Welding fixture for building construction
By introducing the cooperative operation of the cylinder and push rod into the welding fixture, combined with the gas flow controlled by the switch, the problem of inconvenience in removing items from the existing welding fixture is solved, and the clamping efficiency and production efficiency of the welding fixture are improved.
Patent Information
- Application Number
- CN202323588401.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2033-12-27
AI Technical Summary
Existing welding fixtures used in building construction require frequent rotation of the screw during use, which makes it inconvenient to remove welded items and reduces production efficiency.
A welding fixture including a clamping mechanism is designed. The upper clamping mold is lowered and collected through the cylinder, and the upper clamping mold and the lower clamping mold are clamped and closed through the lifting operation of the push rod and the cylinder. Release, use the switch to control the gas flow to achieve the movement and clamping of the clamp.
The coordinated operation of the cylinder and push rod is realized, which improves the clamping efficiency and production efficiency of the welding fixture, and facilitates the removal and position movement of welded items.
Smart Images

Figure CN221833660U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction equipment, in particular to a welding clamp for building construction. Background Art
[0002] Welding fixtures for construction are tools used to fix and connect metal components during construction. They are usually made of metal materials and have specific shapes and structures that can help welders stably maintain the position of the workpiece during welding and ensure the accuracy and quality of the welded joints. Welding fixtures can help welders correctly position and fix the workpieces to be welded in the required position. This is very important to ensure the accuracy and consistency of welded joints, especially in large structures and high-strength welding. In some welding applications, specific gaps and angles need to be maintained between the workpieces. Welding fixtures can help control these parameters to ensure the quality and durability of welded joints.
[0003] A Chinese patent with authorization announcement number CN210615599U discloses a clamp for rapid welding for construction, including a base and a frame, a first connecting rod and a second connecting rod are connected between the base and the frame, one end of the first connecting rod is rotatably connected to the frame through a hinge, and the other end is fixedly connected to the base, one end of the second connecting rod is rotatably connected to the base through a hinge, and the other end is detachably connected to the frame through a locking member, a clamping member is inserted into the base toward the frame, and a clamping portion corresponding to the clamping member is provided toward the base for clamping the workpiece to be processed with the clamping member. When using the device, the staff needs to frequently turn the screw to tighten the clamp, which is inconvenient to remove the welded objects, thereby reducing production efficiency. Utility Model Content
[0004] In view of this, the utility model provides a welding clamp for construction, which can not only lower the upper clamping mold through the cylinder to bring the upper clamping mold and the lower clamping mold together to clamp the objects in the mold for welding, but also switch the cylinder to make the push rod rise and fall, so as to move the upper clamping mold connected to the push rod.
[0005] In order to solve the above technical problems, the utility model provides a welding clamp for construction, including a clamping mechanism, the clamping mechanism includes a fixed base, a lower clamping mold is arranged on the fixed base, a support column is arranged on one side of the lower clamping mold, a fixed plate is arranged on the support column, two cylinders are symmetrically arranged on the fixed plate, push rods are arranged on the cylinders, a connecting block is arranged on the push rods, an upper clamping mold is arranged on the connecting block, a switch is arranged on the side of the fixed plate, a pull rod is arranged on the switch, handles and blocking blocks are respectively arranged at both ends of the pull rod, air intake pipes are arranged on the top of the two cylinders, a T-shaped connecting pipe is arranged on the air intake pipe, an air duct is arranged on the T-shaped connecting pipe, a bracket is arranged on the side of the support column, a gas tank is arranged on the bracket, and an air injection pipe is arranged on the gas tank, the upper clamping mold is moved by pushing the push rod by the cylinder, so that the object is clamped between the upper clamping mold and the lower clamping mold.
[0006] The lower clamping mold is arranged on the upper base surface of the fixed base, the support column is arranged on the upper base surface of the fixed base and the side base surface is connected to the side base surface of the clamping mold, the fixed plate is arranged on the upper base surface of the support column, and the lower clamping mold is installed on the fixed base to assist in clamping the object.
[0007] The cylinder is arranged on the upper base surface of the fixed plate, one end of the push rod is arranged on the output end of the cylinder, and the other end passes through the fixed plate, one end of the push rod is connected to the upper base surface of the connecting block, and the lower base surface of the connecting block is connected to the upper base surface of the upper clamping mold. The upper clamping mold is pushed to move by the push rod to clamp the object.
[0008] The switch is arranged on the side base surface of the fixed plate, the pull rod is arranged at the rotation position of the switch, the handle is arranged at the top end of the pull rod, and the blocking block is arranged at the tail end of the pull rod. The gas flows in the pipeline through the switch.
