Charging operation platform applied to arch frame trolley
By designing a manned working basket and a charging operation platform with movable robotic arms on the arch trolley, the problems of operating efficiency and limited space in the existing technology are solved, rapid charging and safety are achieved, and the project cost is reduced. cost.
Patent Information
- Application Number
- CN202420184727.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-25
AI Technical Summary
The existing arch trolley has limited operating efficiency and space during the charging operation. A single trolley cannot complete the tunnel face charging of the entire tunnel at one time, resulting in an increase in project costs.
A charging operation platform is designed that includes a manned working basket and a freely movable robotic arm. The robotic arm clamps the I-beam through a clamp, and cooperates with the working basket to achieve rapid disassembly, assembly and movement, which increases the number of operations. The number of hanging baskets is adapted to the rapid charging of the section.
It achieves rapid disassembly and movement, shortens the process cycle time, improves construction efficiency, and protects the safety of workers through protective fences, reducing project costs.
Smart Images

Figure CN221917337U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of tunnel blasting equipment, and in particular relates to a charging operation platform applied to an arch frame trolley. Background Art
[0002] Explosives are irreplaceable products in the process of mine development and rock excavation. At present, the domestic tunnel and mine tunnel excavation blasting method is gradually changing from the traditional method of manually building multi-layer gantry to the modern method of aerial work trolley.
[0003] At present, most modern construction uses plateau three-arm rock drilling trolleys and arch installation trolleys to achieve mechanized operation of large machines. Arch trolleys are used for charging in the charging and blasting process, but the two hanging basket arms equipped in this arch trolley limit the working efficiency and working space. A single trolley cannot complete the charging of the entire tunnel face at one time. Purchasing charging trolleys will undoubtedly increase project costs.
[0004] Based on this, our project was actively carried out and an improved working platform for the arch trolley suitable for charging operations was studied. Utility Model Content
[0005] In order to solve the above problems existing in the prior art, a charging operation platform applied to an arch frame trolley is provided.
[0006] The technical solution adopted by the utility model to solve its technical problems is:
[0007] The utility model proposes a charging operation platform applied to an arch frame trolley, comprising:
[0008] A work basket for carrying people, the left side of the work basket is fixedly connected to a support column, and the left side of the support column is fixedly connected to an I-beam;
[0009] It also includes a freely movable mechanical arm arranged on the arch frame trolley, and the other end of the mechanical arm is connected to a clamp for clamping and fixing the I-beam.
[0010] Preferably, the working hanging basket includes a grille bottom plate, a support beam is symmetrically fixed on the left side of the grille bottom plate, a cross beam is fixedly connected above the support beam, and the support column is fixedly connected to the cross beam; a plurality of groups of support rods are vertically connected to the periphery of the grille bottom plate, and at least two groups of support fences are vertically fixed on the support rods.
[0011] Preferably, an entrance and exit are opened on the right side of the working hanging basket; it also includes rings mounted on the support rods on both sides of the entrance and exit, the two rings are slidably arranged up and down on the support rods, the rings are located between the two upper support fences, and an intercepting rod is fixedly connected between the two rings.
[0012] Preferably, the clamp comprises a clamping base, and two groups of clamping claws for clamping and fixing the bottom of the I-beam are symmetrically arranged in the clamping base.
[0013] Preferably, a clamping pad is connected to the bottom of the clamping portion in the clamping claw.
[0014] Preferably, after the clamping claws clamp and fix the I-beam, the two clamping claws are located outside the support column.
[0015] Preferably, at least two groups of symmetrical positioning clamps are fixedly provided on the clamping base, and the positioning clamps are located on the inner side of the supporting column; the positioning clamps are U-shaped.
[0016] Preferably, at least two groups of steel pads are provided on the top surface of the clamping base, and the steel pads are provided between each group of clamping claws.
[0017] Preferably, a pin crossbeam is fixedly connected to the left side of the I-beam, a pin hole is opened on the pin crossbeam, and a safety pin is inserted into the pin hole; the clamp is located between the safety pin and the support column, and the bottom of the safety pin extends to the bottom position of the clamp.
[0018] Compared with the prior art, the beneficial effects of the utility model are:
[0019] 1. The utility model is provided with a working hanging basket, and an I-beam is fixedly connected to the left side of the working hanging basket. The mechanical arm arranged on the arch frame trolley cooperates with the clamp to clamp and fix the working hanging basket, so that the working hanging basket can be quickly disassembled and assembled. Compared with the traditional arch frame trolley, at least one movable working hanging basket is added, which is more suitable for rapid cross-section charging, shortens the process cycle time, improves the construction efficiency, and is simple and convenient to manufacture and install, which is convenient for process promotion.
