Mixed gas supply equipment for single crystal furnace

By designing the mixed gas supply equipment of the single crystal furnace, using nitrogen to replace part of the argon gas and realizing argon gas recovery, and then using the argon gas, the problem of large argon gas usage in the production of the single crystal furnace is solved, the production cost is reduced and the gas efficiency is improved. Usage efficiency.

CN221854850UActive Publication Date: 2024-10-18JIANGSU ZHUHE NEW ENERGY TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323353760.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-09
Publication Date
2024-10-18
Estimated Expiration
2033-12-09

AI Technical Summary

Technical Problem

The use of high-purity argon in single crystal furnace production is large and costly, and the protective gas requirements in the auxiliary chamber are not as strict as those in the main chamber, resulting in higher production costs.

Method used

A mixed gas supply equipment for a single crystal furnace is designed. Through the argon nitrogen separation mechanism and the argon gas treatment mechanism, nitrogen is used to replace part of the argon gas to realize the recovery and reuse of the argon gas, and the gas guide pipe structure is used to prevent gas backflow and pollution. Optimize the use of argon and nitrogen.

Benefits of technology

It effectively reduces the amount of argon gas used, reduces production costs, prevents pollution of argon gas and nitrogen storage tanks, and improves gas usage efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221854850U_ABST
    Figure CN221854850U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of single crystal material production, and particularly relates to mixed gas supply equipment for a single crystal furnace, which comprises a base, the top of the base is fixedly connected with an argon and nitrogen separation mechanism; the top of the argon-nitrogen separation mechanism is fixedly connected with an argon treatment mechanism; the top of the argon treatment mechanism is fixedly connected with a nitrogen storage tank; the top of the argon treatment mechanism is fixedly connected with an argon storage tank; the top of the argon storage tank and the top of the nitrogen storage tank are both communicated with first gas guide pipes; the top of the base is fixedly connected with a single crystal furnace body; the other end of the first gas guide pipe is communicated with an auxiliary chamber of the single crystal furnace body; the side wall of the argon storage tank is communicated with a second gas guide pipe; the other end of the second gas guide pipe is communicated with the main chamber of the single crystal furnace body; through the structure, when the single crystal furnace is used for production, the use amount of argon can be reduced, part of nitrogen is used for replacement, the argon can be recycled, and the production cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of single crystal material production, in particular to a mixed gas supply device for a single crystal furnace. Background Art

[0002] A single crystal furnace is a device that uses a heater to melt polycrystalline materials such as polysilicon and grows dislocation-free single crystals using the Czochralski method.

[0003] The single crystal furnace is mainly composed of a main chamber and a sub-chamber. During the production process of single crystals, the main chamber and the sub-chamber of the single crystal furnace need to be filled with inert gas as protection to isolate them from other gas impurities and provide ideal environmental conditions for the production of single crystals. The current single crystal production generally fills high-purity argon into the main chamber and the sub-chamber of the single crystal furnace as a protective gas. However, the price of high-purity argon is relatively high, and the amount of inert gas used in the production of single crystals is relatively large, resulting in a high production cost of the single crystal. In addition, the protection demand in the sub-chamber is not as great as that in the main chamber, and the requirements for inert gas can be appropriately reduced.

[0004] To this end, the utility model provides a mixed gas supply device for a single crystal furnace. Utility Model Content

[0005] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.

[0006] The technical solution adopted by the utility model to solve its technical problems is: a mixed gas supply device for a single crystal furnace described in the utility model comprises a base; an argon-nitrogen separation mechanism is fixedly connected to the top of the base; an argon processing mechanism is fixedly connected to the top of the argon processing mechanism; a nitrogen storage tank is fixedly connected to the top of the argon processing mechanism; an argon storage tank is fixedly connected to the top of the argon processing mechanism; the tops of the argon storage tank and the nitrogen storage tank are both connected to a first air guide pipe; the top of the base is fixedly connected to a single crystal furnace body; the other end of the first air guide pipe is connected to the auxiliary chamber of the single crystal furnace body; the side wall of the argon storage tank is connected to the auxiliary chamber of the single crystal furnace body; There is a second air guide pipe; the other end of the second air guide pipe is connected to the main chamber of the single crystal furnace body; the middle of the sub-chamber of the single crystal furnace body is connected to a sub-chamber exhaust pipe; the other end of the sub-chamber exhaust pipe is connected to the side wall of the argon-nitrogen separation mechanism; the middle of the main chamber of the single crystal furnace body is connected to a main chamber exhaust pipe; the other end of the main chamber exhaust pipe is connected to the side wall of the argon processing mechanism; the side wall of the argon-nitrogen separation mechanism is connected to a nitrogen exhaust pipe; through the above structure, when using a single crystal furnace for production, the use of argon can be reduced, and part of nitrogen can be used as a substitute, and the argon can be recycled and reused, thereby reducing production costs.

