Mixed type water passing road structure
By adopting a hybrid water-crossing road structure in roads in mountainous areas and flood discharge areas, combined with EPS composite pipe culvert roadbed and fiberglass sand-filled culvert pipes, the problem of seasonal river erosion and scouring is solved, achieving rapid diversion and reducing economic costs. , improving road stability and safety.
Patent Information
- Application Number
- CN202323374665.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-11
AI Technical Summary
Roads in mountainous areas and flood discharge areas are susceptible to erosion and washout in seasonal rivers, resulting in restricted traffic and unstable land. Existing water crossing roads have shortcomings in terms of economic cost and construction efficiency.
A mixed water-crossing road structure is adopted, including cement concrete surface layer, cement-stabilized gravel base layer, geocell-granular transverse drainage layer, fiberglass sand-board water-insulating layer, EPS composite pipe culvert roadbed and retaining wall. EPS composite The pipe culvert roadbed is composed of EPS blocks and fiberglass sand-filled culvert pipes. It combines prefabricated processing and the use of specific materials to improve the water resistance and stability of the road.
It achieves rapid diversion of accumulated water upstream, reduces the damage caused by siltation to the roadbed, saves project costs, improves the stability and safety of the road, reduces the risk of foundation settlement, and extends the service life of the road.
Smart Images

Figure CN221855182U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of highway bridge and culvert construction projects, in particular to a mixed water-passing road structure suitable for roads in mountainous areas and flood discharge areas. Background Art
[0002] Seasonal rivers due to climate reasons are widespread in China. Their main feature is that water flow undergoes significant changes in a specific season or period, usually due to rainfall, snowmelt or other meteorological factors, making the river itself and its surrounding areas susceptible to erosion and scour, leading to land instability and soil erosion problems. In remote and mountainous areas, it may restrict transportation and limit the use of land for agriculture, construction or other types of development.
[0003] A water-passing road is a road structure that allows water to pass through during the rainy or flood season. Usually, water-passing roads are used on sections of roads where floods last for a short time and there is no water flow all year round to replace traditional bridge and culvert structures. In addition, water-passing roads are also suitable for riverside areas or flood discharge areas to ensure that the road does not restrict the flow of flood water without increasing the height of the road.
[0004] The hybrid water-passing road is a design that combines the water-passing road surface with the circular culvert. It is suitable for canyon rivers with low terrain, where the water volume is low in normal times but increases sharply in the rainy season. Compared with building bridges, the hybrid water-passing road allows the water volume to flow through the circular culvert at normal times. Even in the event of mountain torrents, the water can pass through the road surface quickly, reducing the damage of siltation to the roadbed and greatly saving economic costs.
[0005] Expanded Polystyrene (EPS) is a lightweight polymer made by foaming polystyrene particles. It is made by adding a foaming agent to polystyrene resin, heating it to soften it, and generating gas to form a rigid closed-cell foam plastic. EPS has lightweight properties and is lighter than traditional roadbed materials such as gravel or soil. This can reduce the load on the structure and reduce the risk of settlement of the foundation. EPS can reduce soil compaction, which helps reduce the heavy machinery and manpower required for construction, thereby reducing project costs. EPS has a certain resistance to water, which can reduce the risk of soil erosion by rainwater and help maintain the stability of the roadbed. Compared with some traditional materials, EPS is less corrosive to chemicals and salt water, which makes it more durable in some special environments. Utility Model Content
[0006] The purpose of the utility model is to develop a structure with fast construction speed, low construction cost, and rapid diversion of upstream accumulated water, which is suitable for water-passing roads in mountainous areas, flood discharge areas, etc., so as to solve the problems raised in the above-mentioned background technology.
[0007] In order to achieve the above purpose, the technical solution of the utility model is:
[0008] A water-passing road structure includes, from top to bottom, a cement concrete surface layer, a cement stabilized crushed stone base layer, a geocell-granular material transverse drainage layer, a glass fiber reinforced plastic sand-filled board waterproof layer, an EPS composite pipe culvert roadbed, a gravel cushion layer, and a retaining wall. The EPS composite pipe culvert roadbed is composed of EPS blocks and glass fiber reinforced plastic sand-filled culvert pipes, and the geocell-granular material transverse drainage layer includes geocells and filling granular materials.
[0009] The cement concrete surface layer is cast with cement concrete. When laying the cement concrete surface layer, the center line of the road is taken as the highest point, and both sides are symmetrically laid with a certain slope to avoid water accumulation on the road.
