Temporary rigid connection structure for side span closure of cable-stayed bridge
By using a combination of double channel steel connection components and embedded bolts in the cable-stayed bridge, a fast, safe and reliable temporary rigid connection of the side spans of the cable-stayed bridge is achieved, which solves the problem of wasted steel plate welding time and concrete in the existing technology. Deformation problem.
Patent Information
- Application Number
- CN202420482555.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-13
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2034-03-13
AI Technical Summary
The existing temporary rigid structure of the side span closure of the existing cable-stayed bridge is welded with steel plates, which leads to a waste of time and it is difficult to effectively prevent concrete shrinkage cracking or crushing.
Double-jointed channel steel connection components are used to connect to the segmental beams through embedded bolts. The welding is completed in the factory. The Helong braces are quickly installed on site and concrete is poured to ensure welding quality and construction efficiency.
It realizes the fast, safe and reliable temporary rigid connection of the side spans of the cable-stayed bridge, avoids concrete shrinkage cracking or crushing, and saves on-site welding time.
Smart Images

Figure CN221895545U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a temporary rigid connection structure for closing the side spans of a cable-stayed bridge. Background Art
[0002] A cable-stayed bridge, also known as a cable-stayed bridge, is a type of bridge in which the main beam is directly pulled on the bridge tower by many cables. It is a structural system composed of a pressure-bearing tower, a tensioned cable, and a bending beam. It can be regarded as a multi-span elastically supported continuous beam with cables replacing piers. It can reduce the bending moment in the beam body, lower the building height, reduce the structural weight, and save materials. A cable-stayed bridge is mainly composed of a cable tower, a main beam, and a cable-stayed cable.
[0003] Some cable-stayed bridges have the advantages of strong spanning capacity, good structural stability, mature construction technology, and good driving comfort, especially those with a main span of 200 to 350 meters. In order to reduce the expansion and contraction of the box girder caused by temperature difference deformation, as well as the shrinkage of the concrete during solidification, and to prevent the shrinkage cracking or crushing of the concrete in the joint section, it is necessary to temporarily connect the side span joint section. The joint requires a tight time, and the existing steel plate welding generally takes a long time, resulting in a waste of time. Therefore, a temporary rigid connection structure for the side span joint of a cable-stayed bridge is proposed to address the above problems. Utility Model Content
[0004] The utility model aims to overcome the existing defects and provide a temporary rigid connection structure for the side span closure of a cable-stayed bridge, which is time-saving and safe and reliable.
[0005] The technical solution to achieve the above-mentioned purpose is: a temporary rigid connection structure for the side span closure of a cable-stayed bridge, comprising a connecting assembly; the side span closure section is located between two sections of segmental beams, the connecting assembly is connected to the side span closure section and the upper end surfaces of the two sections of the segmental beams, and the two ends of the connecting assembly are connected to the two sections of the segmental beams.
[0006] Preferably, the connection assembly comprises a double-jointed channel steel, and both ends of the double-jointed channel steel are respectively connected to the upper end surface of the segment beam body by embedded bolts.
[0007] Preferably, the upper end surface of the double-jointed channel steel is connected to four connecting plates at equal distances.
[0008] Preferably, four of the embedded bolts are connected to the upper end surface of each segment beam.
[0009] Preferably, both ends of the double-jointed channel steel are provided with holes corresponding to the four embedded bolts.
[0010] Preferably, the joining plate is connected to the double-jointed channel steel by welding.
[0011] The beneficial effects of the utility model are as follows: the temporary rigid connection structure of the side span closure of the cable-stayed bridge is completed by welding in the factory by setting double-jointed channel steel, which not only ensures the welding quality but also saves the on-site welding construction time. The embedded bolts are embedded in advance when pouring the concrete of the previous section beam body. At a lower temperature during the day or at the temperature required by the design, the closure support is installed on the embedded bolts, the nuts are tightened, and then the concrete of the side span closure section is poured immediately. The structure is simple, the on-site installation is convenient, the time is short, and it is safe and reliable, and the shrinkage cracking or crushing of the concrete of the side span closure section is prevented. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of a temporary rigid connection structure for closing the side span of a cable-stayed bridge of the utility model;
[0013] Figure 2 It is a top view of a temporary rigid connection structure for closing the side spans of a cable-stayed bridge according to the utility model.
