A method and system for optimizing the frequency regulation performance of an energy storage power station; an energy storage power station

By introducing a communication architecture based on the GOOSE protocol and a PMS device into the energy storage power station, the frequency regulation performance of the energy storage power station is optimized, the communication delay problem between EMS and PCS is solved, and fast response and high-precision frequency regulation control are achieved.

CN123073774APending Publication Date: 2026-11-10XUCHANG XJ SOFTWARE TECHNOLOGIES LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611020389.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-09
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

The frequency regulation performance of existing energy storage power stations is poor, mainly due to the large communication delay, large data volume, and long remote control command polling time between EMS and PCS, resulting in poor response time and accuracy.

Method used

A communication architecture for scheduling AGC-EMS-PMS-PCS is established using the GOOSE protocol. The scheduling command is separated into frequency modulation command and planning curve command through the PMS device. The PMS and PCS use the GOOSE protocol for high-speed data interaction. The PCS immediately switches to frequency modulation mode, removes the rate limit, optimizes the power allocation strategy, and dynamically allocates power according to the PCS's SOC and maximum allowable power.

Benefits of technology

It significantly improves the frequency regulation performance of energy storage power stations, shortens the response time to the millisecond level, improves regulation accuracy and rate, and enhances the frequency regulation speed and reliability of the power grid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123073774A_ABST
    Figure CN123073774A_ABST
Patent Text Reader

Abstract

This invention belongs to the field of power grid frequency regulation control technology, specifically relating to a method and system for optimizing the frequency regulation performance indicators of an energy storage power station, and an energy storage power station. The method first distinguishes the power commands issued by the dispatch master station from the frequency regulation commands and sends them to the energy storage coordination control device (PMS). Then, the PMS receives key operating information from the energy storage converter PCS, updates the power allocation strategy based on the frequency regulation commands, and sends the target value and frequency regulation command to each controllable PCS according to the power allocation strategy. Each controllable PCS immediately triggers the frequency regulation mode upon receiving the frequency regulation command, removes the regulation rate limit, and responds to the frequency regulation command, thereby improving the response time indicator in the frequency regulation performance indicators. This invention can ensure highly reliable data interaction and transmission, significantly reducing the data delay and execution delay of control commands.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of power grid frequency regulation control technology, specifically relating to a method and system for optimizing the frequency regulation performance indicators of an energy storage power station, and an energy storage power station. Background Technology

[0002] With the integration of numerous wind farms, photovoltaic power plants, and other new energy sources into the power grid, the demand for energy storage power stations is constantly increasing to enhance grid absorption capacity and mitigate power output fluctuations. The installed capacity of energy storage in various regions is also continuously reaching new highs. The operational status of energy storage power stations has a significant impact on the safe and stable operation of the power grid. Therefore, local energy regulatory agencies have revised and improved their "two detailed rules," including energy storage power stations under their supervision and imposing stricter requirements on their operation and assessment. Energy storage power stations must be able to respond quickly and accurately to dispatch commands. In some regions, the K-value of energy storage power stations is even used as a crucial factor in calling upon them for ancillary services such as charging, discharging, frequency regulation, and peak shaving, which significantly impacts their operational profitability. Therefore, improving the K-value of energy storage power stations is essential.

[0003] For example, Chinese invention patent application CN111507565A, with publication date August 7, 2020, discloses a performance evaluation method and system for energy storage power stations in frequency regulation application scenarios. It determines evaluation indicators such as frequency regulation accuracy, frequency regulation correlation, frequency regulation response time, frequency regulation rate, SOC status of energy storage power station, and PCS failure rate of energy storage power station based on the frequency regulation characteristics of energy storage power station.

[0004] For example, for the Southern Power Grid, the frequency regulation performance of energy storage power stations is measured by a comprehensive index K value (composed of regulation rate index K1, response time index K2, and regulation accuracy index K3). The K value is calculated as follows:

[0005]

[0006] In the formula, , This represents the measured regulation rate of the energy storage power station. For this region, the standard adjustment rate is K1≤5; , This refers to the time from when the dispatch command is issued to when the power at the grid connection point of the energy storage station reaches the target value. For the response delay specified by the scheduler, K2∈(0~1); , In response to the deviation between the actual output of the energy storage station and the theoretical target value when adjusting the output, K3 represents the allowable deviation for the energy storage station's response adjustment, where K3 ∈ (0~1).

