Building steel calendaring equipment
By introducing a cleaning mechanism and lubrication components into the steel rolling equipment, the problem of impurities on the steel surface affecting the rolling accuracy is solved, efficient cleaning and lubrication is achieved, and product accuracy and operational safety are improved.
Patent Information
- Application Number
- CN202420117919.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-18
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-01-18
AI Technical Summary
Existing steel rolling equipment lacks cleaning of the steel surface before rolling, resulting in oil, rust, dust and other impurities being pressed into the steel surface, reducing the appearance quality of the product and affecting the stability and dimensional and shape accuracy of the rolling process.
A construction steel rolling processing equipment is designed, including a cleaning mechanism and a lubrication component. The surface of the steel plate is efficiently cleaned through a cleaning roller, and the rolling roller is conveniently lubricated through a wiping pad to avoid the safety hazards of manual lubrication.
It improves the product accuracy after steel rolling, reduces labor intensity, and ensures the stability and safety of the rolling process.
Smart Images

Figure CN221790571U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel rolling, in particular to a construction steel rolling processing device. Background Art
[0002] With the development of economy and the continuous improvement of people's living standards, my country's construction industry has developed very rapidly. Various high-rise buildings have sprung up. The application of steel is crucial. It is related to the strength and safety of a building. Steel needs to be rolled during processing, and cold rolling of steel is one of the key steps.
[0003] Existing calendering equipment lacks a structure to clean the steel surface before calendering. Impurities such as oil, rust, dust, etc. that may remain on the steel may be pressed into the steel surface during the subsequent calendering process, which not only reduces the appearance quality of the product, but also may cause increased friction during the calendering process, thereby affecting the stability of the calendering force, and further affecting the dimensional accuracy and shape accuracy of the product. Utility Model Content
[0004] The utility model aims to solve one of the technical problems in the related art at least to a certain extent.
[0005] Therefore, the purpose of the utility model is to provide a construction steel rolling processing equipment, which can clean the surface of the steel before rolling, thereby improving the size accuracy and shape accuracy of the product and reducing the labor intensity.
[0006] To achieve the above-mentioned purpose, the utility model proposes a construction steel rolling processing equipment, including a support table, an operating bin, a plurality of conveying rollers, a cleaning mechanism, a lubrication assembly and a rolling roller, wherein the operating bin is installed on the support table, and the plurality of conveying rollers are rotatably connected to the inner wall of the operating bin in parallel and equidistantly, and the cleaning mechanism includes a first support frame, two first driving devices and a cleaning assembly, wherein the first support frame is installed on the operating bin, and the two first driving devices are respectively installed on the first support frame and the operating bin, and the cleaning assembly is installed at the output end of the first driving device, and the two rolling rollers are symmetrically rotatably connected to the inner wall of the operating bin, and the lubrication assembly is installed on the operating bin and away from one end of the first support frame, and the end of the lubrication assembly is connected to the outer wall of the rolling roller.
[0007] The construction steel calendering processing equipment of the utility model can drive the cleaning roller to rotate by starting the second driving device, so that the surface of the steel plate can be efficiently cleaned by the cleaning roller, thereby improving the accuracy of the product after later calendering. The outer wall of the calendering roller can be conveniently lubricated by the wiping pad, avoiding the safety hazards caused by manual lubrication and reducing labor intensity.
[0008] In addition, the construction steel rolling processing equipment proposed in the utility model may also have the following additional technical features:
[0009] Specifically, the cleaning assembly includes a mounting frame, a guide plate, a cleaning roller, a supporting side plate and a second driving device, wherein the outer wall of the mounting frame is fixedly connected to the output end of the first driving device, the guide plate is symmetrically slidably installed on the inner wall of the operating bin, the end of the mounting frame is fixedly connected to the outer wall of the guide plate, the cleaning roller is rotatably connected to the inner wall of the guide plate, the supporting side plate is slidably installed on the outer wall of the operating bin and fixedly connected to the end of the guide plate, the second driving device is installed on the supporting side plate, and the output end of the second driving device is fixedly connected to the end of the cleaning roller.
