Mounting tool for ALC (autoclaved lightweight concrete) wallboard in building construction
By designing an ALC wall panel installation tool that includes a trolley base, a column, a pulley and an electric hoist, the installation difficulty and waste problems caused by the weight and size of the wall panels during construction are solved, and efficient and safe wall panel installation is achieved.
Patent Information
- Application Number
- CN202323406585.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-14
AI Technical Summary
In construction, ALC wall panels are difficult to install due to their large weight and size using traditional manual operations, which can easily lead to damage to the edges and corners of the wall panels and waste of materials, affecting the construction progress.
An installation tool is designed that includes a rectangular trolley base, upright columns, horizontal braces, inclined support rods, fixed pulleys, electric hoists and wire ropes. The electric hoists pull the wire ropes to achieve the erection and movement of wall panels, using universal wheels and locking devices. Ensure a stable installation.
It reduces the difficulty of construction, improves work efficiency, avoids damage to the edges and corners of wall panels and waste of materials, and improves the installation efficiency of ALC wall panels.
Smart Images

Figure CN221856242U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to a tool for installing a wall panel in a building construction, in particular to a tool for installing an ALC wall panel in a building construction. Background Art
[0002] AIC wall panels are porous concrete panels (containing treated reinforced steel bars) made of fly ash, cement, lime and other raw materials, cured by high-pressure steam. During the construction process, ALC wall panels are heavy and, when traditional manpower is used in construction, the number of construction workers and the difficulty will increase, affecting the construction progress. During the hoisting process, the edges and corners of the wall panels will be damaged, wasting the raw materials of the ALC wall panels. Especially in public buildings, the size and weight of the wall panels are large, making it more difficult to construct them by manpower. Utility Model Content
[0003] The purpose of the utility model is to provide an ALC wall panel installation tool for construction, which has a reasonable structure, can reduce the difficulty of construction, improve work efficiency, avoid damage to the edges and corners of the wall panel during the lifting process, and avoid waste of ALC wall panel raw materials.
[0004] The purpose of the utility model is achieved as follows: a construction ALC wall panel installation tool, including an ALC wall panel, a wheel with a locking device is arranged at the lower part of a rectangular trolley base, two upright columns are respectively fixed to the two corners of the front end of the trolley base table, a cross brace is evenly connected between the two columns, an inclined support rod is respectively connected between the upper parts of the two columns and the two corners of the rear end of the trolley base table, a fixed pulley is hung on the cross beam arranged at the upper end between the two columns, an electric hoist is installed on the table of the trolley base through a connecting seat, the other end of the wire rope connected to the electric hoist drum passes through the fixed pulley upward and hangs downward, the end of the wire rope hanging downward is connected to a hook, and the hook is hung with a strap tied to the ALC wall panel.
[0005] The utility model includes an operating frame, a fixed pulley, a wire rope, and an electric hoist. The operating frame uses a square steel pipe to weld a rectangular trolley base, and the upper frame body uses a round steel pipe to weld a triangular frame body. A fixed pulley is fixed on the uppermost crossbar. One end of the wire rope is connected to the electric hoist, and the other end is connected to a hook. The electric hoist pulls the wire rope passing through the fixed pulley. The other end is connected to the hook on the strap for tying the wall panel. The electric hoist pulls the wire rope to pull the wall panel off the ground and push the trolley to move to a designated position for installation.
[0006] The universal wheel is fixed to the square steel of the base of the operating frame trolley by welding, so that the trolley can move the ALC wall panel to the specified position and is equipped with a locking device. A fixed pulley is provided at the top of the operating frame, and an electric hoist is provided on the base of the operating frame for lifting the wall panel.
[0007] Specific principle: Before use, lock the locking device of the universal wheel, connect one end of the wire rope to the electric hoist, pass through the fixed pulley and connect the other end to the strap of the ALC wall panel, erect the wall panel through the traction of the electric hoist, open the locking device of the universal wheel, push it to the designated position, lock the universal wheel and install the wall panel.
[0008] The utility model has a reasonable structure, reduces the construction difficulty, improves the work efficiency, avoids the damage to the corners of the wall panel during the hoisting process, and avoids the waste of raw materials of the ALC wall panel. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] The utility model will be further described below in conjunction with the accompanying drawings. Figure 1 This is a schematic diagram of the main structure of the utility model. Figure 2 for Figure 1 Schematic diagram of the right view structure. DETAILED DESCRIPTION
[0010] A construction ALC wall panel installation tool, such as Figure 1 , Figure 2 As shown, it includes an ALC wall panel 1, a wheel 3 with a locking device is arranged at the lower part of a rectangular trolley base 2, two upright columns 4 are respectively fixed to the two corners of the front end of the table top of the trolley base 2, a cross brace 12 is evenly connected between the two columns 4, an inclined support rod 5 is respectively connected between the upper parts of the two columns 4 and the two corners of the rear end of the table top of the trolley base 2, a fixed pulley 6 is hung on the cross beam 13 arranged at the upper end between the two columns 4, an electric hoist 7 is installed on the table top of the trolley base 2 through a connecting seat, the other end of the wire rope 8 connected to the drum of the electric hoist 7 passes through the fixed pulley 6 upward and hangs downward, and the end of the wire rope hanging downward is connected to a hook 9, and the hook 9 is hung with a strap tied to the ALC wall panel 1. A fence is arranged on the table of the trolley base 2. The fence has a structure in which vertical poles 10 are arranged at the four corners of the rear end of the table of the trolley base 2, and horizontal connecting rods 11 are connected to the upper end between two vertical poles 10 and between the two vertical poles 10 and the corresponding columns 4. The trolley base 2 is composed of square steel pipes. The two columns 4 and the support rod 5 are respectively composed of round steel pipes.
Claims
1. A construction ALC wall panel installation tool, comprising an ALC wall panel (1), Its characteristics are: A wheel (3) with a locking device is arranged at the lower part of the rectangular trolley base (2), two upright columns (4) are respectively fixed to the two corners at the front end of the table of the trolley base (2), a cross brace (12) is evenly connected between the two columns (4), an inclined support rod (5) is respectively connected between the upper part of the two columns (4) and the two corners at the rear end of the table of the trolley base (2), a fixed pulley (6) is hung on the cross beam (13) arranged at the upper end between the two columns (4), an electric hoist (7) is installed on the table of the trolley base (2) through a connecting seat arranged, the other end of the steel wire rope (8) connected to the drum of the electric hoist (7) passes through the fixed pulley (6) upward and hangs downward, the end of the steel wire rope hanging downward is connected to a hook (9), and the hook (9) is hung with a strap tied to the ALC wall panel (1).
2. A construction ALC wall panel installation tool according to claim 1, Its characteristics are: A fence is arranged on the table top of the trolley base (2), and the structure of the fence is that vertical poles (10) are respectively arranged at the four corners of the rear end of the table top of the trolley base (2), and horizontal connecting rods (11) are respectively connected at the upper end between two vertical poles (10) and between the two vertical poles (10) and the corresponding columns (4).
3. A construction ALC wall panel installation tool according to claim 1, Its characteristics are: The trolley base (2) is composed of square steel pipes.
4. A construction ALC wall panel installation tool according to claim 1, Its characteristics are: The two upright posts (4) and the support rod (5) are respectively formed of round steel pipes.