[0007] Currently, the power control method of energy storage power stations is basically to distribute dispatch instructions to energy storage converters (PCS) through the Energy Management System (EMS) to adjust the grid-connected power to the dispatch target power. However, this method has the following drawbacks: 1) The EMS and PCS generally communicate using the IEC-61850-MMS protocol or the IEC-104 protocol. Both of these communication schemes are unicast communication, requiring a large amount of data to be parsed, resulting in significant data delays. The EMS needs a long time to receive and process the current information of all PCS in the station. 2) When the EMS issues target value instructions to the PCS, it must use remote adjustment services to issue remote adjustment instructions to each PCS individually. When the number of connected PCS is large, the time required for one polling cycle is long. 3) The real-time grid-connected power collected by the EMS comes from other measurement and control devices, which has a certain delay, resulting in a large deviation in power accuracy control and lag. 4) When there is communication jitter or data loss between the EMS and PCS, the traditional protocol has a long retransmission cycle (seconds), which can easily cause power tracking deviations. Summary of the Invention

[0008] The purpose of this invention is to provide a method and system for optimizing the frequency regulation performance of an energy storage power station, and an energy storage power station, to solve the problem of poor frequency regulation performance caused by the power control method of distributing dispatch instructions to the energy storage converter PCS through the energy management system (EMS).

[0009] To address the aforementioned technical problems, the first aspect of this invention provides a method for optimizing the frequency regulation performance of an energy storage power station, the method comprising:

[0010] The power commands issued by the dispatch master station are distinguished into frequency regulation commands, and then sent to the energy storage coordination control device (PMS).

[0011] The PMS receives key operational information from the PCS (Power Storage Converter), then updates the power allocation strategy in conjunction with the frequency regulation command, and sends the target value and frequency regulation command to each controllable PCS according to the power allocation strategy.

[0012] Upon receiving a frequency modulation command, each controllable PCS immediately triggers the frequency modulation mode, removes the adjustment rate limit, and responds to the frequency modulation command to improve the response time indicator in the frequency modulation performance metrics.

[0013] In one possible implementation, the following power allocation strategy is employed to improve the regulation rate in the frequency modulation performance metrics:

[0014] The power allocation to each PCS is determined based on the SOC and maximum allowable charge / discharge power transmitted by the PCS:

[0015]

[0016] In the formula, The power allocation to the i-th PCS is the percentage of power that can be controlled, where n is the total number of controllable PCS. During charging... for , The maximum allowable charging power of the i-th PCS during discharge. for , The maximum allowable discharge power of the i-th PCS; The adjustment weight for the i-th PCS during charging. for , During discharge for , , For the current SOC of the i-th PCS, , Let S and SOC be the maximum and minimum values ​​for the i-th PCS, respectively.

[0017] In one possible implementation, the real-time loss of the energy storage power station is calculated based on the deviation between the real-time power at the grid connection point and the target power. This loss is then added to the target power and sent to each controllable PCS to achieve power correction, thereby improving the regulation accuracy index in the frequency regulation performance indicators.

[0018] In one possible implementation, the PMS and PCS exchange data via a GOOSE switch using the GOOSE protocol.

[0019] In one possible implementation, the command messages issued by the PMS to the PCS are divided into different priorities according to their urgency, with frequency modulation commands having a higher priority than mode switching commands, and mode switching commands having a higher priority than parameter configuration commands.

[0020] In one possible implementation, power commands are differentiated from active power planning curves and sent to the Energy Management System (EMS). The EMS collects full information from the Power Planning System (PCS) and the Energy Management System (BMS), removes PCS information with anomalies, and sends adjustable PCS information to the Power Management System (PMS).

