Concrete grouting pile sampling device
By designing the sampling drill barrel, filling mechanism and sample clamping mechanism of the concrete pile sampling device, the problems of incomplete sampling and equipment damage in the existing technology are solved, the complete sample removal and equipment protection are achieved, and the sample quality is improved. and equipment life.
Patent Information
- Application Number
- CN202422165319.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-09-04
AI Technical Summary
It is difficult to take out complete samples with existing concrete pile sampling equipment, and the samples and equipment are easily damaged during the sampling process.
A concrete pile sampling device including a sampling drill barrel, a filling mechanism and a sample clamping mechanism is designed. Through the cooperation of the filling mechanism and the clamping mechanism, concrete samples can be drilled and taken out stably, avoiding the use of blunt objects to hit, and protecting Equipment and samples.
It effectively improves the integrity and quality of samples, extends the service life of equipment, and avoids damage to samples and equipment.
Smart Images

Figure CN221803463U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction engineering, in particular to a concrete pile sampling device. Background Art
[0002] Bored piles are a widely used form of foundation. In the process of bored pile construction, core sampling is an indispensable link. Through sampling, we can understand the mechanical properties of the pile foundation, the integrity of the pile body and whether the design parameters meet the requirements. Concrete drilling coring machines are generally used for bored pile core sampling operations. For small buildings, such as 2-3-story buildings, the depth of foundation piling is generally about 2 meters, which is enough to stabilize the building. Compared with large buildings, small building piles are shallower and more convenient for sampling by drilling. The conventional sampling method is to start drilling at the top of the concrete through a cylindrical sampling device with an opening at the bottom until it drills into the soil below and takes out the entire concrete sample. However, in most cases, the sample will remain inside the sampling device, and construction personnel are required to hit the sampling device with a blunt instrument to shake the sample out, which can easily damage the sampling equipment and cause the sample to break, reducing the sample quality. Utility Model Content
[0003] In view of the above situation, in order to overcome the defects of the prior art, the utility model provides a concrete pile sampling device, which effectively solves the problem that the concrete pile sampling equipment currently on the market is difficult to take out a complete sample and may damage the sampling equipment.
[0004] The technical solution adopted by the utility model is as follows: the concrete pile sampling device provided by the utility model includes a sampling drill tube, a filling mechanism and a sample clamping mechanism, the filling mechanism is inserted into the sampling drill tube, and the sample clamping mechanism is sleeved on the outside of the sampling drill tube.
[0005] Furthermore, the sampling drill barrel includes a barrel, a joint, a grinding tooth, a clamping port and a lifting head. The barrel is a cylindrical structure with an opening at the bottom. The grinding tooth is arranged on the bottom wall of the barrel, the joint is arranged on the top of the barrel, the joint is arranged coaxially with the barrel, the clamping port is opened in a circular array on the side wall of the barrel, the clamping port is longitudinal to the side wall of the barrel, and the lifting head is arranged on the top wall of the barrel.
[0006] Furthermore, the filling mechanism includes a connecting ring, a lifting head 2 and a filling plate, the connecting ring is arranged above the cylinder, the lifting head 2 is arranged at the top of the connecting ring, the filling plate circumferential array is arranged at the bottom of the connecting ring, the filling plate is arranged in the clamping port, and the filling plate is fitted with the clamping port.
[0007] Preferably, the height of the filling plate is the same as the height of the side wall of the cylinder, the thickness of the filling plate is the same as the thickness of the side wall of the cylinder, and the filling plate is filled in the clamping port to keep the sampling drill tube stable when drilling concrete piles.
[0008] Furthermore, the sample clamping mechanism includes a fixing ring, an extension rod and a fixing plate, the fixing ring is sleeved on the outside of the cylinder, the extension rod circular array is arranged on the outside of the fixing ring, the fixing plate is arranged on the bottom wall of the extension rod, the fixing plate is arranged on the end of the extension rod, the fixing plate is penetrated by a screw hole, and a screw is rotatably arranged in the screw hole.
[0009] Furthermore, a circumferential array of sliding grooves is provided on the inner wall of the fixed ring, the number of the sliding grooves is the same as the number of the clamping openings, a fixed slider is slidably provided in the sliding groove, the fixed slider is fitted with the sliding groove, a latch is provided on the side of the fixed slider close to the axis of the fixed ring, the fixed slider and the sliding groove are connected by a spring, a through hole is penetrated on the side of the sliding groove away from the center of the fixed ring, a handle is slidably provided in the through hole, and the handle is connected to the fixed slider.
[0010] Preferably, the width of the slide groove is slightly smaller than the width of the clamping opening, and the width of the fixed slider is slightly smaller than the width of the slide groove. Such an arrangement can facilitate the fixed slider to pass through the clamping opening.
[0011] Furthermore, a lifting ring three is provided at the top of the fixing ring.
