Device for fixing dowel bar on concrete pavement

By installing electromagnetic suction components on the road construction formwork to fix the dowel rods, the problem that the dowel rods cannot be accurately fixed in traditional construction methods is solved, the load transfer capacity and the service life of the road surface are improved, and the construction cost is reduced.

CN221837377UActive Publication Date: 2024-10-15MCC TIANGONG GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323515433.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-15
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

The traditional dowel rod construction method cannot accurately fix the dowel rod in the middle of the concrete pavement, which affects the load transfer capacity and the overall bearing capacity of the road. It is also easy to cause the dowel rod to deviate from the preset position due to concrete vibration and external interference, reducing the service life of the road.

Method used

Using a device including a fixed frame and an electromagnetic suction component, the electromagnetic suction component is installed on the road construction formwork, and the electromagnet is used to fix the dowel rod at the preset position to ensure its stability, and after the concrete solidifies, it is powered off and pulled out. Additional concrete was poured to complete the construction.

Benefits of technology

It effectively avoids the position deviation of the dowel rod, improves the load transfer capacity, and extends the service life of the concrete pavement. At the same time, due to its simple structure, easily available and recyclable materials, it reduces the construction cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221837377U_ABST
    Figure CN221837377U_ABST
Patent Text Reader

Abstract

The utility model provides a device for fixing a dowel bar of a concrete pavement, which comprises a fixing frame and an electromagnetic attraction assembly, the fixing frame is used for installing the electromagnetic attraction assembly on a road construction template, and the electromagnetic attraction assembly is used for magnetically attracting and fixing the dowel bar; the electromagnetic attraction assembly comprises a power supply device, an electromagnet and a mounting frame, the power supply device is electrically connected with the electromagnet, and the two ends of the mounting frame are connected with the fixing frame and the electromagnet respectively. According to the utility model, the problems that the dowel bar deviates from a preset position due to concrete vibration and other external interference in the concrete road construction process, so that the arrangement precision of the dowel bar is reduced, the effect of transmitting load cannot be exerted, but the pavement joint is quickly damaged due to the difference of linear expansion coefficients of steel and concrete, and the construction efficiency is reduced can be effectively solved. And the service life of the concrete pavement is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of road construction, in particular to a device for fixing a dowel rod of a concrete pavement. Background Art

[0002] Dowel bars refer to round steel bars arranged at certain intervals along the transverse joints of concrete road panels in the middle of the slab thickness to ensure effective load transfer between concrete slabs and prevent the occurrence of broken slabs and misaligned platforms. However, the traditional dowel bar construction method is to pour concrete to half the thickness of the road when pouring concrete at the transverse joints of the road, and then directly place the dowel bar on the poured concrete, and then continue to pour the upper concrete. This method cannot fix the dowel bar in the exact position in the middle of the concrete pavement, which greatly affects the load transfer capacity of the transverse joints and cannot effectively improve the overall bearing capacity of the road slab. Utility Model Content

[0003] The utility model aims to provide a device for fixing a dowel rod of a concrete pavement to solve the above-mentioned problems.

[0004] The technical solution adopted by the utility model is: a device for fixing a dowel rod of a concrete pavement, which comprises: a fixing frame and an electromagnetic suction component, wherein the fixing frame is used to install the electromagnetic suction component on a road construction template, and the electromagnetic suction component is used to magnetically fix the dowel rod.

[0005] Preferably, the electromagnetic suction assembly includes a power supply device, an electromagnet and a mounting frame, the power supply device is electrically connected to the electromagnet, and two ends of the mounting frame are respectively connected to the fixing frame and the electromagnet.

[0006] Preferably, the interior of the mounting frame is hollow, and the electromagnet is installed at the bottom end of the inner wall of the mounting frame.

[0007] Preferably, the bottom end of the mounting bracket has an arc-shaped portion, and the axis of the arc-shaped portion is parallel to the axis of the force transmission rod.

[0008] Preferably, an electromagnet circuit protection tube is provided on the fixing frame.

