Reverse slope prevention device for tunnel drainage blind pipe
By using anti-slope devices with transverse steel bars and non-enclosed structural hoops in railway tunnel projects, the problem of position deviation and reverse slope of drainage blind pipes caused by vibration has been solved, drainage efficiency and structural stability have been improved, and drainage costs have been reduced. Project cost and lead time.
Patent Information
- Application Number
- CN202420567782.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2034-03-22
AI Technical Summary
In railway tunnel projects, blind drainage pipes are prone to floating or sinking in the middle due to collision and vibration during the concrete pouring and vibrating processes, resulting in reverse slope phenomena, which affects the drainage effect and increases the project cost and cycle.
An anti-reverse slope device including transverse steel bars and non-enclosed structural circular hoops is used, and the steel bars and circular hoops are connected by welding or winding to ensure that the blind drainage pipe is stably fixed in the concrete, absorbing and dispersing vibration forces, and preventing position deviation and reverse slope.
It effectively avoids the problem of position deviation or reverse slope of the drainage blind pipe caused by vibration, improves the drainage efficiency of the tunnel, ensures the stability of the tunnel structure and construction safety, reduces maintenance costs, and extends the service life of the tunnel.
Smart Images

Figure CN221810853U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of tunnel drainage, in particular to a tunnel drainage blind pipe anti-reverse slope device. Background Art
[0002] In modern railway tunnel projects, it is crucial to ensure the stability and functionality of the tunnel's internal structure. The tunnel's drainage system, especially the setting of drainage blind pipes, plays a decisive role in effectively removing moisture from the tunnel, maintaining the dryness of the tunnel structure and extending its service life. The Ningbo-Zhoushan Railway Mining Method Tunnel Project uses drainage blind pipes as the main drainage measure to achieve effective management and removal of moisture inside the tunnel. The drainage blind pipe is a circular pipe arranged around the tunnel to collect and guide the moisture that penetrates into the tunnel to ensure the dryness and safety of the tunnel. In the Ningbo-Zhoushan Railway Mining Method Tunnel Project, the drainage blind pipes are available in two specifications, 50mm and 100mm. They are arranged according to the designed slope, and both ends are fixed to the secondary lining steel bars of the tunnel's side walls to ensure the effectiveness and stability of the drainage system.
[0003] However, in the actual construction process, the installation of drainage blind pipes and the pouring of concrete face a series of challenges. In particular, during the pouring and vibration of concrete, the drainage blind pipes may float or sink in the middle due to the impact of collision and vibration, and then a reverse slope may appear, which seriously affects the drainage effect, resulting in the inability to effectively remove moisture, increasing the humidity inside the tunnel, and posing a threat to the stability and service life of the tunnel structure. Once the drainage blind pipe floats, sinks or reverses, the rectification work will become extremely difficult and costly. Not only does it need to dismantle the poured concrete, but it also needs to readjust and install the drainage blind pipes, which not only increases the project cost, but also prolongs the project cycle and affects the overall progress of the project. Utility Model Content
[0004] In view of the above defects of the existing technical solutions, the main purpose of the utility model is to develop an improved tunnel drainage blind pipe anti-reverse slope device, which can avoid the position deviation or reverse slope problem of the tunnel drainage blind pipe caused by vibration, and ensure good drainage effect.
[0005] To achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a device for preventing reverse slope of tunnel drainage blind pipe, comprising transverse steel bars and multiple circular hoops, the transverse steel bars are welded to the circular hoops, the drainage blind pipe is sleeved in the circular hoops, the two ends of the transverse steel bars are fixed to the second lining steel bars of the side wall, the circular hoops are non-closed structures, one section of which is a notch, connecting steel bars are arranged between the circular hoops, and the connecting steel bars and the transverse steel bars are relatively distributed on both sides of the diameter of the circular hoops.
[0006] Preferably, the inner diameter of the circular hoop is 55 mm or 105 mm.
[0007] Preferably, the spacing between the circular hoops is 10 cm or 15 cm.
[0008] Preferably, the transverse reinforcement is made of φ16mm reinforcement, and the circular hoop is formed by bending φ8mm reinforcement.
[0009] Preferably, the connecting steel bars are φ6mm steel bars.
[0010] Preferably, the connecting steel bar is fixed to the circular hoop by welding.
[0011] Preferably, the connecting steel bars are fixed on the circular hoop by winding.
[0012] Preferably, the connecting steel bars are arranged intermittently.
[0013] Preferably, both ends of the transverse reinforcement are connected to the secondary lining reinforcement of the tunnel side wall by means of steel wire binding.
