Tunnel centralized water outlet point drainage structure

By installing water pipes at centralized water outlets in tunnels and using soft permeable pipes to guide water flow to drainage ditches, the problem of difficult drainage at water outlet points in long underground tunnels has been solved, achieving timely drainage of water flow and improving the stability of the tunnel structure.

CN221799890UActive Publication Date: 2024-10-01POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420450888.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-08
Publication Date
2024-10-01
Estimated Expiration
2034-03-08

AI Technical Summary

Technical Problem

During the excavation process of long underground tunnels, it is easy to encounter concentrated water outlets caused by geological problems such as cracks and faults. The existing drainage structure is difficult to drain water in a timely manner, which affects the construction progress and the stability of the tunnel structure.

Method used

A structure including a first drainage pipe and a second drainage pipe is adopted. The first drainage pipe is installed at the water outlet point. The water flow is introduced into the second drainage pipe through an adapter, and a soft permeable pipe arranged along the tunnel rock wall guides the water flow to the drainage pipe. Ditch, using gravity to achieve natural downward drainage.

Benefits of technology

It achieves timely drainage of concentrated water outlets, reduces the difficulty of sealing and the risk of instability to the tunnel structure, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221799890U_ABST
    Figure CN221799890U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of concrete construction, in particular to a tunnel centralized water outlet point drainage structure. According to the technical scheme, the drainage structure for the centralized water outlet point of the tunnel is characterized by comprising a first drainage pipe, a second drainage pipe and a third drainage pipe, the first drainage pipe is installed at the centralized water outlet point of the tunnel through a first fixing piece, the water inlet end of the first drainage pipe faces the centralized water outlet point, and the first drainage pipe can introduce water flow of the centralized water outlet point into the first drainage pipe; the second drainage pipe is installed on the rock wall of the tunnel through a second fixing piece, the water outlet end of the second drainage pipe is connected to a drainage ditch, and the second drainage pipe can guide internal water flow to the drainage ditch; the first end of the adapter is communicated with the water outlet end of the first drainage pipe, the second end of the adapter is communicated with the water inlet end of the second drainage pipe, and the adapter is used for transferring water flow in the first drainage pipe into the second drainage pipe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of concrete construction, in particular to a drainage structure for centralized water outlet points of a tunnel. Background Art

[0002] During the excavation of long underground tunnels, it is inevitable to encounter some unfavorable geological problems such as cracks, faults, small fracture zones, or crack leakage locations exposed after test inspection. These locations are prone to concentrated water seepage, and after the tunnel is excavated, they become concentrated water source points exposed on the construction surface, which not only makes grouting and plugging difficult, but also affects other construction in the tunnel. The drainage ditches of some tunnels have not been completed, or the drainage ditches cannot play a timely drainage role for the crack leakage at this location, thus affecting the construction and making plugging difficult. Utility Model Content

[0003] The technical problem to be solved by the utility model is: in view of the above existing problems, a drainage structure for centralized water outlet points of a tunnel is provided.

[0004] The technical solution adopted by the utility model is: a tunnel centralized water outlet drainage structure, characterized in that it includes:

[0005] A first drainage pipe is installed at the centralized water outlet point of the tunnel via a first fixing member, the water inlet end of the first drainage pipe faces the centralized water outlet point, and the first drainage pipe can introduce the water flow from the centralized water outlet point into the pipe;

[0006] A second drainage pipe is installed on the rock wall of the tunnel via a second fixing member, the outlet of the second drainage pipe is connected to the drainage ditch, and the second drainage pipe can guide the internal water flow to the drainage ditch;

[0007] A connecting piece, whose first end is connected to the water outlet of the first drain pipe and whose second end is connected to the water inlet of the second drain pipe, is used to connect the water flow inside the first drain pipe to the second drain pipe.

[0008] Through the above-mentioned technical means, the first drain pipe is installed below the centralized water outlet point of the tunnel through the first fixing part, and the water inlet end of the first drain pipe faces the centralized water outlet point, so that the water outlet from the centralized water outlet point can be directly introduced into the first drain pipe, and the water flow in the first drain pipe is switched to the second drain pipe through the adapter, and the second drain pipe directs the water outlet from the centralized water outlet point along the pipeline to the drainage ditch, so that the water source of the centralized water outlet point in the tunnel can be directly and timely drained, thereby reducing the need for blocking, thereby reducing the impact of the centralized water outlet on the tunnel structure.

[0009] In some embodiments, the second drainage pipe is a soft permeable pipe.

[0010] Through the above technical means, the soft water-permeable pipe has good water permeability, can discharge the accumulated water in the first drainage pipe in time, and the soft water-permeable pipe is easy to install and has high construction efficiency.

[0011] In some embodiments, the second drainage pipe is arranged horizontally as a whole and has a slope.

[0012] Through the above technical means, the second drainage pipe is arranged horizontally and is provided with a certain slope, so that the water flow in the second drainage pipe can flow down naturally under the action of gravity and further flow to the drainage ditch.

[0013] In some embodiments, the first fixing member is a quick-setting cement block, which wraps the first drain pipe and exposes at least a portion of the water inlet end of the first drain pipe.

[0014] In some embodiments, the second fixing member is a fixing short nail, and the second drainage pipe is fixed to the rock wall of the tunnel by using the fixing short nail.

[0015] In some embodiments, the first drainage pipe is a PVC-U water pipe.

[0016] In some embodiments, the diameter of the first drain pipe is the same as the diameter of the second drain pipe, the first end of the adapter is adapted to the diameter of the first drain pipe, and the second end of the adapter is adapted to the diameter of the second drain pipe.