[0010] The geocell-granular material transverse drainage layer may be filled with graded crushed stone, gravel aggregate, recycled material from old asphalt pavement, etc., and the height of the filling granular material after compaction should be basically consistent with that of the geocell.
[0011] The surface of the geocell sheet is provided with a certain number and arrangement order of circular permeable holes, and the number and arrangement order are based on the engineering design.
[0012] The glass fiber reinforced plastic sand-filled board waterproof layer is formed by splicing a plurality of glass fiber reinforced plastic sand-filled boards and is fixed by bolts.
[0013] The EPS blocks include special-shaped EPS blocks for receiving culvert pipes at the top and bottom and common EPS blocks for filling EPS composite culvert roadbeds. Both are prefabricated. The special-shaped EPS blocks have grooves corresponding to the annular structures of the outer walls of the glass fiber reinforced plastic sand-filled culvert pipes.
[0014] The FRP sand-filled culvert is prefabricated and has an annular outer wall and a smooth inner wall. The outer wall annular structure increases the friction and bearing capacity of the culvert. Each FRP sand-filled culvert is arranged perpendicular to the driving direction of the road, and the length of the culvert is the same as the width of the road cross-section structure.
[0015] A plurality of drainage pipes are reserved in the retaining wall body, and metal filter screens are arranged at the inlet and outlet of the drainage pipes to prevent the loss of granular materials. The retaining wall can be constructed by template support, vertical casting or prefabricated components.
[0016] A layer of waterproof geotextile with a thickness of 0.5 mm is laid on the gravel cushion layer to prevent water from penetrating into the EPS block and affecting the stability of the EPS composite pipe culvert roadbed.
[0017] Preferably, the density of the EPS block is generally 20-30 kg / m 3 , compressive strength is greater than 100KPa, height is 20~25cm.
[0018] Preferably, the glass fiber reinforced plastic sand-filled culvert has an inner diameter of 1000 mm and a wall thickness of 50 mm.
[0019] Preferably, the thickness of the cement concrete surface layer is in the range of 15 to 20 cm. When laying the cement concrete surface layer 1, the center line of the road is taken as the highest point, and the two sides are symmetrically laid with a slope of 2% to avoid water accumulation on the road.
[0020] Preferably, the cement-stabilized gravel base layer uses graded gravel as a main material, has a paving thickness of 15 to 20 cm, and the maximum particle size of the gravel constituting the cement-stabilized gravel base layer is ≤35 cm and the minimum particle size is ≥10 cm.
[0021] Preferably, the geocell adopts a large rectangular frame of high-strength HDPE, with a cell wall thickness of 2 mm and a height of 10 to 15 cm; the particle size of the filling aggregate should be 10 to 20 mm, and it should be ensured that the filling aggregate is basically consistent with the height of the geocell after compaction.
[0022] Preferably, the gaps between the EPS blocks in the EPS composite pipe culvert roadbed are controlled within 20 mm, and the height misalignment is controlled within 10 mm. The gaps between the EPS blocks exceeding 20 mm and the height misalignment exceeding 10 mm are fully filled with sand or non-shrinkage cement mortar to ensure that the EPS composite pipe culvert roadbed is laid tightly and firmly.
[0023] Preferably, the height of the retaining wall is flush with the upper surface of the pavement structure layer, and there is a transverse drainage pipe inside the retaining wall. The main function of the retaining wall is to prevent the upstream water flow from directly eroding the main structure of the road and harmful substances from damaging the various pavement structure layers. It can also promote drainage of various pavement structure layers through the drainage pipe.
[0024] Beneficial effects of the utility model:
[0025] (1) The polystyrene foam (EPS) used in the EPS composite pipe culvert roadbed of the utility model has the advantages of acid and alkali resistance, water-impermeability, corrosion resistance, and strong durability. The EPS block can not only be used as the roadbed of the road, but also save costs, improve construction efficiency, and reduce problems such as uneven settlement of the foundation that affect the quality of the project.
[0026] (2) Glass fiber reinforced plastic sand-filled culvert is a new type of water supply and drainage pipe with the characteristics of long service life, low price, light weight, good rigidity, corrosion resistance, easy installation and excellent hydraulic properties.
[0027] (3) The geocell-aggregate lateral drainage layer formed by combining geocells with filling aggregates can improve the stability of the road structure, prevent the migration of aggregates, play a reinforcing role, and improve the stability of the road structure.
