Device for replacing beam body of railroad bridge during short-time running interruption

Through the use of the top-loading beam moving machine, the safety hazards of railway bridge beam replacement requiring large blockades and high-altitude operations are solved, beam replacement is achieved in a short time, construction efficiency and safety are improved, and the impact on railway transportation is reduced. influence.

CN221877799UActive Publication Date: 2024-10-22INNER MONGOLIA YUHUI HIGHWAY ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420430309.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-06
Publication Date
2024-10-22
Estimated Expiration
2034-03-06

AI Technical Summary

Technical Problem

The existing railway bridge girder replacement technology requires large blockades and continuous interruption of traffic, which affects railway transportation. It also has hidden safety hazards in high-altitude operations and unstable hoisting capabilities.

Method used

An upper-loading beam moving machine is used, including a jacking mechanism, a supporting mechanism and a traveling mechanism. It uses transverse jacks, hydraulic telescopic arms and telescopic support columns to achieve three-way adjustment and translation of the beam body, avoid high-altitude operations, and improve construction efficiency and Security.

Benefits of technology

It achieves short-term beam replacement without dismantling railway equipment, reduces construction safety risks, improves construction efficiency and stability, and reduces the impact on railway transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221877799U_ABST
    Figure CN221877799U_ABST
Patent Text Reader

Abstract

The utility model discloses a device for replacing a beam body of a railroad bridge during short-time travelling interruption, which relates to the technical field of bridges and comprises a deck type beam moving machine which comprises a jacking mechanism, a first platform, a supporting mechanism, a second platform and a travelling mechanism which are sequentially connected from top to bottom. The jacking mechanism is used for supporting the beam body and achieving three-direction adjustment of the beam body. According to the deck type beam moving machine, the beam body is replaced within a short time without dismantling other railway equipment, a large amount of high-altitude operation is avoided, the construction safety risk is reduced, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridges, in particular to a device for replacing beams of a railway bridge by interrupting driving for a short time. Background Art

[0002] After the railway was put into operation, the beams with quality problems during inspection and acceptance had their defects developed faster. The safety factor of the beam crack resistance could not meet the requirements of the current specification Kf≥1.2, and the beams had already shown horizontal cracks caused by alkali-aggregate reaction. The embedded steel plate at the bottom of the beam at the support was seriously corroded, warped and deformed, and the beam was separated. The embedded steel plate and the upper swing of the support were corroded and separated. The concrete at the bottom of the beam at the embedded steel plate collapsed. The production and construction quality was poor. The bearing capacity of this batch of beams was insufficient, the vertical stiffness of the test hole span was insufficient, and the safety reserve of the transverse stiffness of the beam was insufficient. There was a serious alkali aggregate cracking disease, and the cracks continued to develop, and the bearing capacity and durability of the beam body continued to decrease. It seriously affected the driving safety of the road.

[0003] To sum up, it is necessary to replace the prestressed concrete beams.

[0004] Existing beam replacement technology 1: beam erection machine cooperates with related equipment to replace beams

[0005] This traditional bridge erection construction technology uses the railway TJ165 bridge erection machine in conjunction with bridge transportation equipment.

[0006] Disadvantages of existing beam replacement technology 1:

[0007] 1. It is necessary to conduct a "big blockade" of the existing railways, continuously interrupt the traffic, and dismantle most of the existing power supply, communication and signal equipment.

[0008] 2. The beam replacement has a great impact on the railway section, and a beam storage site is needed. The beam replacement construction section and even the adjacent section stations and lines should "make way" for the beam replacement construction, which will seriously affect railway transportation during the construction period.

[0009] 3. The dismantling and erection of single T-beams involves a large amount of high-altitude operations from dismantling existing equipment, installing new beams to resuming traffic, which poses a safety hazard.

[0010] Existing beam replacement technology 2: whole-hole erection by truck crane and crawler crane

[0011] The method is to use an existing automobile crane or crawler crane to hoist the holed T-beam that has been completed in the transverse connection construction, so as to complete the bridge beam replacement construction.

[0012] Disadvantages of the second prior art:

[0013] 1. Truck cranes and crawler cranes have high requirements for the working environment of large-tonnage bridge hoisting, which results in unstable hoisting capacity and slow hoisting process.

[0014] 2. Although the cost of replacing beams with truck cranes and crawler cranes is not high, the crane station position, lifting angle, lifting distance, T-beam placement, etc. need to be accurately measured each time. Human factors such as technicians and workers have a greater impact on the construction, and there is a high degree of uncertainty.

