimization solution satisfies Kirchhoff's laws at any node and branch. Based on fundamental parameters, the voltage operating range of each node and the current operating range of each branch are determined, thus defining operational safety constraints. This transforms the physical limits of the equipment itself into the feasible domain boundaries of the optimization variables, preventing equipment protection actions due to voltage exceeding limits or current overload. Finally, based on the back-to-back DC remote power supply equipment main port... The connection relationship with the transformer and the connection relationship between the port and the load-side node determine the power balance constraints of the AC line. The power injection and outflow relationship on the AC line is incorporated into the model constraints, so that the power allocation scheme has self-consistency at the physical transmission level. The above three-phase power flow constraints, operation safety constraints, AC line power balance constraints and power balance constraints together constitute a set of constraints, which delineates a complete feasible region for solving the optimization scheduling model. Any power allocation scheme that satisfies this set of constraints must satisfy the physical operation law and safety boundary of the transformer area, thereby ensuring that the optimization results can be directly executed in engineering without subsequent verification or correction.

[0021] Another embodiment of this application provides a distributed power supply DC collection system for a transformer substation, which is used to perform the distributed power supply DC collection method for a transformer substation as described in this application.

[0022] Another embodiment of this application provides a computer-readable storage medium, including: a stored computer program, wherein, when the computer program is executed, it controls the device where the computer-readable storage medium is located to perform the DC collection power supply method for distributed power supply in the transformer substation as described in this application. Attached Figure Description

[0023] To more clearly illustrate the technical solution of this application, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.

[0024] Figure 1 This is a schematic flowchart of one embodiment of the DC collection power supply method for distributed power sources in the transformer substation provided in this application; Figure 2 This is a schematic diagram of a traditional power supply architecture for a transformer substation according to an embodiment provided in this application; Figure 3 This is a schematic diagram of a reconstructed network topology architecture according to an embodiment provided in this application; Figure 4 This is a schematic diagram of the reconstructed network topology architecture for a scenario involving the addition of a transformer, according to one embodiment of this application. Figure 5 This is a distributed photovoltaic power output data curve diagram of one embodiment provided in this application; Figure 6 is a 24-hour three-phase load characteristic diagram of transformer area 1 according to an embodiment of this application. Figure 7 is a node voltage distribution diagram of Scheme 1 of an embodiment provided in this application; Figure 8 is a node voltage distribution diagram of an embodiment of this application; Figure 9 is a node voltage distribution diagram of Scheme 3 of an embodiment provided in this application; Figure 10 This is a heat map of node voltage imbalance according to one embodiment of this application; Figure 11 This is a heat map of node voltage imbalance according to an embodiment of this application; Figure 12 This is a heatmap of node voltage imbalance in topology (a) of one embodiment of this application; Figure 13 This is a line graph showing the transformer power imbalance of one embodiment provided in this application; Figure 14 This is a line graph showing the transformer power imbalance of one embodiment provided in this application; Figure 15 This application provides an embodiment of topology 3, a line graph of transformer power imbalance. Figure 16 This is a diagram illustrating the operation of a back-to-back converter according to one embodiment of this application. Figure 17This is a diagram illustrating the operation of a back-to-back converter according to an embodiment of this application. Figure 18 This is a diagram of the operation of a back-to-back converter in topology (a) of one embodiment of this application. Detailed Implementation

[0025] To make the objectives, technical solutions, and advantages of this application clearer, the technical solutions of this application will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.

[0026] In the description of the embodiments of this application, technical terms such as "first" and "second" are used only to distinguish different objects and should not be construed as indicating or implying relative importance or implicitly specifying the number, specific order, or primary and secondary relationship of the indicated technical features. In the description of the embodiments of this application, "multiple" means two or more, unless otherwise explicitly defined.

[0027] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment mutually exclusive with other embodiments. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.

[0028] In the description of the embodiments in this application, the term "and / or" is merely a description of the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can represent: A existing alone, A and B existing simultaneously, and B existing alone. Additionally, the character " / " in this document generally indicates that the preceding and following related objects have an "or" relationship.

[0029] With a high proportion of distributed photovoltaic (PV) power plants connected to low-voltage distribution areas, a large number of single-phase PV units are connected to the nearby AC grid, leading to significant differences in the three-phase current amplitudes of the transformers in these areas and prominent three-phase imbalance problems. Traditional reactive power compensation-based mitigation methods are insufficient to address the extreme imbalance conditions caused by high-frequency fluctuations in PV output and reverse power flow, resulting in limited mitigation effectiveness. To address this, this application proposes a DC aggregation power supply method for distributed power sources in distribution areas, optimizing power supply control to improve voltage quality, reduce overall losses, and enhance energy efficiency in interaction with the upstream power grid.

[0030] Please refer to Figure 1 , Figure 1This is a flowchart illustrating an embodiment of the DC aggregation power supply method for distributed power sources in a transformer substation provided in this application. To improve the phase balance of power supply in a transformer substation, this application provides a DC aggregation power supply method for distributed power sources in a transformer substation, which includes steps S1 to S6, each step as follows: Step S1: Obtain the network topology of the transformer substation and the basic parameters of each electrical device; The network topology of a distribution area refers to the physical and electrical connections between electrical equipment such as transformers, AC buses, distribution lines, load nodes, distributed photovoltaic power generation systems, and photovoltaic converters within the distribution area. This includes the connection relationships between nodes (which branches connect to the nodes), the electrical parameters of the branches (which two nodes each branch connects to, the resistance and reactance values ​​of the branches), and the access locations of each electrical device within the distribution area.

[0031] The basic parameters of each electrical device refer to the rated parameters and operating boundary parameters of each electrical device in the transformer substation, including the rated capacity and three-phase output current of the transformer, the resistance and reactance values ​​of each line, the voltage operating range of each node, the current operating range of each branch, and the installed capacity of distributed photovoltaic power generation, etc.

[0032] Step S2: Reconstruct the network topology to obtain the reconstructed network topology. Reconstructing the network topology refers to the process of adding a common DC bus, connecting the main ports of back-to-back DC remote power supply equipment to the low-voltage AC bus of the transformer, connecting the slave ports of the back-to-back DC remote power supply equipment to the load-side node with the highest voltage imbalance in the distribution area, and connecting each photovoltaic power generation system to the common DC bus through its corresponding photovoltaic converter. The reconstructed network topology includes a common DC bus, back-to-back DC remote power supply equipment, transformers, photovoltaic converters, and energy storage devices.

[0033] Step S3: Based on the reconstructed network topology and basic parameters, determine the power balance constraints of the common DC bus; The power balance constraint of the common DC bus refers to the equality constraint that the sum of the injected power of each power injection device connected to the common DC bus is equal to the sum of the outflow power of each power outflow device. The common DC bus is a DC bus that connects the DC side of the back-to-back DC remote power supply equipment to the output terminals of each photovoltaic converter, and is used to collect and distribute DC power.

[0034] Step S4: Based on the aforementioned basic parameters, construct a comprehensive objective function; the comprehensive objective function includes a three-phase imbalance objective function, an operating cost objective function, and a voltage deviation objective function; The comprehensive objective function is a scalar mathematical function that uses the minimum three-phase imbalance, minimum operating cost, and minimum voltage deviation as optimization objectives, weighted by coefficients. This function is used in subsequent optimization scheduling models to uniformly quantify the comprehensive performance of the transformer substation. The three-phase imbalance objective function quantifies the degree of imbalance in the three-phase output current of the transformer. This function uses different expressions depending on the direction (forward or reverse) of the three-phase output current to accurately characterize the three-phase current imbalance. The operating cost objective function quantifies the cost of purchasing electricity from the grid and the power transmission loss of AC lines. It consists of two parts: electricity purchase cost and network loss cost. The electricity purchase cost is the sum of the products of the grid price and the total electricity purchased for each phase. The network loss cost is the sum of the grid price and the products of the squares of the currents and resistances of each branch. The voltage deviation objective function quantifies the deviation between the actual voltage value and the rated voltage value of each phase at each node in the transformer substation. It is the sum of the absolute values ​​of the voltage deviation rates of each phase at each node.