[0014] In the figure: 1. Embedded bolts; 2. Double-jointed channel steel; 3. Tie plates; 4. Segmental beam body; 5. Side span joint section. DETAILED DESCRIPTION
[0015] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0016] The utility model will be further described below in conjunction with the accompanying drawings.
[0017] like Figure 1-2 As shown, a temporary rigid connection structure for the side span closure of a cable-stayed bridge includes a connecting assembly; the side span closure section 5 is located between two segment beam bodies 4, the connecting assembly is connected to the side span closure section 5 and the upper end surfaces of the two segment beam bodies 4, and the two ends of the connecting assembly are connected to the two segment beam bodies 4.
[0018] Specifically, the connection assembly includes a double-jointed channel steel 2, and both ends of the double-jointed channel steel 2 are connected to the upper end surface of the segment beam body 4 through embedded bolts 1. Four embedded bolts 1 are connected to the upper end surface of each segment beam body 4, and both ends of the double-jointed channel steel 2 are provided with holes corresponding to the four embedded bolts 1. Four gusset plates 3 are connected to the upper end surface of the double-jointed channel steel 2 at equal distances. The gusset plates 3 are welded to the double-jointed channel steel 2. The height of all welds is not less than 6 mm.
[0019] Specifically, the embedded bolt 1 has a diameter of 42 mm and a length of 415 mm. It is buried in the concrete of the beam body for a length of 300 mm, with a transverse distance of 38 cm and a longitudinal distance of 20 cm.
[0020] Specifically, the double-jointed channel steel 2 is a No. 40a channel steel with a length of 3m. The embedded bolts 1 are respectively inserted into the openings at the bottom edges of both ends, and the opening diameter is 43mm.
[0021] The temporary rigid joint structure of the side span closure of this cable-stayed bridge is welded in the factory, which not only ensures the welding quality but also saves the on-site welding construction time. The embedded bolts 1 are embedded in advance when pouring the concrete of the previous section beam body. At a lower temperature during the day or at the temperature required by the design, the closure support is installed on the embedded bolts 1, and the nuts are tightened, and then the concrete of the side span closure section is poured immediately. The structure is simple, easy to install on site, short in time, safe and reliable, and prevents the shrinkage or crushing of the concrete of the side span closure section.
[0022] The above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model is described in detail with reference to the above embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the above embodiments, or replace some or all of the technical features therein with equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.
Claims
1. A temporary rigid joint structure for the side span closure of a cable-stayed bridge. It is characterized in that It comprises a connection component; a side span joint section (5) is located between two sections of segmental beam bodies (4), the connection component is connected to the side span joint section (5) and the upper end surfaces of the two sections of the segmental beam bodies (4), and the two ends of the connection component are connected to the two sections of the segmental beam bodies (4).
2. The temporary rigid connection structure for the side span closure of a cable-stayed bridge according to claim 1, It is characterized in that The connection assembly comprises a double-jointed channel steel (2), and both ends of the double-jointed channel steel (2) are respectively connected to the upper end surface of the segment beam body (4) via embedded bolts (1).
3. The temporary rigid connection structure for the side span closure of a cable-stayed bridge according to claim 2, It is characterized in that The upper end surface of the double-jointed channel steel (2) is connected to four gusset plates (3) at equal distances.
4. The temporary rigid connection structure for the side span closure of a cable-stayed bridge according to claim 2, It is characterized in that The upper end surface of each segment beam body (4) is connected to four of the embedded bolts (1).
5. The temporary rigid connection structure for the side span closure of a cable-stayed bridge according to claim 4, It is characterized in that Both ends of the double-jointed channel steel (2) are provided with holes corresponding to the four embedded bolts (1).
6. The temporary rigid connection structure for the side span closure of a cable-stayed bridge according to claim 3, It is characterized in that The gusset plate (3) is connected to the double-jointed channel steel (2) by welding.