[0010] Specifically, the lubrication assembly includes a second support frame, two third drive devices, a mounting plate and a wiping pad, wherein the second support frame is mounted on the operating bin and away from one end of the first support frame, the two third drive devices are respectively mounted on the second support frame and the operating bin, one side of the mounting plate is fixedly connected to the output end of the third drive device, and the wiping pad is mounted on the other side of the mounting plate.
[0011] Specifically, the cleaning roller is located between two adjacent conveying rollers.
[0012] Specifically, the calendering roller is located between two adjacent conveying rollers.
[0013] Additional aspects and advantages of the present invention will be given in part in the following description and in part will become apparent from the following description or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0015] Figure 1 A schematic diagram of a construction steel rolling processing equipment according to an embodiment of the utility model;
[0016] Figure 2 This is a schematic diagram of the structure of a conveying roller according to an embodiment of the utility model;
[0017] Figure 3 This is a schematic diagram of the structure of a lubrication component according to an embodiment of the utility model;
[0018] Figure 4 The figure is a schematic diagram of the cleaning mechanism structure of an embodiment of the utility model.
[0019] As shown in the figure:
[0020] 1. Support table; 2. Operation chamber; 3. Conveyor roller;
[0021] 4. Cleaning mechanism; 41. First support frame; 42. First driving device; 43. Cleaning assembly; 431. Mounting frame; 432. Guide plate; 433. Cleaning roller; 434. Support side plate; 435. Second driving device;
[0022] 5. Lubrication assembly; 51. Second support frame; 52. Third driving device; 53. Mounting plate; 54. Wiping pad;
[0023] 6. Calendering roller. DETAILED DESCRIPTION
[0024] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention. On the contrary, the embodiments of the present invention include all changes, modifications, and equivalents that fall within the spirit and connotation of the appended claims.
[0025] The construction steel rolling processing equipment of the embodiment of the utility model is described below with reference to the accompanying drawings.
[0026] like Figure 1-Figure 4 As shown, the construction steel calendering processing equipment of the embodiment of the utility model may include a support platform 1, an operating chamber 2, a plurality of conveying rollers 3, a cleaning mechanism 4, a lubrication component 5 and a calendering roller 6.
[0027] The operation chamber 2 is installed on the support platform 1 , and a plurality of conveying rollers 3 are rotatably connected to the inner wall of the operation chamber 2 in parallel and at equal intervals.
[0028] It should be noted that the operation chamber 2 described in this embodiment is a U-shaped structure.
[0029] The cleaning mechanism 4 may include a first support frame 41 , two first driving devices 42 and a cleaning assembly 43 .
[0030] The first support frame 41 is installed on the operating chamber 2 , and the two first driving devices 42 are installed on the first support frame 41 and the operating chamber 2 respectively.
[0031] It should be noted that the end of the first support frame 41 described in this embodiment is fixedly connected to the upper end of the upper surface of the operating chamber 2, and the output ends of the two first drive devices 42 are both directed toward the conveying roller 3, and the first drive device 42 is a cylinder.
[0032] The sweeping assembly 43 is installed at the output end of the first driving device 42 .
[0033] It should be noted that the two ends of the cleaning assembly 43 described in this embodiment are slidably connected to the inner wall of the operating chamber 2, and the two cleaning assemblies 43 are respectively located on the upper and lower sides of the conveying roller 3, and the distance between the conveying rollers 3 can ensure the operation of the cleaning assembly 43.
[0034] The two calendering rollers 6 are symmetrically rotatably connected to the inner wall of the operating chamber 2 .
[0035] It should be noted that the midpoint of the distance between the outer walls of the two calendering rollers 6 described in this embodiment and the midpoint between the two cleaning assemblies 43 are located on the same plane, and a driving device for driving the calendering rollers 6 is installed on the outer wall of the operating chamber 2.
[0036] The lubrication assembly 5 is installed on the operation chamber 2 and is away from one end of the first support frame 41 . The end of the lubrication assembly 5 is connected to the outer wall of the calendering roller 6 .
[0037] It should be noted that the two groups of lubrication components 5 described in this embodiment are located on the upper and lower sides of the conveying roller 3 respectively.
