Material receiving table of steel pipe cold-drawing machine

Through the design of the adjustable receiving table structure and the use of cushion pads, the existing receiving table's insufficiency in receiving steel pipes of different lengths and the problems of steel pipe wear are solved, and the applicability of the receiving table and the quality of the steel pipes are improved.

CN221754345UActive Publication Date: 2024-09-24LIAOCHENG GUANHUI STEEL PIPE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420106445.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-16
Publication Date
2024-09-24
Estimated Expiration
2034-01-16

AI Technical Summary

Technical Problem

The existing material receiving table is difficult to adapt to the material receiving of steel pipes of different lengths, and the steel pipes are easily worn due to collision when they fall.

Method used

A material receiving platform structure including a first material receiving rack, a first cross bar, a second material receiving rack, a second cross bar and a sliding bar is designed. Through the cooperation of sliding and threaded columns, the spacing between the material receiving platforms is realized. Adjust and install buffer pads and extrusion blocks on the surface of the material receiving frame to avoid wear of the steel pipe.

Benefits of technology

It realizes the splicing of steel pipes of different lengths, improves the practicality of the splicing table, and protects the integrity of the steel pipe surface through the design of buffer pads and extrusion blocks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221754345U
    Figure CN221754345U
Patent Text Reader

Abstract

The utility model discloses a material receiving table of a steel pipe cold-drawing machine, which relates to the technical field of material receiving tables and comprises a first material receiving frame, a first cross rod, a second material receiving frame, a second cross rod and a sliding rod, the first cross rod is welded at the top end of the first material receiving frame, and the second material receiving frame is arranged on the outer side of the first material receiving frame. A second transverse rod is welded to the top end of the second material receiving frame. According to the material receiving table of the steel pipe cold-drawing machine, when a second material receiving frame moves, a second transverse rod can be driven to move, when the second transverse rod moves, a sliding rod can be driven to move, when the sliding rod moves, the sliding rod can slide with a first transverse rod, when the sliding rod slides, a limiting block can be driven to move, and when a threaded column rotates, a movable block can be driven to slide in a threaded mode; and when the steel pipes fall down, the steel pipes can collide with the buffering cushions, the surfaces of the steel pipes can be prevented from being abraded due to collision through the buffering cushions, and therefore the quality of the steel pipes is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of material receiving platforms, in particular to a material receiving platform for a steel pipe cold drawing machine. Background Art

[0002] The cold drawing machine is mainly used for drawing ferrous and non-ferrous metal bars at room temperature and for secondary processing of steel pipes after hot rolling and extrusion. After the steel pipe processing is completed, the steel pipe can be unloaded to the receiving table through the unloading device. The existing receiving table still has certain defects when in use.

[0003] In the prior art, the receiving table is placed outside the unloading device of the cold drawing machine. The receiving table can accommodate a large number of steel pipes. Usually, the overall structure of the receiving table is relatively simple, and two sets of receiving tables are connected by a cross bar, so that the distance between the two sets of receiving tables is fixed. At the same time, only steel pipes of corresponding lengths can be received, and the practicality is poor. Utility Model Content

[0004] The utility model aims to provide a material receiving platform for a steel tube cold drawing machine, so as to solve the problem that the material receiving platforms currently on the market are difficult to receive steel tubes of different lengths, as mentioned in the above background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a steel pipe cold drawing machine receiving platform, comprising: a first receiving frame, a first cross bar, a second receiving frame, a second cross bar and a sliding bar, the first receiving frame is welded with the first cross bar at the top end, the second receiving frame is arranged on the outside of the first receiving frame, the second cross bar is welded with the top end of the second receiving frame, the sliding bar is welded to the end of the second cross bar, a clamping groove is provided inside the sliding bar, a limiting block is welded on the outside of the end of the sliding bar, a limiting groove is provided inside the first cross bar, a mounting seat is welded on the top of the first cross bar, a threaded column is connected to the inside of the mounting seat through a bearing, a moving block is threadedly connected to the outside of the threaded column, and a clamping rod is welded to the outside of the moving block.