[0009] Preferably, the fixing frame includes a full-length support and a mounting plate, the mounting plates are fixedly mounted on both sides of the full-length support, and a plurality of mounting plates are distributed along the length direction of the full-length support, and the electromagnetic suction component is fixedly mounted on the mounting plate.

[0010] Preferably, the fixing frame comprises a stiffening support, and two ends of the stiffening support are respectively connected to the full-length support and the mounting plate to form a triangular stable support system.

[0011] Preferably, both ends of the stiffening support are provided with mutually perpendicular fitting parts.

[0012] Preferably, the fixing frame includes a clamping piece arranged at the bottom of the through-length support, and the clamping piece is used to clamp the road construction template.

[0013] The beneficial effects of the utility model are:

[0014] (1) This device can effectively prevent the dowel rod from deviating from the preset position due to concrete vibration and other external interference during the concrete road construction process, which reduces the accuracy of the dowel rod arrangement. Not only can the dowel rod fail to transfer the load, but it will quickly damage the pavement joints due to the difference in linear expansion coefficients between steel and concrete, thereby reducing the service life of the concrete pavement.

[0015] (2) The device has a simple structure, is easy to install and disassemble, and is easy to arrange. The materials are readily available and recyclable, and the construction cost is low. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a front view of an embodiment of the utility model;

[0017] Figure 2 It is a side view of an embodiment of the utility model;

[0018] Figure 3 This is a schematic diagram of the connection between the fixed frame and the road construction template in the embodiment of the utility model;

[0019] Figure 4 This is a schematic diagram of the connection between the through-length support and the clamping member in the embodiment of the utility model;

[0020] In the figure:

[0021] 100, fixing frame; 110, full-length support; 111, strip-shaped through hole; 120, mounting plate; 130, reinforcing support; 140, clamping piece; 141, bolt hole; 150, locking bolt;

[0022] 200, electromagnetic suction assembly; 210, power supply equipment; 220, electromagnet; 230, mounting frame; 231, arc-shaped portion;

[0023] 300. Road construction template;

[0024] 400, dowel rod;

[0025] 500. Electromagnet circuit protection tube. DETAILED DESCRIPTION

[0026] The technical solution of the embodiment of the utility model is described in detail below with reference to the accompanying drawings.

[0027] In the description of the embodiments of the present utility model, it should be understood that the orientation or positional relationship indicated by the terms "top", "bottom", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In the description of the present utility model, it should be noted that, unless otherwise clearly specified and limited, the terms "set" and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood by specific circumstances.

[0028] Reference Figure 1-2 , a device for fixing a dowel rod on a concrete pavement, comprising: a fixing frame 100 and an electromagnetic suction assembly 200, wherein the fixing frame 100 is used to install the electromagnetic suction assembly 200 on a road construction template 300, and the electromagnetic suction assembly 200 is used to magnetically fix the dowel rod 400. Before construction, the road construction template 300 is built, the dowel rod 400 is arranged according to the construction requirements, and the device is installed above the dowel rod 400. Since the dowel rod 400 is generally made of steel bars, the electromagnetic suction assembly 200 can attract and fix the dowel rod 400 after being powered on; then after the concrete pouring construction, the electromagnetic suction assembly 200 is powered off, and the magnetic suction force between the device and the dowel rod 400 disappears. Finally, the device is pulled out of the concrete, and concrete is poured in the hole created by the pull-out.

[0029] In this embodiment, the fixing frame 100 includes a full-length support 110, a mounting plate 120 and a clamping member 140. The full-length support 110 is arranged along the width direction of the road; the mounting plates 120 are fixedly mounted on both sides of the full-length support 110, and a plurality of the mounting plates 120 are distributed along the length direction of the full-length support 110; the electromagnetic suction assembly 200 is fixedly mounted on the mounting plate 120; the clamping member 140 is arranged at the bottom of the full-length support 110, and is used to clamp the road construction template 300. During road construction, both ends of the full-length support 110 are mounted on the road construction template 300, and the road construction template 300 provides vertical support for the full-length support 110, and the clamping member 140 is arranged at the position where the full-length support 110 overlaps with the road construction template 300, and is clamped with the road construction template 300 to prevent the full-length support 110 from moving in the horizontal direction and causing the installation position of the force transmission rod 400 to move.