[0020] 2. In the utility model, an entrance and an exit are opened on such a hanging basket, and an intercepting rod which can slide up and down is arranged between the entrance and the exit. By lifting the intercepting rod, the workers can enter the working hanging basket conveniently. When all the workers have entered, the intercepting rod falls freely to form a protective fence with the supporting rod and the supporting fence to prevent the workers from falling and ensure their personal safety.
[0021] 3. The clamp in this device includes a clamping base, on which a clamping claw for clamping the bottom of the I-beam is provided. The cooperation between the clamping claw and the I-beam can realize the quick installation of the working hanging basket. When installing, the working hanging basket is lifted to the clamp and the clamping claw is tightened. The whole process is relatively fast and has little impact on the process time. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0023] Figure 1 It is a structural schematic diagram of a mechanical arm controlling an operating hanging basket in the utility model.
[0024] Figure 2 It is a schematic diagram of the matching structure of the clamp and the working hanging basket in the utility model.
[0025] Figure 3 It is a three-dimensional structural schematic diagram of the clamp in the utility model.
[0026] Description of reference numerals:
[0027] 1. Mechanical arm; 2. Working basket; 21. Grille bottom plate; 22. Support beam; 23. Crossbeam; 24. Support rod; 25. Support fence; 26. Inlet and outlet; 27. Ring; 28. Interceptor rod; 3. Clamp; 31. Clamping base; 32. Clamping claw; 33. Clamping pad; 34. Positioning card; 35. Steel pad; 4. Support column; 5. I-beam; 6. Pin column crossbeam; 7. Pin column hole; 8. Safety pin column. DETAILED DESCRIPTION
[0028] In order to make the purpose, features and advantages of the utility model more obvious and easy to understand, the technical scheme in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the embodiment described below is only a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0029] In the description of the present utility model, it is to be understood that when a component is considered to be "connected" to another component, it may be directly connected to the other component or there may be a centrally arranged component at the same time. When a component is considered to be "set on" another component, it may be directly set on the other component or there may be a centrally arranged component at the same time.
[0030] In addition, terms such as "long", "short", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings and are only used to facilitate the description of the present invention. They do not indicate or imply that the device or component referred to must have this specific direction or operate with a specific direction structure, and should not be understood as a limitation of the present invention.
[0031] The present invention will be described in detail below in conjunction with the specific embodiments shown in the accompanying drawings. However, these embodiments do not limit the present invention, and any structural, methodological, or functional changes made by a person skilled in the art based on these embodiments are all within the scope of protection of the present invention.
[0032] Embodiment 1
[0033] like Figure 1-Figure 3 As shown, this embodiment proposes a charging operation platform applied to an arch frame trolley. Explosives are irreplaceable products in the process of mine development and rock and soil excavation. At present, the excavation and blasting methods of domestic tunnels and mine tunnels are gradually changing from the traditional method of manually building multi-layer gantry to the modern method of aerial work trolleys. The most common method is to use the China Railway Construction Heavy Industry SCD112S tunnel multi-function operation trolley for tunnel charging and blasting, but the two hanging basket arms equipped on the trolley limit the working efficiency and working space. Purchasing a charging trolley will undoubtedly increase the project cost, so our project actively carries out the improvement of the tooling of the arch frame trolley suitable for charging operations.
[0034] Based on this, a charging operation platform applied to an arch trolley is studied, which includes a manned operation basket 2, and a support column 4 is fixedly connected to the upper left side of the operation basket 2 by welding or the like, and an I-beam 5 is fixedly connected to the left side of the support column 4 by welding or the like.
[0035] It also includes a freely movable mechanical arm 1 arranged on the arch trolley. Preferably, the mechanical arm 1 can be a hydraulic mechanical arm 1, which is control-connected to the power system on the arch trolley; the other end of the mechanical arm 1 is connected to a clamp 3 for clamping and fixing the I-beam 5.
[0036] For further reference, Figure 2 In this embodiment, the working hanging basket 2 includes a grid bottom plate 21. The grid bottom plate 21 is a trapezoidal structure in this embodiment. The trapezoidal structure has a larger space, which is convenient for carrying multiple people to operate, and the front section of the trapezoidal structure is protruding, which is convenient for charging the tunnel face. Support beams 22 are symmetrically fixed on the left side of the grid bottom plate 21. The support beams 22 and the grid bottom plate 21 are connected with reinforcing ribs. The top of the support beam 22 is fixedly connected to a cross beam 23, and the cross beam 23 is fixedly connected to the above-mentioned support column 4 by welding or other means. Several groups of support rods 24 are vertically connected around the grid bottom plate 21. At least two groups of support fences 25 are vertically fixedly connected to the support rods 24. The two ends of the support fences 25 are respectively fixedly connected to the two ends of the cross beam 23. The support rods 24 and the support fences 25 are coordinated to protect the workers and prevent them from falling, thereby ensuring the personal safety of the workers during the operation.