[0021] To solve the above-mentioned technical problems, the second aspect of the present invention provides an energy storage power station, including an energy storage coordination control device (PMS) and an energy storage converter (PCS); the PMS is used to: receive frequency regulation instructions distinguished from power instructions issued by the dispatch master station, and key operating status information sent by the PCS, and then update the power allocation strategy in combination with the frequency regulation instructions, and issue the target value and frequency regulation instructions of each controllable PCS to each controllable PCS according to the power allocation strategy;

[0022] PCS is used to: immediately trigger frequency modulation mode upon receiving a frequency modulation command, release the adjustment rate limit, and respond to the frequency modulation command, thereby improving the response time indicator in the frequency modulation performance metrics.

[0023] To solve the above-mentioned technical problems, the third aspect of the present invention provides a frequency regulation performance index optimization system for energy storage power stations, including a dispatch master station and an energy storage converter PCS, and also includes an energy storage coordination control device PMS;

[0024] The dispatch master station is used to: distinguish the issued power commands from the frequency modulation commands and send them to the PMS, and receive the frequency modulation execution status;

[0025] The PMS is used to: receive frequency modulation instructions distinguished from power instructions from the scheduling master station, and key operating status information sent by the PCS, and then update the power allocation strategy in combination with the frequency modulation instructions, and send the target value and frequency modulation instructions of each controllable PCS to each controllable PCS according to the power allocation strategy.

[0026] PCS is used to: immediately trigger frequency modulation mode upon receiving a frequency modulation command, release the adjustment rate limit, and respond to the frequency modulation command, thereby improving the response time indicator in the frequency modulation performance metrics.

[0027] In one possible implementation, the following power allocation strategy is employed to improve the regulation rate in the frequency modulation performance metrics:

[0028] The power allocation to each PCS is determined based on the SOC and maximum allowable charge / discharge power transmitted by the PCS:

[0029]

[0030] In the formula, The power allocation to the i-th PCS is the percentage of power that can be controlled, where n is the total number of controllable PCS. During charging... for , The maximum allowable charging power of the i-th PCS during discharge. for , The maximum allowable discharge power of the i-th PCS; The adjustment weight for the i-th PCS during charging. for , During discharge for , , For the current SOC of the i-th PCS, , Let S and SOC be the maximum and minimum values ​​for the i-th PCS, respectively.

[0031] In one possible implementation, the PMS is also used to: calculate the real-time loss of the energy storage power station based on the deviation between the real-time power at the grid connection point and the target power, and then add the loss to the target power and send it to each controllable PCS to achieve power correction, thereby improving the regulation accuracy index in the frequency regulation performance index.

[0032] The beneficial effects of this invention are as follows: This invention optimizes the communication structure, enabling the dispatch master station to no longer interact solely with the PCS via the EMS. Instead, it separates the dispatch master station's commands, extracting the frequency regulation command, which is then sent to the PCS via the PMS. The PCS immediately switches to a fast response mode, temporarily releasing the power regulation rate limit. This allows for the setting and output of the target active power with millisecond-level latency, improving response time. This optimized communication architecture ensures highly reliable data interaction and transmission, significantly reducing the data latency and execution delay of control commands, and substantially enhancing the frequency regulation speed, accuracy, and reliability of the power grid, demonstrating significant technical benefits and commercial value. Attached Figure Description

[0033] Figure 1 This is a complete communication architecture diagram of the scheduling AGC-EMS-PMS-PCS of this invention. Detailed Implementation

[0034] This invention optimizes the communication structure, enabling the scheduling master station to no longer interact solely with the PCS via the EMS. Instead, the frequency commands from the scheduling master station are sent to the PCS through the PMS, and the PCS immediately switches to a fast response mode, temporarily removing the power regulation rate limit. This allows the target active power to be set and output with a millisecond-level delay, improving response time. To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings.

