Wastewater treatment device for constructional engineering

By introducing motor-driven feeding rods and threaded rods in conjunction with the design of the cleaning plate into the wastewater treatment device for construction projects, the problem of inconvenient handling of sand and gravel objects and sludge is solved, and efficient wastewater filtration and sludge cleaning are achieved, improving Improve processing efficiency and equipment reliability.

CN221867692UActive Publication Date: 2024-10-22徐志鑫
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323548804.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-10-22
Estimated Expiration
2033-12-26

AI Technical Summary

Technical Problem

Existing wastewater treatment devices used in construction projects are inconvenient to handle objects such as sand and gravel during filtration, and sludge easily accumulates at the bottom of the water storage cavity, affecting filtration efficiency and difficulty in cleaning.

Method used

A wastewater treatment device including a filter chamber and a water storage chamber is designed. The motor-driven feeding rod drives the sand and gravel objects to filter. The filter plate and the cleaning plate are used to achieve the filtering of sand and gravel and the cleaning of sludge to ensure the filtration effect. and cleaning of the water storage chamber.

Benefits of technology

It effectively filters sand and gravel objects in construction wastewater, and cleans sludge through the cooperation of threaded rods and cleaning plates, which improves the efficiency and convenience of wastewater treatment, avoids sludge accumulation, and improves filtration efficiency and equipment reliability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221867692U_ABST
    Figure CN221867692U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of constructional engineering, in particular to a wastewater treatment device for constructional engineering. According to the technical scheme, the wastewater treatment device comprises a wastewater treatment device body, a filter cavity and a water storage cavity, the filter cavity is formed in the wastewater treatment device body, the water storage cavity is formed in the wastewater treatment device body at the bottom of the filter cavity, and a filter plate is fixedly connected to the interior of the wastewater treatment device body between the filter cavity and the water storage cavity; filtering holes are formed in the filtering plate, an auxiliary block is fixedly connected to the bottom of the wastewater treatment device body, a feeding rod is fixedly connected to the interior of the filtering cavity, and the other side of the feeding rod penetrates through the filtering cavity and is fixedly connected with a motor. According to the building wastewater treatment device, large objects such as gravels in building wastewater can be filtered through mutual matching between the feeding rod and the filter plate, and sludge at the bottom of the water storage cavity can be cleaned through mutual matching between the threaded rod and the sewage cleaning plate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a wastewater treatment device for construction engineering. Background Art

[0002] Construction engineering refers to the planning, investigation, design, construction, completion and other technical work and completed engineering entities for the construction, reconstruction or expansion of buildings and ancillary structures and facilities, as well as the installation of supporting lines, pipelines and equipment. However, a large amount of construction wastewater will be generated during the construction. The construction wastewater comes from the wastewater generated after the use of the project construction. There are also a large amount of sand and gravel and other large impurities in the wastewater. In order to reduce the waste of water resources, these wastewaters are mostly preliminarily treated and then reused. Among them, the "A wastewater treatment device for construction engineering" disclosed in the authorization announcement number "CN214861696U" has solved the current problem that construction engineering wastewater is directly treated by conventional filter mesh filtration, and impurities cannot be treated in time during the filtration process, which is easy to cause insufficient filtration and solid impurities clogging the purification treatment equipment, thereby affecting The filtering effect is affected, resulting in low filtering efficiency. After further searching, it is found that the "A kind of wastewater treatment device for construction engineering" disclosed by the authorization announcement number "CN212982627U" has effectively solved the current problem of low filtering efficiency, poor effect and low recycling efficiency of directly treating the wastewater of construction engineering by conventional filtering nets through specific technical structure settings. However, in actual use, wastewater treatment devices with similar structures still have many defects, such as: the wastewater generated by construction engineering contains a large amount of sand and gravel and other objects inside. When filtering the wastewater, it is inconvenient to handle the sand and gravel and other objects during filtering, and the wastewater after filtering the sand and gravel and other objects still contains sludge and other components. The sludge and other components are easy to accumulate at the bottom of the water storage chamber when standing, and it is inconvenient to clean and filter them. Therefore, it is necessary to design a wastewater treatment device for construction engineering. Utility Model Content

[0003] The purpose of the utility model is to provide a wastewater treatment device for construction engineering to solve the problems raised in the above background technology.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a wastewater treatment device for construction engineering, comprising a wastewater treatment device body, a filter chamber and a water storage chamber, a filter chamber is provided inside the wastewater treatment device body, a water storage chamber is provided inside the wastewater treatment device body at the bottom of the filter chamber, a filter plate is fixedly connected inside the wastewater treatment device body between the filter chamber and the water storage chamber, filter holes are provided inside the filter plate, an auxiliary block is fixedly connected to the bottom of the wastewater treatment device body, a feed rod is fixedly connected inside the filter chamber, a motor is fixedly connected to the other side of the feed rod passing through the filter chamber, a discharge port is provided inside the wastewater treatment device body on one side of the feed rod, a threaded rod is fixedly connected inside the water storage chamber, and a cleaning plate is movably connected inside the water storage chamber outside the threaded rod.