[0014] Preferably, the connecting steel bars are wrapped with a vibration-proof layer, and the vibration-proof layer is used to absorb vibration and press against the drainage blind pipe.
[0015] In summary, the beneficial effects of the utility model are as follows: by adopting the design of transverse steel bars, non-enclosed structure hoop and connecting steel bars, this solution simplifies and facilitates the construction process, is easy to install, and effectively improves the drainage efficiency of the tunnel. This solution particularly solves the problem of position offset or reverse slope of the drainage blind pipe caused by vibration, thereby ensuring the stability of the tunnel surrounding rock, improving the safety of construction, reducing maintenance costs, and extending the service life of the tunnel. It effectively avoids the reverse slope phenomenon of the drainage blind pipe, and is suitable for the construction of drainage blind pipes on the low side walls of tunnels, which is of great significance to improving the overall quality and efficiency of tunnel projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 A schematic diagram of a tunnel drainage blind pipe anti-reverse slope device according to an embodiment of the utility model;
[0018] Figure 2 This is a schematic diagram of the installation of a tunnel drainage blind pipe according to an embodiment of the utility model;
[0019] Figure 3A schematic diagram of a tunnel drainage blind pipe anti-reverse slope device according to another embodiment of the utility model;
[0020] Explanation of the reference numerals: 1- transverse reinforcement, 2- circular hoop, 3- drainage blind pipe, 4- side wall secondary lining reinforcement, 5- notch, 6- connecting reinforcement, 7- initial support structure, 8- construction joint, 9- tunnel side ditch. DETAILED DESCRIPTION
[0021] The following will clearly and completely describe the technical solutions in the embodiments of the utility model in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the utility model belong to the utility model.
[0022] In addition, described feature, structure or characteristic can be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present application. However, those skilled in the art will appreciate that the technical scheme of the present application can be put into practice without one or more of the specific details, or other methods, components, devices, steps, etc. can be adopted. In other cases, known methods, devices, realizations or operations are not shown or described in detail to avoid blurring the various aspects of the application.
[0023] See also Figure 1-2The present embodiment provides a device for preventing reverse slope of blind drainage pipes in tunnels, including transverse steel bars 1 and multiple hoop hoops 2. The transverse steel bars 1 and the hoop 2 are welded and firmly connected by welding, so that the blind drainage pipe 3 can be fixed in the hoop 2 later to ensure the stability of the blind drainage pipe 3 during construction and use. The blind drainage pipe 3 is set in the hoop 2 to enable the blind drainage pipe 3 to be effectively fixed in a predetermined position to prevent it from shifting or deforming. The two ends of the transverse steel bar 1 are fixed to the second lining steel bar 4 of the side wall, and the stability and durability of the overall structure are further enhanced by being connected and fixed to the main structure of the tunnel. The hoop 2 is a non-closed structure, one section of which is a notch 5. This design enables the hoop 2 to better absorb and disperse the vibration force during the concrete vibration process, reducing the negative impact on the blind drainage pipe 3. Connecting steel bars 6 are arranged between the hoop 2, and the connecting steel bars 6 and the transverse steel bars 1 are relatively distributed on both sides of the diameter of the hoop 2. This layout is intended to further enhance the overall stability of the device, ensure that the blind drainage pipe 3 will not float or sink due to vibration during the concrete pouring process, and effectively avoid the occurrence of reverse slope phenomenon. The drainage blind pipe 3 is close to the initial support structure 7, set at the foot of the side wall and lower than the longitudinal construction joint 8, and is connected to the tunnel side ditch 9 set on the driving side of the low side wall of the secondary lining structure. The slope of the drainage blind pipe 3 must be consistent with the slope of the line. This arrangement optimizes the water flow path, reduces the possibility of water erosion and damage to the tunnel structure, and ensures the structural safety and stability of the tunnel.
[0024] See also Figure 1 , the number of round hoops can be selected as 6, which are evenly spaced along the length direction of the transverse steel bar 1. The drainage blind pipe 3 has two specifications of 50mm and 100mm. When the drainage blind pipe 3 is 50mm, the inner diameter of the round hoop 2 is 55mm, and the spacing of the round hoops is 10cm. The purpose of this setting is to ensure that there is enough space to accommodate the drainage blind pipe 3 while allowing a certain amount of adjustment to adapt to different installation requirements and conditions to ensure the effectiveness of the drainage system. When the drainage blind pipe 3 is 100mm, the inner diameter of the round hoop 2 is 105mm, and the spacing of the round hoop 2 is 15cm. This configuration is intended to provide appropriate support and fixation for larger-sized drainage blind pipes 3, while taking into account the spacing requirements of drainage blind pipes 3 of different specifications to optimize drainage efficiency and system stability. Furthermore, the transverse steel bar 1 adopts φ16mm steel bar to ensure sufficient strength and stability. The circular hoop 2 is formed by bending φ8mm steel bar. By using thinner steel bars to make the circular hoop, the elasticity and adaptability of the circular hoop 2 are guaranteed, and the stability requirements of the structure can be met. The connecting steel bar 6 adopts φ6mm steel bar, which can provide a certain toughness while meeting the strength requirements to adapt to different construction conditions and environmental changes.