[0035] An implementation method for optimizing the frequency regulation performance of an energy storage power station:

[0036] As mentioned in the background section, the comprehensive index K value is calculated as follows:

[0037]

[0038] In the formula, , This represents the measured regulation rate of the energy storage power station. For this region, the standard adjustment rate is K1≤5; , This refers to the time from when the dispatch command is issued to when the power at the grid connection point of the energy storage station reaches the target value. For the response delay specified by the scheduler, K2∈(0~1); , In response to the deviation between the actual output of the energy storage station and the theoretical target value when adjusting the output, K3 represents the allowable deviation for the energy storage station's response adjustment, where K3 ∈ (0~1).

[0039] To improve the control response speed and control accuracy of energy storage power stations and enhance the frequency regulation performance index K value, this invention proposes an optimization method for improving the K value of energy storage power stations based on an energy storage coordinated control device. By reconstructing the communication architecture and coordinating with the control algorithm, the method reduces command transmission delay, improves power regulation efficiency, and achieves synchronous optimization of K1, K2, and K3.

[0040] The innovations of this invention mainly include two parts. First, it establishes a complete communication architecture for scheduling AGC-EMS-PMS-PCS using the GOOSE protocol through the PMS device. Second, it establishes optimized power allocation based on real-time power monitoring of the grid connection point and real-time data from the PCS. The communication architecture optimization method based on the GOOSE communication protocol ensures highly reliable data interaction and transmission, significantly reducing the data latency and execution delay of control commands. Based on real-time power monitoring of the grid connection point and real-time data from the PCS, it optimizes the power control method to maximize the utilization of PCS in good condition, thereby improving response speed and control accuracy.

[0041] The first part is a complete communication architecture system established by using the PMS device and the GOOSE protocol to create a scheduling master station-AGC system-EMS-PMS-PCS system. This is a frequency regulation performance optimization system for energy storage power stations according to the present invention. The system includes a remote control device, an energy storage power station-side EMS system, an energy storage power station-side PMS system, an energy storage execution unit, and an energy storage power station communication subsystem. Key information from each module is exchanged at high speed via the GOOSE protocol, while routine information is handled using 104 or MMS protocols. The specific architecture is as follows: Figure 1 As shown, the details are as follows:

[0042] 1. Remote AGC device: It uses the 104 protocol to connect to the power grid dispatch master station, and distributes dispatch instructions to EMS and PMS according to the planned curve or auxiliary frequency regulation service, and pushes them to the power station side through optical fiber or 5G private network; at the same time, it receives real-time energy storage information transmitted back from the power station side.

[0043] 2. PMS: Receives frequency regulation commands from the remote control AGC, interacts with the PCS using the GOOSE communication protocol to obtain key information, and monitors the key operational status of the energy storage station's PCS in real time. Based on this information, it calculates power allocation strategies. Upon receiving a frequency regulation command, it immediately switches to frequency regulation mode and sends the frequency regulation flag to the PCS via GOOSE. The PCS adjusts to frequency regulation mode, releases power restrictions, and immediately responds to the frequency regulation command. Furthermore, the PMS device deploys a data acquisition module (PT / CT) to collect real-time information such as voltage, current, and power at the grid connection point.

[0044] 3. EMS: Receives the planning curve instruction information sent by the remote control AGC, and exchanges full information with the PCS using the 104 or MMS communication protocol.

[0045] 4. Energy Storage Execution Unit (PCS and Battery Management System BMS): The energy storage execution unit cluster supports direct triggering of "frequency modulation mode" by GOOSE command, with a power response time of ≤5ms, and CAN communication is used between PCS and BMS.

[0046] 5. Communication subsystem on the energy storage power station side: including GOOSE switch and data network switch; key information between PMS and PCS is exchanged through an independent GOOSE switch using the GOOSE protocol to reduce data latency; the frequency modulation communication link and the non-real-time monitoring link (the non-real-time monitoring link refers to the communication link between PCS and EMS) are isolated through the switch, that is, PCS and PMS communicate through optical fiber via GOOSE network switch to ensure bandwidth.

[0047] The specific steps are as follows:

[0048] S1 classifies the power commands issued by the dispatch master station into frequency regulation commands and planning curve commands, and sends them to PMS and EMS respectively according to the command type.

