Fabricated energy dissipation buttress for building

By adopting a height adjustment mechanism and an energy dissipation mechanism in the energy-dissipating piers for prefabricated buildings, and using gears and toothed belts to realize friction adjustment, the problems of time-consuming and labor-intensive installation and inaccurate friction in the existing technology are solved, and the installation is realized Time and effort savings in the process and precision in friction adaptation.

CN221895997UActive Publication Date: 2024-10-25SHANDONG BAIDUN SHOCK ABSORPTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323438033.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-14
Publication Date
2024-10-25
Estimated Expiration
2033-12-14

AI Technical Summary

Technical Problem

Existing energy-dissipating piers for prefabricated buildings need to accurately adjust the friction between the first friction component and the second friction component during installation. The installation process is time-consuming and laborious, and it is difficult to ensure that the tightening torque of each fastening bolt is the same.

Method used

An energy-dissipating pier including an upper pier and a lower pier is designed. It uses a height adjustment mechanism and an energy-dissipation mechanism to realize friction adjustment through gears and toothed belts, which reduces the need for manual adjustment and improves installation efficiency and accuracy. sex.

Benefits of technology

It saves time and effort in the installation process, while ensuring the accuracy of friction force adaptation, improving installation efficiency and convenience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221895997U_ABST
    Figure CN221895997U_ABST
Patent Text Reader

Abstract

The utility model discloses an energy dissipation buttress for an assembly type building, which belongs to the technical field of energy dissipation buttresses and comprises an upper buttress fixedly connected onto a top beam through screws and a lower buttress fixedly connected onto a bottom beam through screws, an upper mounting seat is fixedly connected onto the side wall of the upper buttress towards the lower buttress, and a lower mounting seat is fixedly connected onto the side wall of the lower buttress. A plurality of first universal shafts are fixedly connected to the side wall, away from the upper buttress, of the upper mounting base at equal intervals in the circumferential direction, connecting bases are fixedly connected to the side walls, away from the upper mounting base, of the first universal shafts, and friction cylinders are fixedly connected to the side walls, away from the first universal shafts, of the connecting bases; the height adjusting mechanism and the energy dissipation mechanism are of an independent structure, compared with the prior art, only the energy dissipation mechanism matched with friction force needs to be selected, the friction force does not need to be adjusted by installation personnel, time and labor are saved during installation, and meanwhile the accuracy of friction force matching during installation is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of energy dissipation piers, and in particular relates to an energy dissipation pier for assembled buildings. Background Art

[0002] Prefabricated buildings refer to buildings that transfer a large amount of on-site work in traditional construction methods to factories, where building components and accessories are processed and manufactured, transported to the construction site, and assembled and installed on site through reliable connection methods. In order to improve the shock absorption performance, this building usually needs to be equipped with an energy dissipation structure.

[0003] Chinese Patent No. 202121475166.0 discloses an energy dissipation pier and energy dissipation structure for prefabricated buildings, which comprises an upper pier installed on a top beam, a first friction assembly installed on the upper pier, a lower pier installed on a bottom beam, a second friction assembly installed on the lower pier, and a fastening bolt installed between the first friction assembly and the second friction assembly for adjusting the height and friction force between the two. When the energy dissipation pier is installed, the upper pier is installed on the top beam, and the lower pier is installed on the bottom beam, the fastening bolt is unscrewed, the first friction assembly and the second friction assembly are separated, the first friction assembly and the second friction assembly are pushed between the upper and lower piers, the first friction assembly and the second friction assembly are respectively installed on the upper and lower piers, and then the first friction assembly and the second friction assembly are connected by fastening bolts, and the tightening torque of the fastening bolts is adjusted according to the required friction force between the first friction assembly and the second friction assembly. When in use, energy dissipation is achieved by displacement friction between the first friction assembly and the second friction assembly.

