By using the combined design of aligned tubes and support column components in the continuous-arch subway foundation pit enclosure structure, the problem of misalignment during the installation of enclosure units is solved, achieving efficient compression support and improving construction efficiency.
Patent Information
- Application Number
- CN202420250682.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-01
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-02-01
AI Technical Summary
In the existing technology, it is inconvenient to align the enclosure units on adjacent sides of the double-arch subway foundation pit enclosure structure during the installation process. It cannot be guaranteed that they are in the same straight line during the enclosure process, and misalignment is prone to occur.
Use an alignment component including an upper alignment tube, a lower alignment tube and a connecting tube. Correct the horizontal limit under the connecting tube through the fixed connection of these components to ensure that the adjacent two sets of enclosure components can be correctly aligned, and through the support column assembly and Cement mixing piles provide compression support and are combined with infrared equipment and fixed bases, rotating rings, and safety ropes to facilitate installation and subsequent maintenance.
It effectively solves the problem of misalignment of enclosure units, improves installation efficiency and pressure resistance, ensures the horizontal alignment and stability of the enclosure structure, improves construction safety and industrialization, and saves the construction period.
Smart Images

Figure CN221822918U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of foundation pit construction, in particular to a multi-arch type subway foundation pit enclosure structure. Background Art
[0002] Existing straight column-type bored piles generally have dense pile spacing, which requires the bored piles to completely independently resist the pressure difference gradually generated inside and outside the foundation pit. The straight column arrangement has weak compressive strength and high cost. In terms of construction efficiency, traditional crown beams and concrete supports often require on-site tying of steel bars before casting, which is inefficient and the process is complicated.
[0003] In the prior art, patent (CN217580185U) discloses a continuous arch type subway foundation pit retaining structure, including a plurality of arch column type retaining units connected in sequence, the arch column type retaining unit is composed of a first bored cast-in-place pile located at the arch foot, a second bored cast-in-place pile located at the arch top, a plurality of cement soil mixing piles located between the adjacent first bored cast-in-place piles and the second bored cast-in-place piles, and a prefabricated crown beam assembledly connected to the top of the first bored cast-in-place pile and the second bored cast-in-place pile, the cement soil mixing piles are engaged with each other, and the first bored cast-in-place pile and the second bored cast-in-place pile are engaged with the adjacent cement soil mixing piles, the diameter of the first bored cast-in-place pile is larger than that of the second bored cast-in-place pile, and a plurality of supporting steel bars are provided on the inner side wall at the arch foot of the prefabricated crown beam.
[0004] However, in the above-mentioned prior art, the enclosure units on the adjacent two sides are not easy to align during the installation process, and cannot be guaranteed to be in the same straight line during the enclosure process, which is prone to misalignment. Utility Model Content
[0005] The utility model aims to provide a continuous arch type subway foundation pit retaining structure, which solves the problem in the prior art that the retaining units on adjacent sides are difficult to align during installation, cannot be guaranteed to be in the same straight line during the retaining process, and are prone to misalignment.
[0006] To achieve the above-mentioned purpose, the utility model provides a continuous arch type subway foundation pit retaining structure, including two groups of retaining components, multiple alignment components and two groups of support column components, each group of the support column components is fixedly connected to the corresponding retaining components and is respectively located below the corresponding retaining components, each group of the alignment components includes an upper alignment tube, a lower alignment tube and a connecting tube, the upper alignment tube is fixedly connected to the connecting tube and is located at the upper end of the connecting tube, and the lower alignment tube is fixedly connected to the connecting tube and is located below the connecting tube.
[0007] Wherein, the upper alignment tube includes an upper tube and a first tube sleeve, the first tube sleeve is fixedly connected to the upper tube and located on the circumferential side of the upper tube, and the upper tube is fixedly connected to one group of the enclosure components and located on one side of one group of the enclosure components.
[0008] Wherein, the lower alignment tube includes a lower tube and a second tube sleeve, the second tube sleeve is fixedly connected to the lower tube and located on the peripheral side of the lower tube, and the lower tube is fixedly connected to one group of the enclosure components and located on one side of one group of the enclosure components.
[0009] Wherein, each group of the enclosure components includes a enclosure frame, a plurality of reinforcing ribs and an enclosure cover, wherein the enclosure cover is fixedly connected to the enclosure frame and is located above the enclosure frame, and each of the reinforcing ribs is fixedly connected to the enclosure frame and is located on the inner side of the enclosure frame.