[0025] In some embodiments, the connecting steel bar 6 is fixed to the circular hoop 2 by welding, ensuring a stable and lasting connection between the connecting steel bar 6 and the circular hoop 2, thereby enhancing the stability and durability of the overall structure. In other embodiments, the connecting steel bar 6 is fixed to the circular hoop 2 by winding, which is flexible and adjustable, and facilitates necessary adjustments according to on-site conditions.
[0026] See also Figure 3 In addition to the continuous arrangement, the connecting steel bars 6 can also be arranged intermittently to balance the distribution of force by dispersing the supporting points, reduce the local stress concentration caused by concentrated loads, and thus improve the stability and efficiency of the entire drainage system.
[0027] In some embodiments, the two ends of the transverse reinforcement 1 are connected to the second lining reinforcement 4 of the tunnel side wall by steel wire binding, which is a simple and effective fixing method to ensure that the transverse reinforcement is firmly connected to the tunnel structure and enhance the overall stability. In addition, the connecting reinforcement 6 is wrapped with an anti-vibration layer. The effect of this design is to absorb the vibration generated during concrete construction, reduce the impact on the stability of the drainage blind pipe, and at the same time, by pressing the drainage blind pipe tightly, ensure that it is in the correct position and angle to optimize the drainage efficiency.
[0028] The device for preventing reverse slope of the tunnel drainage blind pipe of this embodiment, through a unique structural design, including the use of circular hoops with non-closed structures, transverse steel bars and connecting steel bars, effectively solves the problem of floating and sinking of the tunnel drainage blind pipe 3 during the construction process, and avoids the reverse slope problem.
[0029] Obviously, the above embodiments are merely examples for the purpose of clear explanation and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention of the utility model.
Claims
1. A tunnel drainage blind pipe anti-reverse slope device, characterized in that: The invention comprises a transverse steel bar (1) and a plurality of circular hoops (2), wherein the transverse steel bar (1) and the circular hoop (2) are welded together, a drainage blind pipe (3) is sleeved in the circular hoop (2), two ends of the transverse steel bar (1) are fixed to the secondary lining steel bar (4) of the side wall, the circular hoop (2) is a non-closed structure, one section of which is a notch (5), connecting steel bars (6) are arranged between the circular hoops (2), and the connecting steel bars (6) and the transverse steel bars (1) are relatively distributed on both sides of the diameter of the circular hoop.
2. The tunnel drainage blind pipe anti-reverse slope device according to claim 1 is characterized in that: The inner diameter of the circular hoop (2) is 55 mm or 105 mm.
3. The tunnel drainage blind pipe anti-reverse slope device according to claim 2 is characterized in that: The spacing between the circular hoops (2) is 10 cm or 15 cm.
4. The tunnel drainage blind pipe anti-reverse slope device according to any one of claims 1 to 3, characterized in that: The transverse steel bars (1) are made of φ16 mm steel bars, and the circular hoops (2) are formed by bending φ8 mm steel bars.
5. The tunnel drainage blind pipe anti-reverse slope device according to claim 4 is characterized in that: The connecting steel bars (6) are made of φ6mm steel bars.
6. The tunnel drainage blind pipe anti-reverse slope device according to claim 5, characterized in that: The connecting steel bar (6) is fixed on the circular hoop by welding.
7. The tunnel drainage blind pipe anti-reverse slope device according to claim 5, characterized in that: The connecting steel bar (6) is fixed on the circular hoop in a winding manner.
8. The tunnel drainage blind pipe anti-reverse slope device according to claim 1, characterized in that: The connecting steel bars (6) are arranged intermittently.
9. The tunnel drainage blind pipe anti-reverse slope device according to claim 1, characterized in that: The two ends of the transverse steel bars (1) are connected to the secondary lining steel bars (4) of the tunnel side wall by means of steel wire binding.
10. The tunnel drainage blind pipe anti-reverse slope device according to claim 1, characterized in that: The connecting steel bars (6) are wrapped with a vibration-proof layer, and the vibration-proof layer is used to absorb vibration and press against the drainage blind pipe (3).