Connecting component for suspended ceiling transfer floor and building structural beam
Through the combined structure of clamping plates, connecting frames and clamping components, the safety hazards and accuracy problems of the welding connection between the ceiling conversion layer and the building structural beam are solved, rapid installation and efficient dismantling are achieved, and the material utilization rate and construction safety are improved. sex.
Patent Information
- Application Number
- CN202221839830.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-16
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2032-07-16
AI Technical Summary
The existing welding connection method between the ceiling conversion layer and the building structural beam has fire safety hazards, low installation accuracy, difficulty in reusing the materials after disassembly, and low utilization rate.
It adopts a combined structure of clamping plates, connecting frames, locking blocks and clamping components. Through the locking components and clamping components, the ceiling conversion layer and the building structural beam can be quickly installed and disassembled. Welding connections are avoided and locking screws and lock nuts are used to improve the efficiency. Fixed stability, clamps and support rods enable multi-angle installation.
It realizes welding-free connection, improves the installation accuracy and the utilization rate of materials after disassembly, reduces fire hazards and construction costs, and enhances the convenience of operation and fixation stability.
Smart Images

Figure CN221837819U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building construction technology, and in particular to a connecting component between a suspended ceiling transfer layer and a building structure beam. Background Art
[0002] In modern society, most houses will have a ceiling transfer layer installed under the structural beams after construction is completed. The ceiling transfer layer is used to install air-conditioning ducts, ventilation ducts, electrical wires, etc. At the same time, a ceiling is installed under the ceiling transfer layer to improve the overall aesthetics of the interior.
[0003] At present, the suspended ceiling transfer layer includes multiple longitudinal beams and a transverse beam fixed between two adjacent longitudinal beams. The suspended ceiling transfer layer and the building steel structure beams (I-beams) are usually connected by welding. However, the welding connection poses a fire safety hazard at the construction site. At the same time, each connection point is installed in a non-standard manner with low precision. When the renovation and demolition are required, a large amount of construction waste is easily generated, and the reuse rate is low. Utility Model Content
[0004] In order to reduce the risk of fire safety hazards, improve the installation accuracy of the suspended ceiling transfer layer and the reuse rate of building materials after renovation and demolition, the present application provides a connecting component between the suspended ceiling transfer layer and the building structure beam.
[0005] The present application provides a connecting member between a suspended ceiling transfer layer and a building structure beam, which adopts the following technical solution:
[0006] A connecting component for a suspended ceiling conversion layer and a building structure beam, comprising two clamping plates symmetrically arranged on both sides of an I-beam, a connecting frame fixedly connected to the clamping plates, a locking block arranged below the I-beam, a locking component arranged inside the locking block for simultaneously fixing the two connecting frames, and a clamping component arranged below the locking block for installing the suspended ceiling conversion layer.
[0007] By adopting the above technical scheme, when the construction personnel connect the suspended ceiling conversion layer to the building structure beam, they first clamp the two clamping plates to the two sides of the I-beam beam respectively, and then fix the two connecting frames to the locking block on the side close to each other through the locking assembly, and then install the suspended ceiling conversion layer under the locking block through the clamping assembly, and repeat the above process to complete the installation of the suspended ceiling conversion layer as a whole and the building structure beam; conversely, when the construction personnel dismantle the suspended ceiling conversion layer, they first release the fixed state of the locking assembly, and then remove the clamping plates from the two sides of the I-beam beam, and then release the connection of the clamping assembly to disconnect the connection between the suspended ceiling conversion layer and the building structure beam, thereby completing the dismantling of the suspended ceiling conversion layer; the construction personnel can realize the rapid installation and dismantling of the suspended ceiling conversion layer and the building structure beam through the locking assembly and the clamping assembly, and it is not easy to cause fire safety hazards, and it is not easy to generate material waste after the suspended ceiling conversion layer is dismantled, thereby improving the installation accuracy of the suspended ceiling conversion layer and the reuse rate of building materials after renovation and dismantling.
[0008] Optionally, the locking assembly includes two locking plates respectively fixed on the sides of the two connecting frames close to each other, a locking screw threadedly connected to the top of the locking block, and a pressing plate arranged below the locking screw;
[0009] The locking block is provided with a locking groove in the horizontal direction, the two locking plates are arranged in the height direction, and the two locking plates are both inserted into the locking groove, the pressing plate is located in the locking groove, and the pressing plate abuts against the upper locking plate.