[0007] Preferably, a connecting pipe is fixedly connected to the middle part of the first air guide pipe; a fixing ring is fixedly connected to the middle part of the inner side of the connecting pipe; a vent hole is opened in the middle part of the fixing ring; a plurality of sliding columns are slidably connected to the middle part of the side wall of the fixing ring; a baffle is fixedly connected to the ends of the plurality of sliding columns; a first fixing plate is fixedly connected to the middle part of the inner side of the connecting pipe; a first spring is fixedly connected to the side wall of the first fixing plate; the other end of the first spring is fixedly connected to the side wall of the baffle; through the above structure, after argon or nitrogen is injected into the sub-chamber of the single crystal furnace body, the mixed gas inside the single crystal furnace body can be effectively prevented from flowing back to the inside of the first air guide pipe, thereby preventing the pure nitrogen inside the nitrogen storage tank or the pure argon inside the argon storage tank from being contaminated.

[0008] Preferably, the side wall of the argon storage tank is connected to an air inlet pipe; a sliding cylinder is slidably connected to the inner middle part of the air inlet pipe; a pair of sliding grooves are symmetrically arranged in the middle part of the sliding cylinder; a second fixed plate is fixedly connected to the inner middle part of the air inlet pipe; the second fixed plate is located in the middle part of a pair of sliding grooves and is slidably matched with the pair of sliding grooves; a second spring is fixedly connected to the side wall of the second fixed plate; the other end of the second spring is fixedly connected to the side wall of the sliding cylinder; through the above structure, argon can be conveniently filled into the interior of the argon storage tank, and after the filling is completed, the argon inside the argon storage tank can be effectively prevented from leaking through the filling port, thereby reducing the loss of argon.

[0009] Preferably, a rubber ring is fixed to the side wall of the sliding cylinder; a groove is provided on the inner wall of the argon storage tank; the rubber ring and the groove are both arranged on the side where the sliding cylinder and the argon storage tank are close to each other; through the above structure, the leakage of argon inside the argon storage tank can be further prevented, thereby reducing the loss of argon.

[0010] Preferably, a thermometer is fixedly connected to the middle of the auxiliary chamber exhaust pipe and the main chamber exhaust pipe; the end of the thermometer extends to the inside of the corresponding auxiliary chamber exhaust pipe and the main chamber exhaust pipe; the end of the argon storage tank is fixedly connected to a temperature measuring head; the auxiliary chamber exhaust pipe and the main chamber exhaust pipe are fixedly connected to the middle of the heat insulation sleeve; through the above structure, when high-temperature gas passes through the auxiliary chamber exhaust pipe and the main chamber exhaust pipe, people can be effectively prevented from being scalded by the high-temperature pipe, and the internal temperature of the single crystal furnace body can be understood to a certain extent based on the thermometer.

[0011] Preferably, a gasket is fixedly connected to the side wall of the baffle, and the gasket is located between the baffle and the fixing ring; the gasket is a colloid material; through the above structure, after argon or nitrogen is injected into the auxiliary chamber of the single crystal furnace body, the mixed gas inside the single crystal furnace body can be further prevented from flowing back to the interior of the first air duct.

