Steel pipe structure for weak surrounding rock tunnel body long pipe shed
By adopting the threaded connection structure of the first-end screw-in pipe and the connecting pipe during the construction of the weak surrounding rock tunnel, and using the horn guide pipe and sealing gasket to realize the rapid docking of the steel pipe, the problem of difficult connection of the steel pipe in the soil is solved, and the construction efficiency and Support stability.
Patent Information
- Application Number
- CN202420491927.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-14
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-03-14
AI Technical Summary
During the construction of tunnels in soft surrounding rock, there are difficulties in connecting steel pipes when they are screwed into the soil, resulting in low construction efficiency.
A steel pipe structure including a screw-in pipe at the first end and a connecting pipe is designed. An internally threaded pipe section is set at the end of the screw-in pipe at the first end, and an externally threaded pipe section is set at the end of the connecting pipe. Threaded connection is achieved through a horn guide pipe, and pipe piles are used for drilling. The device connects quickly.
It achieves fast and reliable connection between steel pipes and improves the construction efficiency and stability of long pipe sheds in tunnels.
Smart Images

Figure CN221838352U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of tunnel construction, in particular to a steel pipe structure for a long pipe shed of a soft surrounding rock tunnel. Background Art
[0002] During tunnel construction, the pipe shed construction method is generally used to support the excavated tunnel. When the surrounding rock geology of the construction site is loose, the geological structure of the tunnel entrance is loose and it is difficult to form a hole. During construction, the pipe drilling process can be used. During construction, the single-number steel pipe is first set up and grouting is performed, and then the double-number steel pipe is set up to check the grouting quality of the steel pipe, and then the drilling process is changed to save costs.
[0003] The steel pipes are screwed into the pile drilling equipment so that they are arranged circumferentially along the edge of the tunnel contour to form a pipe shed. The middle area of the pipe shed is the excavation area of the tunnel. The stopper steel pipe is screwed into the steel pipe, and steel bars and grouting are introduced into the steel pipe to eventually form a stable pipe shed. The above-mentioned steel pipe is a segmented structure, and the ends of the steel pipes screwed into the soil need to be connected to form an integral pipe structure to facilitate subsequent grouting operations so that the entire pipe is filled with cement slurry. Therefore, it is a technical problem for the steel pipes to be screwed into the soil for docking. Utility Model Content
[0004] In view of the above shortcomings of the prior art, the purpose of the utility model is to provide a steel pipe structure for a long pipe shed for a soft surrounding rock tunnel, which can facilitate the docking between the ends of the steel pipes screwed into the soil, facilitate the construction of the pipe shed, and improve the construction efficiency.
[0005] In order to achieve the above-mentioned purpose and other related purposes, the utility model provides a steel pipe structure for a long pipe shed of a soft surrounding rock tunnel, comprising:
[0006] The head end is screwed into the pipe, and the tail end is connected to the pipe pile drilling equipment and screwed into the soil;
[0007] A connecting pipe, one end of which is connected to the tail end of the pipe screwed into the head end;
[0008] The tail end pipe mouth of the head end screw-in pipe is provided with an internal threaded pipe section, one end of the connecting pipe is provided with an external threaded pipe section, the pipe mouth of the external threaded pipe section is provided with a trumpet guide pipe, the small-sized end pipe mouth section of the trumpet guide pipe extends into the tail end pipe mouth of the head end screw-in pipe, and the external threaded pipe section is threadedly connected with the internal threaded pipe section.
[0009] In one embodiment of the utility model, a screw-in head is provided at the head end of the head-end screw-in tube, and the screw-in head is in the shape of a truncated cone as a whole.
[0010] In one embodiment of the present invention, a spiral groove is provided on the outer wall of the screw-in head.
[0011] In one embodiment of the utility model, a first table surface is provided on one end of the internally threaded pipe section and the inner wall of the head-end screw-in pipe, the outer diameter of the large-size end of the horn guide pipe is smaller than the outer diameter of the externally threaded pipe section, and a first sealing gasket is provided on the horn guide pipe. When the connecting pipe is screwed into the tail end of the head-end screw-in pipe, the first sealing gasket abuts against the first table surface.
[0012] In one embodiment of the utility model, a second table surface is provided at the tail end of the head-end screw-in tube, the outer diameter of the externally threaded pipe section is smaller than the outer diameter of the connecting pipe, and a second sealing gasket is provided at the connection position between one end of the externally threaded pipe section and the connecting pipe, and when the connecting pipe is screwed into the tail end of the head-end screw-in tube, the second sealing gasket abuts against the second table surface.
[0013] In one embodiment of the utility model, the outer wall of the first end screw-in pipe is provided with a first grouting hole, and a plurality of the first grouting holes are arranged at intervals along the circumferential direction and the length direction of the first end screw-in pipe.
