Beam erecting equipment in tunnel

By designing and installing tunnel girder equipment for hanging silos, cranes and brackets, and using the clamping mechanism of connecting plates and threaded rods, the problems of inconvenient operation of existing equipment and wear and tear of hanging ropes were solved, and the convenient fixing and fixation of T-beams were realized. Solid improvement.

CN221917089UActive Publication Date: 2024-10-29CHINA RAILWAY NO 5 ENGINEERING GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420156150.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-23
Publication Date
2024-10-29
Estimated Expiration
2034-01-23

AI Technical Summary

Technical Problem

When lifting T-beams with existing beam erecting equipment in tunnels, the slings and T-beams need to be tied together first, which is inconvenient to operate and can easily lead to wear of the slings.

Method used

A tunnel girder erecting equipment including the installation of silos, cranes and brackets is designed. The T-beam is clamped by two sets of connecting plates, and the rotation of the threaded rod and the threaded pipe is used to make the connecting plates clamp the T-beam. Combined with the first Use the second plywood, bearings and screws to firmly fix the T-beam and avoid direct friction between the hanging rope and the T-beam.

Benefits of technology

It realizes the convenient fixing and stable lifting of the T-beam, reduces the wear of the lifting rope during the lifting process, and improves the operational convenience and stability of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221917089U_ABST
    Figure CN221917089U_ABST
Patent Text Reader

Abstract

The utility model discloses a tunnel inner girder erection device, which comprises an installation hanging bin, a crown block and a support, the bottom of the support is provided with the crown block, the two ends of the bottom of the crown block are provided with hanging ropes, the bottoms of the hanging ropes are provided with the installation hanging bin, and one end of the interior of the installation hanging bin is provided with a second bearing. A threaded rod is installed in the second bearing, two sets of threaded pipes are installed on the outer side of the threaded rod in a threaded mode, connecting plates are installed at the bottoms of the threaded pipes, fixing screw pipes are installed on the inner sides of the connecting plates, and fixing screw rods are installed in the fixing screw pipes in a threaded mode. The T-beam hoisting tool is provided with the installation hanging bin and the connecting plates, when the T-beam hoisting tool is used, the T-beam can be directly hoisted by clamping and fixing the T-beam through the two sets of connecting plates and then hoisting the installation hanging bin through the hoisting rope, the hoisting rope and the T-beam do not need to be fixed, and the hoisting rope can be prevented from being abraded in the hoisting process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction equipment, in particular to a tunnel internal beam erecting device. Background Art

[0002] A tunnel refers to an engineering building buried in the ground. It is a form of human utilization of underground space. Bridge-building machines and other beam-building equipment are one of the commonly used equipment for tunnel construction. During the tunnel construction process, bridge-building machines are needed to lift and install T-beams to build roads.

[0003] For example, the utility model: "A novel device for erecting beams in tunnels", with the announcement number: "CN216638622U", provides a protective cover on the lifting rope at the bottom of the overhead crane, and the protective cover is wrapped around the lifting rope. When the device is hoisting a T-beam, the protective cover can be moved to the friction point between the lifting rope and the T-beam, thereby reducing the wear of the lifting rope and preventing the lifting rope from being worn and broken during the hoisting process. However, during the implementation of the patent, it is necessary to first bind and connect the lifting rope to the T-beam. When lifting the T-beam, the T-beam cannot be directly clamped and fixed at the bottom of the overhead crane, and the lifting process is inconvenient to operate. Therefore, the utility model provides a device for erecting beams in tunnels to solve the above problems. Utility Model Content

[0004] The purpose of the utility model is to provide a tunnel beam erecting device to solve the problems raised in the above background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a beam erecting device in a tunnel, comprising a hanging silo, a crane and a bracket, the crane is installed at the bottom of the bracket, and both ends of the bottom of the crane are installed with hanging ropes, the hanging silo is installed at the bottom of the hanging rope, and a second bearing is installed at one end inside the hanging silo, a threaded rod is installed inside the second bearing, two groups of threaded pipes are threadedly installed on the outer side of the threaded rod, and connecting plates are installed at the bottom of the threaded pipes, and fixed screws are threadedly installed inside the fixed screws.

[0006] Preferably, sliding components are installed at both ends of the top of the installation silo, and a first guide slider is slidably installed at the bottom of the sliding component, and one end of the first guide slider away from the sliding component is connected to the threaded tube.

[0007] Preferably, the threaded rod passes through the mounting silo and extends to the outside of the mounting silo, and threads in opposite directions are symmetrically arranged on the outer side of the threaded rod.

[0008] Preferably, a slide groove is provided on the inner side of the connecting plate, and a second guide slider is slidably installed inside the slide groove, a second clamping plate is installed at one end of the second guide slider away from the connecting plate, and a first clamping plate is installed at the bottom of the connecting plate.