[0030] The shape, position and connection method of the clip 140 with the full-length support 110 can be configured according to actual usage requirements and are not specifically limited here. The clip 140 can be fixedly connected to the full-length support 110, such as by welding, or it can be slidably connected to the full-length support 110 and fixed by a locking member to match the distance between different road construction templates 300.

[0031] To facilitate material collection and production, the clamping part 140 can be made of angle steel. The recessed parts of the angle steels at both ends of the full-length support 110 are arranged relatively to each other. One end plate of the angle steel is connected and fixed to the full-length support 110, and the other end is perpendicular to the bottom surface of the full-length support 110 and pressed against the outer side surface of the road construction template 300. The position of the full-length support 110 is fixed by the side pressing action of the two angle steels.

[0032] The angle steel can be welded and fixed with the full-length support 110, which is suitable for construction with the same road width; the angle steel and the full-length support 110 are slidably connected, which is suitable for construction with different road widths. For specific implementation, please refer to the attached Figure 4 A strip through hole 111 is set along the length direction on the full-length support 110, and a bolt hole 141 is set on the angle steel. According to different road widths, the relative positions of the bolt hole 141 and the strip through hole 111 are changed, and the locking bolt 150 is passed through the strip through hole 111 and the bolt hole 141 and locked.

[0033] In order to improve the structural stability of the device, in this embodiment, a reinforcing brace 130 is provided on the top of the mounting plate 120, and the other end of the reinforcing brace 130 is connected to the full-length brace 110, and the three form a triangular stable support system.

[0034] In order to facilitate material acquisition and production, and to facilitate the installation and fixation of the mounting plate 120 and the stiffening support 130, the full-length support 110 in this embodiment is made of I-beams, and the wing plates of the I-beams are arranged horizontally. The mounting plate 120 is placed on the top surface of the bottom wing plates of the I-beams and is welded or slidably connected. The sliding connection method is the same as the sliding connection method between the clip 140 and the full-length support 110, which will not be repeated here. The sliding connection is beneficial to changing the distribution of the electromagnetic suction assembly 200 along the length direction of the full-length support 110 according to the layout density and position of the force transmission rod 400, so that the present device is suitable for more working conditions.

[0035] To facilitate connection and fixation, the two ends of the reinforcing brace 130 in this embodiment are provided with mutually perpendicular fitting parts, one fitting part is pressed against the web of the I-beam, welded or slidably connected, and the other fitting part is welded or slidably connected to the mounting plate 120. The sliding connection method is the same as described above and will not be repeated here. The connection method of the fitting part and the mounting plate 120 is not subject to any restrictions, but it should be noted that if the mounting plate 120 is slidably connected to the I-beam to adapt to different working conditions, the fitting part should be slidably connected to the I-beam.

[0036] Reference Figure 2-3The electromagnetic suction component 200 includes a power supply device 210, an electromagnet 220 and a mounting frame 230. The power supply device 210 is electrically connected to the electromagnet 220. An electromagnet line protection tube 500 is provided on the fixing frame 100. The two ends of the mounting frame 230 are respectively connected to the fixing frame 100 and the electromagnet 220. After the electromagnet 220 is energized, it can attract and fix the force transmission rod 400.

[0037] In order to improve the attraction and fixing effect on the force transmission rod 400, the mounting frame 230 in this embodiment is configured as an internal hollow pipe, the electromagnet 220 is installed at the bottom end of the inner wall of the mounting frame 230, and an arc portion 231 with an axis parallel to the axis of the force transmission rod 400 is provided at the bottom end of the mounting frame 230 to fit the outer wall of the force transmission rod 400.