[0012] The beneficial effects achieved by the utility model using the above structure are as follows: When using the concrete pile sampling device provided by the scheme, first remove the sample clamping mechanism, connect the joint through the external drilling equipment, place the sampling drill on the top of the concrete pile, rotate and press down, after drilling through the concrete pile, remove the external drilling equipment, use the external lifting equipment to lift the filling mechanism upward through the lifting head 2, the concrete sample leaks out of the clamping port, then put the sample clamping mechanism on the top of the cylinder, pull the handle, the fixed slider extends to the outside of the fixed ring, and align the fixed slider with the clamping port Finally, the sampling drill hole is slightly lifted upwards by an external lifting device, and the sampling drill tube and the concrete sample emerge from the top wall of the concrete pile. Then the handle is released, and the fixed slider shrinks toward the inside of the fixed ring, passes through the clamping port and clamps the side wall of the concrete sample. Then the screw is turned, and the screw shrinks inwards to clamp the outer wall of the concrete pile. The sample clamping mechanism and the concrete sample are fixed in position, and the sampling drill is continued to be lifted upwards. After passing through, the screw is rotated in the opposite direction. After the screw is loosened, the sample clamping mechanism and the concrete sample are lifted upwards by the lifting head three upwards with an external lifting device to completely remove the concrete sample. This method can remove a complete concrete sample, which can effectively improve the sample quality. At the same time, there is no need to use a blunt instrument to hit the sampling equipment, which can effectively increase the service life of the equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 A schematic diagram of the structure of the concrete pile sampling device provided by the utility model;
[0014] Figure 2 A schematic diagram of the structure of the sample clamping mechanism provided by the utility model;
[0015] Figure 3 A cross-sectional view of the sample clamping mechanism provided by the utility model;
[0016] Figure 4 A schematic diagram of the structure of the sampling drill tube provided by the utility model;
[0017] Figure 5 This is a structural schematic diagram of the filling mechanism provided by the utility model.
[0018] Among them, 1. sampling drill barrel, 2. filling mechanism, 3. sample clamping mechanism, 101. barrel, 102. joint, 103. grinding gear, 104. clamping port, 105. lifting head one, 201. connecting ring, 202. lifting head two, 203. filling plate, 301. fixing ring, 302. extension rod, 303. fixing plate, 304. screw, 305. lifting head three, 306. slide groove, 307. fixed slider, 308. through hole, 309. handle.
[0019] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. They are used together with the embodiments of the present invention to explain the present invention and do not constitute a limitation to the present invention. DETAILED DESCRIPTION
[0020] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments; based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0021] In the description of the present invention, it should be understood that terms such as "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0022] like Figure 1-Figure 5As shown, the concrete pile sampling device provided by the utility model comprises a sampling drill tube 1, a filling mechanism 2 and a sample clamping mechanism 3, the filling mechanism 2 is inserted into the sampling drill tube 1, the sample clamping mechanism 3 is sleeved on the outside of the sampling drill tube 1, the sampling drill tube 1 comprises a barrel 101, a joint 102, a grinding gear 103, a clamping port 104 and a lifting head 105, the barrel 101 is a cylindrical structure with an opening at the bottom, the grinding gear 103 is arranged on the bottom wall of the barrel 101, the joint 102 is arranged on the top of the barrel 101, the joint 102 is arranged coaxially with the barrel 101, the clamping port 104 is arranged in a circumferential array on the side wall of the barrel 101, the clamping port 104 is longitudinal to the side wall of the barrel 101, and the lifting head 105 is arranged on the top wall of the barrel 101.
[0023] The filling mechanism 2 includes a connecting ring 201, a lifting head 202 and a filling plate 203. The connecting ring 201 is arranged above the cylinder 101, the lifting head 202 is arranged at the top of the connecting ring 201, and the filling plates 203 are arranged in a circular array at the bottom of the connecting ring 201. The filling plates 203 are arranged in the clamping port 104, and the filling plates 203 are fitted with the clamping port 104. The height of the filling plates 203 is the same as the height of the side wall of the cylinder 101, and the thickness of the filling plates 203 is the same as the thickness of the side wall of the cylinder 101. The filling plates 203 are filled in the clamping port 104 to keep the sampling drill tube 1 stable when drilling concrete piles.
[0024] The sample clamping mechanism 3 includes a fixing ring 301, an extension rod 302 and a fixing plate 303. The fixing ring 301 is sleeved on the outside of the cylinder 101, the extension rods 302 are arranged in a circular array on the outside of the fixing ring 301, the fixing plate 303 is arranged on the bottom wall of the extension rod 302, and the fixing plate 303 is arranged at the end of the extension rod 302. The fixing plate 303 is penetrated by a screw hole, and a screw 304 is rotatably arranged in the screw hole.