[0009] Preferably, the top of each of the second clamping plates is installed with a first bearing, and the interior of each of the first bearings is installed with a connecting rod, and one end of each of the connecting rods away from the first bearing is connected to a fixing screw.

[0010] Preferably, supporting feet are installed at the four corners of the bottom of the bracket.

[0011] Preferably, reinforcing plates are installed on the tops of both ends of the supporting legs, and the ends of the reinforcing plates away from the supporting legs are connected to the brackets.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] 1. The tunnel beam erection equipment is equipped with an installation silo and a connecting plate. When in use, the T-beam can be clamped and fixed by two sets of connecting plates, and then the installation silo can be lifted by the lifting rope, so that the T-beam can be directly lifted without fixing the lifting rope and the T-beam, which can prevent the rope from being worn during the lifting process;

[0014] 2. The tunnel beam erecting equipment is equipped with threaded rods and threaded tubes. When in use, by rotating the threaded rod clockwise or counterclockwise, the two sets of threaded tubes can be simultaneously moved to the two ends of the threaded rod or to the middle position of the threaded rod, so that the T beam can be clamped by the two sets of connecting plates, and the T beam can be fixed. The fixing process of the T beam is relatively convenient.

[0015] 3. The beam erection equipment in the tunnel is installed with a first clamping plate, a second clamping plate, a first bearing, a fixing screw and a connecting rotating rod. When fixing the T-beam, the T-beam is placed above the first clamping plate. The staff can rotate the fixing screw to make the second clamping plate fit tightly with the T-beam. The T-beam can be clamped by the first clamping plate and the second clamping plate, which can reinforce the T-beam and prevent it from falling during the lifting process, and can effectively improve the stability of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the front cross-sectional view of the utility model;

[0017] Figure 2 It is a main schematic diagram of the utility model;

[0018] Figure 3 It is a partial structural schematic diagram of the utility model;

[0019] Figure 4 For this utility model Figure 3 A magnified view of the structure in Figure 2.

[0020] In the figure: 1. Support leg; 2. Install the hanging nacelle; 3. Overhead crane; 4. Bracket; 5. Connecting plate; 6. Threaded rod; 7. First clamping plate; 8. Sliding assembly; 9. Threaded pipe; 10. First guide slider; 11. Second clamping plate; 12. First bearing; 13. Fixed screw tube; 14. Fixed screw rod; 15. Connecting rotating rod; 16. Second guide slider; 17. Slide groove; 18. Suspension rope; 19. Second bearing. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] See also Figure 1-4 The utility model provides an embodiment: a tunnel beam erecting device, including a hanging silo 2, a crane 3 and a bracket 4, the crane 3 is installed at the bottom of the bracket 4, and the two ends of the bottom of the crane 3 are installed with hanging ropes 18, the hanging silo 2 is installed at the bottom of the hanging rope 18, and the second bearing 19 is installed at one end inside the hanging silo 2, the second bearing 19 is installed inside the threaded rod 6, the outer side of the threaded rod 6 is threadedly installed with two groups of threaded tubes 9, and the bottom of the threaded tubes 9 are all installed with connecting plates 5, the inner side of the connecting plates 5 are all installed with fixed screws 13, and the inside of the fixed screws 13 are all threadedly installed with fixed screws 14.

[0023] In this implementation:

[0024] Furthermore, sliding components 8 are installed at both ends of the top of the hanging warehouse 2, and the bottom of the sliding component 8 is slidably installed with a first guide slider 10. The end of the first guide slider 10 away from the sliding component 8 is connected to the threaded tube 9. The first guide slider 10 limits the threaded tube 9 to prevent the threaded tube 9 from rotating with the threaded rod 6.

[0025] Furthermore, the threaded rod 6 passes through the mounting pod 2 and extends to the outside of the mounting pod 2, and the outer side of the threaded rod 6 is symmetrically provided with threads in opposite directions. By rotating the threaded rod 6 clockwise or counterclockwise, the two groups of threaded tubes 9 can be moved to both ends of the threaded rod 6 or to the middle position of the threaded rod 6 at the same time.

[0026] Furthermore, a slide groove 17 is provided on the inner side of the connecting plate 5, and a second guide slider 16 is slidably installed inside the slide groove 17, and a second clamping plate 11 is installed on the end of the second guide slider 16 away from the connecting plate 5, and a first clamping plate 7 is installed on the bottom of the connecting plate 5. The T-beam is clamped by the first clamping plate 7 and the second clamping plate 11, so that the T-beam can be reinforced to prevent the T-beam from falling during the lifting process, which can effectively improve the stability of the device.

[0027] Furthermore, a first bearing 12 is installed on the top of the second clamping plate 11, and a connecting rod 15 is installed inside the first bearing 12. The end of the connecting rod 15 away from the first bearing 12 is connected to the fixing screw 14. The staff can rotate the fixing screw 14, and the fixing screw 14 drives the connecting rod 15 to move together, so that the connecting rod 15 drives the second clamping plate 11 to move through the first bearing 12, so that the second clamping plate 11 is tightly fitted with the T-beam, and the T-beam can be clamped by the first clamping plate 7 and the second clamping plate 11.