[0004] The inventors of the present application have discovered that the friction force between the first friction assembly and the second friction assembly of the above-mentioned existing energy dissipation pier for prefabricated buildings is achieved by adjusting the tightening torque of the fastening bolts, that is, the installers need to make more precise adjustments during installation, which is time-consuming and labor-intensive, and it is difficult to ensure that the tightening torque of each fastening bolt is the same. Utility Model Content

[0005] In order to solve the problems raised in the above background technology, the utility model provides an energy dissipation pier for assembled buildings, which has the characteristics of saving time and effort in installation and ensuring the accuracy of installation friction adaptation.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an energy dissipation pier for assembled buildings, comprising: an upper pier fixed to a top beam by screws and a lower pier fixed to a bottom beam by screws, the upper pier being fixed with an upper mounting seat toward a side wall of the lower pier, the upper mounting seat being fixed with a plurality of first universal shafts at equal intervals along a circumferential direction away from the side wall of the upper pier, the first universal shaft being fixed with a connecting seat away from the side wall of the upper mounting seat, the connecting seat being fixed with a friction cylinder away from the side wall of the first universal shaft, the lower pier A lower mounting seat is fixedly connected to the side wall of the upper pier, and a plurality of second universal shafts having the same number as the first universal shafts are arranged at equal intervals along the circumferential direction on the side of the lower mounting seat away from the lower pier, and a height adjustment mechanism is assembled between the second universal shafts and the lower mounting seat, and an energy dissipation cylinder is fixedly connected to the side wall of the second universal shaft away from the lower mounting seat, and the bottom end of the friction cylinder extends into the energy dissipation cylinder directly below and is in friction contact with the inner wall of the energy dissipation cylinder, and a friction block is fixedly connected to the friction cylinder near the second universal shaft inside the energy dissipation cylinder and is in friction contact with the inner wall of the friction cylinder.

[0007] Furthermore, the height adjustment mechanism includes a mounting plate fixedly connected to the side wall of the lower mounting seat away from the lower pier and a height adjustment cylinder fixedly connected to the side wall of the lower mounting seat close to the second universal shaft. The mounting plate is rotatably connected to a rotating screw via a bearing away from the side wall of the lower mounting seat. The end of the rotating screw away from the mounting plate passes through the height adjustment cylinder and extends into the height adjustment cylinder. The rotating screw is connected to the through section of the height adjustment cylinder via a transmission nut.

[0008] Furthermore, the rotating screw rod extends to the inner end of the height adjustment cylinder and is fixedly connected to a limit plate.

[0009] Furthermore, a handle is fixedly sleeved on the rotating screw and located below the height adjustment cylinder.

[0010] Furthermore, two sliding grooves are symmetrically provided on the energy dissipation cylinder, and two sliding blocks are symmetrically fixedly connected to the outer wall of the friction cylinder and extend into the two sliding grooves for sliding respectively.

[0011] Furthermore, a gear is fixedly sleeved on the rotating screw rod above the handle, and a plurality of the gears are meshed and connected with a toothed belt.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] 1. The height adjustment mechanism and energy dissipation mechanism of the utility model are independent structures. Compared with the prior art, it is sufficient to select an energy dissipation mechanism that matches the friction force. There is no need for the installer to adjust the friction force himself. The installation is more time-saving and labor-saving, and the accuracy of the installation friction force adaptation is guaranteed at the same time.

[0014] 2. The utility model is provided with gears and toothed belts, which can realize the function of one rotating screw driving other rotating screws to rotate, making the height adjustment more convenient and quick. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a three-dimensional diagram of the utility model;

[0016] Figure 2 It is a vertical cross-sectional view of the utility model;

[0017] Figure 3 For this utility model Figure 2 Enlarged view of point A in the middle;

[0018] Figure 4 For this utility model Figure 2 Enlarged view of point B in the middle;

[0019] In the figure: 1. upper pier; 2. lower pier; 3. upper mounting seat; 4. first cardan shaft; 5. lower mounting seat; 6. height adjustment cylinder; 7. second cardan shaft; 8. energy dissipation cylinder; 9. connecting seat; 10. friction cylinder; 11. friction block; 12. sliding groove; 13. sliding block; 14. limit plate; 15. rotating screw; 16. mounting plate; 17. handle; 18. gear; 19. toothed belt. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] Embodiment 1