[0012] The beneficial effects of the utility model are as follows:

[0013] 1. The utility model discloses a mixed gas supply device for a single crystal furnace. The argon gas in the argon storage tank is introduced into the main chamber of the single crystal furnace body through two gas guide pipes, so that the main chamber of the single crystal furnace body is filled with argon gas. On the other hand, when necessary, the nitrogen gas in the nitrogen storage tank and the argon gas in the argon storage tank are intermittently injected into the sub-chamber of the single crystal furnace body through the first gas guide pipes which are connected to each other. When necessary, the mixed gas in the main chamber of the single crystal furnace body is introduced into the interior of the argon treatment mechanism through the main chamber exhaust pipe, and is treated by the argon treatment mechanism, and then introduced into the interior of the argon storage tank. When necessary, the nitrogen-argon mixed gas in the sub-chamber of the single crystal furnace body is introduced into the interior of the argon-nitrogen separation mechanism through the sub-chamber exhaust pipe. The nitrogen in the nitrogen-argon mixed gas will be separated and discharged through the nitrogen exhaust pipe, and the argon therein will be discharged into the argon treatment mechanism for treatment, and then injected into the argon storage tank after the treatment. Through the above structure, when the single crystal furnace is used for production, the use of argon gas can be reduced, and part of nitrogen can be used as a substitute, and the argon gas can be recycled and reused, thereby reducing the production cost.

[0014] 2. The utility model describes a mixed gas supply device for a single crystal furnace. When gas is injected into the sub-chamber of the single crystal furnace body through the first air duct, the flowing gas will impact the baffle to make it slide, thereby allowing the gas to flow through the vent. After the gas injection is completed, the baffle will slide under the elastic force of the first spring to block the vent. Through the above structure, after argon or nitrogen is injected into the sub-chamber of the single crystal furnace body, the mixed gas inside the single crystal furnace body can be effectively prevented from flowing back to the inside of the first air duct, thereby preventing the pure nitrogen inside the nitrogen storage tank or the pure argon inside the argon storage tank from being contaminated. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The utility model will be further described below in conjunction with the accompanying drawings.

[0016] Figure 1 It is a three-dimensional diagram of the utility model;

[0017] Figure 2 It is a structural schematic diagram of the nitrogen discharge pipe in the utility model;

[0018] Figure 3 It is a structural schematic diagram of the connecting pipe in the utility model;

[0019] Figure 4 It is a structural schematic diagram of the air intake pipe in the utility model;

[0020] Figure 5 It is a structural schematic diagram of the thermometer in the utility model;

[0021] In the figure: 1. base; 12. argon and nitrogen separation mechanism; 13. argon processing mechanism; 14. nitrogen storage tank; 15. argon storage tank; 16. first air duct; 17. second air duct; 18. auxiliary chamber exhaust pipe; 19. main chamber exhaust pipe; 110. nitrogen exhaust pipe; 111. single crystal furnace body; 2. connecting pipe; 21. fixing ring; 22. vent hole; 23. sliding column; 24. baffle; 25. first fixing plate; 26. first spring; 3. air inlet pipe; 31. sliding cylinder; 32. slide groove; 33. second fixing plate; 34. second spring; 4. rubber ring; 41. groove; 5. thermometer; 51. temperature measuring head; 52. thermal insulation sleeve; 6. gasket. DETAILED DESCRIPTION