[0049] S2 simplifies the information exchange between the remote control master station and the PMS, including only the target value and the target instruction execution status, and can transmit information immediately even when using the 104 protocol.

[0050] In S3, the Power Management System (PMS) and the PCS exchange information using the GOOSE protocol. The PCS sends key operational information such as operating status, State of Charge (SOC), real-time power, and allowable adjustable power to the PMS. Upon receiving this information, the PMS updates its power allocation strategy in real time and sends the command type and target value to the PCS. Specifically, upon receiving the frequency modulation target value, the PMS multicasts the target value for each PCS using a single GOOSE message, controlling all controllable PCS to execute the command.

[0051] When PCS receives a frequency modulation command, it changes its operating mode to "frequency modulation mode", removes the adjustment rate limit, and completes the response within 5ms, thus improving the response time index K2.

[0052] S5, EMS receives full data from PCS and BMS, removes PCS with abnormalities, and sends adjustable PCS information to PMS.

[0053] S6, PMS sends the frequency modulation execution status to the motion AGC system, which then feeds back to the dispatch master station.

[0054] The second part relates to an optimization method for improving the K-value of an energy storage power station based on an energy storage coordination control device, the steps of which are as follows:

[0055] S7, GOOSE Message Customization and Priority Classification. Two types of GOOSE messages are defined: command messages (PMS→PCS) and status messages (PCS→PMS). Command messages are prioritized according to urgency: Level 1 (frequency modulation commands, highest priority), Level 2 (mode switching commands), and Level 3 (parameter configuration commands). Status messages include "core status fields" (SOC, actual power, fault code) and "auxiliary fields" (temperature, internal resistance). The transmission period for core fields is ≤10ms, and for auxiliary fields it is ≤100ms.

[0056] S8, low-latency command transmission and parsing. After the AGC master station in the dispatch center generates a frequency modulation command, it is immediately transmitted to the PMS point-to-point via the 104 protocol; the valid command is parsed into the power target value P within 5ms. 目标 The data is then converted into GOOSE protocol messages and sent to the PCS. After the energy storage station completes the execution of the instructions, the execution status is promptly sent to the dispatch master station for feedback.

[0057] S9, based on the PCS's GOOSE messages, performs dynamic power allocation. The PCS transmits key operating information such as operating status, SOC, real-time power, and allowable adjustable power to the PMS in real time via GOOSE. The PMS performs power priority allocation according to the following formula to ensure that each PCS is allocated the power that matches its own, and to ensure that high SOC modules take the lead in regulation tasks, thereby improving the regulation rate index K1.

[0058] The basic approach (also known as Approach 1) is as follows: the power allocated to each controllable PCS is related to the maximum allowable adjustable power of each controllable PCS; the higher the maximum allowable adjustable power of each PCS, the greater the power allocated to it. The specific formula is:

[0059]

[0060] In the formula, This represents the percentage of power allocated to the i-th PCS. Let be the maximum allowable adjustable power of the i-th PCS, and n be the total number of controllable PCS. Specifically, during charging... , The maximum allowable charging power of the i-th PCS during discharge. , This represents the maximum allowable discharge power of the i-th PCS.

[0061] The above basic method only considers the "maximum adjustable power," which may lead to PCS with higher SOC still undertaking a large amount of discharge (or PCS with lower SOC undertaking a large amount of charging), affecting the long-term lifespan of energy storage. Therefore, based on the SOC information of the PCS, P_max_i is weighted and corrected to prioritize allowing the "better state" PCS to undertake more power. Thus, the following method 2 is designed:

[0062] Design the adjustment weights for each PCS. The larger the adjustable SOC of the PCS, The larger, specifically, during charging for , for During discharge for , for ,in, For the current SOC of the i-th PCS, , Let S and SOC be the maximum and minimum values ​​for the i-th PCS, respectively.

[0063] Based on the above adjustment weights The corrected PCS power allocation is as follows:

[0064]

[0065] In the formula, The percentage of power allocated to the i-th PCS, specifically during charging. During discharge , The maximum allowable charging power for the i-th PCS. This represents the maximum allowable discharge power of the i-th PCS.

