Adjustable construction bracket

By designing adjustable construction brackets and using splicing and adjusting support angle structures, the problem that the existing brackets are not suitable for the construction of different high pier cap beams is solved, and the versatility and construction safety are improved.

CN221895589UActive Publication Date: 2024-10-25HEBEI LIANLU CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420504228.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-10-25
Estimated Expiration
2034-03-15

AI Technical Summary

Technical Problem

The existing bridge construction bracket structure is fixed and cannot be suitable for the construction of different high piers and cap beams, resulting in construction inconvenience.

Method used

An adjustable construction bracket is designed. By splicing and adjusting the support angle, including the first fixed block, connecting column, fixed connecting block, safety rope hanging block, cylinder and alarm, it can be constructed according to the specifications of the high pier cap beam. Adjust and support to ensure construction safety.

Benefits of technology

The multifunctionality of the bracket is realized, and it is suitable for the construction of different high piers and cap beams. The alarm improves construction safety and avoids the risk of construction workers falling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221895589U_ABST
    Figure CN221895589U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of construction brackets, in particular to an adjustable construction bracket. The utility model provides an adjustable construction bracket which can be spliced and can adjust a supporting angle so as to be conveniently used for construction of different high pier capping beams. An adjustable construction bracket comprises first fixing blocks, first connecting columns, second fixing blocks and the like, the first fixing blocks comprise the front first fixing block and the rear first fixing block, the first connecting columns are connected to the sides, close to each other, of the first fixing blocks in a clamped mode, and the second fixing blocks are connected between the first connecting columns in a clamped mode. The first connecting columns with the corresponding number are connected between the first fixing blocks through the second fixing blocks, the second connecting columns with the corresponding number are connected between the first rotating type connecting blocks and the third fixing blocks through the air cylinders and the third rotating type connecting blocks respectively, and splicing and supporting angle adjusting can be achieved; and therefore, the construction effect of different high pier capping beams is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of construction brackets, in particular to an adjustable construction bracket. Background Art

[0002] The construction bracket of the bridge high pier cap beam is an important equipment used to support the temporary structure during the construction of the high pier cap beam to ensure the safe and efficient construction. In the construction of the high pier cap beam, the construction bracket plays the role of supporting, fixing and balancing the high pier cap beam formwork and concrete pouring.

[0003] Existing bridge construction brackets are made by welding steel according to the specifications of the bridge piers and the shape of the cap beam template. After the steel is made into a bracket, it is installed on the bridge piers to support the cap beam template. However, due to the fixed structure of the bracket, it can only be used for the corresponding high pier cap beam construction, and cannot be used for different high pier cap beam construction, which is inconvenient.

[0004] Therefore, a kind of adjustable construction bracket which can be spliced ​​and adjust the support angle so as to be used for the construction of different high pier cap beams has been developed. Utility Model Content

[0005] In order to overcome the disadvantage that the existing bridge construction bracket is fixed in structure and can only be used for corresponding high pier cap beam construction but cannot be used for different high pier cap beam construction, the utility model provides an adjustable construction bracket which can be spliced ​​and adjust the support angle so as to be used for different high pier cap beam construction.

[0006] The technical solution is as follows: an adjustable construction bracket, comprising a first fixed block, a first connecting column, a second fixed block and a first fixed connecting block, the first fixed block having two front and rear parts, the first connecting columns being clamped on the sides of the first fixed blocks close to each other, the second fixed blocks being clamped between the first connecting columns, and the first fixed connecting blocks being clamped on the front and rear parts of the first connecting column.

[0007] Preferably, a safety rope hanging block is further included, and the safety rope hanging block is connected to the side of the first fixing blocks that is away from each other.

[0008] Preferably, a hook is provided on the safety rope hanging block.

[0009] Preferably, it also includes a connecting square steel, a fixing screw, a first rotatable connecting block, a second connecting column and a second fixed connecting block. The first fixed connecting block is detachably connected to the connecting square steel by a fixing screw, the right side of the connecting square steel is detachably connected to the second fixed connecting block by a fixing screw, the second connecting column is clamped between the front second fixed connecting blocks, the second connecting column is also clamped between the rear second fixed connecting blocks, and the first rotatable connecting block is clamped on the side of the second connecting columns away from each other.

