Heat insulation well completion pipe string
By using the first and second backstop rings to connect the casing in the completion string, and setting up a vacuum chamber in the heat insulation layer, the problem of loose butt-jointed casings is solved, and the efficiency of the completion string is improved. Stability and insulation efficiency.
Patent Information
- Application Number
- CN202322778086.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-17
- Publication Date
- 2024-09-24
- Estimated Expiration
- 2033-10-17
AI Technical Summary
The steel casing of the existing completion string is not tightly connected and easily loosened, which affects the stability and heat insulation efficiency of the completion string.
A heat-insulated completion string is designed. The first and second resistance rings between casing one and two are connected in conflict with each other. An annular groove is added to increase friction and is set in the heat insulation layer. Vacuum chamber to enhance thermal insulation efficiency.
It effectively improves the tight fit and stability of the casing, avoids loosening, improves the heat insulation efficiency, and enhances the practicality and economic life of the completion string.
Smart Images

Figure CN221761837U
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of well completion, in particular to a heat-insulating well completion pipe string. Background Art
[0002] Well completion refers to the process of connecting the bottom of the well and the oil layer with a certain structure after the open hole well has reached the designed well depth. Well completion is the last important link in drilling work and the beginning of oil production engineering. It is closely related to the subsequent oil production, water injection and the development of the entire oil and gas field. The quality of oil well completion directly affects the production capacity and economic life of the oil well, and even affects whether the entire oil field can be reasonably developed. The completion string needs to use a large drill bit to drill a section of the wellbore, then put the steel casing into the well and cement it with cement, and then use a smaller drill bit to drill on the basis of the first wellbore, and then put another casing in this wellbore. At present, the front and rear casings are not tightly connected, and the subsequent casings are prone to loosening after cementing, which affects the normal use of the completion string. Utility Model Content
[0003] 1. Technical issues to be solved
[0004] In view of the deficiencies of the prior art, the utility model provides a heat-insulating completion string, which solves the problem that a plurality of steel casings of the completion string entering the well are not tightly connected and are loose.
[0005] (II) Technical solution
[0006] In order to achieve the above-mentioned purpose, the utility model specifically adopts the following technical solutions:
[0007] An insulating completion string comprises a completion body and a string body arranged in the completion body, wherein the string body comprises casing one, casing two and an oil layer casing arranged on casing two, the outer sliding sleeve of casing two is provided with a first butt ring, and is fixedly connected with a second butt ring, the first butt ring and the second butt ring are mutually butted and connected, the first butt ring is fixedly connected to the inner wall of the first end of casing one, the second butt ring is fixedly connected to the outer wall of the second end of casing, annular grooves distributed in a linear array are provided on the outer side of casing two, the string body is arranged on the inner side of the completion body, and a cement layer is filled between the string body and the completion body.
[0008] Furthermore, the casing 1 includes an outer tube, an inner tube and a heat insulation layer, the heat insulation layer is arranged between the outer tube and the inner tube, and vacuum chambers distributed in a circumferential array are arranged in the heat insulation layer.
[0009] Furthermore, an upper packer and a lower packer are provided in the completion body, and the upper packer and the lower packer are respectively sleeved on the outside of the first casing and the second casing.
[0010] Furthermore, a tubing rod is arranged in the tubing body, a tubing hanger is arranged in the casing, the tubing hanger is arranged at the end of the tubing rod, the upper packer and the lower packer are both sleeved on the outside of the tubing rod, and a seating joint and a formation isolation valve are arranged on the tubing rod.
[0011] (III) Beneficial effects
[0012] Compared with the prior art, the utility model provides a thermal insulation completion string, which has the following beneficial effects:
[0013] 1. The utility model provides a first butt ring and a second butt ring in the completion string, and utilizes the first butt ring and the second butt ring to contact and squeeze each other, so that the first casing and the second casing are closely matched, thereby effectively improving the practicality of the completion string, and an annular groove is provided on the second casing, and the annular groove is utilized to increase the friction with the cement layer, so as to prevent the second casing from loosening, thereby effectively improving the stability of the completion string.
[0014] 2. The utility model provides a thermal insulation layer in the completion string and a vacuum chamber in the thermal insulation layer, utilizes the thermal insulation layer to increase the thermal insulation efficiency of the casing 1, and utilizes the vacuum chamber to eliminate or reduce heat transfer in the casing 1, thereby effectively improving the thermal insulation efficiency of the completion string. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a cross-sectional stereoscopic schematic diagram of the utility model as a whole;
[0016] Figure 2 It is a schematic diagram of the cross-sectional structure of the utility model as a whole;
[0017] Figure 3 It is a three-dimensional schematic diagram of the matching of the sleeve 1 and the sleeve 2 of the utility model;
[0018] Figure 4 It is a schematic diagram of the cross-sectional structure of a sleeve 1 of the utility model.