[0066] S10, power accuracy feedback regulation based on grid connection point power. The real-time loss of the energy storage station is calculated based on the deviation between the real-time power at the grid connection point and the target power (referring to the theoretical target value that the grid connection point of the energy storage station needs to be adjusted to). The deviation value is then added to the target power and sent to the PCS (i.e., the actual processing of the PCS needs to reach the sum of the theoretical target value and the real-time loss). Power correction is completed within 5ms, reducing regulation errors and improving the regulation accuracy index K3.

[0067] An implementation method for optimizing the frequency regulation performance of an energy storage power station:

[0068] This invention provides a frequency regulation performance optimization system for energy storage power stations, which employs... Figure 1 The communication architecture is shown. The system includes a dispatch master station, a power supply converter (PCS) and a power supply coordination control unit (PMS) located at the energy storage station. In addition, it includes an energy management system (EMS) located at the energy storage station.

[0069] The dispatch master station connects to the PMS through the remote AGC device. The remote AGC uses the 104 protocol to connect to the power grid dispatch master station and distributes dispatch instructions to the EMS and PMS according to the planned curve and frequency regulation instructions. It pushes the instructions to the power station side through fiber optic or 5G private network, and at the same time receives the real-time energy storage information (including frequency regulation execution status) transmitted back from the power station side.

[0070] The Power Management System (PMS) can receive frequency regulation commands from the Remote Control AGC (Automatic Generation Control) system, interact with the PCS (Power Control System) using the GOOSE communication protocol, and monitor the PCS status of the energy storage station in real time. Based on the PCS status, it calculates power allocation strategies and sends target power commands to each controllable PCS via GOOSE. Furthermore, the PMS deploys acquisition modules to collect real-time information such as voltage, current, and power at the grid connection point. The power allocation calculation can employ either Method 1 or Method 2 to improve the regulation rate indicator K1 within the frequency regulation performance metrics.

[0071] Method 1: The power allocated to each controllable PCS is related to the maximum allowable adjustable power of each PCS. The higher the maximum allowable adjustable power of each PCS, the greater the power allocated to it. Specifically, the power percentage allocated to the i-th PCS... for:

[0072]

[0073] Method 2: Power allocation to the i-th PCS for:

[0074]

[0075] In the formula, Let be the maximum allowable adjustable power of the i-th PCS; n is the total number of controllable PCS. Let be the adjustment weight of the i-th PCS, and the larger the adjustable SOC of the PCS, the better. The larger; and when charging, for , for During discharge for , for , among them For the current SOC of the i-th PCS, , Let S and SOC be the maximum and minimum values ​​for the i-th PCS, respectively.

[0076] Method 1 is the basic approach, considering only "maximum adjustable power," which may affect energy storage lifespan. Therefore, based on the PCS's SOC information, [the following is necessary:] A weighted adjustment is performed, prioritizing the PCS with the "better state" to bear more power.

[0077] EMS can receive remote AGC planning curve instruction information and exchange full information with PCS using 104 or MMS communication protocols.

[0078] PCS and BMS are energy storage execution units. The energy storage execution unit cluster supports GOOSE commands to directly trigger the "frequency regulation mode", remove the regulation rate limit and respond to the frequency regulation command, with a power response time ≤5ms.

[0079] The PMS and PCS communicate via a GOOSE switch, while the EMS and BMS communicate via a data network switch. The GOOSE switch and data network switch belong to the communication subsystem of the energy storage power station.

[0080] The communication architecture optimization method based on the GOOSE communication protocol described above can ensure highly reliable data interaction and transmission, and greatly reduce the data latency and execution delay of control commands.

[0081] Furthermore, power accuracy feedback adjustment can be based on the grid connection point power. The real-time loss of the energy storage power station is calculated based on the deviation between the real-time power at the grid connection point and the target power. The deviation value is then added to the target power and sent to the PCS. Power correction is completed within 5ms, reducing adjustment errors and improving the adjustment accuracy index K3.