[0022] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0023] like Figure 1 to Figure 2As shown, a mixed gas supply device for a single crystal furnace described in an embodiment of the utility model comprises a base 1; an argon-nitrogen separation mechanism 12 is fixedly connected to the top of the base 1; an argon processing mechanism 13 is fixedly connected to the top of the argon processing mechanism 13; a nitrogen storage tank 14 is fixedly connected to the top of the argon processing mechanism 13; an argon storage tank 15 is fixedly connected to the top of the argon processing mechanism 13; the tops of the argon storage tank 15 and the nitrogen storage tank 14 are both connected to a first air guide pipe 16; a single crystal furnace body 111 is fixedly connected to the top of the base 1; the other end of the first air guide pipe 16 is connected to the sub-chamber of the single crystal furnace body 111; the argon storage The side wall of the tank 15 is connected with a second air guide pipe 17; the other end of the second air guide pipe 17 is connected with the main chamber of the single crystal furnace body 111; the middle of the sub-chamber of the single crystal furnace body 111 is connected with a sub-chamber exhaust pipe 18; the other end of the sub-chamber exhaust pipe 18 is connected with the side wall of the argon-nitrogen separation mechanism 12; the middle of the main chamber of the single crystal furnace body 111 is connected with a main chamber exhaust pipe 19; the other end of the main chamber exhaust pipe 19 is connected with the side wall of the argon treatment mechanism 13; the side wall of the argon-nitrogen separation mechanism 12 is connected with a nitrogen exhaust pipe 110; when working, when the single crystal furnace body 111 is used for production, the argon gas is discharged by the air pump inside the argon storage tank 15 The argon gas is pumped into the interior of the second gas guide pipe 17, and then flows into the interior of the main chamber of the single crystal furnace body 111 through the second gas guide pipe 17, so that the interior of the main chamber of the single crystal furnace body 111 is filled with argon gas. On the other hand, when necessary, the nitrogen gas in the nitrogen storage tank 14 and the argon gas in the argon storage tank 15 are intermittently injected into the interior of the sub-chamber of the single crystal furnace body 111 through the first gas guide pipes 16 that are connected to each other, so that the interior of the sub-chamber of the single crystal furnace body 111 is filled with a mixed gas of argon and nitrogen. When necessary, the mixed gas mainly composed of argon gas in the main chamber of the single crystal furnace body 111 is introduced into the interior of the argon processing mechanism 13 through the main chamber exhaust pipe 19, and the argon processing mechanism 13 is used to process the argon gas. The argon is processed so that it reaches the usage standard and then injected into the argon storage tank 15. When necessary, the nitrogen and argon mixed gas inside the sub-chamber of the single crystal furnace body 111 is introduced into the argon nitrogen separation mechanism 12 through the sub-chamber exhaust pipe 18. The nitrogen in the nitrogen and argon mixed gas will be separated inside the argon nitrogen separation mechanism 12 and discharged through the nitrogen exhaust pipe 110. The argon therein will be discharged into the argon treatment mechanism 13 for treatment and then injected into the argon storage tank 15 after the treatment. Through the above structure, the use of argon can be reduced when using a single crystal furnace for production, and the argon can be recycled and reused, thereby reducing production costs.

[0024] like Figures 1 to 3As shown, a connecting pipe 2 is fixedly connected to the middle of the first air guide pipe 16; a fixing ring 21 is fixedly connected to the middle of the inner side of the connecting pipe 2; a vent hole 22 is opened in the middle of the fixing ring 21; a plurality of sliding columns 23 are slidably connected to the middle of the side wall of the fixing ring 21; a baffle 24 is fixedly connected to the ends of the plurality of sliding columns 23; a first fixing plate 25 is fixedly connected to the middle of the inner side of the connecting pipe 2; a first spring 26 is fixedly connected to the side wall of the first fixing plate 25; the other end of the first spring 26 is fixedly connected to the side wall of the baffle 24; when working, when gas is injected into the auxiliary chamber of the single crystal furnace body 111 through the first air guide pipe 16, the flowing gas will hit the baffle 24 The baffle 24 will impact the side wall, so that the baffle 24 drives the sliding column 23 to slide, so that the gas can flow from the vent 22. After the gas injection is completed, the baffle 24 will slide in the direction of the fixing ring 21 under the elastic force of the first spring 26, and then block the vent 22, so that the gas inside the sub-chamber of the single crystal furnace body 111 cannot flow back through the vent 22. Through the above structure, after argon or nitrogen is injected into the sub-chamber of the single crystal furnace body 111, the mixed gas inside the single crystal furnace body 111 can be effectively prevented from flowing back to the inside of the first air duct 16, thereby preventing the pure nitrogen inside the nitrogen storage tank 14 or the pure argon inside the argon storage tank 15 from being contaminated.