[0037] In order to facilitate the staff to enter and exit the working hanging basket 2, an entrance and exit 26 is opened on the right side of the working hanging basket 2. The specific opening method is to cut off the part of the supporting fence 25 in the middle between the two supporting bars 24 of the working hanging basket 2, grind the corners after cutting, and form the above-mentioned entrance and exit 26 between the two supporting bars 24 and the supporting fence 25 on the top and the grille bottom plate 21. It also includes a ring 27 sleeved on the supporting bars 24 on both sides of the entrance and exit 26, and the two rings 27 are set to slide up and down with the supporting bars 24. The ring 27 is located between the two upper supporting fences 25, and the two rings 27 are fixedly connected with an intercepting rod 28 by welding or the like. This design facilitates the staff to enter and exit the working hanging basket 2 through the entrance and exit 26, and the intercepting rod 28 that can slide up and down can protect the staff and prevent the staff from falling and getting injured.
[0038] The support column 4 is provided so that there is a certain gap between the hanging basket and the I-beam 5. The clamp 3 is not limited in this embodiment, and can be fastened to the outside of the I-beam 5 in the form of a hoop to fix the working hanging basket 2, or can be directly clamped and fixed to the I-beam 5. It is sufficient to fix the working hanging basket 2 and drive it to move through the mechanical arm 1.
[0039] The working principle of this device is:
[0040] The mechanical arm 1 and the clamp 3 set on the arch trolley are fixed in advance, and then the clamp 3 and the working hanging basket 2 are fixed. The fixing degree is checked, and the staff can enter the working hanging basket 2 after ensuring safety.
[0041] The staff manually moves the interception rod 28 upwards to increase the distance between the interception rod 28 and the grid bottom plate 21, thereby entering the interior of the working hanging basket 2. After the staff are all in, the interception rod 28 slides down with gravity to contact the middle support fence 25, thereby protecting the staff.
[0042] Then, the mechanical arm 1 controls the operation basket 2 to move to the place where the explosives need to be installed, and the workers install the explosives into the tunnel face. After all the installations are completed, the workers and the arch trolley stay away from the blasting point to prevent accidental injuries.
[0043] The device is a further optimization of the conventional arch trolley, which can realize rapid charging of explosives on the face of the tunnel, shorten the process cycle time and improve construction efficiency.
[0044] Embodiment 2
[0045] like Figure 1-3 As shown, this embodiment proposes a charging work platform for an arch frame trolley, and other structures are the same as those of the first embodiment. The difference is that, in this embodiment, a clamp 3 that is more suitable for the working hanging basket 2 and the I-beam 5 is proposed, so that the disassembly and assembly of the working hanging basket 2 is more convenient.
[0046] Specifically, the clamp 3 includes a clamping base 31, in which two groups of clamping claws 32 for clamping and fixing the bottom flange of the I-beam 5 are symmetrically arranged, and a clamping pad 33 is connected to the bottom of the clamping portion of the clamping claw 32. The clamping pad 33 increases the contact area between the clamping claw 32 and the bottom of the I-beam 5, so that the clamping claw 32 clamps the bottom of the I-beam 5 more firmly. The clamping base contains a power unit, and the power unit in the clamping base is controlled by the driving unit in the robot 1 to realize the opening and closing of the clamping claw 32. At least two groups of steel pads 35 are arranged on the top surface of the clamping base, and the steel pads 35 are arranged between each group of clamping claws 32 to prevent the I-beam 5 from directly rubbing against the clamping base 31 and causing wear.
[0047] When the clamping claws clamp and fix the I-beam 5, the two clamping claws 32 are located outside the two support columns 4; two sets of symmetrical positioning clamps 34 are also fixedly arranged on the clamping base, and the positioning clamps 34 are located inside the support column 4, and the clamps are U-shaped. The positioning clamps 34 and the clamping claws 32 are respectively located on both sides of the support column 4, and the interference of the support column 4 is used to limit the two to a certain extent, so as to prevent the claws from moving when the mechanical arm 1 drives the working basket 2 to move.
[0048] Furthermore, a pin crossbeam 6 is fixedly connected to the left side of the I-beam 5, and a pin hole 7 is opened on the pin crossbeam 6, and a safety pin 8 is inserted into the pin hole 7; when the safety pin 8 is inserted into the pin hole 7, the clamp 3 is between the safety pin and the support column 4, and the bottom of the safety pin 8 extends to the bottom of the clamp 3. The clamp 3 is further limited, and after the work hanging basket 2 is fixed, the safety pin 8 is inserted into the pin hole 7. When the clamp 3 fails, the safety pin 8 is clamped with the clamp 3, which is mechanically self-locking to protect the safety of the operator.