[0082] One implementation method for an energy storage power station:

[0083] This invention discloses an energy storage power station, comprising an energy storage coordination control device (PMS) and an energy storage converter (PCS). The PMS is used to: receive frequency regulation commands differentiated from power commands issued by the dispatch master station, and key operational information transmitted by the PCS; then update the power allocation strategy in conjunction with the frequency regulation commands; and, according to the power allocation strategy, distribute the target value and frequency regulation command to each controllable PCS. The PCS is used to: immediately trigger the frequency regulation mode upon receiving the frequency regulation command, release the regulation rate limit, and respond to the frequency regulation command, thereby improving the response time index K2 in the frequency regulation performance indicators.

[0084] Among them, the power allocation strategy of method 1 or method 2 is adopted to improve the regulation rate index K1 in the frequency modulation performance index.

[0085] Method 1: The power allocated to each controllable PCS is related to the maximum allowable adjustable power of each controllable PCS. The greater the maximum allowable adjustable power of each PCS, the greater the power allocated to it.

[0086] Method 2: Power allocation to the i-th PCS for:

[0087]

[0088] In the formula, The maximum allowable regulating power of the i-th PCS; n is the total number of PCS; Let be the adjustment weight of the i-th PCS, and the larger the adjustable SOC of the PCS, the better. The larger.

[0089] Furthermore, PMS is also used to: calculate the real-time loss of the energy storage power station based on the deviation between the real-time power at the grid connection point and the target power, and to add the loss to the target power and send it to each controllable PCS to achieve power correction, thereby improving the regulation accuracy index in the frequency regulation performance index.

[0090] In summary, this invention reconstructs the communication architecture of the energy storage power station using the GOOSE communication protocol, optimizes the power allocation strategy based on real-time PCS status information, and tracks and compensates for energy storage station losses in real time based on grid connection point data. This simultaneously optimizes three key performance indicators of the energy storage power station during frequency regulation services: regulation rate, response delay, and regulation accuracy, significantly improving the K-value of the energy storage power station. Key innovations are as follows:

[0091] 1) GOOSE priority communication architecture: By dividing the command priority and isolating it from the data network-GOOSE network switch, the transmission delay of frequency modulation command is ensured to be ≤20ms, which directly improves the response time index K2;

[0092] 2) Status-command coordination optimization: Dynamic power allocation based on real-time feedback of module status avoids the "weakest link" effect, and the adjustment rate index K1 is increased to more than 4.5 times the regional standard rate;

[0093] 3) Rapid disturbance compensation mechanism: Utilizing GOOSE's high-speed data interaction, power correction for grid disturbances is achieved within 5ms, with adjustment accuracy index K3 error ≤1%.

Claims

1. A method for optimizing the frequency regulation performance of an energy storage power station, characterized in that, The method includes: The power commands issued by the dispatch master station are distinguished into frequency regulation commands, and then sent to the energy storage coordination control device (PMS). The PMS receives key operational information from the PCS (Power Storage Converter), then updates the power allocation strategy in conjunction with the frequency regulation command, and sends the target value and frequency regulation command to each controllable PCS according to the power allocation strategy. Upon receiving a frequency modulation command, each controllable PCS immediately triggers the frequency modulation mode, removes the adjustment rate limit, and responds to the frequency modulation command to improve the response time indicator in the frequency modulation performance metrics.

2. The method for optimizing the frequency regulation performance of an energy storage power station according to claim 1, characterized in that, The following power allocation strategy is adopted to improve the regulation rate index in the frequency modulation performance indicators: The power allocation to each PCS is determined based on the SOC and maximum allowable charge / discharge power transmitted by the PCS: In the formula, The power allocation to the i-th PCS is the percentage of power that can be controlled, where n is the total number of controllable PCS. During charging... for , The maximum allowable charging power of the i-th PCS during discharge. for , The maximum allowable discharge power of the i-th PCS; The adjustment weight for the i-th PCS during charging. for , During discharge for , , For the current SOC of the i-th PCS, , Let S and SOC be the maximum and minimum values ​​for the i-th PCS, respectively.

