Expansion bearing platform anchoring steel pipe pile and pre-embedded grouting pipe structure
By expanding the cap-anchored steel pipe piles and pre-buried grouting pipe structures, the problems of loose bridge foundations and insufficient foundation consolidation were solved. The effective connection and foundation reinforcement of the steel pipe piles and the original cap were achieved, and the bridge's load-bearing capacity was enhanced. performance and structural stability.
Patent Information
- Application Number
- CN202323386207.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-13
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2033-12-13
AI Technical Summary
Looseness and hollowing of the lower part of the bridge pier foundation caused the bridge structure to tilt and shift sideways. It was difficult to effectively connect the original cap and the new steel pipe piles with the existing technology. In addition, insufficient consolidation of the soil in the foundation led to subsidence, which affected the load-bearing performance of the cap.
Design a structure of anchored steel pipe piles and pre-embedded grouting pipes for the extended cap. The steel pipe piles are welded to the main steel bars, and the grouting pipes are set up to fill the void areas of the foundation to form an overall expanded cap, which is reinforced by pre-embedded grouting. foundation.
The effective connection between the steel pipe piles and the original cap is achieved, which enhances the overall load-bearing performance of the cap, solves the problem of foundation settlement, and improves the bearing capacity and structural stability of the bridge foundation.
Smart Images

Figure CN221878205U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of geotechnical engineering construction, and in particular comprises an extended cap anchoring steel pipe pile and a pre-buried grouting pipe structure. Background Art
[0002] With economic development, highway traffic volume continues to increase, and the lower part of the foundation of highway bridge piers is prone to loosening and falling off, causing the upper bridge structure to tilt and shift sideways, affecting traffic safety.
[0003] When a similar situation occurs in a bridge, the bridge piers can be reinforced by adding steel pipe piles and pouring high-strength grout to effectively increase the bearing capacity of the bridge foundation. When the pile foundation pedestal area of the original bridge is insufficient, it is also necessary to lay steel pipe piles in the surrounding area outside the original pedestal, so the area of the original pedestal needs to be increased, and corresponding measures need to be taken to enable the original pedestal and the newly added steel pipe piles to work together.
[0004] The effective connection between the original cap and the additional steel pipe piles in the surrounding area outside the original cap is a difficult problem. In addition, the foundation soil in the surrounding area outside the original cap often has a low degree of pre-consolidation. During the collaborative work of the expanded cap and the steel pipe piles, the foundation may sink, resulting in a gap between the bottom of the cap and the foundation. The gap is often difficult to fill, which affects the designed bearing performance of the cap. Utility Model Content
[0005] The utility model aims to overcome the deficiencies in the prior art and provide an extended cap anchoring steel pipe pile and a pre-buried grouting pipe structure.
[0006] The extended cap anchoring steel pipe pile and pre-buried grouting pipe structure comprises: steel pipe pile, main steel bar, grouting pipe and cap; the cap is arranged on the foundation, the cap comprises a new cap and an original cap, and the main steel bar in the new cap is welded to the main steel bar in the original cap;
[0007] The steel pipe pile is arranged in the new cap through the ground, and the outer side of the steel pipe pile is welded to the main steel bar;
[0008] There is a void area in the foundation below the new cap. Within the void area, a grouting pipe is provided on the side of the steel pipe pile, and the grouting pipe extends into the foundation of the new cap.
[0009] Preferably, in the original cap and the new cap, connecting steel bars are provided between adjacent main steel bars.
[0010] Preferably, several rows of steel pipe piles are provided in the new cap along the width direction of the cap.
[0011] Preferably, the grouting pipe extends into the de-hollowing area.
[0012] The beneficial effects of the utility model are:
[0013] The utility model has a simple structure. By welding the main steel bars, the newly added steel pipe piles and the original cap can form an integral expanded cap, and the hollow area between the cap and the foundation can be grout-reinforced through the pre-buried grouting pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 The cross-sectional view of the structure of the expanded cap anchored steel pipe piles and pre-buried grouting pipes;
[0015] Figure 2 This is a top view of the expanded cap anchoring steel pipe piles and pre-buried grouting pipe structure.
