Well cementation sand control pipe
Through the design of multi-layer sand control sleeves and pressure-holding elements, the problem of cement blocking the screen is solved, ensuring the flow of oil and gas and the fixation of sand on the well wall, and achieving a stable cementing effect.
Patent Information
- Application Number
- CN202420020748.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-04
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-01-04
AI Technical Summary
When the existing sand control pipe is cemented, the screen is easily blocked, causing the oil and gas in the oil layer to be unable to flow into the wellbore, and sand cementing cannot be effectively prevented.
A cementing sand control pipe is designed, which uses a multi-layer sand control sleeve and a pressure-holding element. Before cementing, the sand control sleeve is stretched by holding pressure until it resists the well wall, isolating the sand control net and wellbore liquid, and preventing cement from entering the screen. , and ensures tightness through the tapered structure and O-ring.
It effectively prevents cement from blocking the screen, ensures oil and gas circulation, enhances the support and fixation of sand on the well wall, avoids the eccentricity of the sand control pipe, and improves the cementing effect.
Smart Images

Figure CN221799760U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of petroleum exploitation, in particular to a cementing sand prevention pipe. Background Art
[0002] At present, all sand control pipes cannot be fixed with cement to prevent sand, because cement will block the holes of the screen inside the sand control pipe, and the oil and gas in the oil layer cannot flow into the wellbore. The usual practice now is to put a sand control pipe into the wellbore for sand control without cementing the well.
[0003] However, when the inventors implemented this device, they found that the current screen pipes have the following defects: although the ordinary screen pipes can effectively control the sand control pipes, since the screen is not exposed, cement enters the screen and blocks the screen during cement cementing, and the screen pipes cannot be used for cementing. Utility Model Content
[0004] Based on this, it is necessary to provide cementing sand control pipes to address the above-mentioned technical problems. Several layers of sand control sleeves and pressure-holding elements are used. Before cementing, the sand control sleeves are extended during pressure holding until they press against the well wall, isolating the sand control net from the liquid in the wellbore. This not only effectively supports and fixes the sand on the well wall, but also prevents the risk of cement entering the screen and clogging the screen during cementing.
[0005] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0006] Cementing sand control pipe, including:
[0007] A sand control pipe body, wherein a plurality of mounting grooves are respectively provided on the side walls of the sand control pipe body;
[0008] A sand control sleeve, which is detachably connected to the inner wall of the mounting groove and can be horizontally extended and retracted relative to the radial direction of the sand control pipe body;
[0009] A screen, which is fixedly connected to the innermost wall of the sand control sleeve and is used to filter oil and gas;
[0010] The pressure-holding element is embedded and installed on the inner wall of the sand control sleeve, and can drive the sand control sleeve to extend when performing the pressure-holding movement.
[0011] Furthermore, the number of the sand control sleeves and the mounting grooves are both multiple groups, and the number of the sand control sleeves and the mounting grooves in each group is four, and the four sand control sleeves are connected to the inner wall of the mounting groove in a ring shape.
[0012] Furthermore, the sand control sleeve comprises an outer sleeve, a middle sleeve and an inner sleeve, and the outer sleeve, the middle sleeve and the inner sleeve are slidably connected in sequence through a pressure-holding piston.
[0013] Furthermore, the middle sleeve includes at least two sleeve structures with diameters reduced in proportion.
[0014] Furthermore, the outer wall of the outer sleeve has a tapered structure, and when the outer sleeve is embedded in the installation groove, the tapered structure presses against the outer wall of the sand control pipe body, and the outer wall of the outer sleeve is also covered with an O-ring around the tapered structure;
[0015] A through hole is also provided on the side wall of the conical structure, a fixing bolt is inserted into the inner wall of the through hole, and one end of the fixing bolt passing through the through hole is threadedly connected to the sand control pipe body.
[0016] Furthermore, a clamping groove is provided on the inner side wall of the inner sleeve, and the pressure-holding element is embedded and installed in the inner side wall of the clamping groove.
[0017] Furthermore, the pressure-holding element is an O-type piston.
[0018] Furthermore, one end of the outer wall of the inner sleeve and the middle sleeve is provided with an outer sliding limit portion, the pressure-holding piston is embedded and installed in the middle of the outer sliding limit portion, and the outer walls of the inner sleeve (23) and the middle sleeve (22) are provided with barbs to prevent them from falling back.