[0010] Among them, each group of the support column assemblies includes a plurality of cement mixing piles, a plurality of bored cast-in-place piles and a plurality of support steel columns, each of the support steel columns is fixedly connected to the corresponding protective frame and is respectively located on one side of the corresponding protective frame, each of the bored cast-in-place piles is respectively fixedly connected to the corresponding protective frame and is respectively located on the inner wall of the corresponding protective frame, and each of the cement mixing piles is respectively fixedly connected to the corresponding protective frame and is respectively located on the inner wall of the corresponding protective frame.
[0011] Among them, the continuous arch type subway foundation pit retaining structure also includes a fixed seat, a rotating ring and a safety rope, one end of the safety rope is fixedly connected to the rotating ring and is located at the upper end of the rotating ring, the rotating ring is rotatably connected to the fixed seat and is located above the fixed seat, and the fixed seat is fixedly connected to one of the retaining covers and is located above one of the retaining covers.
[0012] The utility model discloses a continuous arch type subway foundation pit retaining structure, wherein the upper alignment tube and the lower alignment tube are arranged under the connection of the connecting tube, firstly, their own horizontal limit is corrected, and secondly, the two adjacent groups of the retaining components can be better connected. This design solves the problem that the retaining units on the adjacent two sides are not convenient to align during the installation process, and cannot be guaranteed to be in the same straight line during the retaining process, and are prone to misalignment. The safety rope can be well rotated with the cooperation of the rotating ring, so that the staff can move to the bottom of the retaining frame through the safety rope to conduct survey and maintenance. The fixing seat is fixed to the corresponding retaining cover by the staff, and the specific position of the fixing seat can be changed according to specific needs, which is convenient for use. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.
[0014] Figure 1 It is a schematic diagram of the overall structure of the first embodiment of the utility model.
[0015] Figure 2 It is a left view of the first embodiment of the utility model.
[0016] Figure 3 The utility model Figure 2 AA line section view.
[0017] Figure 4 It is an overall structural diagram of the second embodiment of the utility model.
[0018] Figure 5 The utility model Figure 4 Enlarged view of the local structure at point B.
[0019] 101-enclosure assembly, 102-alignment assembly, 103-support column assembly, 104-upper alignment tube, 105-lower alignment tube, 106-connecting tube, 107-upper tube, 108-first pipe sleeve, 109-lower tube, 110-second pipe sleeve, 111-enclosure frame, 112-reinforcement ribs, 113-enclosure cover, 114-cement mixing pile, 115-bored pile, 116-support steel column, 201-fixed seat, 202-rotating ring, 203-safety rope. DETAILED DESCRIPTION
[0020] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0021] The first embodiment of the present application is:
[0022] See also Figure 1-Figure 3 ,in Figure 1 It is a schematic diagram of the overall structure of the first embodiment of the utility model. Figure 2 It is a left view of the first embodiment of the utility model. Figure 3 The utility model Figure 2 AA line section view.
[0023] The utility model provides a continuous arch type subway foundation pit retaining structure, including two groups of retaining components 101, a plurality of alignment components 102 and two groups of support column components 103, each group of the alignment components 102 includes an upper alignment tube 104, a lower alignment tube 105 and a connecting tube 106, the upper alignment tube 104 includes an upper tube 107 and a first pipe sleeve 108, the lower alignment tube 105 includes a lower tube 109 and a second pipe sleeve 110, each group of the retaining components 101 includes a retaining frame 111, a plurality of reinforcing ribs 112 and a retaining cover 113, and each group of the support column components 103 includes a plurality of cement mixing piles 114, a plurality of bored piles 115 and a plurality of supporting steel columns 116.