[0010] Preferably, it also includes a third fixed block, a second rotatable connecting block, a connecting telescopic steel, a cylinder and a third rotatable connecting block, the third rotatable connecting block is clamped between the second connecting columns, the lower side of the first rotatable connecting block is connected to the connecting telescopic steel, the lower side of the connecting telescopic steel is detachably connected to the second rotatable connecting block by fixing screws, the second rotatable connecting block is also clamped with the second connecting column, the front and rear parts of the lower second connecting column are clamped with the third fixed block, the cylinder is clamped between the lower second connecting columns, the telescopic end of the cylinder is connected to the third rotatable connecting block, the cylinder is started to make the cylinder push the third rotatable connecting block to move, so that the third rotatable connecting block rotates on the upper second connecting column, and drives the upper second connecting column to move, so as to adjust the inclination angle of the connecting square steel.

[0011] Preferably, an alarm is also included, and the third fixing blocks on the front and rear sides are both connected with the alarm. When the third fixing block loosens and moves downward to break the alarm, the alarm sounds an alarm to remind the construction workers to evacuate in time to avoid the construction workers falling.

[0012] The beneficial effects of the utility model are: 1. The utility model connects a corresponding number of first connecting columns between the first fixed blocks through the second fixed block, and connects a corresponding number of second connecting columns between the first rotating connecting block and the third fixed block through the cylinder and the third rotating connecting block, thereby achieving the effect of being able to splice and adjust the support angle to facilitate the construction of different high pier cap beams.

[0013] 2. The utility model installs the alarm on the high pier when installing the third fixing block. When the third fixing block loosens and moves downward to break the alarm, the alarm sounds an alarm to remind the construction workers to evacuate in time to avoid the construction workers falling. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a three-dimensional structural schematic diagram of the utility model.

[0015] Figure 2 It is a structural schematic diagram of the utility model.

[0016] Figure 3 This is a schematic diagram of the first three-dimensional structure of the utility model.

[0017] Figure 4 This is a schematic diagram of the second three-dimensional structure of the utility model.

[0018] The marks in the accompanying drawings are: 1_first fixed block, 2_safety rope hanging block, 3_first connecting column, 4_second fixed block, 5_first fixed connecting block, 6_connecting square steel, 7_fixing screw, 8_first rotating connecting block, 9_second connecting column, 10_second fixed connecting block, 11_third fixed block, 12_alarm, 13_second rotating connecting block, 14_connecting telescopic steel, 15_cylinder, 16_third rotating connecting block. DETAILED DESCRIPTION

[0019] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0020] An adjustable construction bracket, such as Figure 1-Figure 3 As shown, it includes a first fixed block 1, a safety rope hanging block 2, a first connecting column 3, a second fixed block 4 and a first fixed connecting block 5. The first fixed block 1 has two front and rear parts. The first fixed blocks 1 are connected to the safety rope hanging blocks 2 on the sides away from each other. The safety rope hanging blocks 2 are provided with hooks to facilitate the fixing of the safety rope. The first fixing blocks 1 are clamped on the sides close to each other. The second fixed blocks 4 are clamped between the first connecting columns 3. The first fixed connecting blocks 5 are clamped on the front and rear parts of the first connecting columns 3.

[0021] like Figure 1 and Figure 2 As shown, it also includes a connecting square steel 6, a fixing screw 7, a first rotatable connecting block 8, a second connecting column 9 and a second fixed connecting block 10. The first fixed connecting block 5 is detachably connected to the connecting square steel 6 by the fixing screw 7, and the right side of the connecting square steel 6 is detachably connected to the second fixed connecting block 10 by the fixing screw 7. The second connecting column 9 is clamped between the front second fixed connecting blocks 10, and the second connecting column 9 is also clamped between the rear second fixed connecting blocks 10. The first rotatable connecting block 8 is clamped on the side away from each other of the second connecting columns 9.

[0022] like Figure 1 , Figure 2 and Figure 4 As shown, it also includes a third fixed block 11, an alarm 12, a second rotatable connecting block 13, a connecting telescopic steel 14, a cylinder 15 and a third rotatable connecting block 16. The third rotatable connecting block 16 is clamped between the second connecting columns 9. The lower side of the first rotatable connecting block 8 is connected to the connecting telescopic steel 14. The lower side of the connecting telescopic steel 14 is detachably connected to the second rotatable connecting block 13 through the fixing screws 7. The second rotatable connecting block 13 is also clamped with the second connecting column 9. The front and rear parts of the second connecting column 9 on the lower side are clamped with the third fixed block 11. The alarm 12 is clamped on the third fixed block 11 on both the front and rear sides. The cylinder 15 is clamped between the second connecting columns 9 on the lower side, and the telescopic end of the cylinder 15 is connected to the third rotatable connecting block 16.