[0022] See also Figure 1-4The utility model provides the following technical solutions: an energy dissipation pier for assembled buildings, comprising: an upper pier 1 fixed to a top beam by screws and a lower pier 2 fixed to a bottom beam by screws, an upper mounting seat 3 fixed to a side wall of the upper pier 1 facing the lower pier 2, a plurality of first universal shafts 4 fixed to the upper mounting seat 3 away from the side wall of the upper pier 1 at equal intervals along the circumferential direction, a connecting seat 9 fixed to a side wall of the first universal shaft 4 away from the upper mounting seat 3, a friction cylinder 10 fixed to a side wall of the connecting seat 9 away from the first universal shaft 4, and a friction cylinder 10 fixed to a side wall of the lower pier 2 facing the upper pier 1 A lower mounting seat 5 is fixedly connected, and a plurality of second cardan shafts 7 having the same number as the first cardan shaft 4 are placed at equal intervals along the circumferential direction on the side of the lower mounting seat 5 away from the lower pier 2. A height adjustment mechanism is assembled between the second cardan shaft 7 and the lower mounting seat 5. An energy dissipation cylinder 8 is fixedly connected to the side wall of the second cardan shaft 7 away from the lower mounting seat 5. The bottom end of the friction cylinder 10 extends to the energy dissipation cylinder 8 directly below and is in friction contact with the inner wall of the energy dissipation cylinder 8. A friction block 11 is fixedly connected to the friction cylinder 10 near the second cardan shaft 7 inside the energy dissipation cylinder 8 and is in friction contact with the inner wall of the friction cylinder 10.

[0023] See attached Figure 2-3 When installing the energy dissipation pier, the upper pier 1 is installed on the top beam by screws, the lower pier 2 is installed on the bottom beam by screws, the upper mounting seat 3 is installed on the upper pier 1 by screws, and the height adjustment mechanism is adjusted according to the distance between the upper pier 1 and the lower pier 2, so that the lower mounting seat 5 abuts against the lower pier 2, and the lower mounting seat 5 is installed on the lower pier 2 by screws; when the energy dissipation pier is damping, energy dissipation is achieved by the friction between the friction cylinder 10 moving up and down and the energy dissipation cylinder 8 and the friction block 11.

[0024] Specifically, the height adjustment mechanism includes a mounting plate 16 fixedly connected to the side wall of the lower mounting seat 5 away from the lower pier 2, and a height adjustment cylinder 6 fixedly connected to the side wall of the second universal joint 7 close to the lower mounting seat 5. The mounting plate 16 is rotatably connected to a rotating screw 15 via a bearing away from the side wall of the lower mounting seat 5. The end of the rotating screw 15 away from the mounting plate 16 passes through the height adjustment cylinder 6 and extends into the height adjustment cylinder 6. The rotating screw 15 is connected to the through section of the height adjustment cylinder 6 via a transmission nut.

[0025] See attached Figure 2 and 4 When the height adjustment mechanism is working, the rotating screw 15 rotates forward and backward. During the forward and backward rotation of the rotating screw 15, the height adjustment cylinder 6 moves up and down on the rotating screw 15 to adjust the height of the lower mounting seat 5.

[0026] Specifically, the rotating screw 15 extends to the inner end of the height adjustment cylinder 6 and is fixedly connected to the limit plate 14 .

[0027] See attached Figure 4 The limit plate 14 plays a limiting role to prevent the height adjustment tube 6 from moving excessively on the rotating screw 15 and causing separation.

[0028] Specifically, a handle 17 is fixedly sleeved on the rotating screw 15 and located below the height adjustment cylinder 6 .

[0029] See attached Figure 4 By rotating the handle 17 forward and reversely, the rotating screw 15 is driven to rotate forward and reversely, thereby improving the convenience and comfort of rotation.

[0030] Specifically, two sliding grooves 12 are symmetrically provided on the energy dissipation cylinder 8 , and two sliding blocks 13 are symmetrically fixedly connected to the outer wall of the friction cylinder 10 and extend into the two sliding grooves 12 for sliding respectively.

[0031] See attached Figure 3 During the up and down movement of the friction cylinder 10, the sliding block 13 moves up and down with the friction cylinder 10 in the sliding groove 12, playing a limiting role to prevent the friction cylinder 10 from disengaging due to excessive movement.