[0024] According to the present specific embodiment, each group of the support column assemblies 103 is respectively fixedly connected to the corresponding enclosure assemblies 101, the upper alignment tube 104 is fixedly connected to the connecting tube 106, the lower alignment tube 105 is fixedly connected to the connecting tube 106, the first pipe sleeve 108 is fixedly connected to the upper tube 107, the upper tube 107 is fixedly connected to one group of the enclosure assemblies 101, the second pipe sleeve 110 is fixedly connected to the lower tube 109, the lower tube 109 is fixedly connected to one group of the enclosure assemblies 101, the enclosure cover 113 is fixedly connected to the enclosure frame 111, and each of the reinforcing ribs 112 is fixedly connected to the enclosure frame 111. 1 is fixedly connected, each of the supporting steel columns 116 is fixedly connected to the corresponding enclosure frame 111, each of the bored piles 115 is fixedly connected to the corresponding enclosure frame 111, and each of the cement mixing piles 114 is fixedly connected to the corresponding enclosure frame 111. The upper alignment pipe 104 and the lower alignment pipe 105 are connected to the connecting pipe 106, firstly, to correct their own horizontal limit, and secondly, to better connect the two adjacent groups of enclosure components 101. This design solves the problem that the enclosure units on the adjacent two sides are not easy to align during the installation process, and cannot be guaranteed to be in the same straight line during the enclosure process, which is prone to misalignment.
[0025] Among them, each group of the support column assemblies 103 is located below the corresponding enclosure assembly 101, the upper alignment tube 104 is located at the upper end of the connecting tube 106, and the lower alignment tube 105 is located below the connecting tube 106. Multiple groups of the support column assemblies 103 cooperate with the enclosure assembly 101 to greatly play a supporting and compressive resistance effect, and have a high safety factor.
[0026] Secondly, the first pipe sleeve 108 is located on the circumferential side of the upper pipe 107, and the upper pipe 107 is located on one side of one group of the enclosure components 101. The second pipe sleeve 110 is located on the circumferential side of the lower pipe 109, and the lower pipe 109 is located on one side of one group of the enclosure components 101. Infrared ray equipment is provided inside the first pipe sleeve 108 and the second pipe sleeve 110, and both can ensure that the connection process maintains the level when connecting two adjacent supporting steel columns 116 to avoid the situation where alignment cannot occur. The setting of the connecting pipe 106 can place the upper pipe 107 and the lower pipe 109 in the same unit, which can better connect the supporting steel columns 116 and avoid the situation where the upper pipe 107 and the lower pipe 109 cannot be aligned up and down.
[0027] At the same time, the protective cover 113 is located above the protective frame 111, each of the reinforcing ribs 112 is located on the inner side of the protective frame 111, each of the supporting steel columns 116 is located on one side of the corresponding protective frame 111, each of the bored piles 115 is located on the inner wall of the corresponding protective frame 111, and each of the cement mixing piles 114 is located on the inner wall of the corresponding protective frame 111. A plurality of the cement mixing piles 114 can be combined with the bored piles 115 to retain soil and water, and can effectively convert the pressure inside and outside the foundation pit generated by the excavation of the foundation pit into horizontal inter-column pressure through the protective frame 111 and offset it. The arched structure of the protective frame 111 can give full play to the compressive strength of reinforced concrete components, and the prefabricated structure has a high degree of industrialization. At the same time, it is green and environmentally friendly and saves construction time.
[0028] In this embodiment, the upper alignment tube 104 and the lower alignment tube 105 are connected to the connecting tube 106, firstly, to correct their own horizontal limit, and secondly, to better connect the two adjacent groups of the enclosure components 101. This design solves the problem that the enclosure units on the adjacent sides are not easy to align during the installation process, and cannot be guaranteed to be in the same straight line during the enclosure process, and are prone to misalignment. Multiple groups of the support column assemblies 103 cooperate with the enclosure assembly 101 to greatly support and resist pressure, and have a high safety factor. The first pipe sleeve 108 and the second pipe sleeve 110 are both provided with infrared ray equipment, which can ensure the connection when connecting the two adjacent support steel columns 116. The process can be kept level to avoid the misalignment. The setting of the connecting pipe 106 can place the upper pipe 107 and the lower pipe 109 in the same unit, which can better connect the supporting steel column 116 to avoid the upper pipe 107 and the lower pipe 109 being misaligned. The use of multiple cement mixing piles 114 and the bored piles 115 can be combined to retain soil and water, and the pressure inside and outside the foundation pit generated by the excavation of the foundation pit can be effectively converted into horizontal pressure between columns through the retaining frame 111 and offset. The arched structure of the retaining frame 111 can give full play to the compressive strength of reinforced concrete components. The prefabricated structure has a high degree of industrialization. At the same time, it is green and environmentally friendly and saves construction time.
[0029] The second embodiment of the present application is:
[0030] Based on the first embodiment, please refer to Figure 4-Figure 5 ,in Figure 4 It is a schematic diagram of the overall structure of the second embodiment of the utility model. Figure 5 The utility model Figure 4 Enlarged view of the local structure at point B.