[0028] (4) The water-passing road in the utility model can effectively drain water, avoid the occurrence of water accumulation, and improve road safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 This is a schematic diagram of the cross-sectional structure of the hybrid water-passing road structure at AA in the embodiment of the utility model;
[0030] Figure 2 yes Figure 1 Left view of;
[0031] Figure 3 It is a schematic diagram of the plan structure of the hybrid water-passing road structure in the embodiment of the utility model;
[0032] Figure 4 It is a schematic diagram of the longitudinal section structure of the hybrid water-passing road structure in the embodiment of the utility model;
[0033] Figure 5 It is a schematic diagram of the structural assembly of the special-shaped EPS blocks and the glass fiber reinforced plastic sand-filled culvert pipe in the EPS composite culvert roadbed of the hybrid water-passing road structure in the embodiment of the utility model;
[0034] In the figure: 1. Cement concrete surface layer; 2. Cement stabilized crushed stone base layer; 3. Geocell-aggregate lateral drainage layer; 3-1. Geocell; 3-2. Filling aggregate; 4. FRP sand-reinforced plastic board waterproof layer; 5. EPS composite culvert roadbed; 5-1. FRP sand-reinforced plastic culvert pipe; 5-2. EPS block; 6. Gravel cushion layer; 7. Retaining wall; 8. Drainage pipe; 9. Waterproof geotextile. DETAILED DESCRIPTION
[0035] The specific implementation methods of the present invention are further described below in conjunction with the accompanying drawings. It should be noted that the description of these implementation methods is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in each implementation method of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0036] Reference Figure 1 to Figure 5 As shown, a water-passing road structure in an embodiment of the utility model includes a cement concrete surface layer 1, a cement-stabilized crushed stone base layer 2, a geocell-aggregate lateral drainage layer 3, a glass fiber reinforced plastic sand-reinforced board waterproof layer 4, an EPS composite culvert roadbed 5, a gravel cushion layer 6, and a retaining wall 7, which are arranged in sequence from top to bottom.
[0037] The cement concrete surface layer 1 is cast with C35 cement concrete and has a thickness in the range of 15 to 20 cm. When laying the cement concrete surface layer 1, the center line of the road is taken as the highest point and the two sides are symmetrically laid with a slope of 2% to avoid water accumulation on the road.
[0038] The cement stabilized gravel base 2 uses graded gravel as the main material and is compacted, with a paving thickness of 15 to 20 cm, a maximum gravel particle size of ≤35 cm and a minimum gravel particle size of ≥10 cm.
[0039] The geocell-granular transverse drainage layer 3 is composed of filling granular materials 3-2 and geocells 3-1. Graded crushed stone, gravel aggregate, old asphalt pavement recycled materials, etc. can be used as fillers. The geocell 3-1 uses high-strength HDPE honeycomb geocells with drainage holes. The cell wall thickness is 2mm and the height is 10-15cm. The particle size of the filling granular materials 3-2 should be 10-20mm, and it should be ensured that the filling granular materials 3-2 are basically consistent with the height of the geocell 3-1 after compaction.
[0040] The glass fiber reinforced plastic sand-filled board waterproof layer 4 is formed by sequentially splicing a plurality of glass fiber reinforced plastic sand-filled boards and is fixed with U-shaped bolts.
[0041] The EPS composite pipe culvert roadbed 5 is composed of EPS blocks 5-2 and multiple glass fiber reinforced plastic sand-filled culvert pipes 5-1. The density of the EPS blocks 5-2 is generally 20-30 kg / m 3 , the compressive strength is greater than 100KPa, the height is 20-25cm, and the EPS special-shaped block is prefabricated to form a groove corresponding to the annular structure of the outer wall of the glass fiber reinforced plastic sand-filled culvert 5-1. The length of the glass fiber reinforced plastic sand-filled culvert 5-1 is the same as the width of the road cross-section structure, with an inner diameter of 1000mm and a wall thickness of 50mm.
[0042] The gravel cushion layer 6 has a paving thickness of 30 to 35 cm and can be used as a construction base and leveling layer for laying the EPS blocks 5 - 2 .
[0043] A plurality of drainage pipes 8 are reserved in the retaining wall 7, and metal filter screens are arranged at the inlet and outlet of the drainage pipes 8 to prevent the loss of granular materials.
