Pre-embedded steel bar straightening tool
By designing the embedded steel bar straightening tool and using the synergistic effect of the cleaning wrench and the correction wrench, the accuracy and durability problems of the bending correction of the embedded steel bars are solved, and the fast, efficient, and accurate straightening of the steel bars and construction efficiency are achieved. promote.
Patent Information
- Application Number
- CN202323498234.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-20
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-20
AI Technical Summary
In the construction of super high-rise buildings, when the embedded steel bars are bent at 90° and need to be straightened to 180°, it is difficult to achieve accurate correction with conventional tools, and the use of steel pipe sleeves has problems with size matching and easy ends.
A pre-embedded steel bar straightening tool is designed, including a cleaning wrench and a correction wrench. The cleaning wrench consists of a first handle, a sleeve and a claw hammer, and the correction wrench consists of a second handle, a first force arm and a second force arm. , the precise correction of steel bars is achieved through the synergy of the sleeve and the force arm.
It achieves fast, efficient and accurate correction of steel bars, reduces fatigue strength, ensures straight axis of steel bars, and improves construction speed and tool durability.
Smart Images

Figure CN221856228U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction, in particular to a pre-buried steel bar straightening tool. Background Art
[0002] In the super high-rise construction system, the core tube is usually constructed first, and the outer frame part is gradually followed. Due to the climbing of the core tube formwork / building machine, the steel bars connected to the outer frame structure cannot be directly retained on the outside, and need to be pre-bent and buried in the protective layer of the core tube wall column. When the floor slab is constructed, the pre-buried steel bars are chiseled out and effectively connected to the outer frame.
[0003] The climbing formwork is raised close to the wall column surface and the old wall is used as a guide wall. Therefore, the steel bars connecting the outer frame floor slab and the core tube cannot be directly buried. Therefore, the embedded bars are bent and buried along the wall column.
[0004] During the construction of the outer frame structural slab, the outer concrete protective layer of the embedded steel bars is removed, and then the steel bars are straightened and connected to the structural slab steel bars.
[0005] The problem with correction is that the steel bar is bent at 90° and needs to be straightened to 180°. Due to the small radius of the bend and the limited position of the hook, it is difficult for the root of the steel bar to be on the same axis as the anchoring section. Conventional straightening uses a steel pipe to put on the bent part of the steel bar to straighten it. First, the steel pipe is difficult to match the diameter of the steel bar, and the correction effect is poor; second, the end of the steel pipe is easily damaged by force. Utility Model Content
[0006] The purpose of the utility model is to overcome the problems of the prior art and disclose a pre-embedded steel bar straightening tool. Through the structural setting of the pre-embedded steel bar straightening tool of the utility model, high-speed and efficient correction of the steel bar to be corrected is achieved.
[0007] The purpose of the utility model is achieved through the following technical solutions:
[0008] A pre-embedded steel bar straightening tool, comprising: a cleaning wrench and a correction wrench; the cleaning wrench comprises a first handle and a sleeve, and the sleeve is arranged at the end of the first handle; the correction wrench comprises a second handle and a first force arm and a second force arm on both sides of the end of the second handle, and the first force arm and the second force arm are arranged in parallel.
[0009] According to a preferred embodiment, the axis of the sleeve is arranged parallel to the axis of the first handle.
[0010] According to a preferred embodiment, the sleeve is a nut.
[0011] According to a preferred embodiment, a claw hammer is also provided at the end of the cleaning wrench.
[0012] According to a preferred embodiment, the claw hammer and the sleeve are arranged on both sides of the first handle.
[0013] According to a preferred embodiment, the claw hammer is connected to the sleeve and the first handle by welding.
[0014] According to a preferred embodiment, the distance between the first force arm and the second force arm is greater than the diameter of the steel bar to be corrected.
[0015] According to a preferred embodiment, the first force arm and the second force arm are alternately arranged on both sides of the second handle end.
[0016] According to a preferred embodiment, the first force arm and the second force arm are welded to the end of the second handle; or, the first force arm and the second force arm are welded to the end of the second handle via a connecting rod.
[0017] According to a preferred embodiment, the cleaning wrench and the correction wrench are steel structures.
[0018] The above-mentioned main scheme of the utility model and its further optional schemes can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection by the utility model. After understanding the scheme of the utility model, those skilled in the art can understand that there are many combinations based on the existing technology and common knowledge, all of which are technical schemes to be protected by the utility model, and they are not exhaustively listed here.
[0019] Beneficial effects of the utility model:
[0020] The utility model provides a pre-buried steel bar straightening tool. Firstly, it can realize the rapid correction of steel bars to avoid repeated bending and reduce fatigue strength. Secondly, it has higher accuracy and the root can be completely straightened to ensure the stress state of the steel bar axis. Thirdly, it improves efficiency and the construction speed is twice as fast as before. Fourthly, it is sturdy and durable and has a high turnover utilization rate. Fifthly, the tool is easy to make and can be customized according to needs. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a structural schematic diagram of a cleaning wrench in the pre-buried steel bar straightening tool of the utility model;
[0022] Figure 2 It is a structural schematic diagram of a correction wrench in the utility model of a pre-buried steel bar straightening tool;
[0023] Among them, 100 is a cleaning wrench, 101 is a first handle, 102 is a sleeve, 103 is a claw hammer, 200 is a correction wrench, 201 is a second handle, 202 is a first lever arm, and 203 is a second lever arm. DETAILED DESCRIPTION
[0024] The following describes the implementation of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific implementations, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict.