[0019] Furthermore, the other ends of the outer walls of the inner sleeve and the middle sleeve are each provided with an inwardly contracted limiting portion, the inwardly contracted limiting portion having an outer convex portion and an inner convex portion, and the side walls of the outer convex portion and the inner convex portion have abutting and matching inclined surfaces.
[0020] Furthermore, a filter plate is provided on the inner wall of the inner sleeve, a plurality of filter holes are provided on the filter plate, and the screen is fixedly mounted on the inner wall of the inner sleeve and fits the filter plate.
[0021] Compared with the prior art, the utility model has the following beneficial effects:
[0022] The cementing sand control pipe provided by the utility model has a plurality of sand control sleeves arranged on the sand control pipe body, and a screen and a pressure-holding element are installed inside the innermost sleeve. The stacked arrangement of the sand control sleeves can extend along the radial direction of the sand control pipe body, and there is a pressure-holding element, which can be sealed. When the sand control pipe body is under pressure, the sand control sleeves extend outward under the action of the internal pressure. At the same time, the same sand control sleeves are installed around the sand control pipe body. When the internal pressure of the sand control pipe body is under pressure, all the sand control sleeves extend outward at the same time, so that the sand control pipe is in the middle of the oil well, avoiding eccentricity to the sand control pipe body, and having a good effect on the cementing of the oil well.
[0023] One end of the outer wall of the inner sleeve and the middle sleeve is provided with an outward sliding limit portion, and the other end of the outer wall of the inner sleeve and the middle sleeve is provided with an inward retraction limit portion. When moving to the limit portion position, it cannot continue to extend, thereby limiting the extension limit and contraction limit of the sand control sleeve. The outer side wall of the outer sleeve has a conical structure and an O-ring is also mounted around the conical structure. The conical structure is connected to the sand control pipe body by fixing bolts, which is convenient for installation, disassembly and maintenance. At the same time, the arrangement of the O-ring can play a sealing effect to ensure the normal pressure holding movement. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0025] Figure 2 This is a schematic diagram of the structure of the sand-proof sleeve of the utility model;
[0026] Figure 3 It is a schematic diagram of the cutaway structure of the utility model sand control sleeve in a three-dimensional elongated state;
[0027] Figure 4 For this utility model Figure 2 A schematic diagram of the second perspective structure;
[0028] Figure 5 It is a schematic diagram of the cross-sectional structure of the utility model.
[0029] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0030] 1. Sand control pipe body; 11. Installation slot;
[0031] 2. Sand-proof sleeve; 21. Outer sleeve; 211. Conical structure; 212. O-ring; 213. Through hole; 214. Fixing bolt; 22. Middle sleeve; 23. Inner sleeve; 231. Clamping groove; 232. Filter hole; 233. Filter plate; 24. Pressure-holding piston; 25. Outer sliding limiter; 26. Inner shrinkage limiter; 261. Outer convex part; 262. Inner convex part; 263. Inclined surface;
[0032] 3. Screen;
[0033] 4. Pressure-holding element. DETAILED DESCRIPTION
[0034] In order to enable those skilled in the art to better understand the solution of the utility model, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is only a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the utility model.
[0035] As in the background art, although the common screen pipe can realize effective control of the sand control pipe, since the screen is not present and is exposed outside, cement enters the screen and blocks the screen during cement cementing, and the screen cannot be used for cementing.
[0036] In order to solve this technical problem, the utility model provides a cementing sand prevention pipe, which is applied to underground sand prevention pipes.
[0037] Specifically, please refer to Figure 1-3 , cementing sand control pipe specifically includes:
[0038] The sand control pipe body 1 has a plurality of mounting grooves 11 respectively formed on the side walls of the sand control pipe body 1;
[0039] The sand control sleeve 2 is detachably connected to the inner wall of the mounting groove 11 and can be horizontally extended and retracted relative to the radial direction of the sand control tube body 1;
[0040] The screen 3 is fixedly connected to the innermost wall of the sand control sleeve 2 and is used for filtering oil and gas;
[0041] The pressure-holding element 4 is embedded and installed on the inner wall of the sand control sleeve 2, and can drive the sand control sleeve 2 to extend when performing the pressure-holding movement.