[0005] After the construction wastewater is introduced into the filter chamber inside the wastewater treatment device body, the feed rod inside the filter chamber is driven by the motor to rotate, so that the feed rod pushes the larger objects such as sand and gravel inside the construction wastewater to move on the filter plate and discharge the interior of the filter chamber through the discharge port, while the remaining construction wastewater will enter the water storage chamber through the filter holes opened on the filter plate, thereby filtering the larger objects such as sand and gravel inside the construction wastewater. After the construction wastewater that has filtered the larger objects such as sand and gravel enters the water storage chamber, because the wastewater still contains sludge and other components, the sludge and other components are easy to accumulate at the bottom of the water storage chamber when standing still, when cleaning the sludge accumulated at the bottom of the water storage chamber, the push rod inside the auxiliary block will first pull the filter cylinder back to the interior of the storage tank, so that the top of the filter cylinder is parallel to the bottom of the water storage chamber, and then the sewage outlet is opened, and then the cleaning plate is driven by the threaded rod to move inside the water storage chamber, thereby pushing the sludge, so that the sludge is discharged from the interior of the water storage chamber through the sewage outlet.

[0006] Preferably, a sewage outlet is provided inside the wastewater treatment device body on one side of the water storage chamber, and a push rod is fixedly connected inside the auxiliary block. The sewage outlet allows the cleaning plate to push the sludge at the bottom of the water storage chamber out of the wastewater treatment device body, and the push rod can drive the filter cartridge to move up and down.

[0007] Preferably, a receiving groove is provided inside the auxiliary block outside the push rod, and a filter cartridge is fixedly connected to the top of the push rod inside the receiving groove. The filter cartridge can be received by the receiving groove, thereby preventing the filter cartridge from affecting the work of the cleaning plate, and the wastewater inside the water storage chamber can be filtered twice by the filter cartridge.

[0008] Preferably, a feed inlet is fixedly connected to the top of the wastewater treatment device body, and a support frame is fixedly connected to the bottom of the wastewater treatment device body outside the auxiliary block. Construction wastewater can be added into the filter cavity through the feed inlet, and the wastewater treatment device body can be supported by the support frame.

[0009] Preferably, a bearing is fixedly connected inside the filter cavity on one side of the feed rod at the top of the discharge port, and a guide rod is fixedly connected inside the water storage cavity at both ends of the threaded rod inside the cleaning plate. The bearing can provide conditions for the rotation of the feed rod and the threaded rod, and the guide rod can prevent the cleaning plate from tilting when the threaded rod drives the cleaning plate to move, thereby avoiding affecting the cleaning of sludge at the bottom of the water storage cavity.

[0010] Preferably, a water guide groove is provided inside the wastewater treatment device body on one side of the filter cartridge at the bottom of the water storage chamber, and a drain port is fixedly connected to the bottom of the water guide groove at the bottom of the wastewater treatment device body on one side of the auxiliary block. The wastewater filtered by the filter cartridge can be guided through the water guide groove, and the wastewater inside the water guide groove can be discharged through the drain port.

[0011] Preferably, one end of the wastewater treatment device body is fixedly connected to a controller, and one end of the wastewater treatment device body at the bottom of the controller is fixedly connected to a liquid level gauge. The controller can be used to control and set parameters of various electrical components on the wastewater treatment device body, and the liquid level of the wastewater inside the water storage chamber can be observed by the liquid level gauge, so as to avoid the wastewater inside the water storage chamber being too high, thereby affecting the work inside the upper filter chamber.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] 1. Through the cooperation between the feeding rod and the filter plate, after the construction wastewater is introduced into the filter chamber, the feeding rod is driven by the motor to rotate, so that the feeding rod pushes the sand and gravel inside the construction wastewater to move larger objects, and discharges them from the filter chamber through the discharge port, while the remaining construction wastewater will enter the water storage chamber through the filter holes opened on the filter plate, thereby filtering larger objects such as sand and gravel inside the construction wastewater.

