Dredging device for reservoir dam piezometric tube

By designing a combination device of pressure-resistant water pipes and desilting nozzles, the problem of blockage of the reservoir dam pressure pipes caused by siltation was solved, rapid and thorough cleaning was achieved, and the accuracy of seepage monitoring was ensured.

CN221790432UActive Publication Date: 2024-10-01临朐县水库运行维护中心
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420164763.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-23
Publication Date
2024-10-01
Estimated Expiration
2034-01-23

AI Technical Summary

Technical Problem

Since the pressure measuring tubes of reservoir dams have been buried in the water for a long time, the seepage holes are easily blocked by the accumulation of fine sand and other substances, making it difficult to clean and affecting the accuracy of seepage monitoring.

Method used

A dredging device for reservoir dam pressure pipes is designed, including a hard-structured pressure-resistant water pipe and a dredging nozzle. The nozzle is equipped with a water spray hole, a silt layer breaking stirring plate and a conical crushing drill bit. Through high-pressure water flow and a rotating nozzle Break up the sludge and use the siphon principle to discharge the sludge.

Benefits of technology

It achieves rapid and thorough cleaning inside the pressure measuring tube, reduces the difficulty of cleaning, and ensures the normal use of the pressure measuring tube and the accuracy of seepage monitoring.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221790432U_ABST
    Figure CN221790432U_ABST
Patent Text Reader

Abstract

The utility model discloses a reservoir dam piezometric tube desilting device which comprises a pressure-resistant water pipe, a booster pump and a water storage tank, the pressure-resistant water pipe is provided with a desilting nozzle and a water spraying hole, and the side portion of the desilting nozzle is further fixedly connected with at least one silt deposition layer crushing and stirring plate of a hard structure. A conical silt accumulation layer crushing drill bit is arranged at the end part of the desilting nozzle; a pressure-resistant water pipe extends into a pressure measuring pipe until a silt accumulation layer crushing drill bit makes contact with silt in the pipe, a booster water pump is started to convey high-pressure water into the pressure-resistant water pipe, the water with pressure can drive a desilting spray head to rotate while being sprayed out through a water spraying hole, and the silt is scattered and mixed with the water under the action of a silt accumulation layer crushing stirring plate; and then the pressure-resistant water pipe is taken out, sludge, fine sand and the like in the pressure measuring pipe are discharged by utilizing a hose under the action of siphoning, internal dredging of the pressure measuring pipe is realized, and the silt accumulation layer crushing drill bit is conveniently and quickly inserted into the silt accumulation layer in the pipe in a more labor-saving manner, so that the dredging efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of equipment for reservoir facility maintenance, in particular to a silt-clearing device for a reservoir dam pressure measuring pipe. Background Art

[0002] Seepage monitoring is required for reservoir dams, especially for earth-rock dams, which is a must-measure item. The specific method is to bury pressure measuring tubes in the dam body to implement the detection. Figure 5 The dam structure shown in FIG. 1 generally has four parts from top to bottom, namely, a grouting backfill section 51, an upper section of fine sand backfill 52, a gravel backfill section 53, and a lower section of fine sand backfill 54. The piezometer runs through the grouting backfill section 51, the upper section of fine sand backfill 52, and the gravel backfill section 53, and the bottom of the piezometer rests on the lower section of fine sand backfill 54. The piezometer includes a tube body 55 and a detachable tube cover 56. A seepage pipe section 57 is arranged at the bottom of the piezometer. A plurality of seepage holes 58 are arranged through the seepage pipe section 57 to infiltrate the seepage water generated by the dam body into the piezometer. An anti-filter geotextile 59 is coated on the outer wall of the seepage pipe section 57. The pores of the anti-filter geotextile 59 are 10-20% of the seepage holes 58 to prevent sediment from entering the pipe, so as to ensure the normal use of the piezometer. The piezometer is made of zinc steel metal, and its lower part is immersed in water all year round. The finer sediment in the water will penetrate the anti-filter geotextile 59 and enter the pipe body 55 through the seepage holes 58 along with the seepage water, and it is difficult to discharge, so it gradually settles at the bottom of the pipe body 55 to form a silt layer, which will block the seepage holes 58 on the seepage pipe section 57 over time, and needs to be cleaned in time to ensure the normal use of the piezometer. However, the piezometer is long and buried deep, which has the technical problem of difficult cleaning. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide a desilting device for a reservoir dam pressure measuring pipe which is easy to clean and thorough.

[0004] In order to solve the above technical problems, the technical solution of the utility model is: a dredging device for a reservoir dam pressure measuring pipe, comprising a pressure-resistant water pipe with a hard structure, one end of the pressure-resistant water pipe is connected to a booster water pump, the water inlet end of the booster water pump is arranged in a water tank, and a dredging nozzle is rotatably installed on the other end of the pressure-resistant water pipe, and the water spray holes set through the dredging nozzle are arranged on the side of the dredging nozzle, and at least one silt layer crushing stirring plate with a hard structure is also fixedly connected to the side of the dredging nozzle, and a conical silt layer crushing drill bit is provided at the end of the dredging nozzle.