[0014] In one embodiment of the utility model, the outer wall of the connecting pipe is provided with second grouting holes, and a plurality of the second grouting holes are arranged at intervals along the circumferential direction and the longitudinal direction of the connecting pipe.
[0015] In one embodiment of the utility model, a first rotation slot is provided on the inner wall of the tail end of the first end screw-in tube, and the first rotation slot is arranged along the length direction of the first end screw-in tube. A plurality of first rotation slots are arranged along the circumference of the first end screw-in tube.
[0016] In one embodiment of the utility model, a second rotation groove is provided on the inner wall of the connecting pipe away from one end of the external threaded pipe section, and the second rotation groove is arranged along the length direction of the connecting pipe. Multiple second rotation grooves are arranged along the circumference of the connecting pipe.
[0017] In one embodiment of the utility model, steel bars are inserted into the first-end screw-in tube and the connecting tube.
[0018] By adopting the above technical scheme, the technical effect of the utility model is that during the construction of the pipe shed, the first end screw-in pipe is first screwed into the soil body by the pipe pile drilling equipment, and the connecting pipe is also screwed into the soil body by the pipe pile drilling equipment, and the tail end of the first end screw-in pipe is approached by the trumpet guide pipe, and the first end screw-in pipe can be accurately guided into the first end screw-in pipe until the external threaded pipe section of the connecting pipe is threadedly connected with the internal threaded pipe section of the first end screw-in pipe, thereby realizing the rapid connection between the first end screw-in pipe and the connecting pipe, and the number of connecting pipes is set according to the use requirements, and the tail end of the connecting pipe is also provided with an internal threaded pipe section, which can quickly improve the connection between the steel pipes screwed into the soil body and improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0020] Figure 1 It is a schematic diagram of the plan structure of a steel pipe structure used for a long pipe shed in a soft surrounding rock tunnel in one embodiment of the utility model;
[0021] Figure 2 It is a structural schematic diagram of a steel pipe structure used for a long pipe shed of a soft surrounding rock tunnel in one embodiment of the utility model;
[0022] Figure 3 This is a schematic diagram of the cross-sectional structure of a steel pipe structure used for a long pipe shed in a soft surrounding rock tunnel according to an embodiment of the utility model;
[0023] Figure 4 It is a schematic cross-sectional structure diagram of a first end screw-in tube in one embodiment of the utility model;
[0024] Figure 5 It is a structural schematic diagram of a connecting pipe in one embodiment of the utility model. DETAILED DESCRIPTION
[0025] The following is an explanation of the implementation of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific implementations, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention.
[0026] It should be noted that the illustrations provided in this embodiment are only used to schematically illustrate the basic concept of the present invention. Therefore, the drawings only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.
[0027] See also Figure 1 and Figure 3As shown, when the steel pipe is screwed into the construction, since the length of the pipe shed is very long, the steel pipe is arranged in multiple sections at intervals along the length direction of the pipe shed. When the steel pipe is screwed into the soil, it is necessary to ensure the effective connection between the steel pipes. When the pipe ends of the steel pipes screwed into the soil are connected, it generally depends on the experience of the construction personnel to plug the steel pipes together to form an integral steel pipe, and then perform grouting operations. However, in actual use, there is still a situation where the steel pipe ends are not connected. In this regard, the utility model provides a steel pipe structure for a long pipe shed for a soft surrounding rock tunnel body, including: The first end is screwed into the pipe 10, and the tail end is connected to the pipe pile drilling equipment and screwed into the soil; a connecting pipe 20 is provided, and one end is connected to the tail end pipe mouth of the head end screwed into the pipe 10; the tail end pipe mouth of the head end screwed into the pipe 10 is provided with an internal threaded pipe section 11, and one end of the connecting pipe 20 is provided with an external threaded pipe section 21, and the pipe mouth of the external threaded pipe section 21 is provided with a trumpet guide pipe 22, and the small-sized end pipe mouth section of the trumpet guide pipe 22 extends into the tail end pipe mouth of the head end screwed into the pipe 10, and the external threaded pipe section 21 is threadedly connected with the internal threaded pipe section 11.
[0028] In one embodiment, the first end screw-in pipe 10 is mounted on the pipe pile drilling equipment, and the tail end of the first end screw-in pipe 10 is connected to the pipe pile drilling equipment, the pipe pile drilling equipment is started, the first end screw-in pipe 10 is screwed into the soil, and then the connecting pipe 20 is mounted on the pipe pile drilling equipment, so that the tail end of the connecting pipe 20 is connected to the pipe pile drilling equipment, and then the connecting pipe 20 can be screwed into the soil. When the trumpet guide pipe 22 is introduced into the pipe mouth of the tail end of the first end screw-in pipe 10, until the external threaded pipe section 21 of the connecting pipe 20 is threadedly connected with the internal threaded pipe section 11 of the first end screw-in pipe 10 and becomes a whole, the connecting pipe 20 and the first end screw-in pipe 10 can continue to be screwed into the soil by continuing to rotate the connecting pipe 20.