[0009] The bracket is arranged on the side base surface of the support column, the gas tank is fixedly arranged on the bracket, one end of the gas injection pipe is arranged on the upper base surface of the gas tank, and the gas tank is supported and fixed by the bracket.
[0010] The other end of the air injection pipe is arranged on the side base surface of the switch, one end of the air bleed pipe is connected to the upper base surface of the switch, and the other end is connected to the T-shaped connecting pipe, both ends of the T-shaped connecting pipe are respectively connected to one end of the intake pipe, and the other end of the intake pipe is connected to the cylinder. The T-shaped connecting pipe diverts the airflow to inflate the two cylinders.
[0011] In summary, compared with the prior art, the present application includes at least one of the following beneficial technical effects:
[0012] 1. When the utility model is used, the gas cylinder is supplied with gas through the gas tank, so that the push rod in the cylinder is pushed, and the push rod drives the upper clamping mold to move, so that the upper clamping mold and the lower clamping mold are brought together to clamp the object.
[0013] 2. When the utility model is used, the air intake is controlled by the switch, the pull rod is pulled down to allow the air to enter the cylinder through the air pipe, and the pull rod is lifted to allow the air to return to the air tank through the air tank.
[0014] 3. When the utility model is used, the gas cylinder is installed through the bracket, so that the gas cylinder is fixed on the equipment and gas is supplied to the gas cylinder. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0016] Figure 2 This is a schematic diagram of the overall structure of the utility model;
[0017] Figure 3 It is a schematic diagram of the overall structure of the utility model from a top view;
[0018] Figure 4 It is a front view cross-sectional structural schematic diagram of the utility model.
[0019] Explanation of the reference numerals: 100, clamping mechanism; 101, fixed base; 102, lower clamping mold; 103, support column; 104, fixed plate; 105, cylinder; 106, push rod; 107, connecting block; 108, upper clamping mold; 109, switch; 110, pull rod; 111, handle; 112, blocking block; 113, air inlet pipe; 114, T-type connecting pipe; 115, air duct; 116, bracket; 117, gas tank; 118, air injection pipe. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical scheme and advantages of the embodiment of the utility model clearer, the following will be combined with the appended drawings of the embodiment of the utility model. Figure 1-4 , the technical scheme of the embodiment of the utility model is clearly and completely described. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments. Based on the described embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the utility model.
[0021] According to one embodiment of the utility model, Figure 1 and Figure 3As shown: This embodiment provides a welding fixture for construction, including a clamping mechanism 100, the clamping mechanism 100 includes a fixed base 101, a lower clamping mold 102 is provided on the fixed base 101, a support column 103 is provided on one side of the lower clamping mold 102, a fixed plate 104 is provided on the support column 103, two cylinders 105 are symmetrically provided on the fixed plate 104, each of the cylinders 105 is provided with a push rod 106, a connecting block 107 is provided on the push rod 106, an upper clamping mold 108 is provided on the connecting block 107, a switch 109 is provided on the side of the fixed plate 104, and the switch 109 is provided on the side of the fixed plate 104. A pull rod 110 is provided on 9, and handles 111 and blocking blocks 112 are provided at both ends of the pull rod 110 respectively. An air inlet pipe 113 is provided on the top of the two cylinders 105, and a T-shaped connecting pipe 114 is provided on the air inlet pipe 113, and an air duct 115 is provided on the T-shaped connecting pipe 114. A bracket 116 is provided on the side of the support column 103, and a gas tank 117 is provided on the bracket 116. The gas tank 117 is provided with an air injection pipe 118, and the upper clamping mold 108 is moved by pushing the push rod 106 through the cylinder 105, so that the object is clamped between the upper clamping mold 108 and the lower clamping mold 102.
[0022] like Figure 2 and Figure 4As shown, the lower clamping mold 102 is arranged on the upper base surface of the fixed base, the support column 103 is arranged on the upper base surface of the fixed base and the side base surface is connected to the side base surface of the clamping mold 102, and the fixed plate 104 is arranged on the upper base surface of the support column. The lower clamping mold 102 is installed on the fixed base to assist in clamping the object. The cylinder 105 is arranged on the upper base surface of the fixed plate 104, one end of the push rod 106 is arranged at the output end of the cylinder 105, and the other end passes through the fixed plate 104. One end of the push rod 106 is connected to the upper base surface of the connecting block 107, and the lower base surface of the connecting block 107 is connected to the upper base surface of the upper clamping mold 108. The upper clamping mold 108 is pushed by the push rod 106 to move and clamp the object. The switch 109 is arranged on the side base surface of the fixed plate 104, the pull rod 110 is arranged at the rotation position of the switch 109, the handle 111 is arranged at the top of the pull rod 110, and the blocking block 112 is arranged at the tail end of the pull rod 110. The switch 109 controls the gas flow in the pipeline, and the blocking block 112 is used to limit the position of the pull rod 110, so that one end of the pull rod 110 is fixed to one side of the rotation position of the switch 109. The bracket 116 is arranged on the side base surface of the support column 103, the gas tank 117 is fixedly arranged on the bracket 116, one end of the gas injection pipe 118 is arranged on the upper base surface of the gas tank 117, and the gas tank 117 is supported and fixed by the bracket 116. The other end of the air injection pipe 118 is set on the side base surface of the switch 109, one end of the air duct 115 is connected to the upper base surface of the switch 109, and the other end is connected to the T-shaped connecting pipe 114. The two ends of the T-shaped connecting pipe 114 are respectively connected to one end of the intake pipe 113, and the other end of the intake pipe 113 is connected to the cylinder 105. The T-shaped connecting pipe 114 diverts the airflow to inflate the two cylinders 105.