[0038] Specifically, in the steel rolling processing production line, since the operating chamber 2 is installed on the support table 1, a plurality of conveying rollers 3 are connected to the inner wall of the operating chamber 2 by rotating side by side and equidistantly, and then the steel plate to be processed is placed on the conveying rollers 3 for transportation. During the transportation process, since the first support frame 41 is installed on the operating chamber 2, two first driving devices 42 are respectively installed on the first support frame 41 and the operating chamber 2, and the cleaning component 43 is installed at the output end of the first driving device 42, the two calendering rollers 6 are connected to the inner wall of the operating chamber 2 by rotating symmetrically, and then the cleaning component 43 is driven to contact the upper and lower sides of the steel plate by starting the first driving device 42, and then the surface of the steel plate is efficiently cleaned by the cleaning component 43, thereby improving the size accuracy and shape accuracy of the product after later calendering.
[0039] During the calendering process, the calendering roller is usually lubricated. Lubricating oil can significantly reduce the direct contact between metals, thereby reducing friction, which helps to reduce the energy required in the calendering process and the wear of the rollers. In the prior art, during the calendering process of steel, the lubrication of the calendering roller is mostly carried out manually with a handheld brush. This method is not only inefficient, but also difficult to ensure the uniform distribution of the lubricating oil, and cannot ensure the stability of the lubrication effect during continuous long-term production processes. Manual lubrication also has safety hazards and increases the labor intensity of operators. Therefore, during the calendering process, the lubrication component 5 is installed on the operating bin 2 and away from one end of the first support frame 41. The end of the lubrication component 5 is connected to the outer wall of the calendering roller 6, and then the outer wall of the calendering roller 6 can be lubricated in real time through the lubrication component 5, thereby avoiding the safety hazards caused by manual lubrication and reducing labor intensity.
[0040] In one embodiment of the present invention, Figure 1-Figure 4 As shown, the cleaning assembly 43 may include a mounting frame 431, a guide plate 432, a cleaning roller 433, a supporting side plate 434 and a second driving device 435, wherein the outer wall of the mounting frame 431 is fixedly connected to the output end of the first driving device 42, the guide plate 432 is symmetrically slidably installed on the inner wall of the operating bin 2, the end of the mounting frame 431 is fixedly connected to the outer wall of the guide plate 432, the cleaning roller 433 is rotatably connected to the inner wall of the guide plate 432, the supporting side plate 434 is slidably installed on the outer wall of the operating bin 2 and is fixedly connected to the end of the guide plate 432, the second driving device 435 is installed on the supporting side plate 434, and the output end of the second driving device 435 is fixedly connected to the end of the cleaning roller 433.
[0041] Furthermore, if Figure 1 As shown, the cleaning roller 433 is located between two adjacent conveying rollers 3 .
[0042] It should be noted that the outer wall of the operating chamber 2 described in this embodiment is provided with a guide groove for adjusting the position of the guide plate 432, thereby driving the cleaning roller 433 to effectively clean steel plates of different thicknesses, and the second driving device 435 is a driving motor.
[0043] Specifically, when the steel plate is conveyed on the conveying roller 3, the two first driving devices 42 are started to drive the position of the mounting frame 431 to move, and under the action of the guide plate 432, the movement of the mounting frame 431 is ensured to be more stable. At the same time, since the supporting side plate 434 is slidably installed on the outer wall of the operating bin 2 and is fixedly connected to the end of the guide plate 432, the second driving device 435 is installed on the supporting side plate 434, and the output end of the second driving device 435 is fixedly connected to the end of the cleaning roller 433, and then the cleaning roller 433 can be driven to rotate by starting the second driving device 435, thereby the surface of the steel plate can be efficiently cleaned by the cleaning roller 433, thereby improving the accuracy of the product after later rolling.
[0044] In one embodiment of the present invention, Figure 1-Figure 4 As shown, the lubrication assembly 5 may include a second support frame 51, two third drive devices 52, a mounting plate 53 and a wiping pad 54, wherein the second support frame 51 is mounted on the operating chamber 2 and away from one end of the first support frame 41, the two third drive devices 52 are respectively mounted on the second support frame 51 and the operating chamber 2, one side of the mounting plate 53 is fixedly connected to the output end of the third drive device 52, and the wiping pad 54 is mounted on the other side of the mounting plate 53.
