Small foundation pit supporting structure
Through the segmented prefabricated support structure and detachable connection method, combined with large-diameter thick-walled steel pipes, annular thick steel plates and flexible water-stopping materials, the complexity of the construction of the foundation pit support structure in a small space is solved, achieving a fast and safe Foundation pit support and effective utilization of resources.
Patent Information
- Application Number
- CN202323490370.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-21
AI Technical Summary
When constructing deep foundation pits in a small space, traditional foundation pit supporting structures cannot meet the space requirements of construction machinery. The existing prefabricated supporting structures have too many parts and the construction organization is complex. How to reduce the number of parts, improve the degree of prefabrication and Convenience to achieve rapid construction is a problem.
It adopts segmented prefabricated support structure and detachable connection method, and combines large-diameter thick-walled steel pipes, annular thick steel plates and flexible water-stop materials to form a rapid assembly combination to ensure the support effect and construction convenience, and in the foundation pit Reinforcement hoops are provided to increase structural strength.
It achieves rapid construction in a narrow space, ensures the safety of foundation pit excavation, facilitates recycling, and reduces economic costs and energy consumption.
Smart Images

Figure CN221855536U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering and municipal engineering, in particular to a small foundation pit support structure, in particular to a prefabricated steel structure support system applied to a deep foundation pit in a narrow space. Background Art
[0002] Currently, there are few support structures used for small foundation pit excavation in narrow spaces. The traditional foundation pit support mode or caisson mode is still mainly adopted. However, the traditional foundation pit support structure generally requires the use of a water-stop system and a retaining system. In many cases, it is difficult to meet the construction space requirements of construction machinery in a narrow space, and construction cannot be carried out according to the traditional support structure.
[0003] At present, various types of steel sheet piles and combined prefabricated structures can partially solve the existing problems. However, the various types of prefabricated support structures currently have many parts and components, and the on-site construction organization is relatively complex. How to reduce the number of parts, improve the degree of prefabrication, and at the same time take into account construction convenience, mechanical miniaturization and other difficult problems, and quickly and effectively complete the construction of foundation pit support structures in a small space is the current key research direction. Summary of the invention
[0004] The purpose of the utility model is to provide a small foundation pit support structure based on the above-mentioned deficiencies of the prior art. It adopts a prefabricated support structure in sections and cooperates with a detachable connection method. It can be applied in a deep foundation pit in a narrow space, and can achieve rapid assembly while ensuring the support effect.
[0005] The purpose of this utility model is achieved by the following technical solutions:
[0006] A small foundation pit support structure, characterized in that: it includes at least two prefabricated steel structures, the outer contour shape and size of the prefabricated steel structures match the shape and size of the foundation pit; the prefabricated steel structures are arranged along the depth direction of the foundation pit; and the upper and lower adjacent prefabricated steel structures form a detachable fixed connection.
[0007] A connecting steel plate is provided between the prefabricated steel structures. The shape and size of the connecting steel plate match the shape and size of the inner contour of the prefabricated steel structure. The connecting steel plate is arranged on the inner side of the prefabricated steel structure and a part of its plate body is connected to the prefabricated steel structure located above, and the other part is connected to the prefabricated steel structure located below.
[0008] The connecting steel plate and the prefabricated steel structure are connected by through-bolts to form a detachable fixed connection.
[0009] A flexible water-stopping material is arranged between the connecting steel plate and the prefabricated steel structure.
[0010] The connecting steel plate is a closed body with an enclosed area and a closed contour.
[0011] A reinforcement hoop is provided on the inner surface of the prefabricated steel structure.
[0012] The reinforcement hoops are arranged on the prefabricated steel structure at alternating intervals and at a certain distance from the connecting steel plates along the depth direction.
[0013] The prefabricated steel structure is a closed body with an enclosed area and a closed outline.