[0029] In one embodiment, the number of connecting pipes 20 along the pipe rack is reasonably arranged according to actual use requirements, the tail end of the connecting pipe 20 is also provided with an internal threaded pipe section according to use requirements, and the connection between the connecting pipes 20 and the connecting pipes 20 also has a trumpet guide pipe 22 and a connection between the inner and outer threaded pipes. Therefore, the steel pipe of this structure can quickly improve the construction efficiency of the pipe rack, and the connection between the steel pipes of the actual pipe rack is reliable, and the pipe rack formed under this structure has strong support stability for the tunnel.
[0030] In one embodiment, see Figure 1 In order to facilitate the first end screwing-in pipe 10 to be screwed into the soil, a screw-in head 12 is provided at the first end of the first end screwing-in pipe 10, and the screw-in head 12 is in a truncated cone shape as a whole.
[0031] In one embodiment, a spiral groove 121 is disposed on the outer wall of the screw-in head 12 .
[0032] In one embodiment, see Figure 3In order to ensure the sealed connection between the tail end of the first-end screw-in tube 10 and the first end of the connecting tube 20, so that an integral tube is formed between the first-end screw-in tube 10 and the connecting tube 20, one end of the internally threaded tube section 11 and the inner wall of the first-end screw-in tube 10 are provided with a first table 111, the outer diameter of the large-size end of the horn guide tube 22 is smaller than the outer diameter of the externally threaded tube section 21, and a first sealing gasket 23 is sleeved on the horn guide tube 22. When the connecting tube 20 is screwed into the tail end of the first-end screw-in tube 10, the first sealing gasket 23 abuts against the first table 111.
[0033] In one embodiment, the tail end pipe opening of the head end screw-in tube 10 is provided with a second table 13, the outer diameter of the externally threaded pipe section 21 is smaller than the outer diameter of the connecting pipe 20, and a second sealing gasket 24 is provided at the connection position between one end of the externally threaded pipe section 21 and the connecting pipe 20. When the connecting pipe 20 is screwed into the tail end of the head end screw-in tube 10, the second sealing gasket 24 abuts against the second table 13.
[0034] In one embodiment, when the connecting tube 20 is screwed into the tail end of the first end screw-in tube 10, the connecting tube 20 and the first end screw-in tube 10 form a whole, and a seal is formed between the connecting tube 20 and the first end screw-in tube 10 through the second sealing gasket 24, and the connecting tube 20 and the first end screw-in tube 10 can form a whole.
[0035] In one embodiment, the outer wall of the first end screw-in pipe 10 is provided with a first grouting hole 14 , and a plurality of the first grouting holes 14 are arranged at intervals along the circumferential direction and the longitudinal direction of the first end screw-in pipe 10 .
[0036] Similarly, the outer wall of the connecting pipe 20 is provided with second grouting holes 25 , and a plurality of the second grouting holes 25 are arranged at intervals along the circumferential direction and the longitudinal direction of the connecting pipe 20 .
[0037] In one embodiment, a first rotation slot 15 is provided on the inner wall of the tail end of the first end screw-in tube 10 , and the first rotation slot 15 is arranged along the length direction of the first end screw-in tube 10 , and a plurality of first rotation slots 15 are arranged along the circumference of the first end screw-in tube 10 .
[0038] In one embodiment, a rotating head is provided on the pipe pile drilling equipment, and the rotating head is plugged into and matched with a first rotating slot 15 provided on the inner wall of the tail end of the head-end screw-in pipe 10. By starting the rotating head on the pipe pile drilling equipment to rotate, the head-end screw-in pipe 10 can be screwed into the soil.
[0039] Similarly, in order to screw the connecting pipe 20 in, a second rotation groove 26 is provided on the inner wall of the connecting pipe 20 away from the end of the external threaded pipe section 21. The second rotation groove 26 is arranged along the length direction of the connecting pipe 20, and multiple second rotation grooves 26 are arranged along the circumference of the connecting pipe 20.
[0040] In one embodiment, in order to improve the overall connection strength between the first end screw-in pipe 10 and the connecting pipe 20 so that the first end screw-in pipe 10 and the connecting pipe 20 form a stable whole, steel bars 30 are inserted into the first end screw-in pipe 10 and the connecting pipe 20 .