[0035] Step S5: Based on the reconstructed network topology, the basic parameters, the power balance constraints, and the comprehensive objective function, determine the optimal scheduling model for the distribution area; Among them, the optimization scheduling model refers to a mathematical model established with the optimization objectives of minimizing the total system operating cost, minimizing the three-phase imbalance, and minimizing the overall voltage deviation, and with the constraints of power balance constraints, three-phase power flow constraints, operational safety constraints, and AC line power balance constraints as conditions. It is used to solve for the power target values ​​of each controllable device in the transformer area.

[0036] Step S6: Obtain the real-time operating data of the transformer substation; input the real-time operating data into the optimization scheduling model for solution, and obtain the power target values ​​corresponding to the back-to-back DC remote power supply equipment and the photovoltaic converter, so as to optimize the power supply control of the transformer substation based on the power target values.

[0037] Among them, real-time operation data refers to the real-time collection of data such as the actual voltage value of each phase of each node, the current value of each branch, the actual output value of each distributed photovoltaic, and the actual demand value of each phase load under the current operating status of the transformer area.

[0038] The power target value refers to the active power setpoint of each port of the back-to-back DC remote power supply equipment and the active power setpoint of each photovoltaic converter, obtained by solving the optimization scheduling model. After the power target value is sent to the corresponding equipment for execution, the active power distribution on each phase line is readjusted, and the three-phase output current of the distribution transformer tends to be balanced, thereby achieving the balance of power supply phase in the distribution area.

[0039] In some embodiments, step S1 obtains the network topology of the transformer area and the basic parameters of each electrical device, which serve as the data basis for subsequent topology reconstruction, constraint construction, and optimization scheduling model establishment.

[0040] Please refer to Figure 2 , Figure 2 This is a schematic diagram of a traditional power supply architecture for a transformer substation, according to one embodiment of this application. Figure 2 As shown, the network topology of the distribution area includes information such as the distribution area transformers, AC buses, distribution lines, load nodes, distributed photovoltaic (PV) power generation systems, and their connection locations. In this 22-node distribution system, node numbers range from 1 to 22, with nodes 22 and 18 serving as the connection points for two ends of a back-to-back DC remote power supply device (which was used as a traditional AC remote power supply device before the reconfiguration process). Distributed PV power generation systems connect to their respective nodes in the distribution area via their inverters. Basic parameters of each electrical device corresponding to the traditional power supply architecture of the distribution area are obtained, including the rated capacity and turns ratio of the transformers, the resistance and reactance values ​​of each branch distribution line, the safe operating range of the voltage at each node, the upper limit of the safe operating range of the current at each branch, the installed capacity of each distributed PV power generation system, and the maximum power point tracking control parameters. These parameters serve as the data foundation for subsequent topology reconfiguration, constraint construction, and the establishment of an optimized scheduling model.

[0041] In some embodiments, please refer to Figure 3 , Figure 3 This is a schematic diagram of a reconstructed network topology architecture according to an embodiment of this application. Step S2 reconstructs the network topology architecture to obtain a reconstructed network topology architecture, including steps S211 to S214, each step of which is as follows: Step S211: Connect the common DC bus to the DC side of the back-to-back DC remote power supply equipment. The common DC bus refers to the DC combiner bus installed on the DC side of the back-to-back DC remote power supply equipment, used to uniformly collect distributed photovoltaic and distributed energy storage on the DC side, serving as a node for collecting and distributing DC power. The back-to-back DC remote power supply equipment is a power electronic device with bidirectional energy conversion capabilities, serving as an energy hub between the AC main grid and the common DC bus. It includes a main port, a slave port, and a DC side. The main port is an AC port used to connect to the AC bus connected to the low-voltage side of the transformer; the slave port is an AC port used to connect to the load-side nodes of the distribution area; the DC side is a DC port used to connect to the common DC bus.

[0042] Specifically, a DC line is led to the DC side of the back-to-back DC remote power supply equipment, and the other end of the DC line is connected to the common DC bus, so that the common DC bus can establish an electrical connection with the DC side of the back-to-back DC remote power supply equipment through the DC line, thereby realizing the electrical connection between the back-to-back DC remote power supply equipment and the common DC bus.

[0043] It should be noted that in actual engineering projects, the number of back-to-back DC remote power supply devices can be flexibly configured according to the power consumption capacity, distributed photovoltaic penetration rate, and power supply reliability requirements of the transformer substation. For transformer substations with small power consumption capacity or low distributed photovoltaic penetration rate, a single back-to-back DC remote power supply device can be used; for transformer substations with large power consumption capacity or high distributed photovoltaic penetration rate, multiple back-to-back DC remote power supply devices can be connected in parallel to a common DC bus, or connected to different power supply nodes in the transformer substation, to improve the power supply capacity and operational reliability of the system. This application uses a single back-to-back DC remote power supply device as an example for illustration, but those skilled in the art will understand that, based on the technical concept of this application, the application scenarios of multiple back-to-back DC remote power supply devices can also implement the technical solution of this application.

[0044] Step S212: Determine the AC busbar connected to the low-voltage side of the transformer and connect the main port of the back-to-back DC remote power supply equipment to the AC busbar; wherein, the AC busbar connected to the low-voltage side of the transformer refers to the three-phase AC busbar connected to the low-voltage winding side of the distribution transformer, which is used to collect and distribute AC power and is the access point of the main port of the back-to-back DC remote power supply equipment.

[0045] Specifically, the transformer in a distribution area typically includes a high-voltage side and a low-voltage side. The low-voltage side is connected to an AC bus, which serves as the common connection point for all equipment on the low-voltage side of the distribution area. After identifying this AC bus, the main port of the back-to-back DC remote power supply equipment is connected to this AC bus via an AC line, establishing an electrical connection between the main port of the back-to-back DC remote power supply equipment and the AC bus connected to the low-voltage side of the transformer. After the connection is completed, the back-to-back DC remote power supply equipment achieves bidirectional power exchange with the AC bus through its main port. That is, the main port can invert the DC power from the common DC bus into AC power and feed it into the AC bus, or it can rectify the AC power from the AC bus into DC power to supply the common DC bus.

[0046] Step S213: Determine the load-side node with the highest voltage imbalance in the distribution area, and connect the slave port of the back-to-back DC remote power supply equipment to the load-side node; wherein, the load-side node with the highest voltage imbalance refers to the load-side node with the largest difference in three-phase voltage amplitude among all load-side nodes in the distribution area, and this node is the connection target of the slave port of the back-to-back DC remote power supply equipment.

[0047] Specifically, by detecting or calculating the three-phase voltage of each load-side node in the distribution area, and comparing the differences in the three-phase voltage amplitudes of each node, the load-side node with the largest difference in three-phase voltage amplitude is identified. After identifying this node, the slave port of the back-to-back DC remote power supply equipment is connected to this load-side node via an AC line, establishing an electrical connection between the slave port of the back-to-back DC remote power supply equipment and the load-side node. After the connection is completed, the slave port is used to supply single-phase power to the load-side node, that is, the slave port inverts the DC power from the common DC bus into AC power and supplies it to the load-side node.

[0048] Step S214: Connect each photovoltaic power generation system to the common DC bus through its corresponding photovoltaic converter to obtain the reconstructed network topology. Here, a photovoltaic power generation system refers to a distributed photovoltaic power generation unit composed of photovoltaic module arrays; a photovoltaic converter refers to a power electronic device used to convert the DC power output from the photovoltaic power generation system into DC power that matches the common DC bus.

[0049] Specifically, for each photovoltaic power generation system, its DC output terminal is connected to the input terminal of the corresponding photovoltaic converter, and the output terminal of the photovoltaic converter is connected to the common DC bus, so that each photovoltaic power generation system is connected to the common DC bus in parallel through its corresponding photovoltaic converter.

[0050] In an alternative embodiment, please refer to Figure 3 The transformer is the existing distribution transformer in the transformer substation. This reconfigured network topology retains the existing distribution transformer, with back-to-back DC remote power supply equipment serving as a bidirectional energy conversion interface between the AC main grid and the internal DC system. During the reconfiguration process, a common DC bus is first added to the DC side of the back-to-back DC remote power supply equipment, forming a DC power aggregation node. Multiple distributed photovoltaic (PV) power generation systems and energy storage systems (ESS) are connected to this common DC bus, with each distributed PV power generation system connected to this common DC bus via its corresponding PV converter. Thus, the dispersed distributed PV and energy storage systems are uniformly aggregated on the DC side. The main port of the back-to-back DC remote power supply equipment is connected to the low-voltage AC bus of the existing transformer substation via an AC line, establishing an electrical connection between the main port and the AC bus; the slave port of the back-to-back DC remote power supply equipment is connected to the load-side node with the highest voltage imbalance in the transformer substation via an AC line.