[0031] The utility model provides a continuous arch type subway foundation pit enclosure structure, which also includes a fixing seat 201, a rotating ring 202 and a safety rope 203.
[0032] According to this specific embodiment, one end of the safety rope 203 is fixedly connected to the rotating ring 202 and is located at the upper end of the rotating ring 202. The rotating ring 202 is rotatably connected to the fixed seat 201 and is located above the fixed seat 201. The fixed seat 201 is fixedly connected to one of the protective covers 113 and is located above one of the protective covers 113. The safety rope 203 can be rotated well with the cooperation of the rotating ring 202, which is convenient for the staff to move to the bottom of the protective frame 111 through the safety rope 203 for survey and maintenance. The fixed seat 201 is fixed to the corresponding protective cover 113 by the staff. The specific position of the fixed seat 201 can be changed according to specific needs for easy use.
[0033] In this embodiment, the safety rope 203 can be rotated well with the cooperation of the rotating ring 202, which is convenient for the staff to move to the bottom of the protective frame 111 through the safety rope 203 for surveying and maintenance. The fixed seat 201 is fixed to the corresponding protective cover 113 by the staff, and the specific position of the fixed seat 201 can be changed according to specific needs for easy use.
[0034] What is disclosed above is only one or more preferred embodiments of the present application, and cannot be used to limit the scope of rights of the present application. Ordinary technicians in this field can understand that all or part of the processes of implementing the above embodiments and equivalent changes made according to the claims of the present application are still within the scope covered by the present application.
Claims
1. A continuous arch type subway foundation pit enclosure structure, comprising two sets of enclosure components and two sets of support column components, wherein each set of support column components is fixedly connected to the corresponding enclosure components and is respectively located below the corresponding enclosure components. It is characterized in that It also includes multiple alignment components, each group of alignment components includes an upper alignment tube, a lower alignment tube and a connecting tube, the upper alignment tube is fixedly connected to the connecting tube and is located at the upper end of the connecting tube, and the lower alignment tube is fixedly connected to the connecting tube and is located below the connecting tube.
2. The multi-arch subway foundation pit retaining structure according to claim 1, It is characterized in that The upper alignment tube includes an upper tube and a first tube sleeve, wherein the first tube sleeve is fixedly connected to the upper tube and located on the circumference of the upper tube, and the upper tube is fixedly connected to one group of the enclosure components and located on one side of one group of the enclosure components.
3. The multi-arch subway foundation pit retaining structure as claimed in claim 2, It is characterized in that The lower alignment tube includes a lower tube and a second tube sleeve, wherein the second tube sleeve is fixedly connected to the lower tube and located on the peripheral side of the lower tube, and the lower tube is fixedly connected to one group of the enclosure components and located on one side of one group of the enclosure components.
4. The multi-arch subway foundation pit retaining structure as claimed in claim 3, It is characterized in that Each group of the enclosure components includes an enclosure frame, a plurality of reinforcing ribs and an enclosure cover. The enclosure cover is fixedly connected to the enclosure frame and is located above the enclosure frame. Each of the reinforcing ribs is fixedly connected to the enclosure frame and is located on the inner side of the enclosure frame.
5. The multi-arch subway foundation pit retaining structure as claimed in claim 4, It is characterized in that Each group of the support column assemblies includes a plurality of cement mixing piles, a plurality of bored cast-in-place piles and a plurality of support steel columns, each of the support steel columns is respectively fixedly connected to the corresponding enclosure frame and is respectively located on one side of the corresponding enclosure frame, each of the bored cast-in-place piles is respectively fixedly connected to the corresponding enclosure frame and is respectively located on the inner wall of the corresponding enclosure frame, and each of the cement mixing piles is respectively fixedly connected to the corresponding enclosure frame and is respectively located on the inner wall of the corresponding enclosure frame.
6. The multi-arch subway foundation pit retaining structure according to claim 5, It is characterized in that The continuous arch type subway foundation pit retaining structure also includes a fixed seat, a rotating ring and a safety rope, one end of the safety rope is fixedly connected to the rotating ring and is located at the upper end of the rotating ring, the rotating ring is rotatably connected to the fixed seat and is located above the fixed seat, and the fixed seat is fixedly connected to one of the retaining covers and is located above one of the retaining covers.