[0041] In short, during the construction of the pipe shed, the first end screw-in pipe 10 is first screwed into the soil through the pipe pile drilling equipment, and the connecting pipe 20 is also screwed into the soil using the pipe pile drilling equipment. The trumpet guide pipe 22 is close to the tail end of the first end screw-in pipe 10 and can be accurately introduced into the first end screw-in pipe 10 until the external threaded pipe section 21 of the connecting pipe 20 is threadedly connected with the internal threaded pipe section 11 of the first end screw-in pipe 10, thereby realizing the quick connection between the first end screw-in pipe 10 and the connecting pipe 20. According to the use requirements, the number of connecting pipes 20 is set according to the use requirements, and the tail end of the connecting pipe 20 is also provided with an internal threaded pipe section, which can quickly improve the connection between the steel pipes screwed into the soil and improve the construction efficiency.
[0042] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope involved in the present application is not limited to the technical solution formed by a specific combination of the above-mentioned technical features, but should also cover other technical solutions formed by any combination of the above-mentioned technical features or their equivalent features without departing from the concept of the utility model, such as a technical solution formed by replacing the above-mentioned features with (but not limited to) technical features with similar functions disclosed in this application.
[0043] Except for the technical features described in the specification, the remaining technical features are known technologies to those skilled in the art. In order to highlight the innovative features of the present utility model, the remaining technical features will not be described here in detail.
Claims
1. A steel pipe structure for a long pipe shed in a soft rock tunnel. It is characterized in that include: The head end is screwed into the pipe (10), and the tail end is connected to the pipe pile drilling equipment and screwed into the soil; A connecting pipe (20) having one end connected to the tail end of the head end screwed-in pipe (10); The tail end pipe opening of the head end screw-in pipe (10) is provided with an internally threaded pipe section (11), one end of the connecting pipe (20) is provided with an externally threaded pipe section (21), the pipe opening of the externally threaded pipe section (21) is provided with a trumpet guide pipe (22), the small-sized end pipe opening section of the trumpet guide pipe (22) extends into the tail end pipe opening of the head end screw-in pipe (10), and the externally threaded pipe section (21) is threadedly connected to the internally threaded pipe section (11).
2. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1, It is characterized in that The head end of the head-end screw-in tube (10) is provided with a screw-in head (12), and the screw-in head (12) is in the shape of a truncated cone as a whole.
3. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 2, It is characterized in that The outer wall of the screw-in head (12) is provided with a spiral groove (121).
4. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1, It is characterized in that One end of the internally threaded pipe section (11) and the inner wall of the head-end screw-in pipe (10) are provided with a first table surface (111); the outer diameter of the large-size end of the horn guide pipe (22) is smaller than the outer diameter of the externally threaded pipe section (21); a first sealing gasket (23) is sleeved on the horn guide pipe (22); when the connecting pipe (20) is screwed into the rear end of the head-end screw-in pipe (10), the first sealing gasket (23) abuts against the first table surface (111).
5. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 4, It is characterized in that The tail end of the head-end screw-in tube (10) is provided with a second table surface (13); the outer diameter of the externally threaded tube section (21) is smaller than the outer diameter of the connecting tube (20); a second sealing gasket (24) is provided at the connection position between one end of the externally threaded tube section (21) and the connecting tube (20); when the connecting tube (20) is screwed into the tail end of the head-end screw-in tube (10), the second sealing gasket (24) abuts against the second table surface (13).
6. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1, It is characterized in that The outer wall of the first end screw-in pipe (10) is provided with a first grouting hole (14), and a plurality of the first grouting holes (14) are arranged at intervals along the circumferential direction and the longitudinal direction of the first end screw-in pipe (10).
7. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1 or 6, It is characterized in that The outer wall of the connecting pipe (20) is provided with second grouting holes (25), and a plurality of the second grouting holes (25) are arranged at intervals along the circumferential direction and the longitudinal direction of the connecting pipe (20).
8. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1, It is characterized in that The inner wall of the rear end of the head-end screw-in tube (10) is provided with a first rotation slot (15), the first rotation slot (15) is arranged along the length direction of the head-end screw-in tube (10), and a plurality of the first rotation slots (15) are arranged along the circumference of the head-end screw-in tube (10).
9. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1, It is characterized in that A second rotation slot (26) is provided on the inner wall of the connecting tube (20) at one end away from the externally threaded tube section (21); the second rotation slot (26) is arranged along the length direction of the connecting tube (20); and a plurality of the second rotation slots (26) are arranged along the circumference of the connecting tube (20).
10. The steel pipe structure for the long pipe shed of a soft surrounding rock tunnel according to claim 1, It is characterized in that Steel bars (30) are inserted into the first-end screw-in tube (10) and the connecting tube (20).