[0051] exist Figure 3In the architecture shown, the active power of photovoltaics interacts with the AC-side distribution areas and the main grid via a common DC bus: when the output of distributed photovoltaics exceeds the load demand, the excess photovoltaic power is directly fed into the AC main grid through the main port; when the photovoltaic output is insufficient, the AC main grid rectifies the power into DC through the main port, and then provides flexible power supply to each user load point through the slave port and photovoltaic converter. The back-to-back DC remote power supply equipment directly addresses the three-phase imbalance of the transformer through three-phase power mutual assistance; the photovoltaic converter can not only indirectly address the three-phase imbalance of the transformer through the DC line, but also directly address the three-phase voltage imbalance of the node by adjusting the active and reactive power injected into the distribution area, effectively solving the power quality problems caused by a large number of single-phase photovoltaics directly connected to the AC distribution area, and realizing source-storage synergy and efficient consumption.

[0052] In some embodiments, please refer to Figure 4 , Figure 4 This is a schematic diagram of the reconstructed network topology architecture for a scenario involving the addition of a transformer, according to an embodiment of this application. Step S2 connects the main port of the back-to-back DC remote power supply equipment to the AC bus, and also includes steps S221 to S222, each of which is detailed below: Step S221: Connect the high-voltage side of the added transformer to the upper-level medium-voltage distribution area; wherein, the added transformer refers to a transformer that is separately installed from the original distribution transformer in the distribution area and is specifically added for the implementation of the scheme of this application.

[0053] Specifically, the high-voltage side of the added transformer is connected to the 10kV medium-voltage distribution area via cable or overhead line, establishing an electrical connection between the added transformer and the upstream medium-voltage distribution area. After this connection is completed, the added transformer serves as an intermediate link between the back-to-back DC remote power supply equipment and the medium-voltage distribution area, providing a channel for the back-to-back DC remote power supply equipment to access the medium-voltage distribution area.

[0054] Step S222: Connect the main port of the back-to-back DC remote power supply equipment to the low-voltage side AC bus of the added transformer; wherein, the back-to-back DC remote power supply equipment adjusts the active power and reactive power of the added transformer respectively, so that the three-phase imbalance of the added transformer is limited to a preset range.

[0055] Specifically, an AC bus is connected to the low-voltage side of the added transformer, which serves as the power collection node on the low-voltage side of the added transformer. The main port of the back-to-back DC remote power supply equipment is connected to this low-voltage side AC bus via an AC line, establishing an electrical connection between the main port of the back-to-back DC remote power supply equipment and the low-voltage side AC bus of the added transformer. Thus, the back-to-back DC remote power supply equipment is connected to the upper-level medium-voltage distribution area through the added transformer.

[0056] The main port of the back-to-back DC remote power supply equipment has three-phase independent adjustment capability. Taking the three-phase current on the low-voltage side of the added transformer as the direct control object, the active power and reactive power of each phase A, B and C of the added transformer are adjusted separately to independently regulate the current of each phase, thereby limiting the three-phase imbalance of the added transformer to a preset range.

[0057] In another alternative embodiment, please refer to Figure 4 The transformer is an additional transformer (i.e., a dedicated transformer independent of the existing distribution transformer in this distribution area). This reconfigured network topology architecture adds an independent transformer in addition to the existing distribution transformer in the distribution area, which is used to connect the main port of the back-to-back DC remote power supply equipment to the upper-level medium-voltage distribution area.

[0058] Specifically, when the photovoltaic penetration rate in this area is low, the following measures are adopted: Figure 3 The existing architecture can meet the requirements. However, with the continuous growth of distributed photovoltaic (PV) installations, the capacity of existing distribution areas to absorb the load often becomes saturated. When the active power output of PV exceeds the load demand of the local distribution area, resulting in a large surplus, if the existing architecture is still used... Figure 3 The existing architecture forces surplus power to be fed back through the original distribution transformer, which greatly exacerbates the risk of reverse overload operation of the original transformer. Therefore, this embodiment further proposes... Figure 4 The extended topology is shown. During the reconfiguration process, a common DC bus is first added to the DC side of the back-to-back DC remote power supply equipment, and each distributed photovoltaic power generation system is connected to this common DC bus through its corresponding photovoltaic converter. Then, the high-voltage side of the added transformer is connected to the upstream medium-voltage distribution area, and the main port of the back-to-back DC remote power supply equipment is connected to the low-voltage AC bus of the added transformer, while the slave port is still connected to the most unbalanced load-side node in the distribution area.

[0059] When the active power output of photovoltaic power at the common DC bus exceeds the absorption capacity of the local distribution area, the excess active power will be preferentially reverse-supplied along a dedicated feeder channel: "common DC bus → back-to-back main port → low-voltage side of the additional transformer → high-voltage side of the additional transformer → upstream medium-voltage distribution area". This transmission path bypasses the original distribution transformer in the local area, reduces the transmission of reverse-supplied power to the original distribution transformer in the local area, avoids reverse power flow encroaching on the original distribution transformer capacity, and reduces transformer losses and heat generation risks.

[0060] refer to Figure 4The physical wiring relationship of the back-to-back DC remote power supply equipment allows it to simultaneously connect the original distribution transformer (via the slave port) and the newly added dedicated transformer (via the main port) in its spatial structure, enabling it to achieve synchronous regulation with "one machine, two controls". On the one hand, the back-to-back equipment can directly address the three-phase imbalance of the original distribution transformer in the local area by adjusting the single-phase power at the slave port; on the other hand, its main port has independent three-phase regulation capabilities, allowing it to directly control the three-phase current on the low-voltage side of the added transformer. Through decoupling regulation of active and reactive components, the three-phase imbalance of the added transformer can be limited to the preset range specified by national standards, thereby achieving synchronous regulation of the three-phase imbalance of the two transformers.

[0061] Figure 4 The parallel architecture based on a common DC bus enables each photovoltaic converter to not only convert electrical energy but also act as the execution end for DC-side response. When back-to-back devices perform imbalance management or power backfeed to the master and slave ports, the DC bus voltage will fluctuate. Each photovoltaic converter can actively respond and adjust its output power using its own maximum power point tracking (MPPT) capability, providing transient support for the back-to-back device's adjustment process and further improving the system's robustness and economy under various extreme operating conditions.

[0062] In some embodiments, the transformer can also be a different type of distribution transformer independent of the existing distribution transformer in the transformer area. That is, it is not limited to a dedicated transformer; any transformer added separately from the existing transformer to connect the main port of the back-to-back DC remote power supply equipment to the upper-level medium-voltage line can be reconfigured using the connection and adjustment methods described above. When other types of distribution transformers are used as the added transformer, its high-voltage side is connected to the upper-level medium-voltage line, and its low-voltage side is connected to the main port of the back-to-back DC remote power supply equipment. The back-to-back DC remote power supply equipment adjusts the active and reactive power of each phase of the added transformer through the main port, limiting the three-phase imbalance of the added transformer to a preset range, thus achieving synchronous management of the three-phase imbalance between the new transformer and the existing transformer in the transformer area.

[0063] In some embodiments, step S3 determines the power balance constraints of the common DC bus based on the reconstructed network topology and basic parameters, including steps S301 to S302, each of which is as follows: Step S301: Based on the reconstructed network topology, determine each power injection device and each power outflow device connected to the common DC bus; based on the basic parameters, determine the injected power value of each power injection device and the outflow power value of each power outflow device. In this context, the power injection device refers to the device that injects active power into the common DC bus. In the topology of this embodiment, the distributed photovoltaic power generation system continuously injects power into the common DC bus during operation; the energy storage system (ESS) also injects power into the common DC bus during discharge.

[0064] Power outflow devices refer to devices that absorb active power from the common DC bus. In the topology of this embodiment, the main port (when feeding power to the AC side) and slave port (when supplying power to the load) of the back-to-back DC remote power supply equipment, as well as the energy storage system (when in charging state), are all power outflow devices. As a node for collecting and distributing DC power, the common DC bus requires real-time balance between inflow and outflow power for stable operation.