[0038] The method of using the utility model comprises the following steps:

[0039] The device is processed according to the road width and the arrangement density of the dowel rods 400; the device is fixed on the road construction template 300 according to the designed position of the transverse joint; the dowel rods 400 are transported between the device and the foundation, the position and direction of the dowel rods 400 are adjusted, and the electromagnetic suction component 200 is energized to attract and fix the dowel rods 400; the road concrete is poured, vibrated and compacted, and solidified, the electromagnetic suction component 200 is powered off to separate from the dowel rods 400, and the device is pulled out in the direction away from the dowel rods 400; concrete is poured in the hole created by the withdrawal of the device to complete the road concrete pouring construction at the transverse joint.

[0040] It is worth noting that while the device is fixing the force transmission rod 400, the concrete vibrator must not touch the device and the force transmission rod 400 to prevent the position of the force transmission rod 400 from shifting; after the device is removed from the road concrete, when pouring additional concrete, the concrete vibration time should be carefully controlled to prevent excessive vibration from causing the force transmission rod 400 to sink and shift.

[0041] Compared with the prior art, the beneficial effects of the utility model are:

[0042] (1) The device can effectively prevent the dowel rod 400 from deviating from the preset position due to concrete vibration and other external interference during the concrete road construction process, which reduces the layout accuracy of the dowel rod 400. Not only can the dowel rod 400 not play a role in transferring loads, but it will quickly damage the pavement joints due to the difference in linear expansion coefficients between steel and concrete, thereby reducing the service life of the concrete pavement.

[0043] (2) The device has a simple structure, is easy to install and disassemble, and is easy to arrange. The materials are readily available and recyclable, and the construction cost is low.

[0044] The above are preferred implementations of the present utility model. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present utility model. These improvements and modifications should also be regarded as the protection scope of the present utility model.

Claims

1. A device for fixing a dowel rod on a concrete pavement, characterized in that: include: A fixing frame and an electromagnetic suction component, wherein the fixing frame is used to install the electromagnetic suction component on a road construction template, and the electromagnetic suction component is used to magnetically fix the force transmission rod.

2. The device for fixing a dowel rod of a concrete pavement according to claim 1, characterized in that: The electromagnetic suction component comprises a power supply device, an electromagnet and a mounting frame. The power supply device is electrically connected to the electromagnet, and two ends of the mounting frame are respectively connected to the fixing frame and the electromagnet.

3. The device for fixing a dowel rod of a concrete pavement according to claim 2, characterized in that: The interior of the mounting frame is hollow, and the electromagnet is installed at the bottom end of the inner wall of the mounting frame.

4. A device for fixing a dowel rod of a concrete pavement according to claim 2 or 3, characterized in that: The bottom end of the mounting frame has an arc-shaped portion, and the axis of the arc-shaped portion is parallel to the axis of the force transmission rod.

5. The device for fixing a dowel rod of a concrete pavement according to claim 4, characterized in that: An electromagnet circuit protection tube is arranged on the fixing frame.

6. A device for fixing a dowel bar on a concrete pavement according to any one of claims 1-3 and 5, characterized in that: The fixing frame comprises a full-length support and a mounting plate. The mounting plates are fixedly arranged on both sides of the full-length support and are distributed in a plurality along the length direction of the full-length support. The electromagnetic suction assembly is fixedly arranged on the mounting plate.

7. The device for fixing a dowel rod of a concrete pavement according to claim 6, characterized in that: The fixing frame includes a stiffening support, and two ends of the stiffening support are respectively connected to the full-length support and the mounting plate to form a triangular stable support system.

8. The device for fixing a dowel rod on a concrete pavement according to claim 7, characterized in that: Both ends of the reinforcing support are provided with mutually perpendicular fitting parts.

9. A device for fixing a dowel rod of a concrete pavement according to claim 7 or 8, characterized in that: The fixing frame includes a clamping piece arranged at the bottom of the through-length support, and the clamping piece is used for clamping the road construction template.