[0017] The beneficial effects of the utility model are:

[0018] 1. The water outlet can be connected to the pipe through the water pipe below the centralized water outlet point of the tunnel. The water flows through the connecting joint to the soft permeable pipe, and then discharged to the drainage ditch through the soft permeable pipe arranged along the rock wall of the tunnel, so that the water outlet of the centralized water outlet point of the tunnel can be discharged in time; blocking the centralized water outlet point not only makes the blocking construction difficult, but also may cause the tunnel structure to be unstable. Compared with the blocking method, timely discharge of accumulated water can reduce the risk of tunnel structure instability and avoid further impact of water on the construction in the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the structure of this application.

[0020] Description of reference numerals:

[0021] 1. Quick-setting cement block; 2. Water pipe; 3. Connecting joint; 4. Soft permeable pipe; 5. Fixing short nails. DETAILED DESCRIPTION

[0022] In order to enable those skilled in the art to better understand the technical solution of the present utility model, the technical solution of the present utility model is further described below in conjunction with specific embodiments.

[0023] Combination Figure 1 As shown, this embodiment is a drainage structure for a centralized water outlet point in a tunnel, including a first drainage pipe, a second drainage pipe, a first fixing member, a second fixing member and an adapter. In this embodiment, there are cracks on the rock wall of the tunnel, and there is a water source in the cracks, and the water source generates a centralized water outlet point at the cracks. The first drainage pipe is installed below the centralized water outlet point through the first fixing member, and the water inlet end of the first drainage pipe faces the centralized water outlet point. The first drainage pipe can connect the water outlet of the centralized water outlet point into the pipe; the second drainage pipe is installed on the inner wall of the tunnel or on the completed structure through the second fixing member, and the water outlet end of the second drainage pipe is connected to the drainage ditch; the first drainage pipe and the second drainage pipe are connected through the adapter, the first end of the adapter is connected to the water outlet end of the first drainage pipe, and the second end of the adapter is connected to the water inlet end of the second drainage pipe, and the adapter is used to transfer the water flow in the first drainage pipe to the second drainage pipe. The first drainage pipe and the second drainage pipe have the same pipe diameter and are matched with the connection joint 3.

[0024] Furthermore, in this embodiment, the first drainage pipe adopts a DN50 PVC-U water pipe 2, the second drainage pipe adopts a φ50 soft permeable pipe 4, the first fixing part adopts a quick-setting cement block 1, the second fixing part adopts a fixing short nail 5, and the adapter adopts a DN50 connecting joint 3.

[0025] The PVC-U water pipe 2 is arranged vertically, and the PVC-U water pipe 2 is fixed below the centralized water outlet point through the quick-setting cement block 1. The quick-setting cement block 1 wraps the PVC-U water pipe 2 and the two sides by about 10 cm. The water inlet end of the top of the PVC-U water pipe 2 is exposed at least partially from the quick-setting cement block 1, and the top of the PVC-U water pipe 2 is close to the centralized water outlet point. The bottom of the PVC-U water pipe 2 is connected to the first end of the connecting joint 3, and the second end of the connecting joint 3 is connected to the soft water-permeable pipe 4. The soft water-permeable pipe 4 is installed on the rock wall through the fixing short nails 5. The water outlet end of the soft water-permeable pipe 4 is connected to the drainage ditch. The soft water-permeable pipe 4 is arranged horizontally and has a certain slope, so that the water flowing through the inside can naturally flow to the drainage ditch under the action of gravity.

[0026] The water flow at the centralized water outlet point enters the PVC-U water pipe 2, and the water in the PVC-U water pipe 2 is transferred to the soft water pipe 4 through the connection joint 3. The water flow inside the soft water pipe 4 is discharged to the drainage ditch through the pipe due to the slope setting. By discharging the water flow at the centralized water outlet point in time, the water flow is discharged to the drainage ditch along the pipe, thereby alleviating the difficulty of blocking the centralized water outlet point and avoiding the impact of water accumulation on other construction operations in the tunnel.

[0027] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.

Claims

1. A tunnel centralized water outlet drainage structure, characterized in that: include: A first drainage pipe is installed at the centralized water outlet point of the tunnel via a first fixing member, the water inlet end of the first drainage pipe faces the centralized water outlet point, and the first drainage pipe can introduce the water flow from the centralized water outlet point into the pipe; A second drainage pipe is installed on the rock wall of the tunnel via a second fixing member, the outlet of the second drainage pipe is connected to the drainage ditch, and the second drainage pipe can guide the internal water flow to the drainage ditch; A connecting piece, whose first end is connected to the water outlet of the first drain pipe and whose second end is connected to the water inlet of the second drain pipe, is used to connect the water flow inside the first drain pipe to the second drain pipe.

2. A tunnel centralized water outlet drainage structure according to claim 1, characterized in that: The second drainage pipe is a soft permeable pipe (4).

3. A tunnel centralized water outlet drainage structure according to claim 1, characterized in that: The second drainage pipe is arranged horizontally as a whole and has a slope.

4. A tunnel centralized water outlet drainage structure according to claim 1, characterized in that: The first fixing member is a quick-setting cement block (1), which wraps the first drainage pipe and exposes at least a portion of the water inlet end of the first drainage pipe.

5. The tunnel centralized water outlet drainage structure according to claim 1, characterized in that: The second fixing member is a fixing short nail (5), and the second drainage pipe is fixed to the rock wall of the tunnel by using the fixing short nail (5).

6. A tunnel centralized water outlet drainage structure according to claim 1, characterized in that: The first drainage pipe is a PVC-U water pipe (2).

7. The tunnel centralized water outlet drainage structure according to claim 1, characterized in that: The diameter of the first drain pipe is the same as that of the second drain pipe, the first end of the adapter is adapted to the diameter of the first drain pipe, and the second end of the adapter is adapted to the diameter of the second drain pipe.