The invention belongs to the technical field of
building construction, and particularly relates to a
laser positioning construction method for a
water stop joint of a drainage vertical
pipe. Comprising the steps that S1, a plurality of
water stop joints in rows are installed on a formwork of a first
floor slab, and
floor slab concrete is poured; s2, enabling
laser emitted from the bottom of the
laser level gauge to be aligned with the central position of one
water stop section, placing the laser level gauge on the water stop section, and leveling the laser level gauge; s3, the laser level gauge upwards emits a cross line and irradiates the template of the adjacent
upper floor slab, and the template of the adjacent
upper floor slab is holed; s4, repeating the steps S2 to S3; s5, straight lines connected with the multiple open holes are drawn on the formwork faces of the adjacent
upper floor slabs, then vertical lines, passing through the open holes, of the straight lines are drawn, round holes in the four positioning lug plates on the periphery of the bottom of the water stop joint are aligned with one cross intersecting line, and the water stop joint and the formwork are fixed;
floor slab concrete is poured; and S6, repeating the steps S2 to S5. And the mounting precision of the water stopping section in the multi-story building can be improved.