Building construction discharging device

By using sliding components and fixed components in the construction unloading device, the problem of transportation inconvenience and safety risks caused by the large suspended area of ​​the hopper is solved, the stable movement and automatic fixation of the hopper are achieved, and the workers are ensured to transport materials safely and quickly.

CN221856247UActive Publication Date: 2024-10-18浙江汉盛建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420314571.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-20
Publication Date
2024-10-18
Estimated Expiration
2034-02-20

AI Technical Summary

Technical Problem

During construction, after the unloading device is installed, the suspended area between the hopper and the building floor is large, making it inconvenient for workers to transport materials and posing safety risks.

Method used

A construction unloading device is designed, which uses sliding components and fixed components. Through components such as sliders, driving parts, rollers and guide wheels, the hopper can move stably and be automatically fixed on the side close to the building, reducing the hanging area and ensuring Safe and fast transportation for workers.

Benefits of technology

It effectively reduces the suspended area between the hopper and the building floor, improves the movement stability and fixation reliability of the hopper, and ensures safe and fast material transportation for workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221856247U_ABST
    Figure CN221856247U_ABST
Patent Text Reader

Abstract

The utility model discloses a building construction discharging device, and relates to the field of building construction, the building construction discharging device comprises a tray, a hopper and a lifting rope, the hopper is arranged on the tray, the tray is fixedly arranged on a building floor, the lifting rope is connected with the tray and a building upper floor, and the tray comprises two supporting beams and a plurality of connecting rods; the two ends of the multiple connecting rods are fixedly connected with the two supporting beams, a sliding assembly is arranged at the bottom of the hopper and arranged on the two supporting beams in the length direction of the supporting beams in a sliding mode, and a positioning assembly used for fixing the hopper is arranged on the hopper. The sliding assembly is used for driving the hopper to move in the building direction, after the hopper moves, the suspended area between the hopper and the building floor is greatly reduced, then the fixing assembly is used for fixing the hopper to the supporting beam, and therefore workers can safely and rapidly transport materials back and forth conveniently.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction, and in particular to a building construction unloading device. Background Art

[0002] The unloading device is a device used for material transportation, turnover and unloading in construction. It is usually installed on the outside of the building. The use of the unloading device can facilitate the transportation of construction materials and equipment, etc., improve construction efficiency, and reduce the labor intensity and safety risks of manual handling.

[0003] At present, the unloading device is composed of a pallet, a hopper and a lifting rope. One side of the hopper is opened and fixedly mounted on the pallet, and the end of the pallet close to the opening of the hopper is fixedly mounted on the building floor. One end of the lifting rope is fixed on the pallet, and the other end is fixed on the upper floor of the building. The pallet and the lifting rope jointly support the hopper, making the hopper more stable.

[0004] The unloading device is lifted by lifting equipment and installed. Since scaffolding and safety nets are installed on the outside of the building, there will be a large suspended area between the hopper and the building floor after the unloading device is installed. On the one hand, it is inconvenient for workers to transport materials back and forth. On the other hand, it is easy to get into danger during the workers' round-trip transportation. Utility Model Content

[0005] In order to facilitate workers to transport materials back and forth safely and quickly, the present application provides a construction unloading device.

[0006] The present application provides a construction unloading device that adopts the following technical solution:

[0007] A construction unloading device includes a pallet, a hopper and a lifting rope, wherein the hopper is arranged on the pallet, and the pallet is fixedly arranged on a building floor, and the lifting rope connects the pallet and the upper floor of the building, and the pallet includes two supporting beams and a plurality of connecting rods, and both ends of the plurality of connecting rods are fixedly connected to the two supporting beams, and a sliding assembly is arranged at the bottom of the hopper, and the sliding assembly is slidably arranged on the two supporting beams along the length direction of the supporting beams, and a positioning assembly for fixing the hopper is arranged on the hopper.

[0008] By adopting the above technical solution, the hopper is installed on the building floor through a pallet and a hanging rope, and the sliding component is used to drive the hopper to move toward the building. After the hopper moves, the suspended area between the hopper and the building floor is greatly reduced. The fixing component is then used to fix the hopper on the support beam, thereby facilitating workers to transport materials back and forth safely and quickly.