[0065] Specifically, based on the reconstructed network topology, the electrical equipment connected to the common DC bus is identified as including: N distributed photovoltaic power generation systems (accessed through N photovoltaic converters), 1 energy storage system (accessed through an energy storage converter), and back-to-back DC remote power supply equipment (accessed through its DC side).

[0066] For a distributed photovoltaic power generation system, its actual output on the common DC bus is denoted as... The sum of the power output values ​​of each photovoltaic unit is .

[0067] For energy storage systems, the power value interacting with the common DC bus is denoted as... ,in Indicates discharge injection. This indicates charging absorption.

[0068] Energy storage operation constraints and state of charge (SOC) constraints: in, , Energy storage Active power that is constantly absorbed or released; , These are the active power charging and discharging indicators for energy storage; , , , These represent the maximum and minimum values ​​of active power charging and discharging in energy storage, respectively. For energy storage SOC at any given moment; The self-discharge rate of the stored energy; , These are the charging and discharging efficiencies of energy storage, respectively. , These are the maximum and minimum SOC of the energy storage, respectively; , These represent the State of Charge (SOC) of energy storage at the beginning and end of the scheduling cycle, respectively. This is one optimization cycle.

[0069] For back-to-back DC remote power supply equipment, the total power absorbed or injected from the common DC bus through the DC side port is denoted as . This power is equal to the sum of the power of each phase at its AC main port and slave port. Specifically, ,in For back-to-back DC remote power supply equipment One communication port The active power of each phase. Since both the main port and the slave port of the back-to-back DC remote power supply equipment have independent power regulation capabilities for each phase, the slave port can selectively connect to a specific single-phase node according to the voltage imbalance of each phase load in the transformer area, thereby realizing targeted management of the three-phase imbalance of the original transformer in the transformer area.

[0070] Step S302: Determine the power balance constraint based on each injected power value and each outflow power value.

[0071] According to the principle of power conservation, the power balance constraint of the common DC bus must satisfy: the sum of all active power injected into the common DC bus equals the sum of all active power flowing out of the common DC bus. Specifically, considering the characteristics of "DC aggregation" in this embodiment, the expanded constraint relationship is as follows: in, This represents the total number of photovoltaic converters. Taiwan District Mutually( ) No. Active power on the AC side of each photovoltaic converter; For back-to-back DC power supply equipment One communication port The active power of the phase (the negative value is taken when the power is fed back, indicating that it flows out from the DC bus); This refers to the interaction power between the energy storage system and the common DC bus. For the first The actual total DC output generated by a distributed photovoltaic power generation system on a common DC bus.

[0072] To ensure the safe operation of the system within the physical capacity limits of the equipment, in addition to the power balance equation constraints mentioned above, optional inequality constraints on the operating boundaries can be introduced to limit the output of each device from exceeding its physical upper and lower limits, specifically including: Photovoltaic output constraints: ,in For the first The maximum output limit of a single photovoltaic power generation system; Energy storage power constraints: ,in and These are the upper limits of the rated charging power and rated discharging power of energy storage, respectively. Converter capacity constraints ,in For the first A photovoltaic converter in The maximum apparent power capacity of the phase ensures that the active power exchange of the photovoltaic converter is limited to its maximum apparent power. within; Back-to-back device power constraints ,in For back-to-back DC remote power supply equipment One communication port The maximum apparent power capacity of each phase ensures that the switching power of each port of the back-to-back device does not exceed its rated apparent capacity.

[0073] In some embodiments, the basic parameters in step S4 include the three-phase output current of the transformer. Determining the objective function for the three-phase unbalance includes steps S401 to S403, each of which is as follows: Step S401: Determine the maximum and minimum current values ​​among the three-phase output currents of the transformer; Specifically, the three-phase output current of a transformer refers to the phase current values ​​output by the A, B, and C phase windings on the low-voltage side of the distribution transformer, denoted as […]. , , The amplitudes of the three-phase output currents are compared to determine the maximum current value. and minimum current value Step S402: Determine the direction of the three-phase output current; Specifically, the current direction refers to the sign of the current in each phase. Due to the bidirectional power flow characteristics of the distributed photovoltaic (PV) grid, the current in each phase may be positive (positive direction, indicating that the current flows from the transformer to the load side, i.e., the load absorbs power from the grid) or negative (negative direction, indicating that the current flows from the load side to the transformer, i.e., the distributed PV feeds power back to the grid). By determining the sign of the current in each phase, the bidirectional power flow operation status of the system can be determined.

[0074] Step S403: Determine the objective function for three-phase unbalance based on the current direction, maximum current value, and minimum current value, including: When the current direction is positive, determine the current difference between the maximum and minimum current values, and divide the current difference by the maximum current value to obtain the objective function of the three-phase unbalance. Specifically, the objective function for three-phase unbalance is determined using a piecewise function based on the different directions of the current. The purpose of introducing piecewise functions is to overcome the mathematical deficiencies of traditional three-phase unbalance formulas when dealing with "full reverse current" conditions. The specific construction method is as follows: When the current direction does not include reverse current (i.e.) and ), or when there is alternation between positive and negative directions in the system (i.e. (At this point, one phase's power purchase and another phase's active power reverse injection coexist.) The ratio of the difference between the maximum and minimum current values ​​to the maximum current value is determined to obtain the objective function for the three-phase unbalance. : Under the two working conditions mentioned above, It is a positive value. The calculation result is greater than 0 and less than or equal to 1 (greater than 1 in extreme imbalance cases). This formula can accurately quantify the standard imbalance and is applicable to complex working conditions such as light load, heavy load and extreme reverse power flow.

[0075] When the current direction is reversed, determine the first absolute value of the minimum current value and the second absolute value of the maximum current value, and divide the first absolute value by the second absolute value to obtain the objective function of the three-phase unbalance.

[0076] Specifically, when the current directions are all opposite (i.e.) and If we directly use the above formula, since both the numerator and denominator are negative, the ratio will be equivalent to the ratio of the maximum current amplitude to the minimum current amplitude, leading to a different calculation result. This approach fails to accurately reflect the actual three-phase balance state of the system. Therefore, in this case, the first absolute value of the minimum current value and the second absolute value of the maximum current value are determined, and the ratio of the difference between the first and second absolute values ​​to the first absolute value is used to obtain the corrected three-phase imbalance objective function. : Since the total reverse current is a typical photovoltaic power generation and extremely low load condition, at this time... The absolute value (i.e., the phase with the largest reverse power among the three phases) is greater than The absolute value of the current (i.e., the phase with the smallest reverse power among the three phases). This formula transforms the all-negative current condition into a positive value calculation by taking the absolute value, ensuring that the result always falls within the range of the three phases. Within this range, the traditional formula's limitation of losing physical meaning when dealing with completely opposite power flows is corrected. Integrating the above cases, the final piecewise expression for the three-phase imbalance objective function is obtained: , This piecewise objective function, as one of the core sub-objectives of the optimization scheduling model, is used for optimization in subsequent steps. It can completely and accurately characterize the degree of three-phase imbalance of transformers in the distribution area under three types of bidirectional power flow conditions: forward, alternating forward and reverse, and completely reverse, when a high proportion of distributed photovoltaic access is implemented.

[0077] In some embodiments, step S5 determines the optimal scheduling model for the transformer area based on the reconstructed network topology, the basic parameters, the power balance constraints, and the comprehensive objective function, including steps S501 to S505, each of which is as follows: Step S501: Obtain the grid electricity price and total electricity purchase amount; determine the electricity purchase cost based on the product of the grid electricity price and the total electricity purchase amount; determine the resistance value and current of each branch in the transformer area based on the reconstructed network topology and basic parameters; calculate the line loss power of each branch based on each resistance value and the square value of each current; sum up the line loss power to obtain the total line loss power of the transformer area; determine the network loss cost based on the product of the total line loss power and the grid electricity price; determine the operating cost objective function based on the electricity purchase cost and the network loss cost. Specifically, obtaining grid electricity prices The total amount of electricity purchased by each substation from the upstream power grid As a decision variable, the system's cost of purchasing electricity from its upstream supplier is determined by the product of the two factors. The formula is as follows: Based on the reconstructed network topology, the resistance of each branch is determined. With current (Decision variables). Branch losses are calculated as the product of the square of the current and the resistance. The total line losses of all branches in the entire network are summed and multiplied by the grid electricity price to obtain the system network loss cost. The formula is as follows: In the formula, The number of nodes in the transformer area; Indicates the grid electricity price; Indicates the node number, and For the first node of the branch road, This is the terminal node of the branch; for Mutually The current in the branch circuit; for Mutually The resistance of the branch circuit. Indicates all in the Taiwan region Summing is performed on each of the branch paths.