[0049] The working principle of this device is:
[0050] The staff lifts the hanging basket to the fixture 3, places the I-beam 5 partly on the base of the fixture 3, and controls the clamping claw 32 in the clamping base to tighten and hold the bottom of the I-beam 5. After tightening, the safety pin 8 is inserted into the pin hole 7, and the staff then enters the working hanging basket 2 and controls the movement of the working hanging basket 2 through the mechanical arm 1.
[0051] By connecting the clamp 3 to the working hanging basket 2 in this way, it is only necessary to tighten the clamp 3. The whole process is relatively fast and has little impact on the process time. At the same time, the personal safety of the staff is guaranteed through an integrated series of safety measures.
[0052] At present, the device is used to load explosives in the No. 2 inclined shaft work area of Kangyu Tunnel. After the implementation of the device, the loading speed has been significantly improved, and the process time of each cycle has been shortened by 45 minutes, which can save 23.25 hours a month and increase the footage of a cycle by 3 meters.
[0053] While the two original hanging basket arms on the arch vehicle are loading explosives 1m above the arch line and in the arch top range, the two newly added mechanical arms 1 are clamping two working hanging baskets 2 to load explosives within a range of 2 meters from the ground. There are 4 people distributed in the hanging baskets on the two original hanging basket arms, and 1 person is added to each of the two newly added working hanging baskets 2. 4 people are loading explosives on the ground range, which fully and comprehensively utilizes the space on the face and significantly improves the loading speed and efficiency.
[0054] Compared with the conventional arch frame trolley, the arch frame trolley in the device is more suitable for rapid cross-section charging after being equipped with two working hanging baskets 2, which shortens the process cycle time, improves the construction efficiency, and is simple and convenient to manufacture and install, and is easy to promote the process.
[0055] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.
Claims
1. A charging operation platform applied to an arch trolley, characterized in that: include: A work hanging basket (2) for carrying people, wherein a support column (4) is fixedly connected to the left side of the work hanging basket (2), and an I-beam (5) is fixedly connected to the left side of the support column (4); It also comprises a freely movable mechanical arm (1) arranged on the arch trolley, and the other end of the mechanical arm (1) is connected to a clamp (3) for supporting and fixing the I-beam (5).
2. The charging operation platform applied to the arch trolley according to claim 1 is characterized in that: The working hanging basket (2) comprises a grille bottom plate (21), a support beam (22) is symmetrically fixed on the left side of the grille bottom plate (21), a cross beam (23) is fixedly connected above the support beam (22), and the support column (4) is fixedly connected to the cross beam (23); a plurality of groups of support rods (24) are vertically connected to the periphery of the grille bottom plate (21), and at least two groups of support fences (25) are vertically fixed on the support rods (24).
3. The charging operation platform applied to the arch trolley according to claim 2 is characterized in that: The working hanging basket (2) is provided with an entrance and exit (26) on the right side thereof; the working hanging basket (2) further comprises a sleeve ring (27) sleeved on the supporting rods (24) on both sides of the entrance and exit (26); the two sleeve rings (27) are slidably arranged on the supporting rods (24) up and down; the sleeve ring (27) is located between the two supporting fences (25) at the upper part; and an intercepting rod (28) is fixedly connected between the two sleeve rings (27).
4. The charging operation platform applied to the arch trolley according to claim 1 is characterized in that: The clamp (3) comprises a clamping base (31), and two groups of clamping claws (32) for clamping and fixing the bottom of the I-beam (5) are symmetrically arranged in the clamping base (31).
5. The charging operation platform applied to the arch trolley according to claim 4 is characterized in that: The bottom of the clamping portion of the clamping claw (32) is connected to a clamping cushion block (33).
6. The charging operation platform applied to the arch trolley according to claim 4 is characterized in that: When the clamping claws (32) clamp and fix the I-beam (5), the two clamping claws (32) are located outside the support column (4).
7. The charging operation platform applied to the arch trolley according to claim 6 is characterized in that: At least two groups of symmetrical positioning clamps (34) are also fixedly arranged on the clamping base (31), and the positioning clamps (34) are located on the inner side of the support column (4); the positioning clamps (34) are U-shaped.
8. The charging operation platform applied to the arch trolley according to claim 4 is characterized in that: At least two groups of steel pads (35) are arranged on the top surface of the clamping base (31), and the steel pads (35) are arranged between each group of clamping claws (32).
9. The charging operation platform applied to the arch trolley according to claim 1 is characterized in that: The left side of the I-beam (5) is fixedly connected with a pin crossbeam (6), the pin crossbeam (6) is provided with a pin hole (7), and a safety pin (8) is inserted into the pin hole (7); the clamp (3) is located between the safety pin (8) and the support column (4), and the bottom of the safety pin (8) extends to the bottom position of the clamp (3).
Citation Information
Cited By
Multifunctional all-in-one unit for drilling and blasting method construction and construction technology
CN121497354A