[0028] Furthermore, legs 1 are installed at the four corners of the bottom of the bracket 4 to facilitate the bracket 4 to be installed firmly.

[0029] Furthermore, reinforcing plates are installed on the tops of both ends of the support leg 1, and the ends of the reinforcing plates away from the support leg 1 are connected to the bracket 4, so that the support leg 1 and the bracket 4 can be firmly installed.

[0030] Working principle:

[0031] When in use, the device is powered on, and the T-beam is placed between the two sets of connecting plates 5, and then the threaded rod 6 is rotated clockwise, and the two sets of threaded tubes 9 outside the threaded rod 6 are limited by the first guide slider 10, so that the threaded tubes 9 cannot rotate with the threaded rod 6, so that the two sets of threaded tubes 9 can only move to the middle position of the threaded rod 6 at the same time through the threads;

[0032] At this time, the threaded tube 9 drives the first guide slider 10 to slide along a straight line on the sliding assembly 8, and the threaded tube 9 drives the connecting plate 5 to move together, so that the connecting plate 5 is closely fitted with the outer side of the T beam, and the T beam can be clamped by the two groups of connecting plates 5, and the bottom of the T beam can be supported by the first clamping plate 7;

[0033] The staff then rotates the two sets of fixing screws 14 clockwise, and the fixing screws 14 drive the connecting rod 15 to rotate, and the connecting rod 15 rotates inside the first bearing 12, and the connecting rod 15 does not drive the second clamping plate 11 to rotate through the first bearing 12;

[0034] The fixing screw 14 moves downward inside the fixing screw tube 13 through the thread, and the fixing screw 14 drives the connecting rotating rod 15 to move together, so that the connecting rotating rod 15 drives the second clamping plate 11 to move through the first bearing 12, so that the second clamping plate 11 can be closely fitted with the T-beam, that is, the T-beam can be clamped by the first clamping plate 7 and the second clamping plate 11, and the T-beam can be reinforced to prevent the T-beam from falling during the lifting process, which can effectively improve the stability of the device;

[0035] After the T-beam is fixed, the overhead crane 3 can be used to drive the lifting rope 18 to lift it, and the installation nacelle 2 can be directly lifted, so that the T-beam can be directly lifted to the designated position for erection.

[0036] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

Claims

1. A tunnel beam erection device, comprising an installation nacelle (2), a crane (3) and a support (4), characterized in that: A crane (3) is installed at the bottom of the bracket (4), and both ends of the bottom of the crane (3) are installed with suspension ropes (18), a hanging silo (2) is installed at the bottom of the suspension rope (18), and a second bearing (19) is installed at one end inside the hanging silo (2), a threaded rod (6) is installed inside the second bearing (19), two groups of threaded tubes (9) are threadedly installed on the outer side of the threaded rod (6), and a connecting plate (5) is installed at the bottom of the threaded tube (9), a fixed screw tube (13) is installed on the inner side of the connecting plate (5), and a fixed screw rod (14) is threadedly installed inside the fixed screw tube (13).

2. The tunnel beam erection device according to claim 1, characterized in that: Sliding assemblies (8) are installed at both ends of the top of the installation silo (2), and a first guide slider (10) is slidably installed at the bottom of the sliding assembly (8), and the end of the first guide slider (10) away from the sliding assembly (8) is connected to the threaded pipe (9).

3. The tunnel beam erection device according to claim 1, characterized in that: The threaded rod (6) passes through the mounting silo (2) and extends to the outside of the mounting silo (2), and threads in opposite directions are symmetrically arranged on the outside of the threaded rod (6).

4. The tunnel beam erection device according to claim 1, characterized in that: The inner side of each of the connecting plates (5) is provided with a slide groove (17), and a second guide slider (16) is slidably mounted inside the slide groove (17), a second clamping plate (11) is mounted on one end of the second guide slider (16) away from the connecting plate (5), and a first clamping plate (7) is mounted on the bottom of each of the connecting plates (5).

5. The tunnel beam erection device according to claim 4, characterized in that: The top of each of the second clamping plates (11) is provided with a first bearing (12), and the interior of each of the first bearings (12) is provided with a connecting rod (15), and one end of each of the connecting rods (15) away from the first bearing (12) is connected to a fixing screw (14).

6. The tunnel beam erection device according to claim 1, characterized in that: Support feet (1) are installed at the four corners of the bottom of the bracket (4).

7. The tunnel beam erection device according to claim 6, characterized in that: Reinforcement plates are installed on the tops of both ends of the support leg (1), and the ends of the reinforcement plates away from the support leg (1) are connected to the bracket (4).