[0044] A hybrid water-passing road structure provided in this embodiment is obtained by the following construction steps:
[0045] (1) Preparation of construction materials: ① Prefabricated special-shaped EPS blocks for holding the FRP sand-filled culvert 5-1 on the upper and lower sides and ordinary EPS blocks for filling the EPS composite culvert roadbed. The EPS special-shaped blocks are prefabricated with grooves corresponding to the annular structure of the outer wall of the FRP sand-filled culvert 5-1. The EPS blocks 5-2 should be inspected for compressive strength, density, self-extinguishing properties, etc. They can only be used if they meet all the requirements. The density is generally 20 to 30 kg / m 3 , compressive strength greater than 100KPa, height 20 ~ 25cm. ② Prefabricate a glass fiber reinforced plastic sand-filled culvert 5-1 with an annular outer wall and a smooth inner wall, the length of which is the same as the width of the road cross-section structure. ③ Select a rectangular large frame geocell 3-1 with a high-strength HDPE with a wall thickness of 2mm and a height of 10 ~ 15cm.
[0046] (2) Foundation treatment: first remove the accumulated water in the roadbed of the construction area, clean up the large particles of impurities and gravel in the river channel, and lay a gravel cushion layer 6 with a thickness of 30 to 35 cm as the construction base and leveling layer for laying EPS blocks 5-2.
[0047] (3) Construction of retaining wall 7: After the gravel cushion layer 6 is laid, the foundation of retaining wall 7 is constructed, the foundation steel bars are tied, and the foundation concrete of retaining wall 7 is poured by artificial formwork. After the foundation is cured, the wall body steel bars are tied on site, and the wall body concrete is poured after assembling the steel formwork. Multiple drainage pipes 8 are reserved at the wall body, and metal filters are installed at the inlet and outlet of the drainage pipes 8.
[0048] (4) EPS composite pipe culvert roadbed 5 laying: ① After the gravel cushion layer 6 is laid, remove the seepage (leakage) water around the EPS block 5-2 to keep the construction base surface dry. First lay a layer of 0.5mm thick waterproof geotextile 9 to prevent water from penetrating into the EPS block 5-2 and affecting the stability of the EPS composite pipe culvert roadbed 5. Use manual paving of the bottom EPS block. The bottom EPS block is fixed to the construction base surface with L-shaped or I-shaped metal pins. The pin is inserted into the base to a depth of not less than 20cm. ② Hoist the glass fiber reinforced plastic sand-filled culvert pipe 5-1 and place it on the special-shaped EPS block. The net distance between the pipes is 1.2m. ③ The filling EPS blocks are staggered and stacked from top to bottom to facilitate the continuous force and deformation between the blocks. Double-sided claw-type connectors are used between the EPS blocks 5-2 to prevent slippage and dislocation. ④ The EPS blocks 5-2 must be laid tightly together. If there are gaps exceeding 20 mm and height misalignment exceeding 10 mm during the paving process, sand or non-shrinkage cement mortar should be used to fully fill and level them to ensure that the EPS blocks 5-2 are laid tightly and firmly.
[0049] (5) Laying of FRP sand-reinforced plastic board waterproof layer 4: Water-impermeable and corrosion-resistant FRP sand-reinforced plastic board is used as the main material of FRP sand-reinforced plastic board waterproof layer 4. Multiple FRP sand-reinforced plastic board are placed horizontally in sequence and fixed with U-shaped bolts. After installation, the gaps between the boards are waterproofed. The FRP sand-reinforced plastic board is in direct contact with the top EPS block to prevent the upper water from infiltrating into the EPS composite pipe culvert roadbed 5. The FRP sand-reinforced plastic board makes the EPS block 5-2 filled in the entire EPS composite pipe culvert roadbed 5 form a whole, adjusts the misalignment and unevenness of the EPS block 5-2 during the laying process, prevents a large amount of water and harmful impurities from invading the EPS block 5-2, and can serve as the construction base surface of the upper pavement structure, so that the pavement structure load is evenly spread.
[0050] (6) Laying of geocell-aggregate lateral drainage layer 3: Plan and mark the construction area above the FRP sand-reinforced plastic board waterproof layer 4, first evenly lay a layer of geocell 3-1, and then fill the filling aggregate 3-2 into the geocell 3-1, ensuring that the filler is evenly distributed and compacted to achieve the required firmness and flatness. Graded crushed stone, gravel aggregate, old asphalt pavement recycled material, etc. can be used as filler.
[0051] (7) Laying of cement-stabilized gravel base layer 2: Cement-stabilized gravel with graded gravel as the main material is laid on top of the geocell-aggregate lateral drainage layer 3. The paving thickness is 15 to 20 cm. The maximum particle size of the gravel constituting the cement-stabilized gravel base layer 2 is ≤35 cm and the minimum particle size is ≥10 cm.