[0010] By adopting the above technical solution, when the construction personnel fix the locking block and the connecting frame through the locking assembly, they first insert the two locking plates into the locking grooves, and then rotate the locking screw. The locking screw drives the pressure plate to move downward so that the lower surface of the pressure plate fits tightly with the upper locking plate, thereby completing the fixation of the locking block and the connecting frame. The construction personnel only need to rotate the locking screw to complete the fixation of the locking block and the connecting frame, which has the effect of facilitating the operation of the construction personnel.
[0011] Optionally, the locking screw is rotatably connected to the pressure plate.
[0012] By adopting the above technical solution, when the construction personnel rotate the locking screw, after the pressure plate abuts against the locking plate, the locking screw continues to be rotated, and the locking screw will apply a force on the pressure plate in the direction close to the locking plate, and it is not easy to apply a rotational force to the pressure plate, thereby making it easier for the construction personnel to rotate the locking screw, and at the same time having the effect of making the pressure plate and the locking plate fit more closely.
[0013] Optionally, a locking nut is sleeved on the outer side wall of the locking screw, and the locking nut abuts against the upper surface of the connecting block.
[0014] By adopting the above technical solution, after the construction personnel complete the fixation of the locking block and the locking plate, they tighten the anti-loosening nut. The anti-loosening nut has a certain self-locking property, so that the locking screw is not easy to loosen after the locking assembly is vibrated, which has the effect of improving the stability of the locking screw.
[0015] Optionally, a plurality of protrusions are fixedly provided on the bottom wall of the locking groove and on the upper and lower surfaces of the locking plate.
[0016] By adopting the above technical solution, when construction workers fix the locking plate, the lower surface of the pressure plate abuts against the upper surface of the upper locking plate, the protrusion of the upper locking plate abuts against the protrusion of the lower locking plate, and the protrusion on the lower surface of the lower locking plate abuts against the protrusion on the bottom wall of the locking groove, which has the effect of preventing the locking plate from slipping and improves the stability of the locking plate.
[0017] Optionally, the clamping assembly includes a clamping hoop spaced below the locking block and a support rod disposed between the clamping hoop and the locking block; the support rod is fixedly connected to the clamping hoop.
[0018] By adopting the above technical solution, when construction workers install the ceiling conversion layer under the locking block through the clamping assembly, they only need to open the clamp, install the longitudinal beam or transverse beam of the ceiling conversion layer into the clamp, and then lock the clamp. The clamp connection has the effects of convenient operation, complete disassembly, and no damage to the structure of the ceiling conversion layer, and allows construction workers to complete the installation of the ceiling conversion layer without welding, thereby improving the reuse rate of materials.
[0019] Optionally, the support rod is rotatably connected to the locking block.
[0020] By adopting the above technical solution, when installing the ceiling transition layer, the construction workers first rotate the support rod to keep the multiple clamps on the horizontal beam or longitudinal beam in the same ceiling transition layer at the same angle, and then connect the longitudinal beam or horizontal beam on the ceiling transition layer to the clamp; the rotating connection facilitates the adjustment of the rotation angle of the clamp, thereby making the construction workers' operation more efficient.
[0021] Optionally, the clamping plate is an arc-shaped plate, and the arc-shaped surface of the arc-shaped plate abuts against the surface of the I-beam.
[0022] By adopting the above technical solution, the arc surface of the clamping plate is matched with the arc surface of the I-beam, increasing the contact area between the clamping plate and the I-beam, thereby improving the friction between the clamping plate and the I-beam, making the clamping plate less likely to slip.
[0023] In summary, the present application includes at least one of the following beneficial technical effects:
[0024] 1. When connecting the building steel beam and the ceiling transfer layer, the construction workers lock the card plate through the locking component, and then connect the ceiling transfer layer to the locking block through the clamping component. The connecting components are all detachable, and there is no need to use welding methods, which is not easy to cause fire hazards and improves the installation accuracy. At the same time, the building materials after dismantling can be reused, which improves the reuse rate of materials;
[0025] 2. Multiple protrusions are fixed in the locking plate and the locking groove, which increase the friction between the two locking plates and between the locking plate and the locking groove, making it difficult for the locking plate to slip off;
[0026] 3. The support rod and the locking block are rotatably connected, so construction workers can keep multiple clamps on the horizontal beam or longitudinal beam in the same ceiling conversion layer at the same angle, thereby realizing multi-angle and multi-directional installation of the ceiling conversion layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 is a schematic diagram showing the structure of the connection member between the ceiling transfer layer and the building structure beam in this embodiment;
[0028] Figure 2 It is a partial structural cross-sectional view showing the connection components between the ceiling transfer layer and the building structure beams;
[0029] Figure 3 It is a schematic diagram of the exploded structure showing the connection components between the suspended ceiling transfer layer and the building structure beams.