[0078] Will and Adding them together, we obtain the objective function for the total operating cost of the system. : The cost of electricity purchase reflects the system's dependence on the external power grid, while the cost of grid loss reflects the system's internal operating efficiency. Introducing a second-order term for losses is intended to force photovoltaic and back-to-back equipment to prioritize local consumption during optimization, reducing losses caused by long-distance transmission.

[0079] Step S502: Based on the reconstructed network topology and basic parameters, determine the voltage deviation between the actual voltage value and the rated voltage value of each node in the transformer area; determine the voltage deviation objective function based on each voltage deviation. Specifically, after a high proportion of distributed photovoltaic (PV) grid connections are established, voltage can easily exceed the upper limit during peak midday power generation and can easily exceed the lower limit during heavy nighttime loads. Given that the PV AC / DC converters connected to each node have active and reactive power regulation capabilities, this objective function, to fully exploit their voltage support potential, penalizes the degree to which the grid voltage deviates from its rated value, forcing PV converters and back-to-back devices to adjust their active and reactive power, thereby achieving active voltage support for the entire grid.

[0080] Obtain the node rated voltage and the actual voltage of each phase at each node (Decision variables). Calculate the sum of the absolute values ​​of the voltage deviation rates of all phases at all nodes to obtain the overall voltage deviation objective function. : in, The number of nodes in the transformer area; For nodes of Mutually( ) node voltage; This is the reference voltage (rated voltage) for the transformer area. The time step for scheduling (optimized time period length) reflects the penalty for accumulated voltage deviation within the scheduling cycle.

[0081] Step S503: Determine the comprehensive objective function based on the three-phase imbalance objective function, the operating cost objective function, and the voltage deviation objective function; Specifically, based on the three-phase imbalance objective function determined in step S4 Operating cost objective function and overall voltage deviation objective function Because the three factors have different dimensions and conflict (reducing operating costs may sacrifice power quality), a weighting coefficient is introduced. , , Construct a multi-objective synthesis function: And it satisfies the weights and constraints: By adjusting the weighting coefficients, differentiated operation can be achieved across multiple scenarios. For example, in areas with extremely high photovoltaic penetration, increasing... Weighting should prioritize ensuring the balance of grid voltage and phase; while during periods of high electricity prices, appropriate increases should be made. Weighting reduces operating costs.

[0082] Step S504: Determine the set of constraints based on the reconstructed network topology and basic parameters; Based on the reconstructed network topology and basic parameters, a set of constraints is determined. This set includes the following key constraints: (1) Based on the reconstructed network topology, determine the node connection relationship and branch connection relationship of the transformer area, and determine the three-phase power flow constraints according to the node connection relationship and branch connection relationship; Based on the reconstructed network topology, the node connection relationships and branch connection relationships of the transformer area are determined, that is, which branches connect the nodes in the transformer area, the direction of power injection and outflow, and the start and end points of each branch.

[0083] The Distflow three-phase AC power flow model describes the relationship between injected power at each node and branch power. Since the traditional voltage drop equation contains nonlinear terms (the product of voltage and current), it is a non-convex constraint, and direct solution easily gets trapped in local optima, failing to guarantee solution stability. This embodiment uses the second-order cone relaxation (SOCP) technique to transform the non-convex voltage drop equation into a convex constraint. Specifically, by utilizing the form that the 2-norm of the vector is less than or equal to the sum of the squares of the current and voltage, the model is transformed into a standard convex optimization problem, ensuring that the model has a unique global optimum.

[0084] The three-phase operation constraints of the transformer substation include two parts: three-phase power flow constraints and operational safety constraints. The three-phase power flow constraints are specifically represented as follows: , in, , Representing nodes respectively of Phase-injected active and reactive power; , Branch roads Active power and reactive power; For nodes of The square of the phase voltage; for Mutually The square of the current in the branch; Indicates the flow of electricity to the node The set of all upstream nodes to which power is injected; Indicates from node The set of all downstream nodes to which the outflowing power reaches via the power grid; , These represent the resistance and reactance of each phase of the line, respectively. The first three equality constraints in the above formula describe the physical relationship between active power, reactive power, and voltage drop, while the fourth inequality constraint is the convex constraint after second-order cone relaxation.

[0085] (2) Based on the basic parameters, determine the voltage operating range of each node and the current operating range of each branch in the transformer area, and determine the operating safety constraints according to the voltage operating range and the current operating range; Specifically, based on fundamental parameters, the voltage operating range of each node in the transformer substation is obtained. Current operating range of each branch and the injection power range of each node Among them, the upper limit of the voltage operating range. and lower limit Given the basic parameters, the upper limit of the current operating range. These are the known basic parameters.

[0086] To ensure the safety of power grid equipment, the voltage, branch current, and injected power at each node must be limited within physically permissible ranges. It should be noted that, since the voltage, current, and power at each node in a three-phase four-wire independent network are complex phasors including the location of the power grid unit, this embodiment uses the amplitude (absolute value) of each phasor as the direct constraint to ensure the physical safety of the power grid operation. The specific operational safety constraints for each phase of the three-phase four-wire independent network are as follows: in, For nodes of Phase voltage amplitude, and These are the upper and lower limits for safe operation of node voltage, respectively. branch road of Phase current amplitude (magnitude), This represents the upper limit of the branch current magnitude (i.e., the line thermal stability limit); For nodes of The magnitude of the phase injection power, and These are the upper and lower limits of the allowable power injected into the node (limited by the rated capacity of the distribution transformer and the physical operating boundaries of the node).

[0087] By introducing the above-mentioned operational safety constraints, on the one hand, the voltage rise of nodes caused by large-scale distributed photovoltaic power generation (preventing voltage from exceeding the upper limit) and the voltage drop of nodes caused by heavy load at night (preventing voltage from exceeding the lower limit) can be effectively curbed, ensuring the safety of user-side electrical equipment; on the other hand, the line current and transformer injected power are strictly limited, effectively preventing problems such as overload burnout of distribution lines and transformer capacity exceeding the limit, providing a hard physical boundary for solving the above-mentioned optimized scheduling model, and ensuring the real feasibility of the optimization results in engineering practice.

[0088] (3) Based on the connection relationship between the main port and the transformer of the back-to-back DC remote power supply equipment, and the connection relationship between the slave port and the load-side node, determine the power balance constraints of the AC line; This constraint is divided into two cases depending on the different topological forms: For example Figure 3 The restructured network topology (for existing transformer substations) connects the main ports of the back-to-back DC remote power supply equipment to the low-voltage side of the existing transformer substations. At this point, the overall AC power balance of the entire network is: the sum of the total network load and node injection = grid power purchase + photovoltaic inverter output + back-to-back port output. Since the substations must simultaneously satisfy active and reactive power balance, the power balance constraint formula for the AC lines is as follows: in, , They are respectively the Taiwan area Xiangdi The injected active and reactive power of each node; , They are respectively the Taiwan area Xiangdi The active and reactive power of each photovoltaic converter; , Back-to-back DC remote power supply equipment The port is The active and reactive power of a phase.

[0089] For example Figure 4 The network topology is restructured by adding transformers. Because dedicated transformers are installed independently of the original distribution areas, the main ports of the back-to-back remote power supply equipment no longer occupy the capacity of the original distribution area transformers, but instead directly feed power to the next higher-level medium-voltage distribution area. To adapt to the dual-transformer system, the entire network load is supplied jointly by the existing transformers in the distribution area and the dedicated transformer. The formula is modified as follows: in, , These represent the active and reactive power transmitted by the existing transformers in the distribution area, respectively. , These represent the active and reactive power transmitted by the dedicated transformer, respectively.

[0090] The above formula introduces The independent settlement term for the channel explicitly removes the bottleneck of the original transformer being limited by its backfeed capacity in the mathematical model. Surplus power will tend to be preferentially fed out from the dedicated transformer, thereby enabling precise power allocation for back-to-back devices through the mathematical model.