[0009] Preferably, the sliding assembly includes a slider, a driving member and a plurality of rollers, the slider is fixedly arranged at the bottom of the hopper, the plurality of rollers are installed in the slider for rotation at intervals along the length direction of the support beam, the rollers are rotatably arranged on the support beam, the driving member is arranged in the hopper, and the driving end of the driving member is transmission-connected to the rotating shaft of the roller.

[0010] By adopting the above technical solution, the driving member drives the roller to rotate on the support beam, the roller drives the slider to move, and the slider drives the hopper to move along the length direction of the support beam, so that the hopper can move stably.

[0011] Preferably, the support beam is an I-beam, the roller is routable on the top wall of the support beam, the slider is provided with connecting blocks on both side walls along the width direction of the support beam, and a plurality of guide wheels are provided on the side walls where two connecting blocks are close to each other, and the plurality of guide wheels are routable on both sides of the width direction of the support beam along the length direction of the support beam.

[0012] By adopting the above technical solution, when the roller drives the hopper to move through the slider, the slider drives the two connecting blocks to move synchronously, and the two connecting blocks drive the two guide wheels to abut against the two sides of the width direction of the support beam respectively, thereby limiting the movement of the slider, making the movement of the hopper along the length direction of the support beam more stable.

[0013] Preferably, the positioning assembly includes a positioning seat, a first fixed block, a second fixed block and a pull rod, the first fixed block is fixedly set at the end of the slider in the length direction, the positioning seat is fixedly set on the top wall of the support beam, the second fixed block is slidably set in the positioning seat along the vertical direction, the pull rod is set on the top of the second fixed block, the top end of the pull rod passes through the positioning seat and extends out of the positioning seat, a positioning groove is opened on the side wall of the positioning seat close to the first fixed block, the first fixed block slides into the positioning groove, and the second fixed block is clamped and fixed to the first fixed block.

[0014] By adopting the above technical solution, when the hopper moves to one side close to the building, the hopper drives the first fixed block to move into the positioning groove of the positioning seat through the slider. At this time, the second fixed block is pulled upward. After the first fixed block moves to below the second fixed block, the pull rod is released, and the second fixed block moves downward and forms a clamping fixation with the first fixed block, thereby fixing the hopper and making the hopper more stable when workers deliver materials back and forth.

[0015] Preferably, a first inclined wall is formed at one end of the first fixing block close to the positioning seat, and a second inclined wall is formed at one end of the second fixing block close to the first fixing block, the first inclined wall slidably abuts against the second inclined wall and causes the second fixing block to rise; a first clamping block is formed on the top wall of the first fixing block close to one end of the positioning seat, and a second clamping block is formed on the bottom wall of the second fixing block close to one end of the first fixing block, when the second fixing block rises, the second fixing block drives the second clamping block to rise, and when the first inclined wall is separated from the second inclined wall, the second fixing block drives the second clamping block to descend, the second clamping block abuts against the first clamping block and causes the second fixing block to be clamped and fixed to the first fixing block.

[0016] By adopting the above technical solution, when the first fixing block is inserted into the positioning groove of the positioning seat, the first fixing block can automatically drive the second fixing block to rise through the first inclined wall and the second inclined wall. After the first inclined wall and the second inclined wall are separated, the second fixing block drives the second clamping block to descend, and the second clamping block abuts against the first clamping block to clamp and fix the first fixing block and the second fixing block. With such a configuration, when the hopper moves to a side close to the building, the first fixing block and the second fixing block can automatically form a clamping fixation, thereby facilitating the rapid fixation of the hopper.

[0017] Preferably, the outer side wall of the pull rod is provided with a first warning ring and a second warning ring at intervals along its own axial direction, and the first warning ring is located above the second warning ring. When the first fixed block has not entered the positioning seat, the first warning ring of the pull rod is located above the positioning seat, and the second warning ring is located in the positioning seat. When the first fixed block and the second fixed block are clamped and fixed, the second warning ring is located above the positioning seat.

[0018] By adopting the above technical solution, when the first fixing block and the second fixing block do not form a snap-fitting fixing relationship, the worker can only see the first warning ring. When the first fixing block and the second fixing block form a snap-fitting fixing relationship, the worker can see the first warning ring and the second warning ring at the same time, thereby facilitating the worker to quickly determine whether the hopper is fixed.

[0019] Preferably, an elastic member is disposed in the positioning seat, one end of the elastic member abuts against the top wall of the second fixing block, and the other end of the elastic member abuts against the top wall of the inner cavity of the positioning seat.