[0019] In the figure: 1. completion body; 2. tubing body; 3. casing one; 301. outer pipe; 302. inner pipe; 303. insulation layer; 304. vacuum chamber; 4. casing two; 5. cement layer; 6. oil layer casing; 7. tubing hanger; 8. tubing rod; 9. upper packer; 10. landing joint; 11. lower packer; 12. formation isolation valve; 13. first retaining ring; 14. second retaining ring; 15. annular groove. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] Example
[0022] like Figures 1 to 4 As shown, an insulating completion string proposed in an embodiment of the utility model comprises a completion body 1 and a string body 2 arranged in the completion body 1, the string body 2 comprises a casing 1 3, a casing 2 4 and an oil layer casing 6 arranged on the casing 2 4, a first butt ring 13 is slidably sleeved on the outer side of the casing 2 4, and a second butt ring 14 is fixedly connected, the first butt ring 13 and the second butt ring 14 are mutually abutted and connected, the first butt ring 13 is fixedly connected to the inner wall of the end of the casing 1 3, the second butt ring 14 is fixedly connected to the outer wall of the end of the casing 2 4, an annular groove 15 distributed in a linear array is opened on the outer side of the casing 2 4, the string body 2 is arranged on the inner side of the completion body 1, and a cement layer 5 is filled between the string body 2 and the completion body 1;
[0023] A section of the wellbore is drilled out by a large drill bit, and then casing 1 3 is placed into the section of the wellbore and fixed with cement, and the cement poured between casing 1 3 and the inner wall of the section of the wellbore forms a cement layer 5; then a smaller drill bit is used to drill inside casing 1 3 and drill out a second section of the wellbore, and then casing 2 4 is placed into the second section of the wellbore along casing 1 3. At this time, casing 2 4 and casing 1 3 are connected to each other by a first retaining ring 13 and a second retaining ring 14; the cement injected into casing 2 4 forms a cement layer 5, and the cement layer 5 wraps the outside of casing 2 4 and the annular groove 15 on the outside of casing 2 4.
[0024] like Figure 4 As shown, in some embodiments, the casing 3 includes an outer tube 301, an inner tube 302 and a heat insulation layer 303, the heat insulation layer 303 is arranged between the outer tube 301 and the inner tube 302, and a vacuum chamber 304 distributed in a circumferential array is arranged in the heat insulation layer 303;
[0025] The interior of the vacuum chamber 304 is set to be vacuum; the heat insulation layer 303 is made of heat insulation material, and the heat insulation layer 303 is used to increase the heat insulation efficiency of the sleeve 3, and the vacuum chamber 304 is used to prevent or reduce the conduction of some heat.
[0026] like Figure 2 As shown, in some embodiments, an upper packer 9 and a lower packer 11 are disposed in the completion body 1, and the upper packer 9 and the lower packer 11 are respectively sleeved on the outside of the casing 1 3 and the casing 2 4.
[0027] like Figure 1 As shown, in some embodiments, a tubing rod 8 is provided in the tubing body 2, a tubing hanger 7 is provided in the casing 3, the tubing hanger 7 is provided at the end of the tubing rod 8, the upper packer 9 and the lower packer 11 are both sleeved on the outside of the tubing rod 8, and a seating joint 10 and a formation isolation valve 12 are provided on the tubing rod 8.
[0028] Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions described in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A thermal insulation completion string, comprising a completion body (1) and a string body (2) arranged in the completion body (1), characterized in that: The tubular column body (2) comprises a casing 1 (3), a casing 2 (4) and an oil layer casing (6) arranged on the casing 2 (4); a first butt ring (13) is provided on the outer sliding sleeve of the casing 2 (4), and a second butt ring (14) is fixedly connected; the first butt ring (13) and the second butt ring (14) are mutually abuttingly connected; the first butt ring (13) is fixedly connected to the inner wall of the end of the casing 1 (3); the second butt ring (14) is fixedly connected to the outer wall of the end of the casing 2 (4); the outer side of the casing 2 (4) is provided with annular grooves (15) distributed in a linear array; the tubular column body (2) is arranged on the inner side of the completion body (1); a cement layer (5) is filled between the tubular column body (2) and the completion body (1).
2. The thermal insulation completion string according to claim 1, characterized in that: The casing (3) comprises an outer tube (301), an inner tube (302) and a heat insulation layer (303), wherein the heat insulation layer (303) is arranged between the outer tube (301) and the inner tube (302), and vacuum chambers (304) distributed in a circumferential array are arranged in the heat insulation layer (303).
3. The thermal insulation completion string according to claim 1, characterized in that: An upper packer (9) and a lower packer (11) are arranged in the completion body (1), and the upper packer (9) and the lower packer (11) are respectively sleeved on the outside of the first casing (3) and the second casing (4).
4. The thermally insulated completion string according to claim 3, characterized in that: A tubing rod (8) is arranged in the tubing column body (2), a tubing hanger (7) is arranged in the casing (3), the tubing hanger (7) is arranged at the end of the tubing rod (8), the upper packer (9) and the lower packer (11) are both sleeved on the outside of the tubing rod (8), and a seat joint (10) and a formation isolation valve (12) are arranged on the tubing rod (8).