[0005] As a preferred technical solution, the silt layer breaking and stirring plate is a straight plate extending vertically outwardly from the surface of the dredging nozzle, and two silt layer breaking and stirring plates are relatively arranged on the dredging nozzle.

[0006] As a preferred technical solution, the number of the water spray holes is two and they are arranged opposite to each other on both sides of the dredging nozzle, and the water spray holes and the silt layer breaking and stirring plates are arranged alternately at intervals.

[0007] As a preferred technical solution, the silt layer breaking and stirring plate is a spiral plate disposed on the surface of the silt removal nozzle.

[0008] As a preferred technical solution, the number of the water spray holes is two and they are arranged up and down on both sides of the dredging nozzle.

[0009] As a preferred technical solution, the diameter of the water spray hole is not less than 5 mm.

[0010] As an improvement to the above technical solution, the pressure of the booster water pump is not less than 2 kilograms.

[0011] Due to the adoption of the above technical scheme, the dredging device for the pressure measuring pipe of the reservoir dam comprises a pressure-resistant water pipe with a hard structure, one end of the pressure-resistant water pipe is connected to a booster water pump, the water inlet end of the booster water pump is arranged in a water storage tank, and a dredging nozzle is rotatably installed at the other end of the pressure-resistant water pipe, and the water spray holes provided through the dredging nozzle are arranged on the side of the dredging nozzle, and the side of the dredging nozzle is also fixedly connected with at least one silt layer breaking stirring plate with a hard structure, and the end of the silt layer breaking drill bit is provided with a conical shape; the utility model has the following beneficial effects Results: The pressure-resistant water pipe is extended into the pressure measuring tube until the silt-layer breaking drill bit contacts the silt in the tube, and the booster water pump is started to deliver high-pressure water to the pressure-resistant water pipe. The pressurized water is ejected through the water spray hole and drives the dredging nozzle to rotate. The silt is broken up and mixed with water under the action of the silt-layer breaking stirring plate. Then the pressure-resistant water pipe is taken out, and a hose is used to discharge the silt, fine sand, etc. in the pressure measuring tube with the help of siphon action, so as to realize internal dredging of the pressure measuring tube. The setting of the silt-layer breaking drill bit facilitates more labor-saving and rapid insertion into the silt layer in the tube, which helps to improve the dredging efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The following drawings are only intended to illustrate and explain the present invention, and do not limit the scope of the present invention.

[0013] Figure 1 It is a schematic diagram of the structure of an embodiment of the utility model;

[0014] Figure 2 It is an enlarged structural schematic diagram of the desilting nozzle and related structures of the embodiment of the utility model;

[0015] Figure 3 This is another enlarged structural schematic diagram of the desilting nozzle and related structures of the embodiment of the utility model;

[0016] Figure 4It is a schematic diagram of the use state of an embodiment of the utility model;

[0017] Figure 5 It is a schematic diagram of the use status of the reservoir dam pressure measuring tube;

[0018] In the figure: 1-pressure water pipe; 2-boosting water pump; 3-water storage tank; 4-dredging nozzle; 5-water spray hole; 6-silt layer breaking stirring plate; 7-silt layer breaking drill bit; 51-grouting backfill section; 52-fine sand backfill upper section; 53-pebble backfill section; 54-fine sand backfill lower section; 55-pipe body; 56-pipe cover; 57-seepage pipe section; 58-seepage hole; 59-anti-filter geotextile. DETAILED DESCRIPTION

[0019] The present invention is further described below in conjunction with the accompanying drawings and examples. In the following detailed description, only certain exemplary embodiments of the present invention are described by way of illustration. Needless to say, those skilled in the art will recognize that the described embodiments may be modified in various ways without departing from the spirit and scope of the present invention. Therefore, the drawings and descriptions are illustrative in nature and are not intended to limit the scope of protection of the claims.

[0020] like Figure 1 , Figure 2 and Figure 4 As shown, the desilting device for the piezometric pipe of the reservoir dam is used to clean the siltation layer in the piezometric pipe buried on the reservoir dam, so as to realize the operation and maintenance of the piezometric pipe and ensure that the seepage monitoring of the reservoir dam can be completed through the piezometric pipe. This embodiment includes a pressure-resistant water pipe 1 with a hard structure, one end of the pressure-resistant water pipe 1 is connected to a booster water pump 2, the water inlet end of the booster water pump 2 is arranged in a water storage tank 3, and the other end of the pressure-resistant water pipe 1 is rotatably mounted with a desilting nozzle 4, and the water spray hole 5 provided through the desilting nozzle 4 is arranged on the side of the desilting nozzle 4. The pressure-resistant water pipe 1 has a certain strength and is set in a straight pipe state. The pressure-resistant water pipe 1 is connected to the water outlet of the booster water pump 2 through a water delivery pipeline. Through the cooperation of the booster water pump 2, the water storage tank 3 and the pressure-resistant water pipe 1, the desilting nozzle 4 is provided with clean water with a certain pressure to flush and clean the siltation layer in the piezometric pipe. The desilting nozzle 4 is a rotary nozzle used for irrigation in the fields of greening and planting, which is well known to ordinary technicians in this technical field and will not be described in detail here.