[0014] The advantages of the utility model are:
[0015] (1) Construction in narrow spaces is achieved by setting up support structures in sections;
[0016] (2) By welding a thick annular steel plate inside a large-diameter thick-walled steel pipe and using the steel plate as a reinforcement hoop, an effective single-section support structure is formed;
[0017] (3) By setting screw holes at both ends of each support structure, connecting steel plates, and sealing flexible water-stopping materials, a quick-assembly combination with water-stopping and connection functions is formed;
[0018] (4) It can ensure the safety of foundation pit excavation;
[0019] (5) It is easy to recycle and reuse, which is beneficial to economic savings and energy consumption reduction. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A cross-sectional schematic diagram of an embodiment provided by the utility model;
[0021] Figure 2 This is a structural schematic diagram of the connection positions between steel pipes in the embodiment provided by the utility model. DETAILED DESCRIPTION
[0022] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0023] like Figure 1-2 As shown, the marks 1-5 in the figure respectively represent: large diameter thick wall steel pipe 1, reinforcement hoop 2, annular thick steel plate 3, flexible water stop material 4, high strength through bolt 5.
[0024] Example: Figure 1 to Figure 2 As shown, the small foundation pit support structure in this embodiment is used to support the foundation pit and can provide a quick assembly construction method in a small space. It can also achieve water stopping of the foundation pit and ensure the safety of excavation, and can be further recycled after the foundation pit construction is completed.
[0025] Specifically, combined Figure 1 and Figure 2 As shown, in this embodiment, the small foundation pit support structure includes a large diameter thick-walled steel pipe 1, which is matched with the contour shape and size of the foundation pit, and can be driven into the predetermined excavation position by vibration or rotation. Here, the large diameter thick-walled steel pipe 1 is matched with the contour shape and size of the foundation pit, which means that the large diameter thick-walled steel pipe 1 is a closed body with a certain enclosed area and a closed contour; for example, when the foundation pit is a circular foundation pit, the cross-section of the large diameter thick-walled steel pipe 1 is circular; when the foundation pit is a rectangle, the cross-section of the large diameter thick-walled steel pipe 1 is actually a rectangle; in short, the large diameter thick-walled steel pipe 1 is a component that plays a supporting role, and it is arranged on the side wall of the foundation pit to resist the soil outside the pit.
[0026] Combination Figure 1 and Figure 2 As shown, in this embodiment, two large-diameter thick-walled steel pipes 1 are arranged along the depth direction of the foundation pit; an annular thick steel plate 3 is arranged between the two large-diameter thick-walled steel pipes 1, and the annular thick steel plate 3 is used to connect the upper and lower large-diameter thick-walled steel pipes 1 to form an integral structure. In this embodiment, the annular thick steel plate 3 is also a closed body with a certain enclosed area and a closed contour, and its shape and size match the inner contour shape and size of the large-diameter thick steel pipe 1. Figure 2 As shown, in the direction shown in the figure, the upper part of the annular thick steel plate 3 is fixedly connected to the large-diameter thick-walled steel pipe located above by high-strength through bolts 5, and the lower part is fixedly connected to the large-diameter thick-walled steel pipe located below by high-strength through bolts 5, thereby fixing the upper and lower large-diameter thick-walled steel pipes 1 to form an integral structure, thereby increasing the structural strength and stability of the support system.
[0027] In this embodiment, when the large-diameter thick-walled steel pipe 1 is prefabricated, through-screw holes matching the high-strength through-screws 5 are reserved, thereby facilitating rapid on-site assembly construction.
[0028] like Figure 2 As shown, in order to avoid water seepage at the joints between the upper and lower adjacent large-diameter thick-walled steel pipes 1, a flexible water-stopping material 4 is arranged between the annular thick steel plate 3 and the large-diameter thick-walled steel pipe 1. The flexible water-stopping material 4 covers the joints between the large-diameter thick-walled steel pipes 1, thereby achieving a water-stopping effect.
