Connecting joint of steel structure and steel beam

By designing the connection method of special-shaped webs and reserved operating holes, the existing technology problems of complicated process and low installation efficiency of connecting nodes between steel structures and steel beams are solved, achieving an efficient and economical connection effect and improving the comfort of the nodes. performance and installation efficiency.

CN221855818UActive Publication Date: 2024-10-18SHANGHAI HUIYE ARCHITECTURAL DESIGN ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323496617.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2024-10-18
Estimated Expiration
2033-12-21

AI Technical Summary

Technical Problem

While ensuring the connection strength, the existing steel structure and steel beam connection nodes have complex processes, low installation efficiency, and low node comfort and economy. Fully welded connections cannot be completed, and additional steel plates and bolts need to be reinforced to prevent deformation and distortion.

Method used

Design a connection node between the steel structure and the steel beam. Through the overlapping connection of special-shaped webs and reserved operating holes, the web connecting plate is omitted, and the mutual overlap and bolt connection between the webs are used to simplify the welding process and avoid additional reinforcement of the steel plate. and the use of bolts.

Benefits of technology

It improves the installation efficiency, improves the comfort and economy of the node, simplifies the process, reduces operating errors, and increases the installation efficiency by about 20%.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855818U_ABST
    Figure CN221855818U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of building steel structures, in particular to a steel structure and steel beam connecting joint which comprises a first component and a second component, the first component comprises a first upper wing plate, a first lower wing plate and a first web plate, and the second component comprises a second upper wing plate, a second lower wing plate and a second web plate. The first upper wing plate is welded with the second upper wing plate, the first lower wing plate is welded with the second lower wing plate, and a first operation hole and a second operation hole are reserved in the two welding positions; the end of the first web and the end of the second web are overlapped and fixed through a connecting piece. After the scheme is adopted, the operation procedures can be reduced and the installation efficiency can be improved while the connection strength is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building steel structures, in particular to a connection node between a steel structure and a steel beam. Background Art

[0002] There are currently two main types of connection nodes between steel structures and beams. One is to set up a cantilever beam connection, and the other is to weld the supporting bracket.

[0003] like Figure 1 As shown, the cantilever beam is mainly prefabricated in two parts, installed centrally on site, and finally locally welded. It is widely used and has a high acceptance rate for component connections. However, node welding requires additional reinforcement steel plate welding, and at the same time, the steel plate position welding is strengthened to connect the steel beams. This type of node cannot complete the rigid-flexible bolt welding connection because the steel plate cannot be fully welded and the deformation connection is insufficient. In order to prevent deformation and distortion, additional bolts are required. The process is complicated and the comfort and safety of the node are not high.

[0004] The supporting structure requires additional supporting steel plates to be welded. It can be used in factories, warehouses and other buildings where comfort requirements are not high. It has certain limitations because there are no exposed beams or columns in civil buildings such as houses. The supporting plates need to be covered by later decoration or other methods, which takes up space and is not economical.

[0005] Therefore, the inventor conducted further research on this and developed a connection node between a steel structure and a steel beam, which resulted in the present case. Utility Model Content

[0006] The utility model aims to provide a connection node between a steel structure and a steel beam, which can reduce the operation procedures and improve the installation efficiency while ensuring the connection strength.

[0007] In order to achieve the above purpose, the technical solution of the utility model is as follows:

[0008] A steel structure and steel beam connection node includes a first component and a second component, the first component includes a first upper wing plate, a first lower wing plate, and a first web plate, and the second component includes a second upper wing plate, a second lower wing plate, and a second web plate; the first upper wing plate is welded to the second upper wing plate, and the first lower wing plate is welded to the second lower wing plate, and a first operation hole and a second operation hole are reserved at the above two welding points; an end of the first web plate overlaps with an end of the second web plate and is fixed by a connecting piece.

[0009] The web plates are directly overlapped and fixed to each other, so the web plate connecting plate can be omitted; through the preset operating holes, full welding can be completed between the wing plates, and there is no need to set up additional reinforcing steel plates for connection.

[0010] Furthermore, both sides of the end of the first web are first arcuate edges, the first upper wing plate and the first lower wing plate are respectively connected to the first arcuate edges, and the end of the first web protrudes from the first upper wing plate and the first lower wing plate.

[0011] Furthermore, both sides of the end of the second web are second arc-shaped edges, and the second upper wing plate and the second lower wing plate are respectively connected to the second arc-shaped edges.

[0012] Furthermore, the first arc-shaped edge and the second arc-shaped edge correspond to form a first operating hole and a second operating hole respectively.

[0013] Since a certain operating space is required for welding, the first web and the second web are designed with special-shaped structures so that operating space for full welding can be reserved when the two are spliced.

[0014] Further, the end of the first web is connected to the end of the second web by bolts.

[0015] Furthermore, pads are provided below the welding points between the first upper wing plate and the second upper wing plate, and below the welding points between the first lower wing plate and the second lower wing plate.