[0014] 2. Through the cooperation between the threaded rod and the cleaning plate, after the construction sewage that has filtered out larger objects such as sand and gravel enters the water storage chamber, the sewage still contains sludge and other components, which are easy to accumulate at the bottom of the water storage chamber when standing still. When cleaning the sludge accumulated at the bottom of the water storage chamber, the push rod will first pull the filter cartridge back into the storage tank, so that the top of the filter cartridge is parallel to the bottom of the water storage chamber, and then the cleaning plate is driven by the threaded rod to move inside the water storage chamber, thereby pushing the sludge and discharging it from the inside of the water storage chamber through the sewage outlet. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is the front view of the utility model;

[0016] Figure 2 It is the main sectional view of the utility model;

[0017] Figure 3 It is a side view of the utility model;

[0018] Figure 4 It is a side sectional view of the utility model;

[0019] Figure 5 This is a schematic diagram of the filter cartridge structure of the utility model.

[0020] In the figure: 1. wastewater treatment device body; 101. filter chamber; 102. water storage chamber; 103. water guide trough; 2. support frame; 3. auxiliary block; 301. storage tank; 4. motor; 5. controller; 6. liquid level gauge; 7. feed port; 8. drain port; 9. discharge port; 10. sewage outlet; 11. feed rod; 12. threaded rod; 13. cleaning plate; 14. bearing; 15. filter plate; 1501. filter hole; 16. push rod; 17. guide rod; 18. filter cartridge. DETAILED DESCRIPTION

[0021] The technical solution of the utility model is further described below in conjunction with the accompanying drawings and specific embodiments.

[0022] Embodiment 1

[0023] like Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 As shown, the utility model proposes a wastewater treatment device for construction engineering, including a wastewater treatment device body 1, a filter chamber 101 and a water storage chamber 102. The wastewater treatment device body 1 is provided with a filter chamber 101, and the wastewater treatment device body 1 at the bottom of the filter chamber 101 is provided with a water storage chamber 102. A filter plate 15 is fixedly connected to the wastewater treatment device body 1 between the filter chamber 101 and the water storage chamber 102, and a filter hole 1501 is provided in the filter plate 15. The bottom of the wastewater treatment device body 1 is fixedly connected with an auxiliary block 3, and the filter chamber 101 is fixedly connected with a feeder 1501. Rod 11, the other side of the feeding rod 11 passes through the filter chamber 101 and is fixedly connected to the motor 4, a discharge port 9 is provided inside the wastewater treatment device body 1 on one side of the feeding rod 11, a threaded rod 12 is fixedly connected inside the water storage chamber 102, a cleaning plate 13 is movably connected inside the water storage chamber 102 outside the threaded rod 12, a sewage discharge port 10 is provided inside the wastewater treatment device body 1 on one side of the water storage chamber 102, a push rod 16 is fixedly connected inside the auxiliary block 3, a receiving groove 301 is provided inside the auxiliary block 3 outside the push rod 16, and a filter cartridge 18 is fixedly connected to the top of the push rod 16 inside the receiving groove 301.

[0024] The working principle of the construction wastewater treatment device based on Example 1 is as follows: after the construction wastewater is introduced into the filter chamber 101 inside the wastewater treatment device body 1, the feed rod 11 inside the filter chamber 101 is driven to rotate by the motor 4, so that the feed rod 11 pushes the sand and gravel inside the construction wastewater to move on the filter plate 15, and is discharged from the filter chamber 101 through the discharge port 9;

[0025] The rest of the construction wastewater will enter the water storage chamber 102 through the filter holes 1501 opened on the filter plate 15, thereby filtering larger objects such as sand and gravel in the construction wastewater;

[0026] After the construction sewage that has filtered out larger objects such as sand and gravel enters the water storage chamber 102, since the sewage still contains sludge and other components, the sludge and other components are easy to accumulate at the bottom of the water storage chamber 102 when standing still. When cleaning the sludge accumulated at the bottom of the water storage chamber 102, the push rod 16 inside the auxiliary block 3 will first pull the filter cartridge 18 back into the storage tank 301, so that the top of the filter cartridge 18 is parallel to the bottom of the water storage chamber 102;

[0027] Then, the sewage outlet 10 is opened, and the threaded rod 12 drives the cleaning plate 13 to move inside the water storage chamber 102 , thereby pushing the sludge so that the sludge is discharged from the water storage chamber 102 through the sewage outlet 10 .

[0028] Embodiment 2

[0029] like Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 As shown, the utility model proposes a wastewater treatment device for construction engineering. Compared with the first embodiment, this embodiment also includes: a feed port 7 is fixedly connected to the top of the wastewater treatment device body 1, a support frame 2 is fixedly connected to the bottom of the wastewater treatment device body 1 outside the auxiliary block 3, a bearing 14 is fixedly connected to the inside of the filter cavity 101 on the side of the feed rod 11 at the top of the discharge port 9, a guide rod 17 is fixedly connected to the inside of the water storage cavity 102 at both ends of the threaded rod 12 inside the cleaning plate 13, a water guide groove 103 is opened inside the wastewater treatment device body 1 on the side of the filter cartridge 18 at the bottom of the water storage cavity 102, a drain port 8 is fixedly connected to the bottom of the water guide groove 103 at the bottom of the wastewater treatment device body 1 on the side of the auxiliary block 3, a controller 5 is fixedly connected to one end of the wastewater treatment device body 1, and a liquid level meter 6 is fixedly connected to one end of the wastewater treatment device body 1 at the bottom of the controller 5.