[0091] (4) Power balance constraints of common DC bus and equipment boundary constraints The power balance constraint of the common DC bus, as defined in S3, ensures that all energy injection terminals (photovoltaics, energy storage discharge) and energy outflow terminals (back-to-back ports, energy storage charging) on ​​the common DC bus are strictly conserved at all times. This is the foundation for stable system operation. The power balance constraint of the common DC bus is as follows: (5) Optionally, the constraint set also includes distributed photovoltaic operation constraints. For the actual operating conditions in which distributed photovoltaic in the transformer area is often single-phase connected and operates according to the maximum power point tracking (MPPT) principle, a full photovoltaic power generation constraint can be set.

[0092] Specifically, when the system does not adopt a strategy of actively reducing photovoltaic output (curtailment), distributed photovoltaic power must meet the full power generation constraint: in, For the first The predicted output of a distributed photovoltaic system during the scheduling cycle. This constraint clarifies the boundary conditions for system operation.

[0093] Step S505: Based on three-phase power flow constraints, operational safety constraints, AC line power balance constraints, and power balance constraints, determine the set of constraint conditions.

[0094] The comprehensive objective function from step S503 and the constraint set determined in step S504 are combined to form the optimal scheduling model for the power distribution area of ​​this invention. This model is a standard mixed-integer second-order cone programming model (MISOC P). Because the second-order cone relaxation (SOCP) technique is used to handle the original non-convex power flow equations, this model belongs to the category of convex optimization and has the characteristics of fast convergence speed and unique global optimal solution. Mathematically, it completely eliminates the technical defect of traditional heuristic algorithms that are prone to getting trapped in "local optima".

[0095] In some embodiments, step S6 acquires real-time operating data of the distribution area; inputs the real-time operating data into the optimization scheduling model for solution, and obtains the power target values ​​corresponding to the back-to-back DC remote power supply equipment and photovoltaic converter, so as to optimize the power supply control of the distribution area based on the power target values.

[0096] Specifically, the real-time operating status data of the distribution area can be collected through the SCADA system, intelligent measurement terminals (AMI), and high-precision sensors deployed at various nodes within the distribution area. The real-time operating data includes at least: the three-phase voltage amplitude and phase angle of each node in the distribution area (including photovoltaic access points, load points, and back-to-back equipment access points); the three-phase current amplitude of each branch; the low-voltage side three-phase current of existing transformers and dedicated transformers in the distribution area; and the real-time output power of each distributed photovoltaic system. The real-time state of charge (SOC) and maximum chargeable / dischargeable power of the energy storage system, as well as the real-time electricity price for the current period. All of the above data must be accurately time-stamped to ensure the timeliness of the solution results.

[0097] The acquired real-time data is then substituted into the optimized scheduling model constructed in step S5. Specifically, the collected real-time load, real-time photovoltaic output, and real-time electricity price are substituted as known basic parameters (constant terms); all the constraints in step S504 are instantiated, and the weight coefficients of each element in the objective function are determined. , , The optimal values ​​are determined under the current operating conditions. Once ready, the model data is input into a commercial solver (such as Gurobi or Cplex) via a standard interface.

[0098] The optimal scheduling model is solved to obtain the power target value. A commercial solver is then used to solve the optimal scheduling model for the current time. Since the model used in this embodiment is a standard mixed-integer second-order cone programming model (MISOCp), which is a convex optimization problem, the solver can guarantee convergence to the global optimum in a very short time (milliseconds / seconds), thus perfectly meeting the timeliness requirements of real-time control of the distribution area.

[0099] After solving the problem, the decision variables output by the model are extracted to obtain the target power values ​​corresponding to the back-to-back DC remote power supply equipment and photovoltaic converters. Specifically, this includes: Back-to-back DC remote power supply equipment master port and slave port at Mutually( The optimal active power target value and reactive power target value ; Each photovoltaic converter in Optimal active power target value of phase and reactive power target value ; Target charging and discharging power of energy storage system .

[0100] The power supply phase of the transformer substation is balanced according to the power target value. The power target value obtained above will be used as the basis for the calculation. , as well as , As control commands, they are sent through the communication network to the master / slave port controllers of the corresponding back-to-back DC remote power supply equipment and the controllers of each photovoltaic converter (AC / DC), driving each AC side to execute the corresponding power output, thereby realizing real-time closed-loop regulation of the power distribution area.

[0101] In some embodiments, the process of balancing the power supply phase includes: through the back-to-back device main port: utilizing its three-phase independent adjustment capability, according to... , The system receives instructions to adjust the active and reactive power components of the output in real time. Under surplus power conditions, excess photovoltaic power on the common DC bus is directionally fed back through the main port and the dedicated transformer (or the original distribution transformer), while suppressing the three-phase imbalance of itself and the dedicated transformer.

[0102] Through back-to-back equipment, specific single-phase active / reactive power is injected from the port to the load-side node with the most severe three-phase imbalance in the transformer substation according to the power command, thereby achieving "internal self-consistent management" of the three-phase imbalance of the original transformer substation.

[0103] Through photovoltaic converters: based on power commands, and on the basis of achieving maximum power point tracking, the active and reactive power injected into each phase node of the transformer area is dynamically adjusted to smooth out node voltage deviations and achieve coordinated management of node voltage deviations and three-phase imbalances.

[0104] Through a complete closed-loop chain of "real-time data acquisition – model solving – closed-loop control," the abstract convex optimization mathematical model is transformed into precise control commands for the actual physical equipment. The convex nature of the model ensures extremely fast solution speed and global optimality, enabling the system to respond to photovoltaic power output fluctuations and time-varying load characteristics with extremely high response speed, shifting from passive management to proactive prevention.

[0105] In an optional embodiment, to verify the effectiveness and superiority of the method of this application, this embodiment uses a 22-node power distribution system to simulate and verify the voltage regulation method of the transformer substation. Please refer to [reference needed]. Figure 2 , Figure 2 This is a diagram of a traditional power supply architecture for a transformer substation, as provided in this application. Figure 2 As shown, the two ends of the back-to-back DC remote power supply device are connected in series at nodes 22 and 18. The relevant parameters for this example are shown in Table 1.

[0106] Table 1 Parameter Table for the Calculation Example Please refer to Figure 5 , Figure 5 This is a distributed photovoltaic (PV) output data curve diagram according to an embodiment of this application. The diagram shows the predicted output of 11 distributed PV systems (PV1 to PV11) within a 24-hour scheduling cycle in the example. The horizontal axis represents time (0~25h), and the vertical axis represents PV output (MW). Figure 5 It can be seen that these 11 output curves exhibit a highly consistent and typical "bell-shaped" characteristic. The photovoltaic systems begin generating power around 6-7 AM, reaching their maximum output peak between 12 PM and 2 PM (each photovoltaic peak output ranges from approximately 0.04MW to 0.07MW). Although the output trend is the same, the peak values ​​differ significantly, reflecting the heterogeneity of the installed capacity or actual sunlight conditions of each photovoltaic device. Most importantly, all 11 photovoltaic systems reach their maximum output almost simultaneously during the midday period (12:00-2:00 PM). This highly intermittent characteristic of multiple photovoltaic systems "concentratedly generating power," combined with the often low load conditions in the afternoon, results in severe power surplus and backflow to the main grid on the AC side of the distribution area. This is the root cause of severe voltage exceedances at distribution nodes and three-phase imbalance problems. This embodiment is based on... Figure 5 The high-proportion, high-concentration photovoltaic power output scenario shown verifies the effectiveness of the architecture proposed in this application.

[0107] Please refer to Figure 6, which is a 24-hour three-phase load characteristic diagram of transformer area 1 according to an embodiment of this application, including three sub-diagrams. Figure 6(a) is the load curve of phase a of transformer area 1 according to an embodiment of this application. As shown in Figure 6(a), phase A load is a typical heavy-load phase, with extremely high and drastic load levels throughout the day, obvious morning and evening peaks, and maximum active power reaching over 180kW, with active and reactive power fluctuating at the same frequency. Figure 6(b) is the load curve of phase b of transformer area 1 according to an embodiment of this application. As shown in Figure 6(b), phase B load exhibits medium load characteristics, with a peak value of around 160kW, and its most obvious feature is a deep trough around 2 PM. This feature combined with Figure 5 Photovoltaic output data can easily lead to severe power backflow in phase B during the peak photovoltaic power generation period at noon, causing voltage to exceed the upper limit. Figure 6(c) is a load curve of phase C in transformer area 1 according to an embodiment provided in this application. As can be seen from Figure 6(c), phase C is a typical lightly loaded phase, with extremely low and flat load throughout the day, and the maximum power does not exceed 60kW, basically fluctuating slightly within the range of 20-40kW.