[0015] 3. The distance between the overhead wire and the top of the rail is 6000mm±30mm and it is directly above the line. If a truck crane or crawler crane is used for lifting, it is necessary to dismantle the locomotive power supply related equipment. Utility Model Content

[0016] In view of this, the utility model provides a device for replacing a beam body of a railway bridge by interrupting driving for a short time, so as to solve the problems raised in the above-mentioned background technology.

[0017] A device for replacing a beam body for a railway bridge during a short-term interruption of driving, comprising an upper-supported beam shifting machine, the upper-supported beam shifting machine comprising a jacking mechanism, a first platform, a supporting mechanism, a second platform and a traveling mechanism connected in sequence from top to bottom, the jacking mechanism being used to support the beam body and realize three-way adjustment of the beam body.

[0018] Furthermore, the jacking mechanism includes a transverse jack and a sliding assembly, the sliding assembly is fixedly arranged at the center position of the top surface of the first platform, a longitudinal jack is fixedly arranged at the center position of the sliding end of the sliding assembly, the output end of the longitudinal jack is used to support the beam body, the fixed end of the transverse jack is fixedly arranged at the four sides of the top surface of the first platform through a fixed seat, and the output end of the transverse jack is fixedly arranged at the four sides of the sliding end of the sliding assembly through a fixed block.

[0019] Furthermore, the sliding assembly includes a sliding base and a supporting steel plate, the sliding base is fixedly arranged at the center position of the top surface of the first platform, the top surface of the sliding base is provided with a sliding groove, and the sliding groove is provided with a silicone grease lubrication layer and a stainless steel plate from top to bottom, the bottom surface of the supporting steel plate is slidably connected to the silicone grease lubrication layer through a polytetrafluoroethylene plate, the longitudinal jack is fixedly arranged at the center position of the top surface of the supporting steel plate, and the output end of the transverse jack is fixedly arranged at the four sides of the top surface of the supporting steel plate through the fixed block.

[0020] Furthermore, the supporting mechanism includes two retractable support columns and two hydraulic retractable arms, the fixed ends of the retractable support columns are symmetrically fixed at the two ends of the top surface of the second platform, and the retractable ends are symmetrically fixed at the two ends of the bottom surface of the first platform, the inner sides of the two retractable support columns are connected by a scissors strut, and the hydraulic retractable arms are located on the outsides of the retractable support columns, the fixed ends of the hydraulic retractable arms are symmetrically fixed at the two ends of the top surface of the second platform, and the retractable ends are symmetrically fixed at the two ends of the bottom surface of the first platform.

[0021] Furthermore, the support mechanism also includes a pin rod, and the fixed end and the telescopic end of the telescopic support column are both provided with pin holes adapted to the pin rod for fixing the height of the telescopic support column.

[0022] Furthermore, the walking mechanism includes a wheel box, which is fixedly arranged on the bottom surface of the second platform through a connecting seat, and wheels are arranged at the bottom of the wheel box. A driving motor is arranged on the wheel box, and the driving motor is transmission-connected to the wheels.

[0023] The beneficial effects of the utility model are:

[0024] The utility model utilizes an upper-supported beam shifting machine to complete beam replacement in a short time without dismantling other railway equipment, thus avoiding a large amount of high-altitude operations, reducing construction safety risks, and improving construction efficiency; the vertical jack is used to adjust the height of the beam in the vertical direction; the transverse jacks fixedly arranged at the four sides of the top surface of the first platform drive the fixed block to move, thereby driving the supporting steel plate to slide, and realizing the movement of the beam in the plane direction; the hydraulic telescopic arm is used to adjust the height of the jacking mechanism, and realizes jacking and placing the beam; the height of the telescopic support column is fixed by the pin rod and the pin hole, thereby improving the overall stability of the support mechanism. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0026] Figure 1 The utility model is a structural schematic diagram of a device for replacing beams of a railway bridge by interrupting driving for a short time.

[0027] Figure 2 It is a cross-sectional view of the jacking mechanism in the utility model.

[0028] Figure 3 It is a side sectional view of the supporting beam body of the upper support type beam shifting machine in the utility model.

[0029] Figure 4 This is a front view of the construction layout for replacing beams on a railway bridge during a short-term interruption of traffic.

[0030] Figure 5 This is a top view of the construction layout for replacing the beam body of a railway bridge during a short-term interruption of traffic.