[0025] like Figures 1 to 4 As shown, the side wall of the argon storage tank 15 is connected to the air intake pipe 3; the sliding cylinder 31 is slidably connected to the inner middle part of the air intake pipe 3; the middle part of the sliding cylinder 31 is symmetrically arranged with a pair of sliding grooves 32; the inner middle part of the air intake pipe 3 is fixedly connected to a second fixing plate 33; the second fixing plate 33 is located in the middle of the pair of sliding grooves 32, and is slidably matched with the pair of sliding grooves 32; the side wall of the second fixing plate 33 is fixedly connected to a second spring 34; the other end of the second spring 34 is fixedly connected to the side wall of the sliding cylinder 31; during operation, when it is necessary to fill the argon storage tank 15 with argon, by extending the filling pipe into the interior of the air intake pipe 3, the filling pipe is The end will squeeze the sliding cylinder 31, so that the sliding cylinder 31 slides along the inner wall of the intake pipe 3, so that the side wall of the sliding cylinder 31 is separated from the inner wall of the argon storage tank 15, so that the argon gas can be injected into the interior of the argon storage tank 15. After the argon gas is injected, the filling pipe is pulled out. At this time, the side wall of the sliding cylinder 31 will fit with the inner wall of the argon storage tank 15 under the pulling force of the second spring 34, so that the argon gas inside the argon storage tank 15 cannot flow out. Through the above structure, the argon gas storage tank 15 can be conveniently filled with argon gas, and after the filling is completed, the argon gas inside the argon storage tank 15 can be effectively prevented from leaking through the filling port, thereby reducing the loss of argon gas.

[0026] like Figures 1 to 4As shown, the side wall of the sliding cylinder 31 is fixedly connected with a rubber ring 4; the inner side wall of the argon storage tank 15 is provided with a groove 41; the rubber ring 4 and the groove 41 are both arranged on the side where the sliding cylinder 31 and the argon storage tank 15 are close to each other; during operation, after the argon storage tank 15 is filled with argon, the side wall of the sliding cylinder 31 will contact the side wall of the argon storage tank 15 under the pulling force of the second spring 34, and then the rubber ring 4 will be pressed into the inside of the groove 41, so that the sliding cylinder 31 and the argon storage tank 15 are more closely combined, and the air tightness is improved. Through the above structure, the leakage of argon inside the argon storage tank 15 can be further prevented, thereby reducing the loss of argon.

[0027] like Figures 1 to 5 As shown, the middle parts of the auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19 are fixedly connected with a thermometer 5; the ends of the thermometer 5 extend to the corresponding auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19; the ends of the argon storage tank 15 are fixedly connected with a temperature measuring head 51; the middle parts of the auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19 are fixedly connected with an insulating sleeve 52; during operation, when the gas inside the single crystal furnace body 111 is discharged through the auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19, these gases will carry a higher temperature, and the temperature of the passing gas can be measured by the temperature measuring head 51, and displayed by the thermometer 5, so that the temperature inside the single crystal furnace body 111 can be understood to a certain extent. Through the above structure, when high-temperature gas passes through the auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19, it can effectively prevent people from being scalded by the high-temperature pipes, and the temperature inside the single crystal furnace body 111 can be understood to a certain extent according to the thermometer 5.

[0028] like Figure 3 As shown, a gasket 6 is fixed to the side wall of the baffle 24; the gasket 6 is located between the baffle 24 and the fixing ring 21; the gasket 6 is a colloid material; during operation, through the setting of the gasket 6, after argon or nitrogen is injected into the auxiliary chamber of the single crystal furnace body 111, the mixed gas inside the single crystal furnace body 111 can be further prevented from flowing back to the inside of the first air duct 16.