[0042] The cementing sand control pipe provided by the utility model has a screen 3 and a pressure-holding element 4 installed inside the innermost sand control sleeve 2. The stacked arrangement of the sand control sleeve 2 can extend along the radial direction of the sand control pipe body 1, and there is a pressure-holding element 4, which can be sealed. When the sand control pipe body 1 is internally pressured, the sand control sleeve 2 extends outward under the action of the internal pressure. At the same time, the same sand control sleeve 2 is installed around the sand control pipe body 1. When the internal pressure of the sand control pipe body 1 is held, all the sand control sleeves 2 extend outward at the same time, so that the sand control pipe is in the middle of the oil well, avoiding eccentricity to the sand control pipe body 1, and having a good effect on the cementing of the oil well.
[0043] In order to enable those skilled in the art to better understand the solution of the utility model, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the accompanying drawings.
[0044] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features and technical solutions in the embodiments may be combined with each other.
[0045] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0046] Please refer to Figure 1-5 The cementing sand control pipe comprises a sand control pipe body 1, a sand control sleeve 2, a screen 3 and a pressure holding element 4. A plurality of mounting grooves 11 are respectively provided on the side wall of the sand control pipe body 1, the sand control sleeve 2 is connected to the inner wall of the mounting groove 11, and the screen 3 and the pressure holding element 4 are fixedly connected to the innermost inner wall of the sand control sleeve 2.
[0047] Please refer to Figure 5 The number of sand-proof sleeves 2 and mounting grooves 11 is multiple, and the number of each group of sand-proof sleeves 2 and mounting grooves 11 is four. The four sand-proof sleeves 2 are connected to the inner wall of the mounting groove 11 in an annular shape. The sand-proof sleeves 2 include an outer sleeve 21, a middle sleeve 22 and an inner sleeve 23. The outer sleeve 21, the middle sleeve 22 and the inner sleeve 23 are slidably connected in sequence through a pressure-holding piston 24. The middle sleeve 22 includes at least two sleeve structures with diameters that are proportionally reduced. The inner wall of the inner sleeve 23 is provided with a clamping groove 231, and the pressure-holding element 4 is embedded and installed in the inner wall of the clamping groove 231. The pressure-holding element 4 is an O-type piston. Preferably, the middle sleeve 22 includes at least two sleeve structures with proportionally reduced diameters. In specific implementation, the number can be adjusted according to actual needs, such as three-section, four-section or five-section middle sleeves 22. Regardless of whether it is three-section, four-section or five-section middle sleeves 22, their structures are the same and the models are proportionally reduced.
[0048] The cementing sand control pipe provided in this embodiment has a beneficial effect. Multiple groups of sand control sleeves are used to support the sand control pipe body 1, so that the sand control pipe body 1 can have a multi-faceted support effect, so that the purpose of strengthening support can be achieved during the cementing operation. The outer sleeve 21, the middle sleeve 22 and the inner sleeve 23 are all sequentially sleeved and slidably connected through the pressure-holding piston 24. The advantage of this arrangement is that the sealing between the outer sleeve 21, the middle sleeve 22 and the inner sleeve 23 can be ensured, and at the same time, it can also play the role of a sliding medium to ensure that the outer sleeve 21, the middle sleeve 22 and the inner sleeve 2 3 can slide relatively and reduce the sliding friction. By setting the clamping groove 231, the pressure holding element 4 can be effectively clamped in the clamping groove 231. In the sealed state of the pressure holding element 4, when the sand control pipe body 1 performs the pressure holding operation, the entire sand control sleeve 2 can be pushed by pushing the pressure holding element 4, so that the outer sleeve 21, the middle sleeve 22 and the inner sleeve 23 move relative to each other and then unfold. When multiple groups of sand control sleeves 2 are unfolded at the same time and hit the well wall, the sand control pipe is in the middle position of the oil well, avoiding eccentricity of the sand control pipe body, and having a good effect on the cementing of the oil well.
[0049] The cementing sand control pipe provided in Example 1 is further optimized. Specifically, Figure 1 , Figure 3 , Figure 4 and Figure 5 As shown, the outer wall of the outer sleeve 21 has a tapered structure 211. When the outer sleeve 21 is embedded in the installation groove 11, the tapered structure 211 presses against the outer wall of the sand control pipe body 1. The outer wall of the outer sleeve 21 is also covered with an O-ring 212 around the tapered structure 211.