[0020] By adopting the above technical solution, after the first fixing block and the second fixing block are clamped and fixed, the elastic member acts on the second fixing block and makes the second fixing block press against the first fixing block, so that the first fixing block and the second fixing block are not easy to be separated from the clamping and fixing relationship.

[0021] Preferably, the elastic member is sleeved on the pull rod.

[0022] By adopting the above technical solution, the pull rod limits the elastic member, making the elastic member more stable when contracting and extending.

[0023] In summary, the present application includes at least one of the following beneficial technical effects:

[0024] 1. Use the sliding assembly to drive the hopper to move toward the building. After the hopper moves, the suspended area between the hopper and the building floor is greatly reduced. Then use the fixing assembly to fix the hopper on the support beam, so that workers can transport materials back and forth safely and quickly;

[0025] 2. With the help of the guide wheel, when the roller drives the hopper to move through the slider, the slider drives the two connecting blocks to move synchronously, and the two connecting blocks drive the two guide wheels to abut on both sides of the width direction of the support beam respectively, thereby limiting the movement of the slider, making the hopper move more stably along the length direction of the support beam;

[0026] 3. By adopting the first warning ring and the second warning ring, when the first fixed block and the second fixed block do not form a snap-fitting relationship, the worker can only see the first warning ring. When the first fixed block and the second fixed block form a snap-fitting relationship, the worker can see the first warning ring and the second warning ring at the same time, thereby facilitating the worker to quickly determine whether the hopper is fixed. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a schematic diagram of the overall structure of the construction unloading device of this application;

[0028] Figure 2 This is a partial structural exploded diagram of the construction unloading device of this application;

[0029] Figure 3 For this application Figure 2 The enlarged schematic diagram at A in the middle;

[0030] Figure 4 The construction unloading device of the present application is a schematic diagram for highlighting the state where the first fixing block and the second fixing block are not fixed by a clamping connection;

[0031] Figure 5 The construction unloading device of the present application is a schematic diagram showing a state in which the first fixing block and the second fixing block are clamped and fixed;

[0032] Figure 6 For this application Figure 2 Enlarged schematic diagram of point B in the middle.

[0033] 1. Tray; 11. Support beam; 12. Connecting rod; 2. Hopper; 3. Lifting rope; 4. Sliding assembly; 41. Sliding block; 42. Driving member; 43. Roller; 5. Positioning assembly; 51. Positioning seat; 52. First fixed block; 53. Second fixed block; 54. Pull rod; 6. Connecting block; 7. Guide wheel; 8. Positioning groove; 9. First inclined wall; 10. Second inclined wall; 13. First clamping block; 14. Second clamping block; 15. First warning ring; 16. Second warning ring; 17. Elastic member; 18. Connecting shaft; 19. First lifting ring; 20. Second lifting ring; 21. Limiting plate; 22. First magnet; 23. Second magnet. DETAILED DESCRIPTION

[0034] The following is combined with Figure 1-6 This application is described in further detail.

[0035] The embodiment of the present application discloses a construction unloading device.

[0036] Reference Figure 1 A construction unloading device includes a tray 1, a hopper 2 and four lifting ropes 3. One end of the hopper 2 in the length direction is open and installed on the tray 1, and the lifting device lifts the unloading device through the hopper 2. The side of the support plate close to the open end of the hopper 2 is fixedly installed on the building floor, and two first lifting rings 19 are installed on both sides of the tray 1 in the width direction of the hopper 2. One end of the four lifting ropes 3 is connected to the four first lifting rings 19, and the other end is connected to the upper floor of the building, and the tray 1 and the lifting ropes 3 jointly support the hopper 2.

[0037] Reference Figure 1 and Figure 2 The pallet 1 is composed of two support beams 11 and a plurality of connecting rods 12. The two support beams 11 are parallel to each other and are both I-beams. The connecting rods 12 are installed in a direction perpendicular to the support beams 11. The two ends of the connecting rods 12 are respectively fixedly connected to the two support beams 11, and the plurality of connecting rods 12 are arranged at intervals along the length direction of the support beams 11. Every two first hanging rings 19 are fixedly installed on one support beam 11, and the ends of the two support beams 11 in the length direction are fixed on the building floor.