[0031] Among them, in the figure:

[0032] 1. Lifting mechanism; 11. Sliding base; 12. Support steel plate; 13. Polytetrafluoroethylene plate; 14. Silicone grease lubrication layer; 15. Stainless steel plate; 16. Fixed seat; 17. Horizontal jack; 18. Fixed block; 19. Vertical jack; 2. First platform; 31. Retractable support column; 32. Hydraulic telescopic arm; 33. Scissors support; 4. Second platform; 5. Traveling mechanism; 61. Loading and unloading area; 62. New beam storage area; 63. Old beam storage area; 7. Pier; 71. Beam body; 8. Gantry crane; 81. Walking rail; 9. Top-supported beam moving machine. DETAILED DESCRIPTION

[0033] The technical solutions in the embodiments of the utility model are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0034] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0035] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0036] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.

[0037] In addition, the terms "installed", "set", "provided with", "connected", "connected", and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0038] See attached Figure 1-5 The utility model discloses a device for replacing a beam body of a railway bridge during a short-term interruption of driving, comprising an upper-bearing beam shifting machine 9, which comprises a jacking mechanism 1, a first platform 2, a supporting mechanism, a second platform 4 and a traveling mechanism 5 connected in sequence from top to bottom, and the jacking mechanism 1 is used to support the beam body 71 and realize three-way adjustment of the beam body 71. The utility model utilizes the upper-bearing beam shifting machine 9 in conjunction with a gantry crane 8 to replace the beam body 71 in a short time without dismantling other railway equipment, thereby increasing the stability of the hoisting construction, avoiding a large number of high-altitude operations, reducing the construction safety risks, and improving the construction efficiency.

[0039] The jacking mechanism 1 includes a transverse jack 17 and a sliding assembly. The sliding assembly is fixedly arranged at the center position of the top surface of the first platform 2. A vertical jack 19 is fixedly arranged at the center position of the sliding end of the sliding assembly. The output end of the vertical jack 19 is used to support the beam body 71. The vertical jack 19 is used to adjust the height of the beam body 71 in the vertical direction. The fixed end of the transverse jack 17 is fixedly arranged at the four sides of the top surface of the first platform 2 through a fixed seat 16. The output end of the transverse jack 17 is fixedly arranged at the four sides of the sliding end of the sliding assembly through a fixed block 18.

[0040] The sliding assembly includes a sliding base 11 and a supporting steel plate 12. The sliding base 11 is fixedly arranged at the center of the top surface of the first platform 2. A sliding groove is arranged on the top surface of the sliding base 11. A silicone grease lubrication layer 14 and a stainless steel plate 15 are arranged in the sliding groove from top to bottom. The bottom surface of the supporting steel plate 12 is slidably connected to the silicone grease lubrication layer 14 through a polytetrafluoroethylene plate 13. The vertical jack 19 is fixedly arranged at the center of the top surface of the supporting steel plate 12. The output end of the transverse jack 17 is fixedly arranged at the four sides of the top surface of the supporting steel plate 12 through a fixing block 18. The transverse jack 17 drives the fixing block 18 to move, thereby driving the supporting steel plate 12 to slide, and realizing the movement of the beam body 71 in the plane direction.

[0041] The support mechanism includes two retractable support columns 31 and two hydraulic telescopic arms 32. The fixed ends of the retractable support columns 31 are symmetrically fixed at the two ends of the top surface of the second platform 4, and the telescopic ends are symmetrically fixed at the two ends of the bottom surface of the first platform 2. The inner sides of the two retractable support columns 31 are connected by scissor braces 33. The hydraulic telescopic arms 32 are located outside the retractable support columns 31. The fixed ends of the hydraulic telescopic arms 32 are symmetrically fixed at the two ends of the top surface of the second platform 4, and the telescopic ends are symmetrically fixed at the two ends of the bottom surface of the first platform 2. The hydraulic telescopic arms 32 are used to adjust the height of the jacking mechanism 1 to achieve jacking and placement of the beam body 71.

[0042] The support mechanism also includes a pin rod. The fixed end and the telescopic end of the telescopic support column 31 are both provided with pin holes adapted to the pin rod, which are used to fix the height of the telescopic support column 31 and improve the overall stability of the support mechanism.

[0043] The walking mechanism 5 includes a wheel box, which is fixedly arranged on the bottom surface of the second platform 4 through a connecting seat, and a wheel is arranged at the bottom of the wheel box, and a driving motor is arranged on the wheel box, and the driving motor is connected to the wheel. In this embodiment, a modular rail steel box adapted to the wheel is used to move the upper beam moving machine 9. The advantage of the rail steel box is that it does not require high bearing capacity of the foundation, and can evenly spread large tonnage loads on the foundation.