[0006] Preferably, a sliding structure is formed between the clamping rod and the first cross bar, and a plug-in structure is formed between the clamping rod and the slide bar via a clamping groove.

[0007] Preferably, the slots are distributed at equal intervals on the slide bar.

[0008] Preferably, the surfaces of the first material receiving frame and the second material receiving frame are both provided with docking grooves, and the inner walls of the docking grooves are bonded with extrusion blocks.

[0009] Preferably, a connecting plate is provided above the extrusion block, and a buffer pad is bonded to the surface of the connecting plate.

[0010] Preferably, a plug-in block is installed at the bottom of the connecting plate.

[0011] Compared with the prior art, the beneficial effects of the utility model are: the steel pipe cold drawing machine receiving platform, when the second receiving rack moves, it can drive the second cross bar to move, when the second cross bar moves, it can drive the sliding rod to move, when the sliding rod moves, it can slide with the first cross bar, when the sliding rod slides, it can drive the limit block to move, when the threaded column rotates, it can drive the moving block to slide threadedly, so that the buffer pad and the connecting plate are installed on the surface of the first receiving rack and the second receiving rack, when the steel pipe falls, the steel pipe will hit the buffer pad, and the buffer pad can prevent the steel pipe surface from being worn due to impact, thereby ensuring the quality of the steel pipe.

[0012] 1. The material receiving table can facilitate personnel to take the steel pipe in the later stage. Usually, the spacing of the material receiving table is fixed, which means that the material receiving table can only receive steel pipes of specified lengths. When the second material receiving rack moves, it can drive the second cross bar to move. When the second cross bar moves, it can drive the sliding bar to move. When the sliding bar moves, it can slide with the first cross bar. When the sliding bar slides, it can drive the limit block to move. When the threaded column rotates, it can drive the moving block to slide threadedly. When the moving block slides threadedly, it can drive the clamping rod to move. When the clamping rod moves, it can slide with the first cross bar. When the first cross bar slides to the specified position, its end can be inserted into the inside of the clamping slot, thereby limiting the position of the second cross bar, so that the distance between the second material receiving rack and the first material receiving rack can be adjusted. By adjusting the distance between the second material receiving rack and the first material receiving rack, the material receiving table can receive steel pipes of different lengths, thereby improving its practicability.

[0013] 2. The whole material of the receiving platform is usually iron, and the steel pipe will collide with the receiving platform during the falling process, which makes the surface of the steel pipe easy to wear. When the buffer pad moves, it can drive the connecting plate to move. When the bottom of the two sets of connecting plates move to the surface of the first receiving rack and the second receiving rack respectively, the plug-in block can be plugged into the inside of the second receiving rack through the docking groove. When the plug-in block is plugged into the inside of the docking groove, it will squeeze the surface of the extrusion block, so that the buffer pad and the connecting plate are installed on the surface of the first receiving rack and the second receiving rack. When the steel pipe falls, the steel pipe will hit the buffer pad. The buffer pad can prevent the surface of the steel pipe from being worn due to impact, thereby ensuring the quality of the steel pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the main structure of the utility model;

[0015] Figure 2 It is a right view structural schematic diagram of the utility model;

[0016] Figure 3 This is a schematic diagram of the front cutaway structure of the first crossbar of the utility model;

[0017] Figure 4 It is a schematic diagram of the right side cutaway structure of the cushion of the utility model;

[0018] Figure 5 It is a three-dimensional structural schematic diagram of the buffer pad of the utility model.