[0038] A sliding assembly 4 is installed on the bottom wall of the hopper 2, and a positioning assembly 5 is installed on the hopper 2 and the support beam 11. The sliding assembly 4 can drive the hopper 2 to move toward the building along the length direction of the support beam 11, and the positioning assembly 5 can fix the hopper 2 on the support beam 11. The sliding assembly 4 is used to drive the hopper 2 to move toward the building. After the hopper 2 moves, the suspended area between the hopper 2 and the building floor is greatly reduced, and then the fixing assembly is used to fix the hopper 2 on the support beam 11, so that workers can safely and quickly transport materials back and forth.

[0039] Reference Figure 2 and 3 Specifically, the sliding assembly 4 includes a driving member 42, two sliders 41 and a plurality of rollers 43. The slider 41 is fixedly installed on the bottom wall of the hopper 2 along the length direction of the support beam 11. The two sliders 41 are fixedly installed along the width direction of the hopper 2, and the two sliders 41 are located directly above the two support beams 11. The plurality of rollers 43 are rotatably installed on the bottom walls of the two sliders 41 at equal intervals along the length direction of the support beam 11, and the rollers 43 are rollingly installed on the top wall of the support beam 11.

[0040] The driving member 42 is fixedly installed in the hopper 2. A connecting shaft 18 is installed between the symmetrical rollers 43 on the two support beams 11. The connecting shaft 18 can make the rollers 43 on the two support beams 11 rotate synchronously. The driving end of the driving member 42 passes through the side wall of the hopper 2 and is connected to the rotating shaft of the roller 43 through gears and a transmission chain. In the present application, the driving member 42 can be selected as a motor. The driving member 42 drives the rollers 43 to rotate through gears and a transmission chain. The rollers 43 on one support beam 11 drive the rollers 43 on the other support beam 11 to rotate synchronously through the connecting shaft 18. In the slider 41 close to the driving member 42, two adjacent rollers 43 are connected through gears and a transmission chain. When one roller 43 rotates, multiple rollers 43 on the slider 41 can rotate synchronously, so that the hopper 2 can move stably.

[0041] Each slider 41 is fixedly mounted with a connection block 6 on both side walls along its width direction, and two connection blocks 6 on one side of the slider 41 are installed at intervals along the length direction of the slider 41, and the two connection blocks 6 are located in two belly cavities in the width direction of the support beam 11. A plurality of guide wheels 7 are installed at intervals along the length direction of the support beam 11 on the side wall of each connection block 6 close to the web of the support beam 11, and the guide wheels 7 are installed on the web of the support beam 11 in a rolling manner along the length direction of the support beam 11.

[0042] When the hopper 2 moves, the slider 41 drives the connecting block 6 to move synchronously, and the connecting block 6 drives the guide wheel 7 to roll on the web of the support beam 11. Since the multiple guide wheels 7 are respectively located on both sides of the web of the support beam 11, the movement of the slider 41 can be limited, so that the slider 41 can move stably along the diameter direction of the support beam 11, thereby making the movement of the hopper 2 more stable.

[0043] Reference Figure 1 and Figure 3, second lifting rings 20 are fixedly installed at the four corners of the inner cavity of the hopper 2. The lifting equipment can lift the hopper 2 through the four second lifting rings 20, and the hopper 2 drives the pallet 1 to move through the slider 41 and the connecting block 6. The two support beams 11 are fixedly installed with a limit plate 21 at the ends away from the building. The slider 41 and the hopper 2 move to abut against the limit plate 21. The limit plate 21 limits the movement of the slider 41 so that the slider 41 will not slip off the support beam 11. At the same time, when lifting the unloading device, a wooden wedge block is inserted into the bottom of the roller 43 at one end away from the limit plate 21 to limit the slider 41 so that the hopper 2 will not slide on the pallet 1 when lifting the unloading device.

[0044] Reference Figure 1 , Figure 4 and Figure 5 Specifically, two positioning assemblies 5 are installed, and the two positioning assemblies 5 are respectively installed on two supporting beams 11. The positioning assembly 5 includes a positioning seat 51, a first fixing block 52, a second fixing block 53 and a pull rod 54. The positioning seat 51 is fixedly installed on the top wall of the supporting beam 11, and the first fixing block 52 is fixedly installed on the end wall of the slider 41 close to the positioning seat 51. A positioning groove 8 is opened on the side wall of the positioning seat 51 close to the first fixing block 52. When the hopper 2 moves to the side close to the building, the slider 41 drives the first fixing block 52 to be inserted into the positioning groove 8.