[0108] Combination Figure 5 Figure 6 shows that this distribution area exhibits extreme imbalance on both the source and load sides. Figure 5 The peak photovoltaic output period (approximately 11:00 AM to 3:00 PM) coincides with the high load on phase A in Figure 6(a), the low load on phase B in Figure 6(b), and the extremely low load on phase C in Figure 6(c). This operating condition of "high photovoltaic output on the source side and severe three-phase imbalance on the load side (heavy on phase A, moderate on phase B, and light on phase C)" is the root cause of severe three-phase imbalance and node voltage exceeding limits in the transformer substation.

[0109] To verify the effectiveness and accuracy of the method proposed in this invention, three planning methods and scenarios were set up for comparison: Option 1: Based on the traditional architecture, photovoltaics follow MPPT control, and active and reactive power cannot be adjusted.

[0110] Option 2: Based on the traditional architecture, the active and reactive power of photovoltaics can be adjusted.

[0111] Option 3: Based on the reconstructed network topology architecture of this application, the active and reactive power of the photovoltaic system itself is not adjustable, while the photovoltaic converter can be flexibly adjusted. Wherein, topology (a) is based on... Figure 3 The existing transformer substation voltage regulation architecture shown is topology (b) based on... Figure 4 The reconstructed network topology is shown in the example of adding a transformer. Table 2 compares the optimization results of the three schemes in the IEEE 22-node example: Table 2 Comparison of optimization results of three schemes under the IEEE 22-node example As shown in Table 2, compared to Schemes 1 and 2, Scheme 3 (topology a) reduces electricity purchase costs by 11.33% and 1.18%, respectively, and reduces grid loss costs by 98.09% and 81.91%, respectively. Regarding transformer loss costs, Scheme 3 (topology a) is slightly higher than Scheme 2. This is because the photovoltaic system in Scheme 2 has active and reactive power regulation capabilities, effectively avoiding the power backflow phenomenon present in Schemes 1 and Scheme 3 (topology a), resulting in the lowest transformer load rate among all schemes, thus reducing transformer losses. However, it should be noted that the lower transformer losses in Scheme 2 are achieved at the cost of reducing photovoltaic output. Although this scheme reduces transformer losses, the reduction in photovoltaic output leads to a lower photovoltaic utilization rate. Meanwhile, although Scheme 3 (topology a) does not have the lowest transformer loss costs, thanks to the significant reduction in electricity purchase costs and grid loss costs, its total operating cost is still the best among all schemes, reducing costs by 24.50% and 2.50% compared to Schemes 1 and 2, respectively. In particular, the grid loss cost shows a precipitous decrease. This is because Scheme 3 aggregates photovoltaic power through a common DC bus, shortens the transmission distance of AC power, and significantly reduces power loss on the line, achieving optimal economic operation from the root of physical topology.

[0112] Please refer to Figures 7 to 9. Figure 7 is a node voltage distribution diagram of Scheme 1 of an embodiment provided in this application. Figure 8 is a node voltage distribution diagram of Scheme 2 of an embodiment provided in this application. Figure 9 is a node voltage distribution diagram of Scheme 3 of an embodiment provided in this application. Analysis of Figures 7 to 9 shows that the overall voltage deviation of Scheme 1 is 64.11 pu, with the highest voltage in the three phases reaching 1.039 pu and the lowest being 0.831 pu; the overall voltage deviation of Scheme 2 is 7.47 pu, with the highest voltage in the three phases reaching 1.013 pu and the lowest being 0.979 pu; the overall voltage deviation of Scheme 3 (a) is 1.69 pu, with the highest voltage in the three phases decreasing to 1.001 pu and the lowest increasing to 0.999 pu. Compared to Schemes 1 and 2, the overall voltage deviation of Scheme 3 (a) is reduced by 97.36% and 77.37% respectively, and the node voltages are all within the ±7% requirement stipulated by the national standard, resulting in a 100% voltage compliance rate. The comparison in Figures 7 to 9 illustrates that, compared to the limitations of relying solely on single-point regulation by photovoltaic inverters in traditional architectures, the "DC aggregation-distributed grid connection" architecture proposed in this application, after aggregation through a common DC bus, allows the master and slave ports of back-to-back remote power supply equipment to work together with the photovoltaic converters to output power, thereby reshaping the power flow distribution from a physical topology perspective and achieving active support for the entire grid voltage.

[0113] Please refer to Figures 10 to 12 , Figure 10 This is a heatmap of node voltage imbalance according to one embodiment of this application. Figure 10As can be seen from the large yellow-green area in the figure, it indicates that under the traditional architecture, due to the non-adjustable photovoltaic system, the three-phase voltage imbalance at the grid node is extremely serious. Furthermore, the three-phase imbalance may also cause the phase with high power to have low voltage. The voltage imbalance at the node in Scheme 1 can reach up to 11.84%, far exceeding the industry standard of 3%. Figure 11 This is a heatmap of node voltage imbalance according to one embodiment of this application. (By...) Figure 11 As can be seen, although the color in the figure has obviously turned blue (improvement), there are still some light blue areas. The highest voltage imbalance at node 2 is 1.448%, which meets the standard but still fluctuates. Figure 12 This is a heatmap of node voltage imbalance in topology (a) of embodiment 3 provided in this application. Figure 12 As can be seen, the entire heat map presents a uniform dark blue color, indicating that the three-phase voltages at the nodes are almost perfectly symmetrical. The highest voltage imbalance at the nodes in topology 3(a) is only 0.563%. Compared to topologies 1 and 2, the maximum voltage imbalance at the nodes in topology 3(a) is reduced by 95.24% and 61.11%, respectively. All three-phase voltages meet industry standards, with the three-phase imbalance not exceeding 3%, and the node voltage imbalance compliance rate is 100%. By significantly reducing the three-phase imbalance, the carrying capacity of new loads and distributed photovoltaic power in the area can be increased.

[0114] Please see Figures 13 to 15 , Figure 13 This is a line graph showing the transformer power imbalance of one embodiment provided in this application. Figure 13 It can be seen that, due to the lack of active adjustment capability, the three-phase imbalance of the transformer in Scheme 1 fluctuates violently, reaching a maximum of 25.09%, and often exceeds the 15% red line. Figure 14 This is a line graph showing the transformer power imbalance of embodiment 2 provided in this application. Figure 14 It can be seen that although Scheme 2 (only photovoltaic active and reactive power can be adjusted) can improve the voltage to a certain extent, when photovoltaic power generation is high and load is low, due to the complex bidirectional power interaction, the transformer imbalance has a huge peak, soaring to a maximum of 79.13%, which is seriously deteriorated. Figure 15 This is a line graph of transformer power imbalance in topology (a) of embodiment 3 provided in this application. Figure 15 As can be seen, the broken line of Scheme 3 remains at an extremely low and stable level, with the highest three-phase imbalance of the transformer being only 9.047%. Compared to Schemes 1 and 2, the maximum three-phase imbalance of the transformer in Scheme 3 topology (a) is reduced by 63.94% and 88.56%, respectively, consistently meeting the requirement of not exceeding 15%. This demonstrates that the back-to-back equipment achieves internal self-consistent management of the transformer's three-phase imbalance from the source through single-phase power mutual assistance at the ports, effectively overcoming the shortcomings of traditional imbalance management methods.

[0115] Please see Figures 16 to 18 , Figure 16 This is a diagram illustrating the operation of a back-to-back converter according to one embodiment of this application. Figure 17 This is a diagram illustrating the operation of a back-to-back converter according to embodiment 2 of this application. In embodiments 1 and 2, the back-to-back DC remote power supply equipment purchases electricity from the master port to supply the load at the slave port during the nighttime photovoltaic power generation period; during the peak photovoltaic power generation period, the surplus active power is transmitted from the slave port to the master port and fed back into the upper-level grid, achieving only basic power transmission, and the output of the master and slave ports exhibits extremely large fluctuations. Figure 18 This is a diagram illustrating the operation of a back-to-back converter in topology 3(a) of one embodiment provided in this application. In topology 3(a), a DC bus is added to the DC side of the back-to-back DC remote power supply equipment. Although it operates similarly to the previous two schemes at night, during periods of high photovoltaic power generation, the DC bus directly collects photovoltaic power, allowing the photovoltaic converter to share the transmission power from the slave port, and excess active power is directly fed back to the grid through the DC bus. This operating mode significantly shortens the transmission distance of AC power, reduces long-term losses in AC lines, effectively reduces network losses in the distribution area, alleviates the regulation pressure on the back-to-back equipment, and extends the equipment's service life.