[0050] The side wall of the conical structure 211 is further provided with a through hole 213 , and a fixing bolt 214 is inserted into the inner side wall of the through hole 213 . One end of the fixing bolt 214 passing through the through hole 213 is threadedly connected to the sand control pipe body 1 .
[0051] Through the above-mentioned structural design, since the outer wall of the outer sleeve 21 is a conical structure 211, when the outer sleeve 21 is inserted into the inner wall of the installation groove 11, it can fit on the sand control pipe body 1, and at the same time, the fixing bolt 214 is inserted into the through hole 213 and then connected and fixed with the sand control pipe body 1, thereby achieving the fixation of the entire sand control sleeve 2. On the one hand, it can facilitate the early assembly, and on the other hand, it can also ensure the stability of the later fixation. Specifically, since an O-ring 212 is used for the connection position, the O-ring 212 can be squeezed during installation to cause it to deform and further fit on the gap at the connection, thereby ensuring the stability and sealing of the connection.
[0052] The cementing sand control pipe provided in Example 1 or 2 is further optimized, such as Figure 1-5As shown, one end of the outer wall of the inner sleeve 23 and the middle sleeve 22 is provided with an outer sliding limit portion 25, and the pressure-holding piston 24 is embedded and installed in the middle part of the outer sliding limit portion 25. The other end of the outer wall of the inner sleeve 23 and the middle sleeve 22 is provided with an inner retracting limit portion 26, and the inner retracting limit portion 26 has an outer convex portion 261 and an inner convex portion 262. The side walls of the outer convex portion 261 and the inner convex portion 262 have an abutting inclined surface 263. The outer walls of the inner sleeve (23) and the middle sleeve (22) are provided with barbs to prevent them from falling back.
[0053] Through the above-mentioned structural design, when the outer sleeve 21, the middle sleeve 22 and the inner sleeve 23 move relative to each other, for example, when extending, they can be limited to slide outward by the outer sliding limit part 25, so that the entire sand control sleeve 2 is in a restricted state when it moves to the extension limit. At the same time, when shrinking, they can be limited to slide inward by the inner shrinking limit part 26, so that the entire sand control sleeve 2 is in a restricted state when it moves to the shrinking limit. In addition, when in conflict, the contact area is increased due to the use of the inclined surface 263 to ensure the stability of the conflict.
[0054] The cementing sand control pipe provided in the above embodiments is further optimized, such as Figure 1 , Figure 3 and Figure 5 As shown, the inner wall of the inner sleeve 23 is also provided with a filter plate 233, and a plurality of filter holes 232 are opened on the filter plate 233. The screen 3 is fixedly installed on the inner wall of the inner sleeve 23 and fits the filter plate 233. The oil and gas can be filtered through the filter holes 232, so that the oil and gas can enter the screen 3 for filtration and then oil production.
[0055] The use process of the cementing sand control pipe provided by the utility model is as follows: the entire sand control pipe body is placed in the oil production well. Before entering the well, the sand control sleeve 2 is installed on the sand control pipe body 1 and is in a contracted state. Figure 3When entering the well and pumping liquid into the sand control sleeve 2 from the ground to hold the pressure, the sand control sleeve 2 is pushed outward like a piston until it hits the well wall, and then cement is poured. At this time, the cement flows around the sand control sleeve 2 without entering the sand control sleeve 2, thereby not blocking the sand control screen 3 in the sand control sleeve 2. Specifically, when installing the sand control sleeve 2, the fixing bolts 214 are inserted into the through holes 213 and then connected and fixed with the sand control pipe body 1, thereby fixing the entire sand control sleeve 2. When disassembling, only four fixing bolts 214 need to be removed to separate the sand control sleeve 2 and the sand control pipe body 1. 2 and the inner sleeve 23 when they move relative to each other, for example, when they are extended, the outer sliding limit portion 25 can be used to limit their outward sliding. Specifically, when extended, the outer sliding limit portion 25 will be limited by the inward shrinking limit portion 26 on the adjacent outer sleeve, so that the entire sand control sleeve 2 is in a restricted state when it moves to the extension limit. At the same time, when they are contracted, the inward sliding limit portion 26 can be used to limit their inward sliding. Thus, when the entire sand control sleeve 2 is in a restricted state when it moves to the contraction limit, specifically, when contracted, the inward shrinking limit portion 26 will be limited by the inward shrinking limit portion 26 on the adjacent outer sleeve, and when in conflict, the contact area is increased due to the use of the inclined surface 263 to ensure the stability of the conflict.