[0019] In the figure: 1. first material receiving rack; 2. first cross bar; 3. second material receiving rack; 4. second cross bar; 5. slide bar; 6. slot; 7. limit block; 8. limit slot; 9. mounting seat; 10. threaded column; 11. moving block; 12. clamping rod; 13. docking slot; 14. extrusion block; 15. connecting plate; 16. buffer pad; 17. plug-in block. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] See also Figure 1 , Figure 2 and Figure 3 It can be seen that the utility model provides a technical solution: a steel pipe cold drawing machine receiving platform, comprising: a first receiving frame 1, a first cross bar 2, a second receiving frame 3, a second cross bar 4 and a sliding bar 5;

[0022] A first cross bar 2 is welded to the top of the first material receiving frame 1, a second material receiving frame 3 is arranged outside the first material receiving frame 1, and a second cross bar 4 is welded to the top of the second material receiving frame 3;

[0023] The slide bar 5 is welded to the end of the second cross bar 4, a slot 6 is provided inside the slide bar 5, a limiting block 7 is welded on the outer side of the end of the slide bar 5, a limiting slot 8 is provided inside the first cross bar 2, a mounting seat 9 is welded on the top of the first cross bar 2, a threaded column 10 is connected to the inside of the mounting seat 9 through a bearing, a moving block 11 is threadedly connected to the outer side of the threaded column 10, a clamping rod 12 is welded to the outer side of the moving block 11, a sliding structure is formed between the clamping rod 12 and the first cross bar 2, a plug-in structure is formed between the clamping rod 12 and the slide bar 5 through the slot 6, and the slots 6 are evenly spaced on the slide bar 5.

[0024] During specific implementation, the material receiving table can facilitate personnel to take the steel pipes at a later stage. Usually, the spacing of the material receiving table is fixed, which means that the material receiving table can only receive steel pipes of a specified length. For this purpose, the second material receiving rack 3 can be pulled. When the second material receiving rack 3 moves, it can drive the second cross bar 4 to move. When the second cross bar 4 moves, it can drive the sliding bar 5 to move. When the sliding bar 5 moves, it can slide with the first cross bar 2. When the sliding bar 5 slides, it can drive the limit block 7 to move. When the limit block 7 moves, it can pass through the limit groove 8 is used for sliding. When the slide bar 5 slides to the specified position, the threaded column 10 can be rotated. When the threaded column 10 rotates, the moving block 11 can be driven to perform threaded sliding. When the moving block 11 threadedly slides, the clamping rod 12 can be driven to move. When the clamping rod 12 moves, it can slide with the first cross bar 2. When the first cross bar 2 slides to the specified position, its end can be inserted into the clamping slot 6, thereby limiting the position of the second cross bar 4, so that the distance between the second material receiving rack 3 and the first material receiving rack 1 can be adjusted.

[0025] See also Figure 1 , Figure 2 and Figure 3 It can be seen that by adjusting the distance between the second receiving rack 3 and the first receiving rack 1, the receiving platform can receive steel pipes of different lengths, thereby improving its practicality.

[0026] See also Figure 1 , Figure 2 , Figure 4 and Figure 5 It can be seen that the surfaces of the first material receiving rack 1 and the second material receiving rack 3 are both provided with a docking groove 13, the inner wall of the docking groove 13 is bonded with an extrusion block 14, a connecting plate 15 is arranged above the extrusion block 14, a buffer pad 16 is bonded to the surface of the connecting plate 15, a plug-in block 17 is installed at the bottom of the connecting plate 15, and two groups of plug-in blocks 17 are symmetrically arranged about the center of the connecting plate 15.

[0027] During specific implementation, the whole material of the receiving platform is usually iron, and the steel pipe will collide with the receiving platform during the falling process, which makes the surface of the steel pipe easily worn. For this reason, the buffer pad 16 can be pushed. When the buffer pad 16 moves, it can drive the connecting plate 15 to move. When the connecting plate 15 moves, it can drive the two groups of plug-in blocks 17 to move. When the bottoms of the two groups of connecting plates 15 move to the surfaces of the first receiving frame 1 and the second receiving frame 3 respectively, the plug-in block 17 can be plugged into the inside of the second receiving frame 3 through the docking groove 13, and the material of the extrusion block 14 is rubber. When the plug-in block 17 is plugged into the inside of the docking groove 13, the surface of the extrusion block 14 will be squeezed, so that the buffer pad 16 and the connecting plate 15 are installed on the surfaces of the first receiving frame 1 and the second receiving frame 3. When the steel pipe falls, the steel pipe will hit the buffer pad 16.