[0044] A method for replacing a beam body by interrupting the operation of a railway bridge for a short period of time comprises the following steps:

[0045] Before the overall construction, a construction access road is set up. Following the principle of adapting measures to local conditions and saving land, the width of the construction access road shall not be less than 4m. The access road is laid along the length of the bridge to ensure that materials and equipment used for construction such as beam replacement and transverse connection can be delivered to the site;

[0046] S1: First, a construction site is set up on one side of the bridge. In this embodiment, land is acquired 30m to the right from the center line of the bridge as the construction site. The side of the construction site close to the bridge is the loading and unloading area 61, and the side away from the bridge is the beam storage area. In this embodiment, the beam storage area is 13.8m wide. The new beam body 71 is transported and placed in the beam storage area;

[0047] S2: A walking rail 81 is arranged along the length direction of the bridge to move the gantry crane 8 and then install the gantry crane 8. The gantry crane 8 is installed by the gantry crane manufacturer and is inspected and tested. It is used after passing the inspection. In this embodiment, an 80t gantry crane and a 200t gantry crane are installed. The 80t gantry crane is used for beam displacement, hole forming, storage, horizontal connection, bridge accessories, roadbed, track, etc., and the 200t gantry crane is used for lifting and displacement after beam hole forming, etc.

[0048] S3: Move the upper beam moving machine 9 to the bottom of the bridge to prepare for lifting the old beam 71;

[0049] S4: Block the bridge, remove the anti-seismic beam-dropping facilities, remove the fences that affect the lateral movement of the old beam body 71, and cut off the bolts connecting the support and the cushion stone; dismantle the line on the bridge, clean the ballast at the expansion joint position, remove the expansion joint, remove the sidewalk treads and brackets at the hanging point of the old beam body 71, and set up cable troughs and hanging wires to ensure that the old beam body 71 can be lifted and moved horizontally without obstacles;

[0050] This embodiment also includes: ① relocation, the cables under the bridge are relocated to the right side of the bridge;

[0051] ② Replace the long rails on the bridge with short rails. Before replacing the beams, release the stress of the rails on the bridge. Cut the long rails into 200m sections and replace them with short rails. Replace them with short rails in the arrangement of (7.7m+25m)*44. When replacing the beams, just disconnect them from the joints to facilitate the horizontal movement of the entire old beam out of the bridge.

[0052] ③Remove the bridge guard rails;

[0053] ④ Drill the anchor bolt holes for the bearings. First, complete the drilling of 8 bearing pad stone holes on the outside of the existing bridge;

[0054] ⑤ Scaffolding erection: Since the bridge pier has no hanging basket at the first time, scaffolding needs to be erected to provide a walking and working platform for personnel to replace the beam;

[0055] ⑥ Installation of ballast blocks to facilitate storage of all ballast on the bridge;

[0056] ⑦ Ballast laying: Lay ballast as required and set ballast bags at the ends of bridge beams to prevent ballast from falling and ensure the height of the bridge deck ballast. Purchase some ballast and lay it on the new beam. After the old beam is removed, collect the ballast from the old beam, clean and screen it for reuse.

[0057] S5: The upper-bearing beam shifting machine 9 lifts the old beam body 71 and moves it to the loading and unloading area 61. The gantry crane 8 lifts the old beam body 71 to the beam storage area and lifts the new beam body 71 onto the upper-bearing beam shifting machine 9. The upper-bearing beam shifting machine 9 moves the new beam body 71 to the top surface of the pier 7, and after the support and the cushion stone are accurately aligned, the beam is dropped to complete the installation of the new beam body 71.

[0058] S6: After the new beam 71 is installed, the expansion joint installation, expansion joint ballast backfilling, connection of the bridge upper line, manual tamping of the roadbed and adjustment of the track elevation are completed; the cable trough hanging wire is removed, so that it falls on the new beam 71 and is bolted to the new beam 71 sidewalk support.

[0059] In this embodiment, after the beam 71 is replaced, the railway bureau's engineering, power supply, and electrical personnel confirm that the line has been restored, cancel the record, and resume train service.

[0060] The beam storage area in S1 includes odd areas and even areas that are spaced along the length of the bridge. The side of the odd area close to the loading and unloading area 61 is the new beam storage area 62, and the side away from the loading and unloading area 61 is the old beam storage area 63. The side of the even area close to the loading and unloading area 61 is the old beam storage area 63, and the side away from the loading and unloading area 61 is the new beam storage area 62. In this embodiment, the new beams are stored alternately (to facilitate the hanging of the beam lifting wire rope 6.4m+1m+6.4m during the beam replacement process). The beam spacing along the length of the bridge is 10cm. The new beam storage area 62 is provided with a beam storage foundation. The top surface of the beam storage foundation must be precisely measured (simulating the relative position after the beam replacement is completed). The new beam body 71 is transversely connected and prestressed on the beam storage foundation, and finally connected to form a hole. After the new beam body hole construction is completed, the processed sidewalk bracket and step board are installed on the new beam body. The sidewalk bracket at the hanging point of the new beam body needs to be disconnected and connected and installed after the beam replacement operation is completed.