3. The method for optimizing the frequency regulation performance of an energy storage power station according to claim 1, characterized in that, The real-time loss of the energy storage power station is calculated based on the deviation between the real-time power at the grid connection point and the target power. This loss is then added to the target power and sent to each controllable PCS to achieve power correction, thereby improving the regulation accuracy index in the frequency regulation performance indicators.

4. The method for optimizing the frequency regulation performance index of an energy storage power station according to any one of claims 1 to 3, characterized in that, The PMS and PCS exchange data via a GOOSE switch using the GOOSE protocol.

5. The method for optimizing the frequency regulation performance of an energy storage power station according to any one of claims 1 to 3, characterized in that, The command messages sent by the PMS to the PCS are divided into different priorities according to their urgency. The frequency modulation command has a higher priority than the mode switching command, and the mode switching command has a higher priority than the parameter configuration command.

6. The method for optimizing the frequency regulation performance index of an energy storage power station according to any one of claims 1 to 3, characterized in that, Power commands are differentiated from active power planning curves and sent to the Energy Management System (EMS). The EMS collects full information from the Power Planning System (PCS) and the Energy Management System (BMS), removes PCS information with anomalies, and sends adjustable PCS information to the Power Management System (PMS).

7. An energy storage power station, comprising an energy storage coordination control device (PMS) and an energy storage converter (PCS), characterized in that, The PMS is used to: receive frequency modulation instructions distinguished from power instructions from the scheduling master station, and key operating status information sent by the PCS, and then update the power allocation strategy in combination with the frequency modulation instructions, and send the target value and frequency modulation instructions of each controllable PCS to each controllable PCS according to the power allocation strategy. PCS is used to: immediately trigger frequency modulation mode upon receiving a frequency modulation command, release the adjustment rate limit, and respond to the frequency modulation command, thereby improving the response time indicator in the frequency modulation performance metrics.

8. A frequency regulation performance optimization system for an energy storage power station, comprising a dispatch master station and an energy storage converter PCS, characterized in that, It also includes a power storage coordination control system (PMS); The dispatch master station is used to: distinguish the issued power commands from the frequency modulation commands and send them to the PMS, and receive the frequency modulation execution status; The PMS is used to: receive frequency modulation instructions distinguished from power instructions from the scheduling master station, and key operating status information sent by the PCS, and then update the power allocation strategy in combination with the frequency modulation instructions, and send the target value and frequency modulation instructions of each controllable PCS to each controllable PCS according to the power allocation strategy. PCS is used to: immediately trigger frequency modulation mode upon receiving a frequency modulation command, release the adjustment rate limit, and respond to the frequency modulation command, thereby improving the response time indicator in the frequency modulation performance metrics.

9. The frequency regulation performance optimization system for energy storage power stations according to claim 8, characterized in that, The following power allocation strategy is adopted to improve the regulation rate index in the frequency modulation performance indicators: The power allocation to each PCS is determined based on the SOC and maximum allowable charge / discharge power transmitted by the PCS: In the formula, The power allocation to the i-th PCS is the percentage of power that can be controlled, where n is the total number of controllable PCS. During charging... for , The maximum allowable charging power of the i-th PCS during discharge. for , The maximum allowable discharge power of the i-th PCS; The adjustment weight for the i-th PCS during charging. for , During discharge for , , For the current SOC of the i-th PCS, , Let S and SOC be the maximum and minimum values ​​for the i-th PCS, respectively.

10. The frequency regulation performance optimization system for energy storage power stations according to claim 8, characterized in that, PMS is also used to: calculate the real-time loss of the energy storage power station based on the deviation between the real-time power at the grid connection point and the target power, and add the loss to the target power and send it to each controllable PCS to achieve power correction, thereby improving the regulation accuracy index in the frequency regulation performance index.

Citation Information

Patent Citations

  • Performance evaluation method and system of energy storage power station in frequency modulation application scene

    CN111507565A