[0045] A first clamping block 13 is fixedly mounted on one end of the top wall of the first fixing block 52 near the positioning seat 51, and a first inclined wall 9 is formed between the first clamping block 13 and the end of the first fixing block 52 near the positioning seat 51. The second fixing block 53 is slidably mounted in the positioning seat 51 along the vertical direction, and a second clamping block 14 is fixedly mounted on one end of the bottom wall of the second fixing block 53 near the first fixing block 52, and a second inclined wall 10 is formed between the second clamping block 14 and the end of the second fixing block 53 near the first fixing block 52, and the second inclined wall 10 is parallel to the first inclined wall 9.

[0046] The pull rod 54 is fixedly mounted on the top wall of the second fixing block 53, and the top end of the pull rod 54 slides through the positioning seat 51 and extends outside the positioning seat 51. An elastic member 17 is sleeved on the pull rod 54, and the two ends of the elastic member 17 respectively abut against the top wall of the inner cavity of the positioning seat 51 and the top wall of the second fixing block 53. In the present application, the elastic member 17 can be selected as a spring.

[0047] When the first fixing block 52 enters the positioning seat 51 through the positioning groove 8, the first inclined wall 9 abuts against the second inclined wall 10. As the first fixing block 52 continuously moves into the positioning seat 51, the second fixing block 53 is continuously lifted up, and the second fixing block 53 presses the elastic member 17. When the first inclined wall 9 is separated from the second inclined wall 10, the elastic member 17 releases elastic potential energy and pushes the second fixing block 53 to move downward. At this time, the first clamping block 13 and the second clamping block 14 abut against each other, so that the first fixing block 52 and the second fixing block 53 are clamped and fixed.

[0048] When the hopper 2 moves to a side close to the building, the slider 41 drives the first fixing block 52 to be inserted into the positioning groove 8, and the second fixing block 53 automatically forms a snap-fitting fit with the first fixing block 52, thereby automatically fixing the hopper 2, making the hopper 2 more stable when workers transport materials back and forth.

[0049] The first warning ring 15 and the second warning ring 16 are installed on the outer wall of the pull rod 54 along its own axis direction. The first warning ring 15 is red, the second warning ring 16 is green, and the first warning ring 15 is located above the second warning ring 16. When the first fixing block 52 does not enter the positioning seat 51, the first warning ring 15 of the pull rod 54 is located above the positioning seat 51, and the second warning ring 16 is located inside the positioning seat 51. When the first fixing block 52 and the second fixing block 53 are clamped and fixed, the pull rod 54 is driven up by the second fixing block 53, and the second warning ring 16 moves to the top of the positioning seat 51. The warning rings of different colors can help workers quickly determine whether the hopper 2 is fixed.

[0050] When the worker finishes transporting the materials, he pulls up the pull rod 54, which drives the second fixing block 53 to rise, and the second fixing block 53 drives the second clamping block 14 to rise, and the second clamping block 14 separates from the first clamping block 13, thereby contacting the clamping and fixing relationship between the first fixing block 52 and the second fixing block 53. At this time, the hopper 2 can be reset by moving it away from the building.

[0051] Reference Figure 2 and Figure 6 Two first magnets 22 are fixedly embedded on the side wall of the limit plate 21 close to the hopper 2, and a second magnet 23 is fixedly embedded in the end wall of each slider 41 close to the limit plate 21, and the first magnet 22 and the second magnet 23 attract each other. When the hopper 2 moves away from the building to reset, the hopper 2 drives the slider 41 to move against the limit plate 21, and the first magnet 22 and the second magnet 23 attract each other, thereby fixing the hopper 2 so that the hopper 2 will not move.

[0052] The implementation principle of a construction unloading device in an embodiment of the present application is: a driving member 42 is used to drive multiple rollers 43 to rotate synchronously, and the rollers 43 drive the hopper 2 to move toward the building direction through the slider 41. After the hopper 2 moves, the suspended area between the hopper 2 and the building floor is greatly reduced; when the hopper 2 moves to one side close to the building, the slider 41 drives the first fixed block 52 to be inserted into the positioning groove 8 of the positioning seat 51, and the second fixed block 53 automatically forms a snap-fitting and fixed fit with the first fixed block 52, so that the hopper 2 can be automatically fixed, which makes it safer and faster for workers to carry and transport materials back and forth.