[0061] In S5 , the new beam body 71 is hoisted in front of the upper-supported beam shifting machine 9 , and new supports are installed on the new beam body 71 .

[0062] In this embodiment, when the rail row is hoisted:

[0063] ① For sleeper replacement lines, if concrete sleepers need to be replaced, new rail tracks with a length of 25m+7.7m will be assembled and hoisted by an 80t gantry crane onto the new beam with ballast laid, and then tamped.

[0064] ② For the line without changing sleepers, assemble 5-hole (25m+7.7m) long rail rows for backup. After the old beam is replaced, use an 80t gantry crane to lift the entire rail row from the old beam to the new beam.

[0065] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A device for replacing beams on a railway bridge by interrupting traffic for a short period of time, characterized in that: The invention comprises an upper-supported beam moving machine (9), wherein the upper-supported beam moving machine (9) comprises a jacking mechanism (1), a first platform (2), a supporting mechanism, a second platform (4) and a walking mechanism (5) which are sequentially connected from top to bottom, and the jacking mechanism (1) is used to support a beam body (71) and realize three-way adjustment of the beam body (71).

2. The device for replacing the beam body of a railway bridge by interrupting the operation for a short time according to claim 1 is characterized in that: The lifting mechanism (1) comprises a transverse jack (17) and a sliding assembly, wherein the sliding assembly is fixedly arranged at the center position of the top surface of the first platform (2), a vertical jack (19) is fixedly arranged at the center position of the sliding end of the sliding assembly, the output end of the vertical jack (19) is used to support the beam body (71), the fixed end of the transverse jack (17) is fixedly arranged at the four sides of the top surface of the first platform (2) through a fixing seat (16), and the output end of the transverse jack (17) is fixedly arranged at the four sides of the sliding end of the sliding assembly through a fixing block (18).

3. The device for replacing beams of a railway bridge by interrupting operation for a short period of time according to claim 2 is characterized in that: The sliding assembly comprises a sliding base (11) and a supporting steel plate (12); the sliding base (11) is fixedly arranged at the center position of the top surface of the first platform (2); a sliding groove is arranged on the top surface of the sliding base (11); a silicone grease lubrication layer (14) and a stainless steel plate (15) are arranged in sequence from top to bottom in the sliding groove; the bottom surface of the supporting steel plate (12) is slidably connected to the silicone grease lubrication layer (14) through a polytetrafluoroethylene plate (13); the vertical jack (19) is fixedly arranged at the center position of the top surface of the supporting steel plate (12); and the output end of the transverse jack (17) is fixedly arranged at the four sides of the top surface of the supporting steel plate (12) through the fixing block (18).

4. The device for replacing beams of a railway bridge by interrupting operation for a short period of time according to claim 1 is characterized in that: The support mechanism comprises two retractable support columns (31) and two hydraulic retractable arms (32); the fixed ends of the retractable support columns (31) are symmetrically fixedly arranged at the two ends of the top surface of the second platform (4); the retractable ends are symmetrically fixedly arranged at the two ends of the bottom surface of the first platform (2); the inner sides of the two retractable support columns (31) are connected by a scissor brace (33); the hydraulic retractable arms (32) are located on the outer sides of the retractable support columns (31); the fixed ends of the hydraulic retractable arms (32) are symmetrically fixedly arranged at the two ends of the top surface of the second platform (4); and the retractable ends are symmetrically fixedly arranged at the two ends of the bottom surface of the first platform (2).

5. The device for replacing beams of a railway bridge by interrupting operation for a short period of time according to claim 4 is characterized in that: The support mechanism also includes a pin rod, and both the fixed end and the telescopic end of the telescopic support column (31) are provided with pin holes matched with the pin rod, which are used to fix the height of the telescopic support column (31).

6. The device for replacing beams of a railway bridge by interrupting operation for a short period of time according to claim 1 is characterized in that: The walking mechanism (5) comprises a wheel box, which is fixedly arranged on the bottom surface of the second platform (4) via a connecting seat, a wheel is provided at the bottom of the wheel box, a drive motor is provided on the wheel box, and the drive motor is connected to the wheel in a transmission manner.