[0023] The method of using the utility model is as follows: when welding an object to be welded, the object is placed on the lower clamping mold 102, and then the pull rod 110 is pulled downward to allow the gas in the gas tank 117 to pass into the cylinder 105 through the gas tank 117, and the push rod 106 is pushed downward by the gas to make the upper clamping mold 108 move closer to the lower clamping mold 102, and the object is clamped by the upper clamping mold 108 and the lower clamping mold 102 that are brought closer together, and then the object is welded. After the welding is completed, the pull rod 110 is lifted to allow the air flow to return to the gas tank 117, so that the push rod 106 is retracted into the cylinder 105, and the upper clamping mold 108 is raised when the push rod 106 is retracted, and then the welded object is taken out.
Claims
1. A welding fixture for construction, comprising a clamping mechanism (100), characterized in that: The clamping mechanism (100) comprises a fixed base (101), a lower clamping mold (102) is provided on the fixed base (101), a support column (103) is provided on one side of the lower clamping mold (102), a fixed plate (104) is provided on the support column (103), two cylinders (105) are symmetrically provided on the fixed plate (104), each of the cylinders (105) is provided with a push rod (106), a connecting block (107) is provided on the push rod (106), an upper clamping mold (108) is provided on the connecting block (107), and a side of the fixed plate (104) is provided with a support column (103). A switch (109) is provided, and a pull rod (110) is provided on the switch (109), and handles (111) and blocking blocks (112) are provided at both ends of the pull rod (110), and an air intake pipe (113) is provided on the top of each of the two cylinders (105), and a T-shaped connecting pipe (114) is provided on the air intake pipe (113), and an air bleed pipe (115) is provided on the T-shaped connecting pipe (114), and a bracket (116) is provided on the side of the support column (103), and a gas tank (117) is provided on the bracket (116), and a gas injection pipe (118) is provided on the gas tank (117).
2. A welding fixture for construction as claimed in claim 1, characterized in that: The lower clamping mold (102) is arranged on the upper base surface of the fixed base, the support column (103) is arranged on the upper base surface of the fixed base and the side base surface is connected to the side base surface of the clamping mold (102), and the fixed plate (104) is arranged on the upper base surface of the support column.
3. A welding fixture for construction as claimed in claim 1, characterized in that: The cylinder (105) is arranged on the upper base surface of the fixed plate (104), one end of the push rod (106) is arranged at the output end of the cylinder (105), and the other end passes through the fixed plate (104), one end of the push rod (106) is connected to the upper base surface of the connecting block (107), and the lower base surface of the connecting block (107) is connected to the upper base surface of the upper clamping mold (108).
4. A welding fixture for construction as claimed in claim 1, characterized in that: The switch (109) is arranged on the side base surface of the fixing plate (104), the pull rod (110) is arranged at the rotation point of the switch (109), the handle (111) is arranged at the top end of the pull rod (110), and the blocking block (112) is arranged at the tail end of the pull rod (110).
5. A welding fixture for construction as claimed in claim 1, characterized in that: The bracket (116) is arranged on the side base surface of the support column (103), the gas tank (117) is fixedly arranged on the bracket (116), and one end of the gas injection pipe (118) is arranged on the upper base surface of the gas tank (117).
6. A welding fixture for construction as claimed in claim 1, characterized in that: The other end of the air injection pipe (118) is arranged on the side base surface of the switch (109), one end of the air bleed pipe (115) is connected to the upper base surface of the switch (109), and the other end is connected to the T-shaped connecting pipe (114).
7. A welding fixture for construction as claimed in claim 1, characterized in that: Both ends of the T-shaped connecting pipe (114) are respectively connected to one end of the air intake pipe (113), and the other end of the air intake pipe (113) is connected to the cylinder (105).