[0032] Embodiment 2

[0033] The difference between this embodiment and the first embodiment is that:

[0034] Specifically, a gear 18 is fixedly sleeved on the rotating screw rod 15 above the handle 17 , and a toothed belt 19 is meshedly connected between the plurality of gears 18 .

[0035] See attached Figure 1 and 4 , a handle 17 can be rotated to drive a rotating screw 15 to rotate, and a rotating screw 15 drives the connected gear 18 to rotate, and the connected gear 18 drives the meshing toothed belt 19 to rotate, and the rotating toothed belt 19 drives other meshing gears 18 to rotate, and other meshing gears 18 drive their respective connected rotating screws 15 to rotate, so that one handle 17 can drive multiple rotating screws 15 to rotate simultaneously, that is, the function of adjusting the height of the lower mounting seat 5 can be achieved by operating one handle 17.

[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An energy dissipation pier for assembled buildings, characterized in that: include: An upper pier (1) fixedly connected to the top beam by screws and a lower pier (2) fixedly connected to the bottom beam by screws, the upper pier (1) is fixedly connected to an upper mounting seat (3) on the side wall facing the lower pier (2), the upper mounting seat (3) is fixedly connected to a plurality of first universal shafts (4) at equal intervals along the circumferential direction away from the side wall of the upper pier (1), the first universal shaft (4) is fixedly connected to a connecting seat (9) on the side wall away from the upper mounting seat (3), the connecting seat (9) is fixedly connected to a friction cylinder (10) on the side wall away from the first universal shaft (4), the lower pier (2) is fixedly connected to a lower mounting seat (5) on the side wall facing the upper pier (1), the lower mounting seat (5) is fixedly connected to the side wall of the lower pier (2) facing the upper pier (1), the lower mounting seat (5) is fixedly connected to the side wall of the upper pier (1), the upper ... A plurality of second universal joints (7) having the same number as the first universal joints (4) are arranged at equal intervals along the circumferential direction on the side of the seat (5) away from the lower pier (2); a height adjustment mechanism is arranged between the second universal joints (7) and the lower mounting seat (5); an energy dissipation cylinder (8) is fixedly connected to the side wall of the second universal joint (7) away from the lower mounting seat (5); the bottom end of the friction cylinder (10) extends into the energy dissipation cylinder (8) directly below and is in friction contact with the inner wall of the energy dissipation cylinder (8); a friction block (11) is fixedly connected to the friction cylinder (10) on the side of the friction cylinder (10) near the second universal joint (7) and is in friction contact with the inner wall of the friction cylinder (10).

2. The energy dissipation buttress for assembled buildings according to claim 1, characterized in that: The height adjustment mechanism comprises a mounting plate (16) fixedly connected to the side wall of the lower mounting seat (5) away from the lower pier (2) and a height adjustment cylinder (6) fixedly connected to the side wall of the second universal shaft (7) close to the lower mounting seat (5); the mounting plate (16) is rotatably connected to a rotating screw rod (15) via a bearing at the side wall away from the lower mounting seat (5); the end of the rotating screw rod (15) away from the mounting plate (16) penetrates the height adjustment cylinder (6) and extends into the height adjustment cylinder (6); the rotating screw rod (15) is connected to the penetration section of the height adjustment cylinder (6) via a transmission nut.

3. The energy dissipation buttress for assembled buildings according to claim 2, characterized in that: The rotating screw rod (15) extends to the inner end portion of the height adjustment cylinder (6) and is fixedly connected to a limiting disk (14).

4. The energy dissipation buttress for assembled buildings according to claim 2, characterized in that: A handle (17) is fixedly sleeved on the rotating screw rod (15) and located below the height adjustment cylinder (6).

5. The energy dissipation buttress for assembled buildings according to claim 1, characterized in that: The energy dissipation cylinder (8) is symmetrically provided with two sliding grooves (12), and the outer wall of the friction cylinder (10) is symmetrically fixed with two sliding blocks (13) which extend into the two sliding grooves (12) and slide respectively.

6. The energy dissipation buttress for assembled buildings according to claim 4, characterized in that: A gear (18) is fixedly sleeved on the rotating screw rod (15) above the handle (17), and a plurality of the gears (18) are meshedly connected with a toothed belt (19).