[0030] Explanation of the reference numerals: 1. suspended ceiling transition layer; 11. horizontal beam; 12. longitudinal beam; 2. I-beam; 3. clamping plate; 4. connecting frame; 5. locking block; 51. locking groove; 6. locking assembly; 61. locking plate; 62. protrusion; 63. pressure plate; 64. locking screw; 65. knob; 66. anti-loosening nut; 7. clamping assembly; 71. clamp; 72. support rod. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-3 This application is described in further detail.
[0032] The present application embodiment discloses a connecting member for a ceiling transfer layer and a building structure beam. Figure 1 The ceiling conversion layer 1 includes a plurality of transverse beams 11 and a plurality of longitudinal beams 12 .
[0033] Reference Figure 1 and Figure 2The connecting member includes two clamping plates 3 symmetrically arranged on both sides of the I-beam 2. The clamping plates 3 are arc-shaped plates, and the arc surface of the arc-shaped plates matches the arc surface of the I-beam 2. A connecting frame 4 is fixed on the clamping plate 3, and the connecting frame 4 abuts against the bottom wall and side wall of the I-beam 2. Locking blocks 5 are arranged at intervals below the I-beam 2, and a locking assembly 6 is arranged inside the locking block 5. The locking assembly 6 is used to fix the two connecting frames 4. A clamping assembly 7 is arranged below the locking block 5, and the clamping assembly 7 is used to install the ceiling conversion layer 1.
[0034] When installing the suspended ceiling conversion layer 1 on the building structure beam, the construction personnel firstly abut the two clamping plates 3 against the I-beam 2 respectively, then fix the locking block 5 with the two connecting frames 4 at the same time through the locking assembly 6, and then connect the suspended ceiling conversion layer 1 with the locking block 5 through the clamping assembly 7. Conversely, when the suspended ceiling conversion layer 1 needs to be removed, the connection between the suspended ceiling conversion layer 1 and the locking block 5 is first disconnected through the clamping assembly 7, so that the two clamping plates 3 move in opposite directions, so that the clamping plates 3 leave the I-beam 2, and then the locking assembly 6 is operated to disconnect the connection frame 4 from the locking block 5, and the removal of the suspended ceiling conversion layer 1 can be completed.
[0035] Reference Figure 2 and Figure 3 The locking assembly 6 includes two locking plates 61 respectively fixed on the sides of the two connecting frames 4 close to each other. The two locking plates 61 are arranged in the height direction. The locking block 5 is provided with a locking groove 51. The two locking plates 61 are simultaneously inserted into the locking groove 51. A plurality of protrusions 62 are fixed on the upper and lower surfaces of the locking plates 61 and the inner bottom wall of the locking groove 51. The protrusions 62 are used to prevent the locking plates 61 from slipping and improve the stability of the locking plates 61. A pressing plate 63 is abutted on the top of one of the locking plates 61 located at the top. The pressing plate 63 is located in the locking groove 51. A locking screw 64 is rotatably connected to the top of the pressing plate 63. The locking screw 64 is threadedly connected to the locking block 5. One end of the locking screw 64 passes through the locking block 5 and is located outside the locking block 5. A knob 65 is fixed on one end of the locking screw 64 located outside the locking block 5. A locking nut 66 is sleeved on the locking screw 64. The locking nut 66 abuts against the upper surface of the locking block 5.
[0036] When the construction personnel fix the connecting frame 4 through the locking assembly 6, they first insert the two locking plates 61 into the locking grooves 51, so that the two locking plates 61 abut against each other, and make the two locking plates 61 and the locking plates 61 and the protrusions 62 on the bottom wall of the locking grooves 51 abut against each other, and then turn the knob 65 to lock the screw 64, and the locking screw 64 drives the pressure plate 63 to move in the direction close to the locking plate 61. After the pressure plate 63 abuts against the upper locking plate 61, the locking screw 64 continues to be turned, and the locking screw 64 always gives the pressure plate 63 a downward force, so that the locking block 5 and the locking plate 61 fit tightly, and then tighten the anti-loosening nut 66 to complete the fixing of the connecting frame 4. Conversely, when the construction personnel need to remove the connecting frame 4, they only need to loosen the anti-loosening nut 66, and then turn the knob 65. The knob 65 drives the locking screw 64 to rotate, and the locking screw 64 drives the pressure plate 63 to move upward, and then the construction personnel move the connecting frame 4 in the opposite direction to complete the removal of the connecting frame 4.
[0037] Reference Figure 2 and Figure 3 The clamping assembly 7 includes a clamp 71 spaced below the locking block 5 , a support rod 72 is provided between the clamp 71 and the locking block 5 , one end of the support rod 72 is fixedly connected to the clamp 71 , and the other end is rotatably connected to the locking block 5 .