[0029] In this embodiment, if Figure 1 As shown, a reinforcing hoop 2 is welded on the inner surface of the large-diameter thick-walled steel pipe 1 to improve the structural strength of the large-diameter thick steel plate 1 and its ability to resist the soil outside the pit. In some cases, the reinforcing hoop 2 is arranged alternately and spaced with the annular thick steel plate 3 at a certain distance along the depth direction of the foundation pit on the large-diameter thick-walled steel pipe 1 to uniformly improve its structural strength.
[0030] During construction, this embodiment includes the following construction methods:
[0031] 1) A large-diameter thick-walled steel pipe 1 prefabricated and welded with a reinforcing hoop 2 is driven into a predetermined excavation position of a foundation pit by means of vibration or rotation, and the large-diameter thick-walled steel pipe 1 is pressed downward.
[0032] 2) Fix the high-strength through bolts 5 to the annular thick steel plate 3, connect it to the next standard section and press down the large-diameter thick-walled steel pipe.
[0033] 3) According to step 2), the long-diameter thick-walled steel pipe 1 is extended in sequence and the annular thick steel plate 3 is connected until the entire support structure reaches the designed length.
[0034] 4) Excavate the earth inside the large-diameter thick-walled steel pipe until the structural construction reaches the designed elevation.
[0035] 5) After the structure is completed, the supporting structure is pulled out and recovered in sections by vibration or rotation.
[0036] In the specific implementation of this embodiment: as the depth of the foundation pit increases, when the height of the large-diameter thick-walled steel pipe 1 is constant, the support purpose can be achieved by further increasing the number of large-diameter thick-walled steel pipes 1; the connection method of the upper and lower adjacent large-diameter thick-walled steel pipes 1 is referred to Figure 2 The method shown is implemented.
[0037] As a prefabricated steel structure, the large diameter thick wall steel pipe 1 always matches the shape and size of the foundation pit; that is, in this embodiment, the prefabricated foundation pit support structure is mainly segmented along the depth direction of the foundation pit to ensure the stability of the support. When recycling is required, the large diameter thick wall steel pipe 1 and each component can be conveniently adapted according to the different shapes and sizes of the foundation pit, so as to adapt to the support requirements of different foundation pits; in this process, the steel components are effectively retained and reused, which is beneficial to economic savings and energy consumption reduction.
[0038] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A small foundation pit support structure, characterized in that: It comprises at least two prefabricated steel structures, the outer contour shape and size of the prefabricated steel structures are consistent with the shape and size of the foundation pit; the prefabricated steel structures are arranged along the depth direction of the foundation pit; The upper and lower adjacent prefabricated steel structures are connected in a detachable fixed manner.
2. A small foundation pit support structure according to claim 1, characterized in that: A connecting steel plate is provided between the prefabricated steel structures. The shape and size of the connecting steel plate match the shape and size of the inner contour of the prefabricated steel structure. The connecting steel plate is arranged on the inner side of the prefabricated steel structure and a part of its plate body is connected to the prefabricated steel structure located above, and the other part is connected to the prefabricated steel structure located below.
3. A small foundation pit support structure according to claim 2, characterized in that: The connecting steel plate and the prefabricated steel structure are connected by through-bolts to form a detachable fixed connection.
4. A small foundation pit support structure according to claim 2, characterized in that: A flexible water-stopping material is arranged between the connecting steel plate and the prefabricated steel structure.
5. A small foundation pit support structure according to claim 2, characterized in that: The connecting steel plate is a closed body with an enclosed area and a closed contour.
6. A small foundation pit support structure according to claim 1, characterized in that: A reinforcement hoop is provided on the inner surface of the prefabricated steel structure.
7. A small foundation pit support structure according to claim 6, characterized in that: The reinforcement hoops are arranged on the prefabricated steel structure at alternating intervals and a certain distance from the connecting steel plates along the depth direction.
8. A small foundation pit support structure according to claim 1, characterized in that: The prefabricated steel structure is a closed body with an enclosed area and a closed outline.