[0053] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A construction unloading device, comprising a pallet (1), a hopper (2) and a suspension rope (3), wherein the hopper (2) is arranged on the pallet (1), the pallet (1) is fixedly arranged on a building floor, and the suspension rope (3) connects the pallet (1) and the upper floor of the building. Features: The tray (1) comprises two support beams (11) and a plurality of connecting rods (12), both ends of the plurality of connecting rods (12) are fixedly connected to the two support beams (11), a sliding assembly (4) is provided at the bottom of the hopper (2), the sliding assembly (4) is slidably arranged on the two support beams (11) along the length direction of the support beams (11), and a positioning assembly (5) for fixing the hopper (2) is provided on the hopper (2); the sliding assembly (4) comprises a slider (41), a driving member (42) and a plurality of rollers (43), the slider (41) is fixedly arranged at the bottom of the hopper (2), and the plurality of rollers (43) are slidably arranged on the two support beams (11) along the length direction of the support beams (11). ) is rotatably mounted in the slider (41) at intervals in the length direction, the roller (43) is rollingly mounted on the support beam (11), the driving member (42) is arranged in the hopper (2), and the driving end of the driving member (42) is drivingly connected to the rotating shaft of the roller (43); the positioning assembly (5) comprises a positioning seat (51), a first fixed block (52), a second fixed block (53) and a pull rod (54), the first fixed block (52) is fixedly mounted at the end of the slider (41) in the length direction, the positioning seat (51) is fixedly mounted on the top wall of the support beam (11), the second fixed block (53) is slidingly mounted in the positioning seat (51) along the vertical direction, and the A pull rod (54) is arranged at the top of the second fixed block (53), and the top end of the pull rod (54) passes through the positioning seat (51) and extends out of the positioning seat (51). A positioning groove (8) is provided on the side wall of the positioning seat (51) close to the first fixed block (52), and the first fixed block (52) slides into the positioning groove (8), and the second fixed block (53) is clamped and fixed to the first fixed block (52); a first inclined wall (9) is formed on one end of the first fixed block (52) close to the positioning seat (51), and a second inclined wall (10) is formed on one end of the second fixed block (53) close to the first fixed block (52), and the first inclined wall (9) slides abuts against the second inclined wall (11). The first fixing block (52) is provided with a first clamping block (13) on the top wall near one end of the positioning seat (51), and the second fixing block (53) is provided with a second clamping block (14) on the bottom wall near one end of the first fixing block (52). When the second fixing block (53) is lifted up, the second fixing block (53) drives the second clamping block (14) to be lifted up. When the first inclined wall (9) and the second inclined wall (10) are separated, the second fixing block (53) drives the second clamping block (14) to be lowered. The second clamping block (14) abuts against the first clamping block (13) and enables the second fixing block (53) to be clamped and fixed with the first fixing block (52).

2. A construction unloading device according to claim 1, Features: The support beam (11) is an I-beam, the roller (43) is rollably arranged on the top wall of the support beam (11), the slider (41) is provided with connecting blocks (6) on both side walls along the width direction of the support beam (11), a plurality of guide wheels (7) are arranged on the side walls of the two connecting blocks (6) close to each other, and the plurality of guide wheels (7) are rollably arranged on both sides of the width direction of the support beam (11) along the length direction of the support beam (11).

3. A construction unloading device according to claim 1, Features: The outer wall of the pull rod (54) is provided with a first warning ring (15) and a second warning ring (16) at intervals along its own axial direction. The first warning ring (15) is located above the second warning ring (16). When the first fixing block (52) does not enter the positioning seat (51), the first warning ring (15) of the pull rod (54) is located above the positioning seat (51), and the second warning ring (16) is located inside the positioning seat (51). When the first fixing block (52) and the second fixing block (53) are clamped and fixed, the second warning ring (16) is located above the positioning seat (51).

4. A construction unloading device according to claim 1, Features: An elastic member (17) is disposed in the positioning seat (51), one end of the elastic member (17) abuts against the top wall of the second fixing block (53), and the other end abuts against the top wall of the inner cavity of the positioning seat (51).

5. A construction unloading device according to claim 4, Features: The elastic member (17) is sleeved on the pull rod (54).