[0025] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0026] In the description of the present utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate the orientation or position relationship based on the orientation or position relationship shown in the accompanying drawings, or the orientation or position relationship in which the utility model product is usually placed when in use, which is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.
[0027] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0028] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0029] In addition, the present utility model should point out that, in the present utility model, if the specific structure, connection relationship, position relationship, power source relationship, etc. are not specifically written out, the structure, connection relationship, position relationship, power source relationship, etc. involved in the present utility model are all known by technical personnel in this field on the basis of existing technology without creative work.
[0030] Example 1
[0031] refer to Figure 1 and Figure 2 As shown in the figure, a pre-embedded steel bar straightening tool is shown, and the pre-embedded steel bar straightening tool comprises: a cleaning wrench 100 and a correction wrench 200, and the cleaning wrench 100 and the correction wrench 200 are steel structures. The cleaning wrench 100 is used to complete the rough adjustment of the pre-embedded steel bar, and the correction wrench 200 is used to complete the precise correction of the pre-embedded steel bar.
[0032] Preferably, the cleaning wrench 100 includes a first handle 101 and a sleeve 102 , and the sleeve 102 is disposed at the end of the first handle 101 .
[0033] Furthermore, the axis of the sleeve 102 is arranged parallel to the axis of the first handle 101. By arranging the axis of the sleeve 102 to be coaxial with the first handle 101, it is helpful to improve the user-friendliness of the operator, that is, the length of the first handle 101 is the length of a lever, which is helpful to save effort.
[0034] Preferably, the end of the cleaning wrench 100 is also provided with a claw hammer 103. The claw hammer 103 can be used to remove the concrete attached to the embedded steel bars.
[0035] Preferably, the claw hammer 103 and the sleeve 102 are disposed on both sides of the first handle 101 , which helps to protect the connection stability between the sleeve 102 and the first handle 101 .
[0036] Preferably, the claw hammer 103 is welded to the sleeve 102 and the first handle 101. Further, the sleeve 102 can be made of a nut, and the hole diameter is selected to be 2mm larger than the diameter of the correction steel bar to ensure that the steel bar can pass smoothly.
[0037] Preferably, the calibration wrench 200 includes a second handle 201 and a first lever 202 and a second lever 203 disposed at both ends of the second handle 201, and the first lever 202 and the second lever 203 are disposed in parallel. The distance between the first lever 202 and the second lever 203 is greater than the diameter of the steel bar to be calibrated.
[0038] Preferably, the first force arm 202 and the second force arm 203 are alternately arranged on both sides of the end of the second handle 201 .
[0039] Furthermore, the first force arm 202 and the second force arm 203 are connected to the end of the second handle 201 by welding; or, the first force arm 202 and the second force arm 203 are connected to the end of the second handle 201 by welding via a connecting rod.
[0040] Specifically, the main function of the cleaning wrench 100 is to cover the steel bar with the sleeve 102 to initially turn it from the original buried state along the wall to the same direction as the anchor end, and then use the correction wrench 200 to gradually straighten the bent hook.
[0041] The utility model provides a pre-buried steel bar straightening tool. Firstly, it can realize the rapid correction of steel bars to avoid repeated bending and reduce fatigue strength. Secondly, it has higher accuracy and the root can be completely straightened to ensure the stress state of the steel bar axis. Thirdly, it improves efficiency and the construction speed is twice as fast as before. Fourthly, it is sturdy and durable and has a high turnover utilization rate. Fifthly, the tool is easy to make and can be customized according to needs.
[0042] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A pre-buried steel bar straightening tool, characterized in that: The pre-buried steel bar straightening tool comprises: a cleaning wrench (100) and a correction wrench (200); The cleaning wrench (100) comprises a first handle (101) and a sleeve (102), wherein the sleeve (102) is arranged at the end of the first handle (101); The calibration wrench (200) comprises a second handle (201) and a first force arm (202) and a second force arm (203) arranged at two sides of the end of the second handle (201), and the first force arm (202) and the second force arm (203) are arranged in parallel; The axis of the sleeve (102) is arranged parallel to the axis of the first handle (101); the sleeve (102) is a nut; The end of the cleaning wrench (100) is also provided with a claw hammer (103); the claw hammer (103) and the sleeve (102) are respectively provided on both sides of the first handle (101); The distance between the first force arm (202) and the second force arm (203) is greater than the diameter of the steel bar to be corrected; The first force arm (202) and the second force arm (203) are alternately arranged on both sides of the end of the second handle (201); The first force arm (202) and the second force arm (203) are welded and connected to the end of the second handle (201); Alternatively, the first force arm (202) and the second force arm (203) are connected to the second handle (201) by welding via a connecting rod to the end of the second handle (201).
2. The embedded steel bar straightening tool according to claim 1, characterized in that: The claw hammer (103), the sleeve (102) and the first handle (101) are connected by welding.
3. The embedded steel bar straightening tool according to claim 1, characterized in that: The cleaning wrench (100) and the calibration wrench (200) are steel structures.