[0025] A sliding groove 306 is provided in a circular array on the inner wall of the fixing ring 301, and the number of the sliding grooves 306 is the same as the number of the clamping openings 104. A fixed slider 307 is slidably provided in the sliding groove 306, and the fixed slider 307 is fitted with the sliding groove 306. A latch is provided on the side of the fixed slider 307 close to the axis of the fixing ring 301, and the fixed slider 307 is connected to the sliding groove 306 by a spring. A through hole 308 is penetrated on the side of the sliding groove 306 away from the center of the fixing ring 301, and a handle 309 is slidably provided in the through hole 308, and the handle 309 is connected to the fixed slider 307. The width of the sliding groove 306 is slightly smaller than the width of the clamping opening 104, and the width of the fixed slider 307 is slightly smaller than the width of the sliding groove 306. Such an arrangement can facilitate the fixed slider 307 to pass through the clamping opening 104, and a lifting ring three is provided on the top of the fixing ring 301.
[0026] When in use, first remove the sample clamping mechanism 3, connect the joint 102 through the external drilling equipment, place the sampling drill on the top of the concrete pile, rotate and press down to perform core sampling, and after drilling through the concrete pile, remove the external drilling equipment, and use the external lifting equipment to lift the filling mechanism 2 upward through the lifting head 202. After the filling mechanism 2 is detached, the concrete sample leaks out of the clamping port 104, and then the sample clamping mechanism 3 is sleeved on the top of the cylinder 101, and the handle 309 is pulled, and the fixed slider 307 extends to the outside of the fixed ring 301. After aligning the fixed slider 307 with the clamping port 104, the sampling drill hole is pulled upward by the external lifting equipment, so that the sampling drill barrel 1 and the concrete sample emerge from the top wall of the concrete pile. The sample holding mechanism 3 is locked, and the position of the sample holding mechanism 3 and the concrete sample is fixed. After the sampling drill tube 1 is lifted upward, the screw rod 304 is rotated in the opposite direction. After the screw rod 304 is loosened, the sample holding mechanism 3 and the concrete sample are lifted upward through the lifting head 305 using an external lifting device to completely lift the sample holding mechanism 3 and the concrete sample. The handle 309 is then pulled, and the fixed slide block 307 leaves the side wall of the concrete sample. The sample holding mechanism 3 is removed, and the entire concrete sample can be obtained.
[0027] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0028] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.
Claims
1. Concrete pile sampling device, Features: The invention comprises a sampling drill tube (1), a filling mechanism (2) and a sample clamping mechanism (3); the filling mechanism (2) is inserted into the sampling drill tube (1); the sample clamping mechanism (3) is sleeved on the outside of the sampling drill tube (1); the sampling drill tube (1) comprises a barrel (101), a joint (102), a grinding tooth (103) and a clamping opening (104); the barrel (101) is a cylindrical structure with an opening at the bottom; the grinding tooth (103) is arranged on the bottom wall of the barrel (101); the joint (102) is arranged on the top of the barrel (101); the joint (102) and the barrel (101) are coaxially arranged; and the clamping opening (104) is arranged in a circumferential array on the side wall of the barrel (101).
2. The concrete pile sampling device according to claim 1, Features: The sample clamping mechanism (3) comprises a fixing ring (301), an extension rod (302) and a fixing plate (303); the fixing ring (301) is sleeved on the outside of the cylinder (101); the extension rods (302) are arranged in a circular array on the outside of the fixing ring (301); the fixing plate (303) is arranged on the bottom wall of the extension rod (302); the fixing plate (303) is arranged at the end of the extension rod (302); a screw hole is penetrated by the fixing plate (303); a screw rod (304) is rotatably arranged in the screw hole.
3. The concrete pile sampling device according to claim 2, Features: The inner wall of the fixed ring (301) is provided with a sliding groove (306) in a circular array, the number of the sliding grooves (306) is the same as the number of the clamping openings (104), a fixed slider (307) is slidably provided in the sliding groove (306), the fixed slider (307) is fitted with the sliding groove (306), a locking tooth is provided on the side of the fixed slider (307) close to the axis of the fixed ring (301), the fixed slider (307) and the sliding groove (306) are connected by a spring, a through hole (308) is penetrated on the side of the sliding groove (306) away from the center of the fixed ring (301), a handle (309) is slidably provided in the through hole (308), and the handle (309) is connected to the fixed slider (307).
4. The concrete pile sampling device according to claim 3, Features: The filling mechanism (2) comprises a connecting ring (201) and a filling plate (203); the connecting ring (201) is arranged above the cylinder (101); the filling plates (203) are arranged in a circular array at the bottom of the connecting ring (201); the filling plates (203) are arranged in a clamping opening (104); and the filling plates (203) are fitted with the clamping opening (104).
5. The concrete pile sampling device according to claim 4, Features: The top wall of the cylinder (101) is provided with a lifting head (105).
6. The concrete pile sampling device according to claim 5, Features: A second lifting head (202) is provided on the top of the connecting ring (201).
7. The concrete pile sampling device according to claim 6, Features: A lifting ring three is provided at the top of the fixing ring (301).