[0030] In this embodiment, Figure 1 , Figure 2 , Figure 3 and Figure 4As shown, construction wastewater can be added into the filter chamber 101 through the feed port 7, and the wastewater treatment device body 1 can be supported by the support frame 2; Figure 2 and Figure 4 As shown, the bearing 14 can provide conditions for the rotation of the feeding rod 11 and the threaded rod 12, and the guide rod 17 can prevent the cleaning plate 13 from tilting when the threaded rod 12 drives the cleaning plate 13 to move, thereby avoiding affecting the cleaning of the sludge at the bottom of the water storage chamber 102;

[0031] like Figure 1 , Figure 2 , Figure 3 and Figure 5 As shown, the waste water filtered by the filter cartridge 18 can be guided through the water guide groove 103, and the waste water inside the water guide groove 103 can be discharged through the drain port 8; Figure 1 , Figure 3 and Figure 4 As shown, the controller 5 can be used to control and set parameters of various electrical components on the wastewater treatment device body 1, and the liquid level height of the wastewater inside the water storage chamber 102 can be observed through the liquid level meter 6, so as to avoid the wastewater level inside the water storage chamber 102 being too high, thereby affecting the work inside the upper filter chamber 101.

[0032] The above-mentioned specific embodiments are only several preferred embodiments of the present invention. Based on the technical solution of the present invention and the relevant inspiration of the above-mentioned embodiments, those skilled in the art can make various alternative improvements and combinations to the above-mentioned specific embodiments.

Claims

1. A wastewater treatment device for construction engineering, comprising a wastewater treatment device body (1), a filter chamber (101) and a water storage chamber (102), characterized in that: A filter chamber (101) is provided inside the wastewater treatment device body (1), a water storage chamber (102) is provided inside the wastewater treatment device body (1) at the bottom of the filter chamber (101), a filter plate (15) is fixedly connected inside the wastewater treatment device body (1) between the filter chamber (101) and the water storage chamber (102), a filter hole (1501) is provided inside the filter plate (15), and an auxiliary filter is fixedly connected at the bottom of the wastewater treatment device body (1). The auxiliary block (3) is fixedly connected to a feeding rod (11) inside the filter chamber (101), and the other side of the feeding rod (11) passes through the filter chamber (101) and is fixedly connected to a motor (4), a discharge port (9) is provided inside the wastewater treatment device body (1) on one side of the feeding rod (11), a threaded rod (12) is fixedly connected to the inside of the water storage chamber (102), and a cleaning plate (13) is movably connected to the inside of the water storage chamber (102) outside the threaded rod (12).

2. A construction wastewater treatment device according to claim 1, characterized in that: A sewage outlet (10) is provided inside the wastewater treatment device body (1) on one side of the water storage chamber (102), and a push rod (16) is fixedly connected inside the auxiliary block (3).

3. A construction wastewater treatment device according to claim 2, characterized in that: A receiving groove (301) is provided inside the auxiliary block (3) outside the push rod (16), and a filter cartridge (18) is fixedly connected to the top of the push rod (16) inside the receiving groove (301).

4. A construction wastewater treatment device according to claim 1, characterized in that: The top of the wastewater treatment device body (1) is fixedly connected to a feed port (7), and the bottom of the wastewater treatment device body (1) outside the auxiliary block (3) is fixedly connected to a support frame (2).

5. A construction wastewater treatment device according to claim 1, characterized in that: A bearing (14) is fixedly connected inside the filter cavity (101) on one side of the feeding rod (11) at the top of the discharge port (9), and a guide rod (17) is fixedly connected inside the water storage cavity (102) at both ends of the internal threaded rod (12) of the cleaning plate (13).

6. A construction engineering wastewater treatment device according to claim 1, characterized in that: A water guide groove (103) is provided inside the wastewater treatment device body (1) on the side of the filter cartridge (18) at the bottom of the water storage chamber (102), and a drainage outlet (8) is fixedly connected to the bottom of the water guide groove (103) at the bottom of the wastewater treatment device body (1) on the side of the auxiliary block (3).

7. A construction wastewater treatment device according to claim 1, characterized in that: One end of the wastewater treatment device body (1) is fixedly connected to a controller (5), and one end of the wastewater treatment device body (1) at the bottom of the controller (5) is fixedly connected to a liquid level meter (6).