[0016] Figure numerals: 1-steel pipe pile, 2-main steel bar, 3-connecting steel bar, 4-grouting pipe, 5-new cap, 6-foundation, 7-original cap, 8-gap. DETAILED DESCRIPTION
[0017] The utility model is further described below in conjunction with the embodiments. The description of the following embodiments is only used to help understand the utility model. It should be pointed out that for ordinary people in this technical field, the utility model can also be modified in some ways without departing from the principle of the utility model, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.
[0018] As an example, Figure 1 and Figure 2 As shown, the extended cap anchoring steel pipe pile and pre-buried grouting pipe structure includes: steel pipe pile 1, main steel bar 2, connecting steel bar 3, grouting pipe 4, new cap 5;
[0019] The cap includes a new cap 5 and an original cap 7. The main steel bars 2 in the new cap 5 are welded to the main steel bars 2 in the original cap 7. The steel pipe piles 1 are arranged through the new cap 5, and the outer sides of the steel pipe piles 1 are welded to the main steel bars 2.
[0020] There is a hollow area in the foundation 6 below the new cap 5 . Within the hollow area, a grouting pipe 4 is provided on the side of the steel pipe pile 1 . The grouting pipe 4 extends into the foundation 6 of the new cap 5 .
[0021] The outer side of the steel pipe pile 1 is welded to the main steel bar 2, and the end of the main steel bar 2 is welded to the main bar in the original cap 7;
[0022] A grouting pipe 4 is arranged along the steel pipe pile 1 near the main steel bar 2 and extends to the hollow area of the foundation 6 of the new cap 5;
[0023] Connecting steel bars 3 are arranged between the upper main steel bars 2 and the lower main steel bars 2 to enhance the overall bearing capacity of the structure.
[0024] The surface concrete outside the original cap 7 is chiseled off in advance to expose the main steel bars 2 and the fresh uncarbonated concrete surface; according to the design, steel pipe piles 1 are arranged in the surrounding area outside the original cap 7, and the outer side of the end of the steel pipe pile 1 is welded to the main steel bars 2, and the end of the main steel bars 2 is welded to the main steel bars 2 in the original cap 7; at the position where the main steel bars 2 are close to the steel pipe pile 1, a grouting pipe 4 is arranged along the steel pipe pile 1 and extended to the foundation 6 of the new cap 5 for later grouting; connecting steel bars 3 are arranged between the upper main steel bars 2 and the lower main steel bars 2 to enhance the overall bearing capacity of the structure. After the structure is set and the steel bars are tied, the template is laid, the concrete is poured, and the new cap 5 is made.
Claims
1. An extended cap anchor steel pipe pile and pre-buried grouting pipe structure, characterized in that: include: Steel pipe piles, main steel bars, grouting pipes and caps; the caps are set on the foundation, the caps include new caps and original caps, and the main steel bars in the new caps are welded to the main steel bars in the original caps; The steel pipe pile is arranged in the new cap through the ground, and the outer side of the steel pipe pile is welded to the main steel bar; There is a void area in the foundation below the new cap. Within the void area, a grouting pipe is provided on the side of the steel pipe pile, and the grouting pipe extends into the foundation of the new cap.
2. The extended cap anchor steel pipe pile and pre-buried grouting pipe structure according to claim 1 is characterized in that: In the original cap and the new cap, connecting steel bars are arranged between the adjacent main steel bars.
3. The extended cap anchor steel pipe pile and pre-buried grouting pipe structure according to claim 1 is characterized in that: Along the width of the cap, several rows of steel pipe piles are installed in the new cap.
4. The extended cap anchor steel pipe pile and pre-buried grouting pipe structure according to claim 1 is characterized in that: The grouting pipe extends into the de-hollowed area.