[0045] Furthermore, if Figure 2 As shown, the calender roller 6 is located between two adjacent conveying rollers 3 .
[0046] It should be noted that an oil filling hole is installed on the surface of the mounting plate 53 described in this embodiment, and a sealing plug is installed at the opening of the oil filling hole.
[0047] Specifically, during the process of calendering the steel plate, since the two third driving devices 52 are respectively installed on the second support frame 51 and the operating chamber 2, one side of the mounting plate 53 is fixedly connected to the output end of the third driving device 52, and the wiping pad 54 is installed on the other side of the mounting plate 53. After the wiping pad 54 contacts the outer wall of the calendering roller 6, lubricating oil is injected into the interior of the mounting plate 53, and then the lubricating oil is evenly transported to the wiping pad 54 through multiple oil drain holes. The outer wall of the calendering roller 6 can be conveniently lubricated through the wiping pad 54, thereby avoiding the safety hazards caused by manual lubrication and reducing labor intensity.
[0048] In summary, the construction steel calendering processing equipment of the embodiment of the utility model can drive the cleaning roller to rotate by starting the second driving device, so that the surface of the steel plate can be efficiently cleaned by the cleaning roller, thereby improving the accuracy of the product after later calendering. The outer wall of the calendering roller can be conveniently lubricated by the wiping pad, avoiding the safety hazards caused by manual lubrication and reducing labor intensity.
[0049] In the description of this specification, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the utility model, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0050] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0051] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in this field can change, modify, replace and deform the above embodiments within the scope of the present invention.
Claims
1. A rolling processing equipment for building steel, It is characterized in that It includes a support platform, an operating chamber, a plurality of conveying rollers, a cleaning mechanism, a lubrication assembly and a calendering roller, wherein: The operation chamber is mounted on the support platform, and a plurality of conveying rollers are rotatably connected side by side and equidistantly to the inner wall of the operation chamber; The cleaning mechanism comprises a first support frame, two first driving devices and a cleaning assembly, wherein: The first support frame is installed on the operation compartment; The two first driving devices are respectively mounted on the first supporting frame and the operating compartment; The sweeping assembly is mounted at the output end of the first driving device; The two calendering rollers are symmetrically rotatably connected to the inner wall of the operating chamber; The lubrication assembly is installed on the operation chamber and is away from one end of the first support frame, and the end of the lubrication assembly is connected to the outer wall of the calendering roller.
2. The construction steel rolling processing equipment according to claim 1, It is characterized in that The sweeping assembly includes a mounting frame, a guide plate, a sweeping roller, a supporting side plate and a second driving device, wherein: The outer wall of the mounting frame is fixedly connected to the output end of the first driving device; The guide plate is symmetrically slidably mounted on the inner wall of the operating chamber, and the end of the mounting frame is fixedly connected to the outer wall of the guide plate; The cleaning roller is rotatably connected to the inner wall of the guide plate; The supporting side plate is slidably mounted on the outer wall of the operating compartment and is fixedly connected to the end of the guide plate; The second driving device is installed on the supporting side plate, and the output end of the second driving device is fixedly connected to the end of the cleaning roller.
3. The construction steel rolling processing equipment according to claim 1, It is characterized in that The lubrication assembly includes a second support frame, two third drive devices, a mounting plate and a wiping pad, wherein: The second support frame is installed on the operation compartment and is away from one end of the first support frame; The two third driving devices are respectively mounted on the second supporting frame and the operating compartment; One side of the mounting plate is fixedly connected to the output end of the third driving device, and the wiping pad is mounted on the other side of the mounting plate.
4. The construction steel rolling processing equipment according to claim 2, It is characterized in that The cleaning roller is located between two adjacent conveying rollers.
5. The construction steel rolling processing equipment according to claim 1, It is characterized in that The calendering roller is located between two adjacent conveying rollers.