[0038] When the construction personnel install the ceiling conversion layer 1 under the locking block 5, they first rotate the support rod 72 to keep the multiple clamps 71 on the cross beam 11 or the longitudinal beam 12 in the same ceiling conversion layer 1 at the same angle, then open the clamp 71, and abut the cross beam 11 or the longitudinal beam 12 of the ceiling conversion layer 1 against the inner wall of the clamp 71, and then lock the clamp 71 to achieve the connection between the ceiling conversion layer 1 and the locking block 5; otherwise, the connection between the ceiling conversion layer 1 and the locking block 5 can be released.
[0039] The implementation principle of a connecting member of a suspended ceiling conversion layer and a building structure beam in the embodiment of the present application is as follows: when installing the suspended ceiling conversion layer 1 on the building structure beam, the construction personnel firstly abut the clamping plate 3 against the arc surface of the I-beam beam 2, then insert the two locking plates 61 into the locking groove 51, and rotate the knob 65 to fix the locking plate 61, then tighten the anti-loosening nut 66, and then rotate the support rod 72 to keep the multiple clamps 71 on the cross beam 11 or the longitudinal beam 12 in the same suspended ceiling conversion layer 1 at the same angle, and then connect the longitudinal beam 12 or the cross beam 11 on the suspended ceiling conversion layer 1 with the clamp 71; On the contrary, when the construction personnel remove the suspended ceiling conversion layer 1 from the building structure beam, they first loosen the anti-loosening nut 66, then rotate the knob 65 in the opposite direction, then pull out the locking plate 61 from the locking groove 51, and then open the clamp 71, and take the suspended ceiling conversion layer 1 out of the clamp 71, and the removal of the suspended ceiling conversion layer 1 is completed; the construction personnel can realize the rapid installation and disassembly of the suspended ceiling conversion layer 1 and the building structure beam through the locking component 6 and the clamping component 7, which is not easy to cause fire safety hazards, and is not easy to generate material waste after removal, thereby improving the installation accuracy of the suspended ceiling conversion layer 1 and the reuse rate of building materials after modification and removal.
[0040] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A connecting member for a ceiling transfer layer and a building structure beam, characterized in that: The invention comprises two clamping plates (3) symmetrically arranged on both sides of an I-beam (2), a connecting frame (4) fixedly connected to the clamping plates (3), a locking block (5) arranged below the I-beam (2), a locking assembly (6) arranged inside the locking block (5) for simultaneously fixing the two connecting frames (4), and a clamping assembly (7) arranged below the locking block (5) for installing a suspended ceiling conversion layer (1).
2. The connecting member for a suspended ceiling transfer layer and a building structure beam according to claim 1, characterized in that: The locking assembly (6) comprises two locking plates (61) respectively fixed on the sides of the two connecting frames (4) close to each other, a locking screw (64) threadedly connected to the top of the locking block (5), and a pressing plate (63) arranged below the locking screw (64); The locking block (5) is provided with a locking groove (51) in the horizontal direction, the two locking plates (61) are arranged in the height direction, and the two locking plates (61) are both inserted into the locking groove (51), the pressing plate (63) is located in the locking groove (51), and the pressing plate (63) abuts against the upper locking plate (61).
3. The connecting member for connecting a suspended ceiling transfer layer to a building structure beam according to claim 2, characterized in that: The locking screw (64) is rotationally connected to the pressing plate (63).
4. The connecting member for connecting a suspended ceiling transfer layer to a building structure beam according to claim 2, characterized in that: A locking nut (66) is sleeved on the outer side wall of the locking screw (64), and the locking nut (66) abuts against the upper surface of the locking block (5).
5. The connecting member for connecting a suspended ceiling transfer layer to a building structure beam according to claim 2, characterized in that: A plurality of protrusions (62) are fixedly provided on the inner bottom wall of the locking groove (51) and on the upper and lower surfaces of the locking plate (61).
6. The connecting member for connecting a suspended ceiling transfer layer to a building structure beam according to claim 1, characterized in that: The clamping assembly (7) comprises a clamp (71) arranged at intervals below the locking block (5), and a support rod (72) arranged between the clamp (71) and the locking block (5); the support rod (72) is fixedly connected to the clamp (71).
7. The connecting member for connecting a suspended ceiling transfer layer to a building structure beam according to claim 6, characterized in that: The support rod (72) is rotatably connected to the locking block (5).
8. A connecting member between a suspended ceiling transfer layer and a building structure beam according to any one of claims 1 to 7, characterized in that: The clamping plate (3) is an arc-shaped plate, and the arc-shaped surface of the arc-shaped plate abuts against the surface of the I-beam (2).