[0029] During operation, when the single crystal furnace body 111 is used for production, the argon gas is pumped into the second gas duct 17 through the gas pump inside the argon storage tank 15, and then flows into the main chamber of the single crystal furnace body 111 through the second gas duct 17, so that the main chamber of the single crystal furnace body 111 is filled with argon gas. On the other hand, when necessary, the nitrogen gas inside the nitrogen storage tank 14 and the argon gas inside the argon storage tank 15 are intermittently injected into the sub-chamber of the single crystal furnace body 111 through the first gas duct 16 that are connected to each other, so that the sub-chamber of the single crystal furnace body 111 is filled with a mixed gas of argon and nitrogen. When necessary, the mixed gas mainly composed of argon gas in the main chamber of the single crystal furnace body 111 is introduced into the interior of the argon treatment mechanism 13 through the main chamber exhaust pipe 19, and the argon treatment mechanism 13 is used to treat the argon gas. The argon is processed so that it reaches the usage standard and then injected into the argon storage tank 15. When necessary, the nitrogen-argon mixed gas in the sub-chamber of the single crystal furnace body 111 is introduced into the argon-nitrogen separation mechanism 12 through the sub-chamber exhaust pipe 18. The nitrogen in the nitrogen-argon mixed gas will be separated inside the argon-nitrogen separation mechanism 12 and discharged through the nitrogen exhaust pipe 110. The argon therein will be discharged into the argon treatment mechanism 13 for treatment. After the treatment is completed, it will be injected into the argon storage tank 15. Through the above structure, the use of argon can be reduced when the single crystal furnace is used for production, and the argon can be recycled and reused, thereby reducing the production cost. When the gas is injected into the sub-chamber of the single crystal furnace body 111 through the first gas guide pipe 16, the flowing gas will The side wall of the baffle 24 is impacted, so that the baffle 24 drives the sliding column 23 to slide, thereby allowing the gas to flow from the vent 22. After the gas injection is completed, the baffle 24 will slide toward the direction of the fixing ring 21 under the elastic force of the first spring 26, and then block the vent 22, so that the gas inside the sub-chamber of the single crystal furnace body 111 cannot flow back through the vent 22. Through the above structure, after argon or nitrogen is injected into the sub-chamber of the single crystal furnace body 111, the mixed gas inside the single crystal furnace body 111 can be effectively prevented from flowing back to the inside of the first air guide pipe 16, thereby preventing the pure nitrogen inside the nitrogen storage tank 14 or the pure argon inside the argon storage tank 15 from being contaminated. When it is necessary to fill the argon storage tank 15 with argon, the filling pipe is extended into the inlet. Inside the air pipe 3, the end of the filling pipe will squeeze the sliding cylinder 31, so that the sliding cylinder 31 slides along the inner wall of the air inlet pipe 3, so that the side wall of the sliding cylinder 31 is separated from the inner wall of the argon storage tank 15, so that the argon gas can be injected into the interior of the argon storage tank 15. After the argon gas is injected, the filling pipe is pulled out. At this time, the side wall of the sliding cylinder 31 will fit with the inner wall of the argon storage tank 15 under the pulling force of the second spring 34, so that the argon gas inside the argon storage tank 15 cannot flow out. Through the above structure, the argon gas storage tank 15 can be easily filled with argon gas, and after the filling is completed, the argon gas inside the argon storage tank 15 can be effectively prevented from leaking out through the filling port, thereby reducing the loss of argon gas. After the argon gas is filled into the argon storage tank 15,The side wall of the sliding cylinder 31 will contact the side wall of the argon storage tank 15 under the pulling force of the second spring 34, and then the rubber ring 4 will be pressed into the inside of the groove 41, so that the sliding cylinder 31 and the argon storage tank 15 are more tightly combined to improve the air tightness. Through the above structure, the argon gas inside the argon storage tank 15 can be further prevented from leaking, thereby reducing the loss of argon gas. When the gas inside the single crystal furnace body 111 is discharged through the auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19, these gases will carry a higher temperature, and the temperature of the passing gas can be measured by the temperature measuring head 51. , and displayed by the thermometer 5, the temperature inside the single crystal furnace body 111 can be understood to a certain extent. Through the above structure, when the high-temperature gas passes through the auxiliary chamber exhaust pipe 18 and the main chamber exhaust pipe 19, it is possible to effectively prevent people from being scalded by the high-temperature pipes, and the temperature inside the single crystal furnace body 111 can be understood to a certain extent according to the thermometer 5. Through the setting of the gasket 6, after argon or nitrogen is injected into the auxiliary chamber of the single crystal furnace body 111, the mixed gas inside the single crystal furnace body 111 can be further prevented from flowing back to the inside of the first air guide pipe 16. ,