[0028] See also Figure 1 , Figure 2 , Figure 4 and Figure 5 It can be seen that the buffer pad 16 can prevent the surface of the steel pipe from being worn due to impact, thereby ensuring the quality of the steel pipe.

[0029] To sum up, when using the steel pipe cold drawing machine receiving platform, the first receiving rack 1 and the second receiving rack 3 are placed on the outside of the cold drawing machine unloading device. When the steel pipe is unloaded from the unloading device, the steel pipe can roll onto the first receiving rack 1 and the second receiving rack 3, so that the processed steel pipe can be received and stored. The receiving platform is a prior art and will not be described in detail here. When the first cross bar 2 slides to the specified position, its end can be inserted into the card slot 6, so as to limit the position of the second cross bar 4, so that the distance between the second receiving rack 3 and the first receiving rack 1 can be adjusted. The distance between the second receiving rack 3 and the first receiving rack 1 allows the receiving platform to receive steel pipes of different lengths, thereby improving its practicality. When the plug-in block 17 is plugged into the docking groove 13, it will squeeze the surface of the extrusion block 14, thereby installing the buffer pad 16 and the connecting plate 15 on the surfaces of the first receiving rack 1 and the second receiving rack 3. When the steel pipe falls, the steel pipe will hit the buffer pad 16. The buffer pad 16 can prevent the surface of the steel pipe from being worn due to the impact, thereby ensuring the quality of the steel pipe. The contents not described in detail in this description belong to the existing technology known to professional and technical personnel in this field.

[0030] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art may still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A material receiving platform for a steel pipe cold drawing machine, include: The first material receiving frame (1), the first cross bar (2), the second material receiving frame (3), the second cross bar (4) and the sliding bar (5) are characterized in that: A first cross bar (2) is welded to the top of the first material receiving frame (1), a second material receiving frame (3) is arranged on the outside of the first material receiving frame (1), and a second cross bar (4) is welded to the top of the second material receiving frame (3); A slide bar (5) is welded to the end of the second cross bar (4); a slot (6) is provided inside the slide bar (5); a limit block (7) is welded on the outer side of the end of the slide bar (5); a limit slot (8) is provided inside the first cross bar (2); a mounting seat (9) is welded on the top of the first cross bar (2); a threaded column (10) is connected to the inside of the mounting seat (9) through a bearing; a moving block (11) is threadedly connected to the outer side of the threaded column (10); and a clamping rod (12) is welded on the outer side of the moving block (11).

2. A steel pipe cold drawing machine receiving station according to claim 1, Features: A sliding structure is formed between the clamping rod (12) and the first crossbar (2), and a plug-in structure is formed between the clamping rod (12) and the slide bar (5) via a clamping groove (6).

3. A steel pipe cold drawing machine receiving station according to claim 2, Features: The clamping grooves (6) are distributed at equal intervals on the slide bar (5).

4. A steel pipe cold drawing machine receiving station according to claim 1, Features: The surfaces of the first material receiving frame (1) and the second material receiving frame (3) are both provided with docking grooves (13), and the inner walls of the docking grooves (13) are bonded with extrusion blocks (14).

5. A steel pipe cold drawing machine receiving station according to claim 4, Features: A connecting plate (15) is arranged above the extrusion block (14), and a buffer pad (16) is bonded to the surface of the connecting plate (15).

6. A steel pipe cold drawing machine receiving station according to claim 5, Features: A plug-in block (17) is installed at the bottom of the connecting plate (15).