[0116] In some embodiments, this application provides a power supply phase balancing system based on transformer substations, which is used to perform the power supply phase balancing method based on transformer substations as described in this application.

[0117] It is understood that the above system embodiments correspond to the method embodiments of this application, and can implement the power supply phase balancing method based on transformer substations provided by any of the above method embodiments of this application.

[0118] Based on the above-described method embodiments, another embodiment of this application provides a computer-readable storage medium, including: a stored computer program, wherein, when the computer program is executed, it controls the device where the computer-readable storage medium is located to perform a power supply phase balancing method based on a transformer substation as described in any of the above-described method embodiments of this application.

[0119] The modules / units integrated into the device / terminal equipment, if implemented as software functional units and sold or used as independent products, can be stored in a computer-readable storage medium. Based on this understanding, all or part of the processes in the methods of the above embodiments of the present invention can also be implemented by a computer program instructing related hardware. The computer program can be stored in a computer-readable storage medium, and when executed by a processor, it can implement the steps of the various method embodiments described above. The computer program includes computer program code, which can be in the form of source code, object code, executable files, or certain intermediate forms. The computer-readable medium can include: any entity or device capable of carrying computer program code, recording media, USB flash drives, portable hard drives, magnetic disks, optical disks, computer memory, read-only memory (ROM), random access memory (RAM), electrical carrier signals, telecommunication signals, and software distribution media, etc.

[0120] The above are preferred embodiments of this application. It should be noted that, for those skilled in the art, several improvements and modifications can be made without departing from the principles of this application, and these improvements and modifications are also considered to be within the scope of protection of this application.

Claims

1. A method for DC collection and power supply of distributed power sources in a transformer substation, characterized in that, include: Obtain the network topology of the transformer area and the basic parameters of each electrical device; The network topology is reconstructed to obtain a reconstructed network topology; wherein the reconstructed network topology includes a common DC bus, back-to-back DC remote power supply equipment, transformers, photovoltaic converters, and energy storage devices; Based on the reconstructed network topology and the basic parameters, the power balance constraints of the common DC bus are determined. Based on the aforementioned fundamental parameters, a comprehensive objective function is constructed; the comprehensive objective function includes a three-phase imbalance objective function, an operating cost objective function, and a voltage deviation objective function. Based on the reconstructed network topology, the basic parameters, the power balance constraints, and the comprehensive objective function, the optimal scheduling model for the transformer area is determined. The real-time operating data of the transformer substation is obtained; the real-time operating data is input into the optimization scheduling model for solution to obtain the power target values ​​corresponding to the back-to-back DC remote power supply equipment and the photovoltaic converter, so as to optimize the power supply control of the transformer substation based on the power target values.

2. The DC collection power supply method for distributed power sources in a transformer substation according to claim 1, characterized in that, The process of reconstructing the network topology to obtain a reconstructed network topology includes: The common DC bus is connected to the DC side of the back-to-back DC remote power supply equipment; wherein, there may be several back-to-back DC remote power supply equipment. Determine the AC busbar connected to the low-voltage side of the transformer, and connect the main port of the back-to-back DC remote power supply equipment to the AC busbar; Identify the load-side node with the highest voltage imbalance in the transformer area, and connect the slave port of the back-to-back DC remote power supply equipment to the load-side node. Each photovoltaic power generation system is connected to the common DC bus through the DC port of its corresponding photovoltaic converter to obtain the reconstructed network topology.

3. The DC collection power supply method for distributed power sources in a transformer substation according to claim 2, characterized in that, The transformer includes an additional transformer, and the step of connecting the main port of the back-to-back DC remote power supply equipment to the AC busbar also includes: Connect the high-voltage side of the added transformer to the upstream medium-voltage line; The main port of the back-to-back DC remote power supply equipment is connected to the low-voltage AC bus of the added transformer; wherein, the back-to-back DC remote power supply equipment adjusts the active power and reactive power of the added transformer respectively, so that the three-phase imbalance of the added transformer is limited to a preset range.

4. The DC collection power supply method for distributed power sources in a transformer substation according to claim 1, characterized in that, The determination of the power balance constraints of the common DC bus based on the reconstructed network topology and the basic parameters includes: Based on the reconstructed network topology, each power injection device and each power outflow device connected to the common DC bus is determined. Based on the aforementioned basic parameters, the injected power value of each power injection device and the outflow power value of each power outflow device are determined. The power balance constraint is determined based on each of the injected power values ​​and each of the outflow power values.

5. The DC collection power supply method for distributed power sources in a transformer substation according to claim 1, characterized in that, The basic parameters include the three-phase output current of the transformer, and the objective function for determining the three-phase unbalance includes: Determine the maximum and minimum current values ​​among the three-phase output currents of the transformer; Determine the current direction of the three-phase output current; The objective function for the three-phase unbalance is determined based on the current direction, the maximum current value, and the minimum current value.

6. The DC collection power supply method for distributed power sources in a transformer substation according to claim 5, characterized in that, The step of determining the objective function for the three-phase unbalance based on the current direction, the maximum current value, and the minimum current value includes: When the current direction is positive, the current difference between the maximum current value and the minimum current value is determined, and the current difference is divided by the maximum current value to obtain the first three-phase unbalance objective function; When the current direction is reversed, determine the first absolute value of the minimum current value and the second absolute value of the maximum current value, and divide the first absolute value by the second absolute value to obtain the second three-phase unbalance objective function.

7. The DC collection power supply method for distributed power sources in a transformer substation according to claim 1, characterized in that, The step of determining the optimal scheduling model for the distribution area based on the reconstructed network topology, the basic parameters, the power balance constraints, and the comprehensive objective function includes: Obtain the grid electricity price and the total electricity purchase amount; determine the electricity purchase cost based on the product of the grid electricity price and the total electricity purchase amount; Based on the reconstructed network topology and the basic parameters, the resistance and current of each branch in the transformer substation are determined; the line loss power of each branch is calculated according to the resistance value and the square of the current; the line loss power of each branch is accumulated to obtain the total line loss power of the transformer substation; the network loss cost is determined according to the product of the total line loss power and the grid electricity price. Based on the electricity purchase cost and the network loss cost, determine the objective function for operating costs; Based on the reconstructed network topology and the basic parameters, the voltage deviation between the actual voltage value and the rated voltage value of each node in the transformer area is determined; and a voltage deviation objective function is determined based on each voltage deviation. The comprehensive objective function is determined based on the three-phase imbalance objective function, the operating cost objective function, and the voltage deviation objective function; Based on the reconstructed network topology and the basic parameters, a set of constraints is determined; The optimized scheduling model is determined based on the comprehensive objective function and the set of constraints.

8. The DC collection power supply method for distributed power sources in a transformer substation according to claim 7, characterized in that, The determination of the constraint set based on the reconstructed network topology and the basic parameters includes: Based on the reconstructed network topology, the node connection relationships and branch connection relationships of the transformer area are determined, and the three-phase power flow constraints are determined according to the node connection relationships and branch connection relationships. Based on the aforementioned basic parameters, the voltage operating range of each node and the current operating range of each branch in the transformer substation are determined, and operational safety constraints are determined based on the voltage operating range and the current operating range. Based on the connection relationship between the main port of the back-to-back DC remote power supply equipment and the transformer, and the connection relationship between the slave port and the load-side node, the power balance constraints of the AC line are determined. Based on the three-phase power flow constraints, the operational safety constraints, the AC line power balance constraints, and the power balance constraints, the constraint condition set is determined.

9. A DC collection power supply system for distributed power sources in a transformer substation, characterized in that, The distributed power supply DC collection system for the transformer substation is used to perform the distributed power supply DC collection method for the transformer substation as described in any one of claims 1 to 8.

10. A computer-readable storage medium, characterized in that, include: A stored computer program, wherein, when the computer program is executed, the device containing the computer-readable storage medium is controlled to perform the DC collection power supply method for distributed power sources in a transformer substation as described in any one of claims 1 to 8.