[0030] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. A mixed gas supply device for a single crystal furnace, comprising a base (1); characterized in that: The top of the base (1) is fixedly connected to an argon-nitrogen separation mechanism (12); the top of the argon-nitrogen separation mechanism (12) is fixedly connected to an argon processing mechanism (13); the top of the argon processing mechanism (13) is fixedly connected to a nitrogen storage tank (14); the top of the argon processing mechanism (13) is fixedly connected to an argon storage tank (15); the tops of the argon storage tank (15) and the nitrogen storage tank (14) are both connected to a first air guide pipe (16); the top of the base (1) is fixedly connected to a single crystal furnace body (111); the other end of the first air guide pipe (16) is connected to a sub-chamber of the single crystal furnace body (111); the argon The side wall of the storage tank (15) is connected to a second air guide pipe (17); the other end of the second air guide pipe (17) is connected to the main chamber of the single crystal furnace body (111); the middle of the sub-chamber of the single crystal furnace body (111) is connected to a sub-chamber exhaust pipe (18); the other end of the sub-chamber exhaust pipe (18) is connected to the side wall of the argon-nitrogen separation mechanism (12); the middle of the main chamber of the single crystal furnace body (111) is connected to a main chamber exhaust pipe (19); the other end of the main chamber exhaust pipe (19) is connected to the side wall of the argon processing mechanism (13); and the side wall of the argon-nitrogen separation mechanism (12) is connected to a nitrogen exhaust pipe (110).

2. The mixed gas supply device for a single crystal furnace according to claim 1, characterized in that: A connecting tube (2) is fixedly connected to the middle of the first air guide tube (16); a fixing ring (21) is fixedly connected to the middle of the inner side of the connecting tube (2); a vent hole (22) is opened in the middle of the fixing ring (21); a plurality of sliding columns (23) are slidably connected to the middle of the side wall of the fixing ring (21); a baffle (24) is fixedly connected to the ends of the plurality of sliding columns (23); a first fixing plate (25) is fixedly connected to the middle of the inner side of the connecting tube (2); a first spring (26) is fixedly connected to the side wall of the first fixing plate (25); and the other end of the first spring (26) is fixedly connected to the side wall of the baffle (24).

3. The mixed gas supply device for a single crystal furnace according to claim 2, characterized in that: The side wall of the argon storage tank (15) is connected to an air intake pipe (3); a sliding cylinder (31) is slidably connected to the inner middle part of the air intake pipe (3); a pair of sliding grooves (32) are symmetrically arranged in the middle part of the sliding cylinder (31); a second fixing plate (33) is fixedly connected to the inner middle part of the air intake pipe (3); the second fixing plate (33) is located in the middle part of the pair of sliding grooves (32) and is slidably matched with the pair of sliding grooves (32); a second spring (34) is fixedly connected to the side wall of the second fixing plate (33); the other end of the second spring (34) is fixedly connected to the side wall of the sliding cylinder (31).

4. The mixed gas supply device for a single crystal furnace according to claim 3, characterized in that: A rubber ring (4) is fixedly connected to the side wall of the sliding cylinder (31); a groove (41) is provided on the inner side wall of the argon gas storage tank (15); the rubber ring (4) and the groove (41) are both arranged on a side where the sliding cylinder (31) and the argon gas storage tank (15) are close to each other.

5. The mixed gas supply device for a single crystal furnace according to claim 4, characterized in that: The middle parts of the secondary chamber exhaust pipe (18) and the main chamber exhaust pipe (19) are both fixedly connected with a thermometer (5); the ends of the thermometer (5) extend to the inside of the corresponding secondary chamber exhaust pipe (18) and the main chamber exhaust pipe (19); the end of the argon storage tank (15) is fixedly connected with a temperature measuring head (51); the middle parts of the secondary chamber exhaust pipe (18) and the main chamber exhaust pipe (19) are fixedly connected with a heat insulation sleeve (52).

6. The mixed gas supply device for a single crystal furnace according to claim 5, characterized in that: A gasket (6) is fixedly connected to the side wall of the baffle (24); the gasket (6) is located between the baffle (24) and the fixing ring (21); and the gasket (6) is made of a colloid material.