[0056] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0057] Obviously, the embodiments described above are only some embodiments of the utility model, rather than all embodiments. The preferred embodiments of the utility model are given in the accompanying drawings, but they do not limit the patent scope of the utility model. The utility model can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the utility model more thorough and comprehensive. Although the utility model is described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific implementation methods, or to replace some of the technical features therein with equivalents. Any equivalent structure made using the contents of the utility model specification and the accompanying drawings, directly or indirectly used in other related technical fields, is also within the scope of patent protection of the utility model.
Claims
1. Cementing sand control pipe, characterized in that: It includes: A sand control pipe body (1), wherein a plurality of mounting grooves (11) are respectively provided on the side walls of the sand control pipe body (1); A sand control sleeve (2) which is detachably connected to the inner wall of the mounting groove (11) and can be horizontally extended and retracted relative to the radial direction of the sand control pipe body (1); A screen (3) fixedly connected to the innermost wall of the sand control sleeve (2) for filtering oil and gas; The pressure-holding element (4) is embedded in the inner wall of the sand-control sleeve (2) and can drive the sand-control sleeve (2) to extend when performing a pressure-holding movement.
2. The cementing sand control pipe according to claim 1, characterized in that: The number of the sand-proof sleeves (2) and the installation grooves (11) is multiple, and the number of the sand-proof sleeves (2) and the installation grooves (11) in each group is four, and the four sand-proof sleeves (2) are connected to the inner wall of the installation groove (11) in a ring shape.
3. The cementing sand control pipe according to claim 1, characterized in that: The sand control sleeve (2) comprises an outer sleeve (21), a middle sleeve (22) and an inner sleeve (23), and the outer sleeve (21), the middle sleeve (22) and the inner sleeve (23) are slidably connected in sequence via a pressure-holding piston (24).
4. The cementing sand control pipe according to claim 3, characterized in that: The middle sleeve (22) comprises at least two sleeve structures with diameters reduced in proportion.
5. The cementing sand control pipe according to claim 4 or 3, characterized in that: The outer wall of the outer sleeve (21) has a conical structure (211). When the outer sleeve (21) is embedded in the installation groove (11), the conical structure (211) is pressed against the outer wall of the sand control pipe body (1). The outer wall of the outer sleeve (21) is also provided with an O-ring (212) surrounding the conical structure (211). The side wall of the conical structure (211) is also provided with a through hole (213), the inner wall of the through hole (213) is plugged with a fixing bolt (214), and one end of the fixing bolt (214) protruding from the through hole (213) is threadedly connected to the sand control pipe body (1).
6. The cementing sand control pipe according to claim 4 or 3, characterized in that: The inner side wall of the inner sleeve (23) is provided with a clamping groove (231), and the pressure-holding element (4) is embedded and installed in the inner side wall of the clamping groove (231).
7. The cementing sand control pipe according to claim 1, characterized in that: The pressure-holding element (4) is an O-type piston.
8. The cementing sand control pipe according to claim 3, characterized in that: An outer sliding limit portion (25) is provided at one end of the outer wall of the inner sleeve (23) and the middle sleeve (22), the pressure-holding piston (24) is embedded and installed in the middle of the outer sliding limit portion (25), and barbs are provided on the outer walls of the inner sleeve (23) and the middle sleeve (22).
9. The cementing sand control pipe according to claim 8, characterized in that: The other ends of the outer walls of the inner sleeve (23) and the middle sleeve (22) are both provided with an inwardly contracted limiting portion (26), the inwardly contracted limiting portion (26) having an outer convex portion (261) and an inner convex portion (262), the side walls of the outer convex portion (261) and the inner convex portion (262) having abuttingly matching inclined surfaces (263).
10. The cementing sand control pipe according to claim 3, characterized in that: The inner wall of the inner sleeve (23) is further provided with a filter plate (233), the filter plate (233) being provided with a plurality of filter holes (232), and the screen (3) is fixedly mounted on the inner wall of the inner sleeve (23) and in contact with the filter plate (233).