[0052] (8) Laying of cement concrete surface layer 1: C35 cement concrete is laid on top of cement stabilized gravel base 2. The thickness of cement concrete surface layer 1 is in the range of 15-20 cm. When laying, the middle is high and the sides are low along the center line of the road, with a slope of 2%. After the concrete is laid, its surface needs to be treated to increase the skid resistance and durability of the road surface.
[0053] Furthermore, steel pipe warning posts are arranged at even intervals on the cement concrete pavement, and flooded pavement warning signs are set at a suitable distance from the intersection.
[0054] Furthermore, drainage during the construction period is mainly to prevent water from soaking the EPS block 5-2. Water absorption will increase the deadweight. In order to improve the waterproof effect, a layer of anti-seepage geotextile can be laid between the FRP sand-reinforced plastic board waterproof layer and the top EPS block.
[0055] In addition, the following matters need to be considered during construction: Given that most flood-crossing roads are located in special environments such as river beaches and flood discharge areas, the construction plan should be arranged reasonably to avoid unfavorable seasons. It is best to complete the roadbed, pavement, culverts and slope protection projects of the sections that have been started in the dry season. For sections that have not been started, it is necessary to carefully advance the project according to weather conditions to avoid floods during the flood season that destroy the unfinished road projects. In addition, since the roadbed of the flood-crossing road is low, when backflow, silt, or soft soil occurs during the construction of the base or subbase, measures should be taken immediately, such as replacing the fill with gravel or mixing lime, to ensure the strength of the base and subbase. A "flood-crossing road" warning sign should be set about 30 meters in front of the flood-crossing road to remind passing drivers to slow down and ensure driving safety.
[0056] As a special type of road, water-crossing roads are suitable for mountainous areas and flood discharge areas. They can not only save investment in road construction and land acquisition, but also minimize the problem of land flooding caused by road construction, effectively ensuring normal traffic. With limited capital investment, water-crossing roads can generate huge economic and social benefits, so they are worthy of further promotion and application.
[0057] The present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and variations of these embodiments without departing from the principles and spirit of the present invention are still within the scope of protection of the present invention.
Claims
1. A hybrid water-passing road structure, characterized in that: From top to bottom, a cement concrete surface layer (1), a cement stabilized crushed stone base layer (2), a geocell-granular material lateral drainage layer (3), a glass fiber reinforced plastic sand-reinforced board waterproof layer (4), an EPS composite pipe culvert roadbed (5), a gravel cushion layer (6), and a retaining wall (7) are sequentially arranged; The EPS composite pipe culvert roadbed (5) comprises an EPS block (5-2) and a glass fiber reinforced plastic sand-filled culvert pipe (5-1); The geocell-granular material transverse drainage layer (3) comprises a geocell (3-1) and filling granular materials (3-2); The glass fiber reinforced plastic sand-filled culvert (5-1) is prefabricated and has an annular outer wall and a smooth inner wall; The EPS block (5-2) comprises a prefabricated special-shaped EPS block for receiving the glass fiber reinforced plastic sand-filled culvert pipe (5-1) from top to bottom and a common EPS block for filling the EPS composite culvert roadbed (5), wherein the special-shaped EPS block has a groove corresponding to the annular structure of the outer wall of the glass fiber reinforced plastic sand-filled culvert pipe (5-1); A layer of waterproof geotextile is laid on top of the gravel cushion layer (6); The retaining wall (7) is flush with the upper surface of the pavement structure layer, and a transverse drainage pipe (8) is provided inside the retaining wall (7).
2. A hybrid water-passing road structure according to claim 1, characterized in that: The cement concrete surface layer (1) is made of cement concrete and is symmetrically laid along the center line of the road to ensure that a certain slope is present on both sides.
3. A hybrid water-passing road structure according to claim 1, characterized in that: After being compacted, the filler in the geocell-granular material transverse drainage layer (3) is consistent with the height of the geocell (3-1).
4. The hybrid water-passing road structure according to claim 1, characterized in that: Each glass fiber reinforced plastic sand-filled culvert (5-1) is arranged perpendicular to the driving direction of the road, and the length of the culvert is the same as the width of the road cross-section structure.
5. The hybrid water-passing road structure according to claim 1, characterized in that: The EPS block (5-2) has a density of 20-30 kg / m³, a compressive strength greater than 100 KPa, and a height of 20-25 cm.