[0016] First, add a pad under the welding point, which is used to seal the solder during welding.

[0017] After adopting the above scheme, the utility model has the following advantages compared with the prior art:

[0018] Two special-shaped components are used for connection, and welding operations are performed through designed operating holes. This does not take up building space and does not require additional bolts, thereby improving the comfort and economy of the node. The process is simple and easy to operate, easy to install, and the error can be controlled. The installation efficiency can be increased by about 20% due to the reduction in operating procedures. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 is a schematic diagram of a prior art cantilever beam connection;

[0020] Figure 2 is a schematic diagram before the first component and the second component are connected;

[0021] Figure 3 It is one of the schematic diagrams after the first component and the second component are connected;

[0022] Figure 4 This is the second schematic diagram after the first component and the second component are connected;

[0023] Description of symbols

[0024] first component 1, first upper wing plate 11, first lower wing plate 12, first web plate 13,

[0025] The second member 2, the second upper wing plate 21, the second lower wing plate 22, the second web plate 23,

[0026] A first operating hole 3 , a second operating hole 4 , a bolt 5 , and a backing plate 6 . DETAILED DESCRIPTION

[0027] The utility model is further described below in conjunction with the accompanying drawings and specific embodiments.

[0028] like Figure 2 As shown, a connection node between a steel structure and a steel beam includes a first member 1 on the left and a second member 2 on the right, wherein the first member 1 includes a first upper wing plate 11, a first lower wing plate 12, and a first web plate 13, and the second member 2 includes a second upper wing plate 21, a second lower wing plate 22, and a second web plate 23. The first web plate 13 has first arcuate edges on both sides of its end, the first upper wing plate 11 and the first lower wing plate 12 are connected to the first arcuate edges respectively, and the end of the first web plate 13 protrudes from the first upper wing plate 11 and the first lower wing plate 12; the second web plate 23 has second arcuate edges on both sides of its end, the second upper wing plate 21 and the second lower wing plate 22 are connected to the second arcuate edges respectively, and the end of the second web plate 23 is flush with the second upper wing plate 21 and the second lower wing plate 22.

[0029] like Figure 3 As shown, when the first component 1 and the second component 2 are connected, the first upper wing plate 11 is welded to the second upper wing plate 21, and the first lower wing plate 12 is welded to the second lower wing plate 22. The two welding points are formed by the structure of their respective webs to form a first operation hole 3 and a second operation hole 4; a pad 6 is arranged under the corresponding operation hole, and the pad 6 is used to assist welding.

[0030] The end of the first web 13 and the overlapping portion of the end of the second web 23 can be fixed by bolts 5, such as Figure 3 As shown, when the end of the first web 13 is relatively wide and short, the bolts 5 are arranged vertically; Figure 4 As shown, when the end of the first web 13 is relatively narrow and long, the bolts 5 are arranged transversely; the specific arrangement depends on the structure of the first component 1 and the second component 2, but the basic connection method remains unchanged.

[0031] The above node connection method and Figure 1 Compared with the prior art, the connecting steel plates are omitted, and the wing plates can be fully welded, thereby improving the installation efficiency.

[0032] The above are only specific embodiments of the present utility model. At the same time, all words such as "upper, lower, left, right, middle" involved in the present utility model are for reference only and are not absolutely limiting. Any non-substantial changes made using the present utility model shall be deemed as an infringement of the protection scope of the present utility model.

Claims

1. A connection node between a steel structure and a steel beam, characterized in that: The invention comprises a first component and a second component, wherein the first component comprises a first upper wing plate, a first lower wing plate, and a first web plate, and the second component comprises a second upper wing plate, a second lower wing plate, and a second web plate; the first upper wing plate is welded to the second upper wing plate, and the first lower wing plate is welded to the second lower wing plate, and a first operating hole and a second operating hole are reserved at the above two welding places; an end portion of the first web plate overlaps with an end portion of the second web plate and is fixed by a connecting member.

2. A steel structure and steel beam connection node according to claim 1, characterized in that: Both sides of the end of the first web are first arcuate edges, the first upper wing plate and the first lower wing plate are respectively connected to the first arcuate edges, and the end of the first web protrudes from the first upper wing plate and the first lower wing plate.

3. The connection node between a steel structure and a steel beam according to claim 1, characterized in that: The second web has second arc-shaped edges on both sides of its end, and the second upper wing plate and the second lower wing plate are respectively connected to the second arc-shaped edges.

4. The connection node between a steel structure and a steel beam according to claim 1, characterized in that: The first arc-shaped edge and the second arc-shaped edge correspond to form a first operating hole and a second operating hole respectively.

5. The connection node between a steel structure and a steel beam according to claim 1, characterized in that: The end of the first web is connected to the end of the second web by bolts.

6. The connection node between a steel structure and a steel beam according to claim 1, characterized in that: Pads are provided below the welding point between the first upper wing plate and the second upper wing plate, and below the welding point between the first lower wing plate and the second lower wing plate.