[0023] When using the utility model, firstly, according to the specifications of the high pier of the bridge, a corresponding number of first connecting columns 3 are connected between the first fixing blocks 1 through the second fixing block 4, and a corresponding number of second connecting columns 9 are respectively connected between the first rotating connecting block 8 and the third fixing block 11 through the cylinder 15 and the third rotating connecting block 16, and then the first fixing block 1 and the second fixing block 4 are installed on the high pier of the bridge, the first connecting column 3 is fixed, the third fixing block 11 is installed on the high pier of the bridge, and the lower second connecting column 9 is fixed, and then the first fixed connecting block 5 is connected to the connecting square steel 6 through the fixing screws 7, and the connecting square steel 6 is connected to the second fixed connecting block 10, and then according to the construction requirements of the high pier cap beam, the cylinder 15 is started to make the cylinder 15 push the third rotating connecting block 16 to move, so that the third rotating connecting block 16 is on The second connecting column 9 at the bottom rotates, and drives the upper second connecting column 9 to move, adjusts the inclination angle of the connecting square steel 6, and the connecting telescopic steel 14 is extended or recovered accordingly. The second rotating connecting block 13 rotates on the lower second connecting column 9. After the adjustment, the first rotating connecting block 8 is rotated and adjusted, and the first rotating connecting block 8 is installed on the high pier of the bridge to fix the connecting square steel 6, thereby playing the role of being able to splice and adjust the support angle, so as to be used for different high pier cap beam construction. When workers are constructing, they can connect the safety rope to the safety rope hanging block 2 to improve construction safety. When installing the third fixing block 11, the alarm 12 can also be installed on the high pier. When the third fixing block 11 loosens and moves downward to break the alarm 12, the alarm 12 sounds an alarm to remind the construction workers to evacuate in time to avoid the construction workers falling.

[0024] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. An adjustable construction bracket, characterized in that: The invention comprises a first fixing block (1), a first connecting column (3), a second fixing block (4) and a first fixing connecting block (5); the first fixing block (1) has two front and rear parts; the first connecting columns (3) are clamped on the sides of the first fixing blocks (1) close to each other; the second fixing blocks (4) are clamped between the first connecting columns (3); and the first fixing connecting blocks (5) are clamped on the front and rear parts of the first connecting columns (3).

2. An adjustable construction bracket according to claim 1, characterized in that: It also comprises a safety rope hanging block (2), and the safety rope hanging block (2) is connected to each side of the first fixing block (1) which is away from each other.

3. An adjustable construction bracket according to claim 2, characterized in that: A hook is provided on the safety rope hanging block (2).

4. The adjustable construction bracket according to claim 1, characterized in that: The invention also comprises a connecting square steel (6), a fixing screw (7), a first rotatable connecting block (8), a second connecting column (9) and a second fixed connecting block (10); the first fixed connecting block (5) is detachably connected to the connecting square steel (6) via the fixing screw (7); the right side of the connecting square steel (6) is detachably connected to the second fixed connecting block (10) via the fixing screw (7); the second connecting column (9) is clamped between the front second fixed connecting blocks (10); the second connecting column (9) is also clamped between the rear second fixed connecting blocks (10); and the first rotatable connecting block (8) is clamped on the side of the second connecting columns (9) away from each other.

5. An adjustable construction bracket according to claim 4, characterized in that: The invention also comprises a third fixed block (11), a second rotatable connecting block (13), a connecting telescopic steel material (14), a cylinder (15) and a third rotatable connecting block (16); the third rotatable connecting block (16) is clamped between the second connecting columns (9); the lower side of the first rotatable connecting block (8) is connected to the connecting telescopic steel material (14); the lower side of the connecting telescopic steel material (14) is detachably connected to the second rotatable connecting block (13) via a fixing screw (7); the second rotatable connecting block (13) is also clamped to the second connecting screw (16); The second connecting column (9) at the lower side is clamped with a third fixed block (11) at both the front and rear parts, and a cylinder (15) is clamped between the second connecting columns (9) at the lower side, and the telescopic end of the cylinder (15) is connected to the third rotating connecting block (16). The cylinder (15) is started to push the third rotating connecting block (16) to move, so that the third rotating connecting block (16) rotates on the upper second connecting column (9), and drives the upper second connecting column (9) to move, thereby adjusting the inclination angle of the connecting square steel (6).

6. An adjustable construction bracket according to claim 5, characterized in that: The device also comprises an alarm (12), and the third fixing blocks (11) on the front and rear sides are both connected with the alarm (12). When the third fixing block (11) becomes loose and moves downward to break the alarm (12), the alarm (12) sounds an alarm to remind construction workers to evacuate in time and prevent the construction workers from falling.