[0021] The side of the desilting nozzle 4 is also fixedly connected with at least one hard structured silt layer breaking stirring plate 6, which can rotate with the desilting nozzle 4, stirring and breaking the silt layer during the rotation process, so that it gradually mixes with the supplied clean water to form a muddy state, so as to facilitate suction. Figure 2As shown, the silt layer breaking and stirring plate 6 is a straight plate extending vertically outward from the surface of the silt removal nozzle 4, and two silt layer breaking and stirring plates 6 are arranged opposite to each other on the silt removal nozzle 4. Two water spray holes 5 are arranged opposite to each other on both sides of the silt removal nozzle 4, and the water spray holes 5 and the silt layer breaking and stirring plates 6 are arranged alternately at intervals, so that the silt removal nozzle 4 is evenly stressed and rotates smoothly.

[0022] like Figure 3 As shown, the silt layer breaking stirring plate 6 can also be a spiral plate arranged on the surface of the silt removal nozzle 4, and the water spray holes 5 are set to two and arranged up and down on both sides of the silt removal nozzle 4, which can also achieve the purpose of the silt removal nozzle 4 and the silt layer breaking stirring plate 6 rotating synchronously to loosen the silt layer. The diameter of the water spray hole 5 of this embodiment is not less than 5mm, and the pressure of the booster water pump 2 is not less than 2 kilograms, preferably in the range of 2-8 kilograms, which can not only ensure the water output and water output force of the silt removal nozzle 4, realize the flushing of the pressure measuring tube, but also reduce the power of the booster water pump 2.

[0023] A conical siltation layer breaking drill bit 7 is provided at the end of the silt removal nozzle 4, so that the siltation layer is easily broken when the silt removal nozzle 4 contacts the siltation layer, thereby facilitating rapid breaking of the siltation layer.

[0024] The desilting process of this embodiment is as follows:

[0025] The pressure-resistant water pipe 1 is extended into the pressure measuring tube until the silt layer breaking drill bit 7 contacts the silt layer in the tube, and the booster pump 2 is started to deliver high-pressure water to the pressure-resistant water pipe 1. The pressurized water is ejected through the water spray hole 5 and drives the dredging nozzle 4 to rotate. The silt layer breaking stirring plate 6 will rotate synchronously to break up the silt and mix it with water. During this period, the pressure-resistant water pipe 1 can be pumped up and down so that the silt layer breaking drill bit 7 can be smoothly inserted into the silt layer to prevent the dredging nozzle 4 from being blocked due to excessive resistance. In addition, the silt layer breaking stirring plate 6 is used to stir for a period of time and then taken out, and inserted into the broken silt layer with the help of a hose, and the mixed liquid of the broken silt and water is sucked out by the siphon principle. The above process can be repeated several times depending on the turbidity of the sucked out mixed liquid, until the silt layer in the pressure measuring tube is basically cleaned up as judged by the turbidity of the discharged mixed liquid. The operation is convenient and the cleaning is thorough.

[0026] The description of the present invention is given for the purpose of illustration and description, and is not intended to be exhaustive or to limit the present invention to the disclosed form. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments are selected and described to better illustrate the principles and practical applications of the present invention and to enable those of ordinary skill in the art to understand the present invention and design various embodiments with various modifications suitable for specific uses.

Claims

1. A desilting device for a reservoir dam pressure measuring pipe, comprising a pressure-resistant water pipe with a hard structure, characterized in that: One end of the pressure-resistant water pipe is connected to a booster water pump, and the water inlet end of the booster water pump is arranged in a water tank. A dredging nozzle is rotatably installed on the other end of the pressure-resistant water pipe. The water spray holes set through the dredging nozzle are arranged on the side of the dredging nozzle. The side of the dredging nozzle is also fixedly connected to at least one hard-structured silt layer crushing stirring plate, and the end of the dredging nozzle is provided with a conical silt layer crushing drill bit.

2. The desilting device for a reservoir dam pressure measuring tube according to claim 1, characterized in that: The silt layer breaking and stirring plate is a straight plate extending vertically outwardly from the surface of the silt removal nozzle, and two silt layer breaking and stirring plates are arranged opposite to each other on the silt removal nozzle.

3. The desilting device for a reservoir dam pressure measuring tube according to claim 2, characterized in that: The water spray holes are provided in two and are arranged opposite to each other on both sides of the dredging nozzle, and the water spray holes and the silt layer breaking and stirring plates are arranged alternately at intervals.

4. The desilting device for a reservoir dam pressure measuring tube according to claim 1, characterized in that: The silt layer breaking and stirring plate is a spiral plate arranged on the surface of the silt removal nozzle.

5. The desilting device for a reservoir dam pressure measuring tube according to claim 4, characterized in that: The water spray holes are provided in two and are arranged up and down on both sides of the dredging nozzle.

6. The desilting device for a reservoir dam pressure measuring tube according to claim 3 or 4, characterized in that: The diameter of the water spray hole is not less than 5 mm.

7. The desilting device for a reservoir dam pressure measuring tube according to claim 1, characterized in that: The pressure of the booster water pump is not less than 2 kg.